DOE-STD-3024-2011, Content of System Design Descriptions
Functional areas: Design Descriptions, Facility Safety, Design Process
This Standard provides criteria and guidance for the development of a System Design Description (SDD). An SDD identifies the requirements associated with structures, systems, and components (SSCs); explains why those requirements exist (that is, provides the bases for the requirements); and describes the features of the system design provided to meet those requirements. Supersedes DOE-STD-3024-98
Supersedes:
DOE-STD-3024-98, Content of System Design Descriptions on Aug 22, 2011
Version history and related documents
Supersedes
Earlier documents this one replaced.
- DOE-STD-3024-98Content of System Design Descriptions (Aug 22, 2011)
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
DOE-STD-3024-2011
August 2011
________________________
Superseding
DOE-STD-3024-98
DOE STANDARD
CONTENT OF SYSTEM DESIGN
DESCRIPTIONS
U.S. Department of Energy AREA EDCO
Washington, D.C. 20585
DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.
NOT MEASUREMENT
SENSITIVE
DOE-STD-3024-2011
ii
Available on the Department of Energy Technical Standards web page at
http://www.hss.energy.gov/nuclearsafety/ns/techstds/
DOE-STD-3024-2011
iii
CONTENTS
PAGE
Foreword ..................................................................................................................................................... iv
1. PURPOSE ............................................................................................................................................1
2. APPLICABILITY ................................................................................................................................1
3. OVERVIEW OF STANDARD ............................................................................................................1
4. OBJECTIVE OF SYSTEM DESIGN DESCRIPTIONS .....................................................................1
5. CRITERIA AND GUIDANCE FOR SDDs .........................................................................................2
APPENDICES .................................................................................................................................................
APPENDIX A: Glossary ................................................................................................................ A-1
APPENDIX B: Abbreviations and Acronyms ................................................................................ B-1
APPENDIX C: Developmental References .................................................................................... C-1
APPENDIX D: Format of System Design Descriptions ................................................................ D-1
APPENDIX E: Technical Content Criteria and Guidance .............................................................. E-1
1. Chapter 1: Introduction of an SDD.......................................................................................... E-1
2. Chapter 2: General Overview .................................................................................................. E-2
3. Chapter 3: Requirements and Bases ........................................................................................ E-4
4. Chapter 4: System Description .............................................................................................. E-16
Appendices to the SDD .............................................................................................................. E-25
APPENDIX F: Compiling Technical Information for the Development of SDDs ......................... F-1
1. Availability of Design Information .......................................................................................... F-1
2. The DOE-STD-3009 Approach ................................................................................................ F-1
3. Document Retrieval .................................................................................................................. F-2
4. Reviewing Retrieved Documents ............................................................................................. F-2
Section 2
5. Resolving Conflicting Information........................................................................................... F-3
6. Missing Information ................................................................................................................. F-3
APPENDIX G: Application of the Graded Approach to the Development of SDDs .................... G-1
1. Facility Categorization ............................................................................................................ G-1
2. Facility Remaining Lifetime ................................................................................................... G-1
3. SSC Classification ................................................................................................................... G-1
4. Grading Within an SDD .......................................................................................................... G-2
5. Phased Approach ..................................................................................................................... G-2
APPENDIX H: Preparation of Facility Design Descriptions (FDDs) ............................................ H-1
DOE-STD-3024-2011
iv
FOREWORD
This Department of Energy (DOE) standard is approved for use by all Departmental organizational
units and contractors of the Department.
This Standard provides criteria and guidance for the development of a System Design Description
(SDD). An SDD identifies the requirements associated with structures, systems, and components
(SSCs); explains why those requirements exist (that is, provides the bases for the requirements); and
describes the features of the system design provided to meet those requirements. The SDD helps
ensure consistency among the engineering requirements for systems, the actual installed physical
configuration, and the associated documentation.
This Standard is referenced in DOE Order (O) 420.1B, Facility Safety, as a source of guidance on the
identification of key design documents supporting facility safety basis development and
documentation.
Like National consensus standards, the DOE Technical Standards Program generally expects its
standards to be applied voluntarily. Sometimes, a standard is mandated by a higher authority or a
regulatory agency, and hence the standard becomes mandatory. To distinguish the requirements
contained in this Standard from its recommendations, the term “shall” has been used to designate
requirements and “should” to designate recommendations within the standard. Compliance with a
standard is achieved by adherence to its requirements and consideration of its recommendations.
Beneficial comments for improvements of this Standard (additions, deletions, or other changes) and
any pertinent information should be addressed to Ms. Ashley Ruocco, U. S. Department of Energy,
19901 Germantown Road, Germantown, Maryland 20874-1290; or e-mailed at
ashley.ruocco@hq.doe.gov. Commenters are encouraged to use the form DOE F 1300.3, Document
Improvement Proposal.
DOE-STD-3024-2011
1
1. PURPOSE
This Standard provides criteria and guidance for the technical content and organizational structure of
system design descriptions (SDDs) at Department of Energy (DOE) facilities.
2. APPLICABILITY
Section 3
This Standard should be used to develop an SDD for all active safety class (SC) and safety significant
(SS) systems for nuclear facilities. On a case-by-case basis, it may be beneficial to create SDDs for
complex or unique passive SC or SS systems, or for complex and unique process safety and general
service systems. Examples of such passive system structures and components (SSCs) include an
especially complex shielding system, a natural convection (passive) ventilation system, or a complex
containment structure. Application of this Standard should be considered for systems, including those
in other than Hazard Category 1, 2 or 3 nuclear facilities, because SDDs can support cost-effective
operation of systems.
3. OVERVIEW OF STANDARD
The main body of this Standard describes the objective of SDDs and provides higher level criteria and
guidance for SDD development (Section 4 and 5).
Appendices A through C provide the following general supporting and background information:
Appendix A – Glossary
Appendix B – Abbreviations and Acronyms
Appendix C – Developmental Resources
Appendices D through H provide the following details supporting SDD development:
Appendix D – Format of SDDs
Appendix E – Technical Content Criteria and Guidance
Appendix F – Compiling Technical Information for the Development of SDDs
Appendix G – Application of the Graded Approach to the Development of SDDs
Appendix H – Preparation of Facility Design Descriptions
4. OBJECTIVE OF SYSTEM DESIGN DESCRIPTIONS
4.1 General
A major purpose of the SDD is to collect system information to facilitate efficient design,
maintenance, operation, and training (because personnel will not have to review multiple documents
in an effort to locate pertinent information). An SDD identifies the requirements associated with
SSCs, explains why those requirements exist (that is, provides the bases for the requirements), and
describes the features of the system design provided to meet those requirements. The SDD helps
ensure consistency among the engineering requirements for systems, the actual installed physical
configuration, and the associated documentation. The SDD often serves as the central coordination
link among the engineering documents, facility safety basis, and procurement and construction
documents. SDDs also provide a key reference to facilitate design reviews when integrated early in
DOE-STD-3024-2011
2
the design. An SDD does not generate requirements or basis information, but rather collects that
information into a usable form.
4.2 Development as Part of Facility and Project Design
DOE Standard (STD) 1189, Integration of Safety into the Design Process, has been developed to
show how project management, engineering design, and safety analyses can interact to successfully
integrate safety into the design of a new facility or major modification of an existing facility early in
the project. One of the design outputs of the safety-in-design process is an initial SDD developed
during conceptual design to capture the functional and performance requirements of facility systems
as they relate to the facility-level design basis accidents that provide necessary input to the
identification and classification of important safety functions. The iterative and evolutionary nature
of safety-in-design requires engagement of project operations, maintenance, engineering, and safety
personnel throughout the process and design output (e.g., drawings, SDDs) to support project
milestones and critical decisions through final design and to reflect as-built configurations.
Section 4
4.3 Users of System Design Descriptions
The intended users of SDDs vary depending on the facility and system covered. Normally, the
Cognizant System Engineer assigned to the system is responsible for the development and
maintenance of this document. Intended users include those involved in the facility safety analysis,
engineering, operations, training, and procedures staff, as well as oversight staff such as DOE Safety
System Oversight personnel or Facility Representatives.
An SDD does not generate a system’s design, requirements, or basis information, but rather collects
such information from multiple sources, such as original technical documents (e.g., safety basis
documents, drawings, specifications, vendor technical manuals, etc.) into a conveniently usable
vehicle for accessing this information. Since an SDD author cannot anticipate or address all needs,
uses, or vintages in a system’s evolution for which specific information is sought, it cannot reliably
serve as, and therefore should not be used as, a primary source or basis for actual design, operations,
maintenance, testing, or other technical activities. Such activities should always be based on original
primary documentation sources, where available, in order to minimize the potential for information
loss or misinterpretation in the translation, and to assure that all information that the user may find
pertinent, but that may not have been recognized as such by the SDD author and therefore not
included in the SDD, may be appropriately considered. Though not a primary source, the SDD has
been proven to be a valuable tool for staff to obtain information and as a pointer to more detailed
design information.
5. CRITERIA AND GUIDANCE FOR SDDS
5.1 SDD Physical Form/Location
SDD data shall be housed either in a physical document or in an approved data system, such as an
“enterprise” system (ES) that meets the site’s configuration management requirements. Either
approach should provide the reader a single point of reference rather than requiring access to different
documents to obtain pertinent information or interpreting details in vendor technical manuals and
engineering documents. Where an ES is used in lieu of a hard copy document, the ES shall provide
the same type and level of information in a configuration controlled, accessible manner that meets
both the facility configuration management requirements and provides equal or greater functionality
to the end-users in supporting their ability to find information.
DOE-STD-3024-2011
3
5.2 SDD Level of Detail
The SDD should collect and provide more detail than would normally be included in safety basis
documents but less detail than in engineering design documents. Early in a project’s development,
this can assist procedure writers in determining what procedures are needed. Later, it can benefit the
training staff and new technical staff. When an enterprise system is used, the SDD’s references can
become links, allowing rapid access to needed procedures and information.
5.3 Procedure Identification
The SDD should identify procedures for facility operations, testing, and maintenance related to the
system being described, and point the reader to those specific documents in their proper context.
5.4 Performance Criteria
Section 5
The SDD shall include information on the functionality and requirements (performance criteria) for
evaluating the performance of the system. Performance evaluation may include assessing overall
facility operational effectiveness and efficiency, compliance with regulatory requirements, the
possible need for improvements to increase system reliability, and the possible need for system design
modifications to meet changing programmatic mission needs and demands. SDDs should identify
which performance characteristics of the system are the most important.
5.5 Facility Design Descriptions
SDDs may be developed in conjunction with Facility Design Descriptions (FDDs). In an FDD, all
the systems in a facility can be addressed with their top-level functions and requirements. Using a
graded approach, an FDD can provide a mechanism for addressing simple, less important systems,
without requiring a separate SDD. The FDD may be the only document needed for less than Hazard
Category 2 facilities. For more complex or important systems within a larger facility, the FDD
should refer to individual SDDs for more detailed information. For simple systems that do not
implement safety requirements, a separate SDD should not be required if the FDD provides sufficient
information. Similarly, for a facility with limited systems, an FDD may not be necessary if an SDD
provides necessary information. For guidance on preparing FDDs, see Appendix H.
5.6 Design Information
The SDD shall contain all information about features of the design that demonstrate how the design
satisfies the safety criteria in the safety basis documents.
5.7 SDDs and Safety Basis
An SDD shall support the safety basis and help ensure that the operation of the system will be
consistent with the safety basis. Even though the SDD may precede the development of the
Documented Safety Analysis (DSA), it should not serve as a source of information for the safety
basis, since the SDD is not a part of the safety basis. DOE does not rely upon information found
uniquely in the SDD to make decisions regarding the safety of the facility. In addition to engineering
and safety requirements, the SDD should contain requirements that are derived from programmatic
needs.
DOE-STD-3024-2011
4
5.8 Non-Safety Information
While a primary focus of the SDD is on system safety features, the SDD should also address other
important features provided to accomplish the programmatic mission, maintain system reliability, and
promote effectiveness, efficiency, and flexibility in operations and maintenance.
5.9 SDD Evolution
For a new facility or system, the SDD scope and level of detail may change throughout design and
construction. Initially [at conceptual design, either Critical Decision-1 (CD-1) or early CD-2 stage],
the SDD may include information on primary system functions and boundaries. It may contain
preliminary data and indicators of “to be determined” (TBD) that should be refined as the design
matures. It shall serve as the vehicle for collecting and conveying the system requirements, their
bases, and how the system meets the requirements to support integration of system design and the
safety functions and requirements development during the safety analysis process.
5.10 Documenting Design Changes
Section 6
The SDD may be used for documenting changes as the design evolves from conceptual design
through the preliminary and final design. The development of the SDD shall be coordinated with the
engineering design process and with the safety analysis development. During design, updates will
iterate between the design and development of the safety basis. To assure that the development of the
SDD proceeds as planned, it is recommended that the Safety Design Strategy, per DOE-STD-1189,
specifically address the configuration control and development strategy of the SDD parallel with the
Preliminary Documented Safety Analysis and hazard analysis development.
During design, construction and commissioning the data needs are different than for operations. The
enterprise systems are particularly beneficial to support this process. For example, the ability to have
different, custom reports or data presentation is particularly beneficial during design, procurement,
construction, and commissioning. The data can be presented from an enterprise system for each
group in a different format. The data itself is what is important and shall be configuration controlled
and managed in a manner that all data required for operations shall be available when the facility is
started up.
For an existing facility or system, where the development and approval of the safety basis have
preceded the development of the SDD, the SDD shall contain requirements and descriptions of all
relevant features of safety SSCs contained in safety basis documents that are needed to meet the
safety functions. The SDD is not a safety basis document. The SDD has proven to be an excellent
source for documenting requirements and system characteristics in a facility that has had multiple
changes and safety documents (and often contractors) over its operating life.
5.11 SDD Change Control
After the facility is in operations, the SDD shall be a controlled document, or controlled SDD data
maintained in an approved data system. It shall be maintained as an authoritative, up-to-date source
of technical information on the system. Prior to starting operations, the configuration management
approach should be defined in the design strategy.
When a change to the system is proposed, the SDD should be consulted to identify the pertinent
requirements and the referenced engineering source documents. The results of the change should be
DOE-STD-3024-2011
5
reflected back into the SDD. Changes to the SDD itself are within the purview of the DOE contractor
within an appropriate change control process.
5.12 Distinguishing Mandatory Versus Optional Requirements
An SDD shall distinguish between the items that are mandatory requirements that the system shall
meet and those additional characteristics that are optional/desirable. If the format recommended in
this Standard is followed, Section 3 shall contain only the requirements on the system (and their
bases) necessary to fulfill the system function statements, and not the extra, non-mandatory
performance capabilities that might exist in the actual system design configuration. Section 4 of the
SDD describes how the actual system currently is designed and configured to satisfy its requirements,
and also describes the full capacity and capabilities of the system beyond the mandatory
requirements.
5.13 SDD Use of Source Documents
Section 7
The information in the SDD is a combination of narrative and index (“road map”) approaches. It is
not intended that the SDD be a “cut and paste” of sections from the DSA or Technical Safety
Requirements (TSRs). Data or information from these higher-level documents should be linked (or
road-mapped) to minimize the maintenance of information in the SDD and to reduce the potential for
the staff to fail to use the source documents. Including photographs of equipment and arrangements
is encouraged, particularly when the equipment/room is inaccessible during operations and/or
difficult to access. Photographs and sketches provide valuable information in an SDD.
Engineering judgment should be applied to determine when information might be more detailed than
is worthwhile for the intended audience of the SDD. The status of the source document for
information (that is, current document or archived historical record) should not be a deciding factor in
determining if the information may be needed by the SDD user. The best practice is to provide a
summary and a reference to the details. To omit information from an SDD on the basis that the
information might need to be revised sometime in the future if a change were to be made is not a
valid basis for determining what information to include in the SDD. If the information is important to
the overall purposes of an SDD and to the intended audience, it should be included in the SDD.
If not captured in other facility documentation (example: System Health Reports), then the SDD
should provide for collecting/capturing operating experience information, including lessons learned
from other facilities that have similar systems. This would normally be captured in an Appendix if
not retrievable elsewhere.
5.14 SDD Details
All SDD detail areas to be covered are included in the Appendices; if not applicable, the document or
enterprise system should so state the non-applicability.
The SDD shall identify by title the “owner” of the SDD and shall define responsibilities and
authorities for maintaining the technical content of, and for reviewing changes to, the SDD.
DOE-STD-3024-2011
A-1
APPENDIX A: GLOSSARY
This glossary explains important terms in this Standard. To the extent practical, standard definitions
have been used. The full bibliographical information on these references is given in Appendix C to
this Standard. In some cases, the general definitions have been supplemented in order to explain
more fully how the term is used in this Standard.
Basis. The basis explains why a requirement exists and why it has been specified in a particular
manner or at a particular value during the engineering design process. Basis information is
delineated in design input information, design constraints, and intermediate outputs, such as
design studies, analyses, and calculations. The basis encompasses consideration of such
factors as facility mission, facility availability, facility efficiency, costs, schedule,
maintainability, and safety. (10 CFR 830)
Cognizant System Engineer. The engineer designated by the organization to each system to which
the System Engineer Program, as defined in DOE O 420.1B, applies. The CSE maintains
overall cognizance of the system and is responsible for system engineering support for
operations and maintenance. The CSE provides technical assistance in support of line
management safety responsibilities and ensures continued system operational readiness.
(DOE-STD-1073-2003)
Section 8
Controlled Documents. Documents whose content is maintained uniform among the copies by an
administrative control system. The goal of controlling documents is to ensure that work is
performed using approved current information, not obsolete information. Important
documents to be controlled are uniquely identified (including revision number, date, and
specific copy number), and distribution is formally controlled. Revisions to controlled
documents are uniquely tracked and implemented, including mandatory page replacements
and receipt acknowledgment. Controlled documents typically include procedures for
operations, surveillance, and maintenance, and safety basis documents such as the DSA,
TSRs, and hazard and accident analyses. (10 CFR 830)
Design Information. Design information is the combination of the requirements and the
corresponding basis information associated with the engineering design process. (DOE-STD-
1073-2003)
Engineering Design Process. The technical and management process that begins with the
identification of design inputs and constraints (e.g., mission objectives, commitments,
applicable codes, standards, regulations, procedures, and methodologies), processes this
information, and results in the issuance of requirements and of formal design analyses and
design documents from which SSCs are fabricated, constructed, installed, and commissioned.
This process defines and documents the inputs; adheres to the constraints; performs and
documents analyses, calculations, technical studies and evaluations; and ensures that the
outputs of the process (i.e., the requirements that dictate a design that satisfies the inputs and
constraints) are documented and complete.
Enterprise System. Enterprise systems (ES) are large-scale, integrated application-software
packages that use the computational, data storage, and data transmission power of modern
information technology (IT) to support processes, information flows, reporting, and data
analytics within and between complex organizations. The integrated content may then be
used to provide a configuration management solution throughout the life cycle in relation to
the products, assets, processes and requirements of the entity (laboratory, facility, SDD, etc.).
Enterprise applications can be described as a means to manage both the content and the
configuration (including change control) of the enterprise. Enterprise content management
DOE-STD-3024-2011
A-2
systems are electronic systems effective in capturing, managing, storing and delivering
content across an enterprise, managing the content (e.g., the information and data of an SDD)
“in context” with the entire business (facility/national laboratory).
Facility Design Description. A document that defines the facility, its systems and functions.
Requirements. The results of the engineering design process that define what has been required.
Requirements are typically defined on design output documents (such as drawings and
specifications) that specify the functions, capabilities, capacities, physical dimensions, limits,
setpoints, etc. for a structure, system, or component.
Safety Basis. The documented safety analysis and hazard controls that provide reasonable assurance
that a DOE nuclear facility can be operated safely in a manner that adequately protects
workers, the public, and the environment. (10 CFR 830)
Section 9
Safety Basis Documents. Documents providing safety basis information. These typically include,
but are not necessarily limited to, the DSA, TSRs, Unreviewed Safety Question (USQ)
Process, DOE-issued Safety Evaluation Reports, and DOE Conditions of Approval.
Safety Function Statements. Top-level statements that express the objective of the SSC in
preventing or mitigating a given accident scenario. Safety functions should include: 1)
situations and any general accident types during which the function is required to be met; 2)
specific functional needs that prevent, detect, and mitigate an event; and 3) sufficient
description to enable clear functional requirements, design requirements, and acceptance
limits to be defined for those SSCs chosen to meet the safety function.
Safety Structures, Systems, and Components (Safety SSCs). The set of safety-class SSCs and
safety-significant SSCs for a given facility. (10 CFR 830) The definitions for safety-class
SSCs and safety-significant SSCs and associated relevant information are provided in DOE-
STD-3009.
Subsystem. A combination of components, modules, devices, or software within a system that can
perform a function or an identifiable part of a function. A subsystem may be deemed to exist
when specific flow paths or equipment or functional capabilities can be correlated with
different parts of the system functions or system requirements. For example, if the system
function statement were to say to maintain negative differential pressures in various zones,
there might be one flow path that could be correlated with maintaining the negative
differential pressure in one of these zones. In another example, a general fire protection
system might have one subsystem that detects fire conditions, another subsystem that holds
the fire water, and a third subsystem that delivers the fire water to the proper location to
suppress the fire. In some systems, programmable software is treated as a subsystem
associated with the system.
Support System. A system that provides another system with a supporting service that is necessary
for the supported system to be capable of meeting its system requirements. For example, an
instrument air system may be needed for a ventilation system to meet its system requirements
with regard to certain dampers opening, modulating to maintain a specified negative pressure
differential, or closing under specified conditions. In another example, an HVAC system
may be required to maintain the temperature of an environment within the limits for which
some components are rated. In some designs, components of the system may go to a so-
called “fail-safe” condition upon loss of electric power or some other supporting service, but
that is a preferred failure mode. Preferred failure modes do not negate the need for the
support system.
DOE-STD-3024-2011
A-3
System. An interrelated set of structures, equipment, subsystems, modules, components, devices,
parts, and/or interconnecting items that is capable of performing a specified function or set of
functions that fulfill a purpose. Systems usually have defined physical boundaries, and
systems often depend upon human interactions. Some aspects of a system might be important
to safety or programmatic mission, while others might not. Sometimes a distributed set of
individual structural elements may be considered collectively to be a system. Accordingly,
the term “system” is used in this Standard to fully encompass structures, systems, and
components (SSCs). A system design description may be appropriate even if a particular set
of items does not meet this definition.
Section 10
System Functions. Those functions that the system needs to be capable of performing in order to
accomplish its intended purpose in the facility.
DOE-STD-3024-2011
B-1
APPENDIX B: ABBREVIATIONS AND ACRONYMS
CD
Critical Decision
CM Configuration Management
CMMS Computer Maintenance Management System
COTS Commercial Off-the-Shelf
CSE Cognizant System Engineer
DSA Documented Safety Analysis
EIS Environmental Impact Statement
ES Enterprise System
FDD Facility Design Document
FMEA Failure Modes and Effects Analysis
HVAC Heating, Ventilation, Air Conditioning system
MEL Master Equipment List
P&ID Piping and Instrumentation Diagram
PDL Project Decision List
PID Proportional-integral-derivative [controller]
PLC Programmable Logic Controller
QA Quality Assurance
SC Safety Class
SDD System Design Description
SNM Special Nuclear Material
SS Safety Significant
SSC Structure, System, or Component
TSR Technical Safety Requirement
DOE-STD-3024-2011
C-1
APPENDIX C: DEVELOPMENTAL REFERENCES
This Attachment identifies documents that were considered during the development of this Standard,
either directly or indirectly.
1. 10 Code of Federal Regulations (CFR) Part 830, Nuclear Safety Management
2. 10 Code of Federal Regulations (CFR) Part 835, Occupational Radiation Protection
3. DOE O 410.1, Central Technical Authority Responsibilities Regarding Nuclear Safety
Requirements, 8-28-07
4. DOE O 414.1D, Quality Assurance, 4-25-11
5. DOE O 420.1B, Facility Safety, 12-22-05, Change 1: 4-19-10
6. DOE G 420.1-1, Nonreactor Nuclear Safety Design Criteria and Explosives Safety Criteria
Guide for use with DOE O 420.1, Facility Safety, 3-28-00
7. DOE O 422.1, Conduct of Operations, 6-29-10
8. DOE-STD-1027-92, Hazard Categorization and Accident Analysis Techniques for Compliance
with DOE Order 5480.23, Nuclear Safety Analysis Reports, December 1992, Change 1:
September 1997
9. DOE-STD-1073-2003, Configuration Management, October 2003
10. DOE-STD-1189-2008, Integration of Safety into the Design Process, March 2008
11. DOE-STD-3009-94, Preparation Guide for U. S. Department of Energy Nonreactor Nuclear
Facility Safety Analysis Reports, July 1994, Change 3, March 2006
DOE-STD-3024-2011
D-1
APPENDIX D: FORMAT OF SYSTEM DESIGN DESCRIPTIONS
SDDs should adhere to the following outline to the extent that it is relevant to the SSC being
described. When a section of the outline below is not applicable to the system, the section shall be
retained in the SDD with a statement that the section is not applicable. A brief explanation of its non-
applicability should also be provided, especially if the reason for the non-applicability might not be
immediately obvious to the readers. Conversely, the outline might need to be expanded to address
aspects of some systems not covered previously. If an ES is used to capture the SDD information, all
aspects recommended by this Standard shall be searchable and, if the data is not applicable, the ES
shall capture the non-applicability rather than just not having the information available.
Note: The outline below is not intended to define minimum content requirement, but rather
to provide general guidance. This outline is intentionally exhaustive to encompass important
aspects of virtually any system. The content of specific SDDs is expected to vary with the
type of physical system being described (e.g., ventilation/confinement systems, electrical
power systems, chemical processes). Site format consistency has been shown to assist
training and orientation of new staff and/or backup staff, to aid in use by the CSE staff, and to
aid in updating and maintaining multiple SDDs for a facility.
Section 11
1. Chapter 1: Introduction of an SDD
1.1 System Identification
1.2 Limitations of this SDD
1.3 Ownership of this SDD
1.4 Definitions/Glossary
1.5 Acronyms
2. Chapter 2: General Overview
2.1 System Functions/Safety Functions
2.2 System Classification
2.3 Basic Operational Overview
3. Chapter 3: Requirements and Bases
3.1 Requirements
3.2 Bases
3.3 References
3.4 General Requirements
3.4.1 System Functional Requirements
3.4.2 Subsystems and Major Components
3.4.3 Boundaries and Interfaces
3.4.4 Codes, Standards, and Regulations
3.4.5 Operability
3.4.6 Performance Criteria
3.5 Specific Requirements
3.5.1 Radiation and Other Hazards
3.5.2 As Low As Reasonably Achievable
3.5.3 Nuclear Criticality Safety
3.5.4 Industrial Hazards
3.5.5 Operating Environment and Natural Phenomena
3.5.6 Human Interface Requirements
DOE-STD-3024-2011
D-2
3.5.7 Specific Commitments
3.6 Engineering Disciplinary Requirements
3.6.1 Civil and Structural
3.6.2 Mechanical and Materials
3.6.3 Chemical and Process
3.6.4 Electrical Power
3.6.5 Instrumentation and Control
3.6.6 Computer Hardware and Software
3.6.7 Fire Protection
3.7 Testing and Maintenance Requirements
3.7.1 Testability
3.7.2 TSR-Required Surveillances
3.7.3 Non-TSR Inspections and Testing
3.7.4 Maintenance
3.8 Other Requirements
3.8.1 Security and Special Nuclear Material Protection
3.8.2 Special Installation Requirements
3.8.3 Reliability, Availability, and Preferred Failure Modes
3.8.4 Quality Assurance
3.5.5 Miscellaneous Requirements
4 Chapter 4: System Description
4.1 Configuration Information
4.1.1 Description of System, Subsystems, and Major Components
4.1.2 Boundaries and Interfaces
4.1.3 Physical Layout and Location
4.1.4 Principles of Operation
4.1.5 System Reliability Features
4.1.6 System Control Features
4.2 Operations
4.2.1 Initial Configuration (Pre-startup)
4.2.2 System Startup
4.2.3 Normal Operations
4.2.4 Off-Normal Operations
4.2.5 System Shutdown
4.2.6 Safety Management Programs and Administrative Controls
4.3 Testing and Maintenance
4.3.1 Temporary Configurations
4.3.2 TSR-Required Surveillances
4.3.3 Non-TSR Inspections and Testing
4.3.4 Maintenance
4.4 Supplemental Information
Appendices to the SDD
A - Source Documents
B- System Drawings and Lists
C - System Procedures
D - System History
DOE-STD-3024-2011
E-1
APPENDIX E: TECHNICAL CONTENT CRITERIA AND GUIDANCE
The chapters described in this Appendix provide criteria and guidance for each section of the SDD
based on the format recommended in Appendix D.
1. CHAPTER 1: INTRODUCTION OF AN SDD
This section provides limited preliminary information related to the specific SDD such that the SDD
can be understood and can be used effectively and efficiently.
1.1 System Identification
This section shall identify the scope of the system being described in the particular SDD. This
section should identify the boundaries of the system concisely to explain the physical scope of the
system that is covered by the SDD and shall identify the interfacing systems.
1.2 Limitations of this SDD
This section shall explain any limitations that may exist for the SDD. If the scope of the SDD is
limited in some way, the reader needs to be made aware of that limitation. For example, the current
version may be preliminary and provide basis information for only the safety requirements.
Similarly, if certain sections of the SDD have not been fully addressed or developed completely, the
reader should be informed of this limitation. This section may contain notes to the user, e.g., known
limitations of source document information, missing source documents, or missing source data.
Section 12
1.3 Ownership of this SDD
This section shall identify by title the owner of the SDD and shall define responsibilities and
authorities for maintaining the technical content of, and for reviewing changes to, the SDD. The
owner should not be identified by name, because assignments could change. Rather, the SDD should
point the reader to a title, place, or document that would identify the specific individual assigned as
SDD owner. Normally, the owner is the assigned Cognizant System Engineer for the system
described. For some facilities, the Design Authority for the facility is designated as the Approval
Authority for changes. Depending on the significance of the system and the maturity of the facility,
additional reviewers should be specifically identified in this section.
1.4 Definitions/Glossary
This section should define or explain key terms and phrases necessary for the reader to understand the
SDD.
1.5 Acronyms
This section should define the acronyms used in the SDD.
DOE-STD-3024-2011
E-2
2. CHAPTER 2: GENERAL OVERVIEW
The SDD shall include an overview of the system that includes: 1) statements of the safety functions
and other functions assigned to the system; 2) the overall classification of the system; and 3) a basic
operational overview of the system, including a simplified system diagram. This general overview
section should be limited to information necessary to establish a foundation for understanding the
requirements and bases information that follows in the SDD.
2.1 System Functions/Safety Functions
The SDD shall state the functions that the system needs to be capable of performing in order to
accomplish its intended purpose in the facility. To the extent applicable to the system being
described, the system’s function statements should address the areas of safety (protection of onsite
and offsite personnel from radiological and other types of hazards), environmental protection,
programmatic mission, and general functions. Statements of the functions of the system should be
sufficiently specific to the system as to be distinctively different from the functions of other systems.
When taken collectively, the functions of all the systems should describe comprehensively how those
systems contribute to the overall operation of the facility.
Statements of safety function serve as the key link between the safety basis documents and supporting
documents. As discussed in References 14 and 15, the essential constituents of statements of safety
function are:
a. The situations and any general accident types during which the system may be called upon to
perform its safety function(s).
b. The specific functional needs that prevent, detect, or mitigate undesirable occurrences.
c. Those performance characteristics that have been specifically relied upon in the safety basis,
including the hazard analysis and accident analysis (this may include initial conditions or
assumptions concerning the system or its operation).
Specific requirements and bases that are derived from the safety functions should be defined in detail
in Chapter 3: Requirements and Bases.
Statements of safety functions in the SDD shall be consistent with the corresponding information in
the facility safety basis and specific references to the safety basis documents shall be provided. More
than one safety function may be assigned to a system. Safety functions may also be assigned to a
subsystem when the SDD is for a process system that includes subsystems required to prevent, detect,
or mitigate an event involving the process system.
Section 13
Note: A fundamental understanding of the functions to be provided by safety SSCs is
integral to maintaining the analyzed and approved engineering basis, as well as to operations,
testing, surveillance, maintenance, and modification activities. It is important that safety
function statements contain sufficient information and clarity to provide the fundamental
understanding that supports the development of functional requirements, identification of
appropriate design and performance criteria, evaluation of system performance, and
evaluation of changes.
DOE-STD-3024-2011
E-3
2.2 System Classification
The SDD shall state the overall classification that has been assigned to the system. This classification
should be based on the highest ranking (most important) requirements identified for the system, using
the hierarchy presented in Chapter 3 of this Standard (or the DOE contractor equivalent). For
example, if a system were to have safety-significant, mission-critical, and general requirements, but
no safety-class (SC) requirements, it would be classified as a “safety-significant” system. If a system
were to have mission-critical and general requirements, but no safety or environmental requirements,
it would be classified as a “mission-critical” system. This part of the section should be limited to a
simple, one-sentence statement such as, “This system is classified as mission-critical.”
This section shall include a simple positive or negative statement indicating whether or not the system
being described (or a subsystem of the system being described, such as a high temperature interlock)
is the subject of the facility TSRs.
2.3 Basic Operational Overview
This section should include a simplified system diagram, including boundaries and interfaces. Where
subsystems exist, they should be illustrated on the simplified system diagram. Where the safety
function(s) are provided by a subsystem(s) (e.g., high temperature interlock safety system associated
with an evaporation system), a simplified system diagram for the safety system should be provided.
The system boundary shall be consistent with that of the approved safety basis documents. This is
particularly important for safety system boundaries. Responsibilities of the Cognizant System
Engineer should normally align with the established system boundary, such that one Cognizant
System Engineer should typically be responsible for the SDD. The scope should not require multiple
CSEs to be responsible for the same document.
This section shall include a brief discussion of how the system operates. This discussion should be
limited to those operational aspects necessary to understand the requirements in Chapter 3.
DOE-STD-3024-2011
E-4
3. CHAPTER 3: REQUIREMENTS AND BASES
This section of the SDD shall identify both the requirements of the system and the bases for those
requirements. This section should also present the classification of those requirements with regard to
importance, thereby differentiating whether or not each requirement applies to a safety function of the
system. The bases should also refer to the source documents from which the requirements and bases
were obtained. If the requirements of an applicable standard were tailored, a justification that
explains the adequacy of the design with the tailored requirements should be included in the basis,
either explicitly or by reference.
Section 14
Requirements and bases statements should be appropriate, concise, and meaningful. System
requirements statements should be clear and specific and should not include basis information. For
example, a requirement statement such as, “Redundancy is required to mitigate component failures”
would be better stated as, “Full-capacity redundancy is required for the following components: ...”
with the explanation for this requirement provided as part of the basis information. In addition, the
bases statements should be informative and add value instead of merely re-stating the requirement in
different words. Value-added statements may include, for example, a brief explanation/summary of
the application of specific subsections of a consensus code and standard with reference to the specific
edition (code of record) of the standard and any associated facility engineering design documents.
3.1 Requirements
System requirements build on and logically support the system functions. For example, a system
general or overall function statement might say that the system has to function “on a highly reliable
basis.” The system requirement statements would then specify those features, such as component
quality requirements, redundancy, diversity and environmental requirements that provide the high
reliability for the system.
Requirements come from various sources. For example, some requirements might originate from
regulatory agencies such as DOE or EPA, from state and local governments (such as release limits or
building codes), or from DOE contractor organizations such as site management, design engineering,
construction, ES&H, or facility management. Also, requirements should have different levels of
importance. Some requirements are part of the DOE safety basis for a facility, and operation of that
facility is allowed only if it complies with those requirements (such a requirement can be changed
only if prior approval is obtained from DOE). Other requirements may have no bearing on the
facility safety basis, and may be changed as deemed appropriate by the design authority (which may
be the facility management) without prior approval from DOE.
The requirements and bases that should be included are those related to the system as a whole and
those that are specific to individual subsystems and components within the system. Requirements
and their bases (using a graded approach) should be included in the SDD, regardless of their source,
because the SDD should identify the requirements and bases needed for operations, engineering, and
maintenance personnel to have the understanding to operate and maintain the system safely, reliably,
and efficiently. Requirements should be stated in such a way as to communicate the information as
design output requirements within the context of an operating facility even if the SDD is prepared
prior to commencement of operations. These requirements should be maintained throughout the
operational life of the facility and updated to reflect changes to the requirements and their sources,
typically stemming from facility engineering design change documents (the level at which the change
control process for the system is accomplished).
Categorizing requirements by type is useful for identifying information that may be sought quickly
for making decisions concerning system operability and compliance with the safety basis. This
DOE-STD-3024-2011
E-5
Section 15
categorization is also helpful for routine searches, e.g., finding all seismic requirements for a given
system or for the facility overall.
Repetition of requirements should be avoided. However, some requirements could fit into more than
one section of the SDD. For example, a requirement might say that certain components shall go to
specified positions (open or closed) upon loss of electrical power. This might be considered to be an
electrical power engineering requirement (Section 3.3.4), or this same requirement could be viewed
as a reliability requirement (Section 3.5.3). In such cases, the information should be presented in only
one section of the SDD, with a reference to that section in other sections where the same information
becomes pertinent. One approach is to place the requirement in the first section in the SDD in which
it becomes relevant. Alternatively, use judgment to select the most fitting section for the requirement.
Requirements should be classified with regard to their importance to ensure appropriate consideration
in system operation, maintenance, performance evaluations, and evaluation of system changes. The
following hierarchy, or equivalent, should be used. The hierarchy is not intended to define a required
format for this information.
1. Safety Requirements
a. Safety Class
b. Safety Significant
c. Other “Important to Safety” Requirements
2. Environmental Requirements
3. Mission-Critical Requirements
4. General Requirements
Requirements classified as safety-class or safety-significant are those identified in safety basis
documents to accomplish safety functions, as established by the hazards analysis and safety analysis
processes. The “Important to Safety” requirements classification applies to those requirements that,
although not classified as safety-class or safety-significant, still perform functions considered
important to overall facility safety and are part of worker safety (e.g., standard industrial hazards) or
the defense-in-depth safety basis for the facility as defined in the facility’s safety basis.
The safety requirements statements shall be consistent with the corresponding statements of
functional requirements and performance criteria in the facility DSA, TSRs, and other safety basis
documents, if the safety basis has already been established for the facility. Performance criteria
(normally provided in Section 3.16) for the system shall be consistent with the performance criteria
specified in the facility DSA. Often, additional performance criteria are needed to meet program or
project goals. These should also be provided along with a brief description of the driver/basis for
those criteria.
One convenient way to correlate these requirements is to use footnotes. A footnote to a particular
requirement statement might say, “This requirement corresponds to Requirement 4.4.3.8 on Page 4.4-
12 in the DSA (Reference 3 in Appendix A).” An alternate way to correlate these requirements is
with a table (e.g., a requirements matrix) in a separate appendix or attachment to the SDD. The
environmental protection category should be considered separately and explicitly in the SDD to
assure this important set of requirements is not overlooked and to address requirements related to
environmental permits, when applicable.
DOE-STD-3024-2011
E-6
Mission-critical functions are those that prevent or mitigate substantial interruptions of facility
operations or severe cost or other adverse impacts, or satisfy other DOE programmatic mission
considerations.
Section 16
The general category is used for requirements that do not fit into the other categories.
This set of classifications is based on DOE-STD-3009 for Hazard Category 1, 2 or 3 nuclear facilities.
This set of classifications, a modified set, or a completely new set of classifications may be used for
other than Hazard Category 1, 2 or 3 nuclear facilities.
3.2 Bases
A major function of the SDD is not only to state the engineering requirements of the system, but also
to explain the basis for those requirements. Basis information explains why the requirement exists,
why it is specified in a particular manner, and why it has a particular value. While documenting the
bases for all requirements in the SDD is desirable, the basis information for safety requirements shall
be stated in the SDD.
Technical basis information should be included directly in the body of the SDD immediately after the
requirement, rather than placing such information in an appendix or referring to another document.
However, the basis for a group of related requirements may be provided in one place. The bases for
the requirements should be presented in a manner that minimizes the disruption of the reader’s flow
of thought. The recommended manner for presenting the basis information is to provide it in separate
paragraphs that are set off in a special format or font that is clearly discernable. The following
example illustrates this approach:
Requirement: The exhaust air high temperature trip setpoint on the ventilation exhaust fan
shall be less than or equal to 185°F.
Basis: The setpoint is established high enough above the normal operating exhaust air
temperature of 140°F to avoid spurious trips of the ventilation exhaust fan, but low enough to
provide early detection of hot gases. The safety analysis shows that, in the event of a fire, the
consequences to workers from the spread of toxic products of combustion are acceptable if
the fan is tripped before exhaust air temperature reaches 200°F (Reference #, Section xyz).
Basis information can take different forms. Specific engineering documents (such as studies,
analyses, calculations, and reports) are important basis references. Appropriate and specific
references to national codes and standards also should be included in the basis references, when
appropriate. Operational experience and standard engineering practices are valid reasons that could
justify a requirement. Basis information should be as detailed as possible with controlled document
reference to aid future personnel in fully understanding the technical basis, especially when no other
information is available.
3.3 References
Specific references are essential to understanding and using the SDD. Reference to source documents
from which requirements and basis information has been extracted adds traceability to the SDD and
improves its credibility. To the extent that such reference documents are available, the source
documents that contain the cited requirements or the bases information should be referenced in the
SDD. Even if the supporting reference document contains only the requirement but not the basis
information, such as may be the case for a procurement specification, the SDD should include that
document as a reference.
DOE-STD-3024-2011
E-7
If the requirement or basis information is not recorded in a separate document, the documentation no
longer exists, or retrieval of such a document is not feasible, the basis should note that a documented
reference is not available, so as to avoid potential confusion and wasted effort by other staff who may
try to research the basis.
Section 17
One effective method of referencing the source documents is to provide the bibliographical
information on the source documents in an appendix to the SDD (i.e., Appendix A). Footnotes, or an
equivalent, can refer to particular source documents and provide specific page references where they
are appropriate in the body of the SDD. For example, the footnote for a particular requirement might
say: “See Appendix A, Reference 5, pages 12-16.” This technique has the advantage that complete
bibliographical details do not need to be repeated each time a document is referenced. This technique
should also make SDD revisions easier. Such footnotes need not be limited to a single source
document. If more than one source document/reference contains pertinent information, they should
be included in the footnote.
3.4 General Requirements
3.4.1 System Functional Requirements
This section shall state those functional requirements and their bases, for both safety requirements and
non-safety requirements, that fulfill the system function statements. Using a graded approach,
emphasis should be placed on ensuring that a comprehensive set of safety functional requirements is
identified. If the requirements and bases have already been presented earlier in the SDD (see e.g.,
item c. in Section 2.1), refer to that section rather than repeating the information.
Note: Functional requirements relate to how the system functions, performs, behaves, or
responds to particular conditions. Non-functional requirements should be addressed in other
sections that correspond to the most fitting engineering or topical category, such as those that
address reliability features, electrical power needs, testability, or quality assurance provisions.
Functional requirements should address the system or facility situations to which the system is
designed to respond. When applicable, this should include the expected ambient operating conditions
related to those situations under which the system is required to perform its assigned function(s), and
the sequence in which certain actions are to be accomplished. Refer to DOE-STD-3009 for examples
of functional requirements.
These requirements statements should include sufficient detail to establish the acceptance criteria or
limits against which the actual performance capability of the as-built system can be evaluated. In
some situations, such acceptance criteria may be called “Performance Criteria.”
3.4.2 Subsystems and Major Components
General requirements and their bases that are unique to subsystems and major components should be
identified in this section.
3.4.3 Boundaries and Interfaces
This section should identify requirements and their bases that might exist concerning the boundaries
of the system being described, with emphasis on the components at the boundaries such as isolation
valves. For example, the boundary with an associated instrument air system may be required to be at
the upstream side of a particular check valve. Not all boundaries will have specific requirements;
DOE-STD-3024-2011
E-8
however, those that do have specific requirements shall be included in this section. Referring to the
simplified system diagram in Chapter 2 of the SDD may be useful for this purpose.
Section 18
The SDD should identify any requirements and their bases relating to interfacing systems, especially
“support systems” (see Glossary, page 1-2). For example, if a system requires a support power
supply that is to be operated on electric power available only from an uninterruptible power system,
that interface should be described. The SDD should also identify those interface requirements and
their bases that exist if the system being described provides support to another system, especially if
needed for the operation of a safety function of the other system. Not all interfaces will have specific
requirements.
3.4.4 Codes, Standards, and Regulations
This section should identify those codes, standards, or portions thereof that have been applied to the
system. It should identify codes and standards that have been required either by regulatory
organizations or by the DOE contractor.
Note: Where codes, standards, or portions thereof have been applied at the option of the
DOE contractor and compliance is expected by the contractor, they become requirements on
the system and hence they need to be included in this section. In contrast, if codes and
standards (or similar documents such as handbooks or guides) are intended to be used only as
general guidance and compliance is not required, they are not requirements on the system and
hence should be addressed in other sections of the SDD and clearly identified as guidance
rather than a requirement.
To the extent practical, the bases associated with codes and standards should identify the authority
that determined that it was appropriate to apply each of the codes and standards, so that future
proposed changes or exceptions in the application of those codes and standards can be referred to the
appropriate authority.
The specific codes and standards should be identified, rather than simply the general name of the
standards organization. Consideration should also be given to the desirability of identifying the
edition (or year of publication) for each identified code or standard, i.e., the code of record, to
eliminate confusion as to the specific requirement that is applicable.
Note: Subsequent editions of some codes or standards might contain requirements that this
particular system does not meet and should not have to meet. If the editions of the standards
are not specified, it implies an intent to maintain compliance with all subsequent editions.
This is a lesson learned by many facilities that leads to a failure to meet requirements “on
paper,” when management, engineering, etc., do not intend for subsequent revisions to a code
and standard to automatically apply.
A system may need to meet a particular section of, but not the entire, code or standard. Identify only
those sections with which the system will comply or has complied and for which such compliance
will be maintained.
Note: If the whole standard is identified without any qualifications, it implies an intent to
comply with the entire standard.
This section should identify government regulations that are applicable to the system being described.
These include: the Code of Federal Regulations (CFRs), DOE nuclear safety directives and
DOE-STD-3024-2011
E-9
regulations from other Federal agencies such as the EPA, court orders (if applicable), state laws and
regulations, and state permit requirements.
3.4.5 Operability
Section 19
When the system being described is the subject of TSRs that require the system to be operable, this
section shall be consistent with that of the safety basis documents. This section shall define system
operability; that is, the aspects of this system that are required to be capable of performing as intended
in order for this system to be formally considered “Operable.” This section may summarize and point
to the appropriate safety basis document operability requirements (e.g., TSR LCOs, limiting safety
system settings, or TSR design feature requirements), rather than duplicating extensive and complex
controls and surveillance requirements within the SDD. To the extent that the facility safety basis,
including the TSRs, defines operability specifically for the system, that definition shall be the one
stated/identified in the SDD. This section should also identify the facility operating modes or
conditions for which the system is required to be operable.
Note: System compliance with its “Operability” requirements will ensure accomplishment of
those safety functions specified by the applicable safety basis documents such as the DSA or
TSRs. The general definition of operability is that a system, subsystem, component, or
device shall be considered operable or have operability when it is capable of performing its
specified function(s), and when all necessary attendant instrumentation and controls,
electrical power, cooling water, or other auxiliary equipment that are required for the system,
subsystem, train, component, or device to perform its function(s) are also capable of
performing their related support function(s).
If the system has additional operability requirements established by facility management that go
beyond those requirements included in the TSRs, these should also be included in this section in a
manner distinctive from the TSR operability requirements.
3.5 Specific Requirements
3.5.1 Radiation and Other Hazards
This section shall address those safety requirements and their bases that have been established for the
design of the system in consideration of radiation or other hazards (such as lasers and hazardous
chemicals) that are beyond those typically accepted in an industrial workplace covered by OSHA.
These requirements pertain to the required level of protection for facility workers, other employees
located at the site, and the public. All system functional requirements assumed in facility safety basis
documents should be identified if they have not already been presented in the SDD.
This section includes all radiological safety requirements needed to comply with specific numerical
exposure limits regardless of cost. Those additional safety features that may be provided on a cost-
beneficial basis are generally referred to as “As Low As Reasonably Achievable” (ALARA) and
should be addressed in the next section and excluded from this section.
3.5.2 As Low As Reasonably Achievable
This section should identify requirements in the design safety features (such as special shielding) to
reduce the radiation exposures to personnel to ALARA. In general, ALARA goals are achieved (or
implemented) on a cost-beneficial basis, as contrasted with numerical radiation exposure limits that
must be met regardless of cost. This section should also address those requirements (and bases) that
DOE-STD-3024-2011
E-10
might exist to protect sensitive components from radiation exposure or to minimize radiological
contamination. Monitoring equipment and alarms should also be addressed.
Section 20
This section should include only information that is specifically related to the system being described;
general information about the facility radiation control program or ALARA program should not be
repeated here.
3.5.3 Nuclear Criticality Safety
This section shall identify those requirements and their bases that might exist related to design
features to prevent an inadvertent nuclear criticality. An example would be critical dimensions on the
size and shape of pipes, tanks, or other containers. This section also should identify items that
intentionally are not present, such as sources of water that have been routed so as not to be overhead
or in the immediate vicinity.
Non-design, operational (or administrative) aspects of the nuclear criticality safety program that apply
to this system, such as the use of materials/contents placards, should be addressed under Safety
Management Programs in Section 4.
3.5.4 Industrial Hazards
This section should identify requirements for safety features for hazards that are typically accepted at
commercial industrial workplaces. This section should identify safety and health requirements
pertaining to the system being described related to personnel safety and OSHA considerations.
This section is not intended to identify all the features of a piece of equipment that may be related to
the safety of personnel operating the equipment. Prominent aspects (such as guards surrounding
rotating machinery) or those that were part of the basis for selecting the particular equipment from a
vendor should be identified. This section provides the information that would help preclude potential
future modifications that might compromise features important to protecting employees.
3.5.5 Operating Environment and Natural Phenomena
This section should identify requirements (and their bases) related to the normal environment under
which the system is required to be capable of operating; for example, ambient temperature, humidity,
altitude, noise, radiation, electromagnetic or radio frequency interference (EMI/RFI) and vibration.
Requirements in this section typically will be unique to the particular system.
This section should also address abnormal and accident environments, consistent with the hazards
analysis and accident analysis. This section should be limited to environmental conditions that go
beyond typical design requirements such as those found in the International Building Code. This
section should address design requirements for protection from natural phenomena such as tornadoes,
floods, or seismic events. For example, if the system is required by the Facility Safety Basis to
operate during or following an earthquake, the associated acceleration spectra should be identified.
3.5.6 Human Interface Requirements
This section should identify the requirements (and bases) that may exist related to the design of the
system to enhance the interface between the system and the human operator. Where appropriate, this
should also include human factors or ergonomics requirements.
DOE-STD-3024-2011
E-11
This section shall identify any design requirements for alarms intended to trigger manual safety
actions. The basis for such a requirement should include a summary of the conditions that are
intended to generate the alarm (the meaning or significance of the condition) and a brief summary of
the actions that need to be taken manually in response to the alarm. Response actions to these alarms
are typically summarized in section 4.2 or 4.1.6 of the SDD.
Section 21
Requirements for alarms that are related to non-safety actions should be similarly described. This
section should identify requirements that may exist for the design to distinguish indications and
alarms that promote the prompt and effective performance of required operator safety actions from
other indications and alarms. Similarly, this section should identify requirements related to features
such as shapes, colors, or locations of particular indicators, controls, or displays if the feature is
critical to ensure the task can be correctly completed by the operator.
3.5.7 Specific Commitments
This section shall identify unique or special commitments that have been made to the DOE or another
regulatory agency such as the EPA and court orders. For example, in the investigation of an
operational event at a facility, it might have been determined that a major contributor to the incident
was the absence of positive position indication for some critical dampers or valves. As part of the
corrective actions to prevent recurrences of that or similar events, the contractor may have made a
commitment to DOE that all dampers and valves will have positive position indicators provided. In
that case, this commitment would be identified as a requirement for the system, and a reference made
to the appropriate document(s) that provide the commitment. Such commitments may be contained in
occurrence reports, correspondence, or other documents.
3.6 Engineering Disciplinary Requirements
This section should identify those requirements and their bases that are typically related to particular
disciplines of engineering. The focus should be on the requirements needed to meet the system and
safety functions; optional capabilities or excess capacities should be discussed in Section 4.
3.6.1 Civil and Structural
This section should identify those civil and structural engineering requirements and their bases related
to the system being described. This section should include only the civil or structural requirements
for a typical facility such as may be found in the International Building Code. Examples of
requirements that should be included are anchorage, bracing, or support requirements for equipment
(e.g., to prevent damage to equipment or injury to personnel).
3.6.2 Mechanical and Materials
This section should identify those mechanical or materials engineering requirements and their bases
related to the system being described. Such requirements may relate to pumps (e.g., type, net positive
suction head, flow capacity, discharge pressure), valves (e.g., type, size, stroke time, location), HVAC
system components and flow rates or differential pressures, equipment heat generation limits or
cooling system parameters, and parameters relating to compressors, filters, fans, boilers, and other
equipment.
3.6.3 Chemical and Process
This section should identify those chemical or process requirements and their bases related to the
system being described. Such requirements might include process or engineering limits on physical
parameters such as temperature, pressure, concentrations, feed rate, pH, heat transfer rates, and
DOE-STD-3024-2011
E-12
chemical compositions (e.g., amount or concentration of impurities allowable). Other requirements
that might relate to the type of process (e.g., continuous or batch, reactive or non-reactive), waste
generation considerations, or process evolutions (e.g., hold times, agitation rates) should be identified.
Section 22
3.6.4 Electrical Power
This section should identify those electrical power engineering requirements and their bases related to
the system being described. In most cases, these will involve the need for electrical power at a
particular voltage level, current, frequency, or quality. In some cases, these requirements might
involve providing electrical power for other systems. Examples of these later cases would be systems
that include diesel generators, motor-generator sets, uninterruptible power supplies, or battery banks.
Such systems would typically include the associated electrical distribution system plus automatic and
manual transfer features and the associated alternate power paths or circuits.
Examples of requirements are the length of time the system shall be capable of performing its
function(s) following the loss of normal utility power, and fail-safe states that equipment shall assume
upon loss of power. Another such requirement may be power quality. For example, a component
that is critical to the proper functioning of a safety system may be sensitive to voltage or frequency
perturbations and thus have a power quality requirement that the component receive regulated power
from an uninterruptible power supply with specific output parameters, such as between 118.5 and
121.5 Vac and between 59 and 61 Hz at the input terminal of the device.
3.6.5 Instrumentation and Control
This section should identify those instrumentation and control engineering requirements and their
bases related to the system being described. This section is focused primarily on hardware controls;
computer hardware and software controls are addressed separately in a later section.
This section should include requirements for manual and automatic actions for system initiation and
control, indicators, alarms, and manual controls that are used to operate the system. This section
should identify required ranges and accuracies.
This section shall distinctively identify instrumentation that either is (or will be) directly subject to
TSR requirements or provides information to verify compliance with TSRs. This section of the SDD
should identify the required nominal values of the setpoints associated with the system and ranges of
acceptable setpoint values. The basis information should explain any limitations, either
administrative, design, or limits important to safety, that may exist on the system or its components.
3.6.6 Computer Hardware and Software
This section should identify those computer hardware and software engineering requirements and
their bases related to the system being described. Many of the instrumentation and control topics
discussed in section 3.6.5 are also relevant to computer hardware and software. The topics addressed
in section 3.6.6 should be those unique to computer hardware and software. Examples include:
sample rates, real-time performance, data communications, and provisions for backing up programs
and data.
If there are requirements on the design and development process for computer hardware and software
aspects of the system being described (e.g., verification and validation, or qualitative reliability
goals), they should be described in this section. Key design documentation (such as the Software
Requirements Specification) should be referenced.
DOE-STD-3024-2011
E-13
Section 23
Note: The performance of digital systems over the entire range of input conditions cannot be
inferred from testing a limited sample of input conditions. Therefore, the design qualification
for digital systems is often based on requirements for employing a high-quality development
process that incorporates disciplined specification and implementation of design
requirements.
If diverse or defense-in-depth features are provided as backup to protect against hardware or software
features, these features should be identified in this section.
Note: Software and hardware are often shared to provide multiple functions to a greater
degree than is typical for analog systems. Although this sharing is the basis for many of the
advantages of digital systems, it also presents the potential for common mode failures (or
common cause failures) that might defeat the redundancy provided within the hardware and
software. Sometimes diverse or defense-in-depth features that are not susceptible to the
effects of such failures are provided to ensure that their consequences are tolerable. For
example, the automatic computer monitoring and alarming for certain facility variables may
be backed up by separate hardware indicators or manual surveillances.
If requirements exist related to the reliability of commercial off-the-shelf (COTS) hardware or
software, they should be described. Such requirements may include vendor documentation
demonstrating high reliability based on a formal program for recording and tracking failures.
Note: Computer based systems often employ COTS; for example, source code embedded in
a programmable logic controller (PLC) or local application programming of commercial
software such as database management system software.
Administrative programs that support computer and software activities (such as software
configuration management and quality assurance) should be described in the appropriate section of
the SDD, which might be in Section 4.
3.6.7 Fire Protection
This section should identify requirements and their bases that might exist for fire protection features
within the system, including detection, suppression, and other mitigation features. An example of the
information provided in this section would be requirements on ventilation system fire dampers to
close at or before a critical temperature is reached, and for the dampers to be rated for preventing the
spread of fire for a specific time. This section should also identify special types of fire suppression
materials, such as the need to use gaseous fire suppression systems in a particular area rather than a
water sprinkler system.
3.7 Testing and Maintenance Requirements
This section should address those aspects of testing and maintenance of the system being described
that are related to the design of the system.
3.7.1 Testability
This section should identify those design requirements and their bases that might exist for features
that make the system testable, especially those design features that preclude the need to install
temporary configurations manually on a frequent basis (e.g., every 12 months). For example, a
requirement might exist to provide a test panel, with spring-loaded switches and bypass indicating
lights, that eliminates the use of manually installed temporary configurations. Another example
DOE-STD-3024-2011
E-14
Section 24
might be a requirement to bring certain electrical connections to external test points to avoid internal
electrical hazards and to avoid potential errors in manually installing temporary configurations.
Operational (non-design) limitations on the use of temporary configurations are addressed in
Section 4.3.1.
3.7.2 TSR-Required Surveillances
A summary of the TSR-required surveillances, with reference to the safety basis documents (e.g.,
TSRs), should be provided here in lieu of direct duplication of those documents. This section should
not contain verbatim restatement of the TSR surveillance requirements. Rather, it should provide
additional supportive technical information and explanations of the surveillance requirements such as
those features provided in the design to facilitate those performing the testing.
3.7.3 Non-TSR Inspections and Testing
If the system being described is the subject of required inspection, testing, or surveillance
requirements (including setpoint verifications or adjustments) that are not due to TSRs, this section
should identify them, state how often they are required to be performed, state the acceptance criteria
for these activities, and describe any design features necessary to perform those surveillance actions.
These items should be clearly distinguished from TSR-required items.
Note: Where surveillances, inspections, or testing beyond the TSRs have been applied at the
option of the DOE contractor and compliance is expected by the contractor, they become
requirements on the system and hence they should be included in this section.
Note: In some cases, an industry code or standard may mandate certain in-service inspection
(ISI) or testing (IST) activities. In many cases, the manufacturer recommends certain checks,
tests, and calibrations that need to be adhered to (unless an engineering analysis establishes a
basis for alternate activities or a modified schedule for those activities).
3.7.4 Maintenance
This section should identify maintenance activities required to comply with the manufacturer’s
recommendations or otherwise required to ensure continued reliability. Examples include
requirements to periodically replace specified components in order to prevent a failure such as seals,
lubricants that degrade over time, or certain parts that wear out-of-tolerances after a number of cycles
or operations. When maintenance requirements are extensive, it may be beneficial to point to the
applicable maintenance documents such as vendor technical manuals for the components of the
system that support the intended safety function of the system.
3.8 Other Requirements
3.8.1 Security and Special Nuclear Material Protection
This section shall identify those requirements and their bases that are applicable to the system, related
to the general security of the facility or the need to protect special nuclear materials (SNM). For
example, the design of a vault to store SNM may be required to include features such as combination
locks, weight, size, and seismic capability in order to protect the contents of the vault from certain
postulated situations. However, the level of detail should be limited to protect security safeguards
information, and simply referencing the applicable security source documents may be appropriate.
DOE-STD-3024-2011
E-15
3.8.2 Special Installation Requirements
Section 25
This section shall identify any requirements and their bases that may exist related to special
arrangements, locations, or installation of components of the system being described. These might
include alignments, shock mounting, lengths of electrical signal cable, special routing requirements
for pump net positive suction head considerations, physical separation between redundant equipment,
location requirements to minimize equipment interferences, and “free space” requirements for
maintenance access.
Note: Some installation requirements may be specified in the vendor’s or manufacturer’s
technical information that comes with the equipment. For example, equipment may be
required to be wall mounted instead of floor mounted, be oriented in a particular direction,
maintain a minimum bend radius for interconnecting equipment, or locate certain types of
components in a fluid system (liquid or air) a minimum distance from a bend or other flow-
perturbing component.
3.8.3 Reliability, Availability, and Preferred Failure Modes
This section should identify requirements and their bases for design provisions that will ensure the
system will perform its function(s) by improving system availability, improving reliability by
minimizing ways in which it can fail, or minimizing the impact of failures. Such provisions might
include equipment redundancy, diversity, physical separation, electrical isolation, features that
provide mechanisms for on-line testing, features that avoid frequent use of temporary configurations
(such as lifted leads or jumpers) for testing and maintenance, automatic fault detection capability, and
preferred failure modes (“fail-safe” states).
3.8.4 Quality Assurance
This section should identify the general category of quality assurance (QA) to be applied to the
system as a whole and to the components of the system and should identify any specific QA actions
and how the system meets the QA requirements specified in the facility-specific QA plan. When the
general QA category provides for options related to specific QA activities, the SDD should identify
which options apply to this system. When specific QA requirements, such as witnessing vendor
testing, are applicable only to certain components, those requirements should be identified (perhaps in
a table) in the SDD. Safety features that should be demonstrated during procurement, startup, and
maintenance should be included and uniquely identified.
3.8.5 Miscellaneous Requirements
This part of the system requirements section of the SDD is for requirements and their bases that do
not fit conveniently into the other defined sections.
DOE-STD-3024-2011
E-16
4. CHAPTER 4: SYSTEM DESCRIPTION
The SDD shall include a comprehensive description of the system safety features. It should also
include a description of its important non-safety features. The description should emphasize those
features provided to meet the requirements of the system. This section should identify the
components of the system; describe how those components are laid out physically and interconnected;
explain the system flow paths; identify the indicators, controls, and alarms provided; define the
acceptable ranges for system performance and setpoints; and explain how the system operates.
Section 26
The manufacturer and model number for components in the current system configuration should be
recorded in a controlled document for several reasons including to facilitate identifying the applicable
information in vendor-supplied documents. In some cases, the SDD may be the most appropriate
place to record this information. In other cases, the SDD may reference a separate controlled
document or ES such as the Computer Maintenance Management System (CMMS or Master
Equipment List) or Bill of Materials that contains this configuration information.
The system should be described with specific values, rather than simply a repetition of the
requirements. For example, a requirement on a system might be that the centerline of a pump suction
line be located more than 8 inches and less than 14 inches above the bottom of a tank. This
requirement might have been based on a combination of net positive suction head considerations for
the pump and avoiding debris that may be on the bottom of the tank. The system description should
not simply repeat the 8 to 14 inches requirement, but rather describe the actual installation more
specifically, such as stating that the centerline of the suction pipe is 11.25 inches above the bottom of
the tank. In another example, for a requirement that a valve be provided with position indication that
is displayed in the control room, the SDD should not simply say that valve indication is provided in
the control room. Instead, it should state specifically that valve position limit switches are provided
on the valve that indicate on the auxiliary systems panel in the control room when the valve is greater
than 90% open (green light) or greater than 90% closed (red light).
In addition, features of the system description that are related to the system requirements should be
correlated. One effective method for this correlation is use of footnotes. For example, a footnote to a
particular feature, characteristic, or performance capability might say, “This feature is related to
System Requirement 3.3.4.15.” Conversely, the requirements in Chapter 3 of the SDD may contain
footnotes/notes as to the corresponding description section of Chapter 4.
4.1 Configuration Information
4.1.1 Description of System, Subsystems, and Major Components
A more detailed system diagram than that provided in Chapter 2 of the SDD should identify the
components in the system and their interconnections. This diagram should extend sufficiently to
identify the interfacing equipment and systems. The boundary between the system being described
and the interfacing systems shall be shown on the diagram in a distinctive manner. Similarly, the
subsystems that have already been shown in the simplified system diagram in Chapter 2 of the SDD
should be identified in a distinctive manner that can be correlated with the earlier diagram. For a very
simple system, a single diagram may be used. For complex systems, multiple subsystem diagrams
may be needed to describe the system.
A purpose of the system diagram is to illustrate which components are needed to fulfill the system
functions. To the extent practical, piping and instrumentation diagrams (P&IDs) should be provided
as the system diagram. For a fluid system or a ventilation system, the system diagram might be some
form of a flow diagram. A P&ID is a system flow diagram that also shows the location of installed
DOE-STD-3024-2011
E-17
Section 27
instrumentation and controls. For an electrical system, the system diagram might take the form of a
one-line diagram. For electronic systems that involve components such as transducers, bi-stable
voltage comparators, and power supplies, a system functional block diagram might be the most
informative. For a computer system, the system diagram might take the form of a combination of a
hardware diagram and a summary logic diagram. In many cases, it may be appropriate to provide a
reference to the system drawing rather than including it in the SDD.
The system diagram shall encompass at least all the major components provided to meet the
requirements of the system. The components shown on the diagram should be identified in the same
manner as the equipment is labeled in the field. Pertinent sizing values should be shown on the
diagram. For example, a fan may be identified as 10,000 cfm, a pump may be labeled as 250 gpm,
and an electrical transformer may be identified as 480V/120V.
This section should also describe any operational or maintenance features that are beyond the design
requirements. For example, a ventilation damper position indicator may have been installed in the
operations center (in addition to the local position indicator) as an enhancement due to operational
problems with that particular damper. These operational problems should be explained in sufficient
detail to provide lessons learned. Appendix D, System History, may also be used to provide a
synopsis of key maintenance and system changes and the associated lessons learned.
4.1.2 Boundaries and Interfaces
Defining the boundaries of the system is important so that components at or near the boundaries are
classified properly and hence receive appropriate attention in activities such as the procurement of
replacement parts and maintenance actions.
The precise boundaries of the system shall encompass all components needed for the system to meet
all of its requirements. This includes mechanical boundaries, electrical boundaries, other support
systems’ boundaries, and instrumentation and controls boundaries. Mechanical boundaries should be
based on components, and not based on a room location. Such components may be capable of
isolating one system from another system. For example, these components might be isolation valves
or dampers, fill and drain valves, vent valves, or safety relief valves. The system boundaries should
extend out to and include such interface isolation devices.
Heat exchangers are typically assigned to the system from which the heat is being removed when the
primary function is to remove heat; or to the system that is being heated when the primary function is
to provide heat. Mechanical support components for piping and duct work should be included in the
primary system, unless a separate facility system has been defined to address such supports
generically.
Electrical boundaries are usually located at circuit breakers. For an electrical power distribution
system, those breakers that route power to other distribution points are usually considered to be part
of the electrical power system. However, those breakers that provide power uniquely to a particular
system are often considered to be part of that system, instead of the electrical power system. For
example, if a particular pump motor gets its electrical power from a specific circuit breaker in a panel,
the breaker may be assigned with the pump motor to the pump system. In this case, the system
boundary for the pump system should be at the input/line/supply side of the circuit breaker, not at the
load side of the circuit breaker.
Section 28
When instrument air is provided to support the functioning of a system, the instrument air
components necessary for the system to accomplish its functions should be part of that system.
DOE-STD-3024-2011
E-18
Where applicable, the boundary of the system should extend out to and include the first upstream
isolation valve in the air supply if the system can still function when the isolation valve is closed.
Sometimes this may be at a check valve associated with an air accumulator.
The instrumentation and controls (I&C) systems usually are not designated as separate systems but
are most often considered integral portions of the system being controlled. The system boundaries
should be determined by the interfaces with the supporting electrical power or instrument air
necessary to make the I&C portions perform properly.
A separate I&C system may include sensors, controls, and signals to actuated equipment, and alarms.
For example, an I&C computer-based system that provides overall operator control for a reactor (or
multiple systems) is typically identified as a separate system. Such an I&C system might include
flow, pressure, and temperature sensors; signal comparators; and alarm, control, and interlock signals.
These signals and controllers may position valves, control motors, provide information and status
displays to operators, provide alarm indicators for operators, and support data recording. If the I&C
system has been designated as a separate system, the boundaries might be selected at the mechanical
output connections to the flow sensor and at the input signal connections to the valve actuator since
these components are typically a part of the system that is being controlled.
Interfacing systems should be defined to the level of detail needed to ensure proper functioning and
support. The most critical of these interfacing systems are “support systems” because they provide
services that are required for the system to perform as described. Electric power (both motive power
and control power), steam power, and instrument air are examples. For the current actual
configuration of the system, the important characteristics of the support systems should be defined.
The system being described may also provide support that is essential to the performance of another
system. For example, a particular control system may be essential for the proper operation of a
ventilation system.
4.1.3 Physical Layout and Location
The system diagram, being schematic in nature, does not identify the location of the equipment or
physical configuration. This section (or another figure) should explain where the equipment is
installed (building, room numbers) and its physical arrangement within each room. Any special
features regarding the installation, location or arrangement of the equipment should be explained.
4.1.4 Principles of Operation
This section should describe generally how the system operates with emphasis on how the system
accomplishes its required functions. This discussion should also describe other operational features
about the system. For ease of understanding, the discussion should use a walk-down approach,
referring to and following the system and subsystem flow paths in the diagram.
Section 29
The description should not be limited to the required performance; rather, it should reflect the full
capabilities and capacities of the installed system. Extra optional capabilities of the system design
beyond that required, such as extra capabilities beyond the safety margins that were added by the
designer or were obtained as part of the procurement process, should be identified to prevent these
from being considered as part of the “safety margin” at some time in the future. For example, a
particular set of components might have been required to be designed for a 0.20 g earthquake, but the
actual equipment was designed and qualified for a 0.35 g earthquake.
DOE-STD-3024-2011
E-19
The discussion should be appropriate to the intended audience of the SDD (e.g., Cognizant System
Engineers, operations, maintenance). This discussion should not be as detailed as an engineering
analysis or so simplistic as to not add value. This discussion should be developed in coordination
with the discussion of the system operational considerations to be provided in Section 4.2,
Operations, to avoid overlap or repetition.
When components of the system are unusual or complicated, the principles of their operation should
be explained. For example, if the system contains a proportional-integral-derivative (PID) controller,
the SDD should summarize its operation. When a system contains multiple components of similar
type (e.g., PID controllers, gamma radiation detectors, sonic level sensors, etc.) a generic description
of the operating principles for each type of instrument or component may be more practical.
4.1.5 System Reliability Features
This section should describe any attributes, features, design or operating characteristics, and other
information important to the reliability of the system. System design characteristics such as preferred
failure modes or “fail-safe” positions or states should be discussed. This section should discuss other
known failure modes of the system and their effects on the system and the facility. (The associated
compensatory measures and recovery action are addressed in Section 4.2.4.) References should be
provided to applicable engineering studies or failure modes and effects analyses (FMEAs), if such
reports are known to exist. Features in the system design that make the system testable should be
described.
Where the system includes redundant subsystems or components, the SDD description should
identify these redundant features. The SDD should describe the capacity and degree of redundancy
provided. For example, a particular design might require the operation of two exhaust fans at all
times, but four fans are provided in the design. If two fans are required, each might be a 50 percent
capacity fan, with two additional 50 percent fans in standby, ready for operation. Also, this section
should discuss independence of the redundant features and any technical limitations on their use. For
example, although four fans are available for operation, a maximum of only three fans is allowed to
be operated at one time to avoid excessive flow rates.
4.1.6 System Control Features
This section should describe the indication, alarm, and control features of the system that are used to
operate the system and monitor its performance. Control logic diagrams should be provided directly
or via a link or reference.
4.1.6.1 System Monitoring
Section 30
The instrumentation, indicators, alarms, and other information provided to operations personnel,
remote and local, to allow assessment of system status and performance should be described,
including types, ranges, and accuracies. This may include indicators, recorders, status lights,
computer monitor displayed information, computer printouts, and information automatically stored on
disks or tapes. The locations of these items should be identified clearly, such as being mounted
directly on the equipment, installed remotely on a nearby control panel, or installed remotely in a
central location.
Instrumentation either directly subject to TSRs or that provides information to verify compliance with
TSRs should be identified as such.
DOE-STD-3024-2011
E-20
4.1.6.2 Control Capability and Locations
System, equipment, and component manual operational controls should be described. The locations
of these controls and the actions caused by actuating these controls should be identified clearly.
4.1.6.3 Automatic and Manual Actions
The SDD should describe the conditions under which important features are to be activated and
whether these features are activated automatically or manually. Where automatic or manual controls
are specifically associated with specific instrumentation, the instrumentation and control actions
should be correlated in the SDD. For example, the control action might be taken only upon reaching
a particular value as detected by a specific instrumentation channel or displayed by a specific
indicating device, or an indicator might provide feedback of system response that shall be closely
monitored.
Where alarms are provided that are intended to trigger manual safety actions, the SDD should provide
an overview of the operator actions that are to be taken and refer to the corresponding operating
procedures that govern the operator responses to the alarms. Alarms for non-safety actions (such as
those that identify the need for operational adjustments or fine tuning) should be described similarly.
Footnotes should be used to point to the particular procedure in the appropriate appendix to the SDD.
This discussion should be coordinated with the discussion in Section 4.2, Operations, related to off-
normal operations in a manner that avoids overlap and repetition.
4.1.6.4 Setpoints and Ranges
This section of the SDD should identify setpoints associated with the system (including pre-trip
alarms) and the purpose of the setpoints. The values of setpoints and other system limitations should
be correlated with the system requirements, especially TSR-required setpoints.
Note: A common practice is including setpoints and limitations information in a set of tables
in a stand-alone document that contains such information for numerous systems. When a
setpoint entry is made into the table, the entry should identify the adjustment by name, where
the adjustment is located physically, where and how the adjusted value is determined, the
nominal value of the adjustment, the range of acceptable values for the setpoint, and the bases
for the values. The acceptable ranges should be specified in actual values, not as tolerances,
percentages, or other approaches that necessitate calculations. The setpoint value should be in
terms of the measured value. For example, the requirement for a ventilation system may be
in terms of ventilation flow rate (cubic feet per minute) while the actual measured value
might be in differential process (psid).
Section 31
Not repeating setpoint data in the SDD may be advantageous in order to avoid the need to revise the
SDD each time a setpoint specification is changed. When complete setpoint data is not provided as
part of the SDD, provide a reference to the governing setpoint information.
Internal controls and adjustments that are beyond the domain of operators but within the domain of
maintenance personnel should be identified. Not all adjustments need to be identified in the SDD;
however, some setpoints affect the limits of performance of the equipment and should be identified in
the SDD. For example, a backup diesel generator may have an automatic trip on overspeed or
overcurrent. The preferred approach to these setpoints is to identify in the SDD those setpoints that
have a direct bearing on the limits of system performance and to present the nominal values of those
setpoints. The SDD should also provide a footnote reference to the maintenance procedures or other
DOE-STD-3024-2011
E-21
information that identifies all the internal setpoints and adjustments and provides the range of
acceptable values.
4.1.6.5 Interlocks, Bypasses, and Permissives
This section should identify interlocks, automatic and manual operating bypasses, permissives, and
other design constraints or conditions associated with the system being described. For example, the
function of a particular safety system may become available automatically after system pressure
exceeds a specified value, but be deactivated below this pressure to prevent inadvertent actuation
when the system is operating within a pressure range for which the safety function is not needed.
Interlocks provided to prevent or permit certain system actions or responses only when specific
conditions are met should be listed. This section also should identify and explain provisions for
manually disabling, bypassing or otherwise altering system performance, and the conditions and
limitations under which they are to be used.
4.2 Operations
When procedures exist, this section should provide an overview of system operations to enable the
reader to gain an understanding of the scope and intent of the approved procedures. The system
operations should be described in a general manner that will aid the reader in understanding the
detailed procedure steps, their required sequence, and how the system operations is integrated with
facility operations. This section should identify good practices related to the operation of the system
that operations personnel have voluntarily adopted. For example, operations personnel may have
assigned equipment nomenclatures and equipment labeling in accordance with a particular good
practices guide.
4.2.1 Initial Configuration (Pre-startup)
Some systems are required by their safety basis or other external requirement to be verified (e.g., by
system walkdown or status checks) in the proper configuration for system operation prior to those
systems being started. When this is the case, the SDD should describe the pre-startup configuration
in general terms and provide a reference to the applicable procedure(s).
Note: As described in previous sections, footnotes should be used to refer to procedures for
system operations.
4.2.2 System Startup
This section should summarize the key steps in the startup procedure and refer to the corresponding
procedure.
Section 32
Particular attention should be drawn to the startup sequence, any timing that is involved, and how it is
determined that the system is ready for the next step. Finally, this section should describe how to
determine if the system was started up successfully or unsuccessfully.
4.2.3 Normal Operations
This section shall identify all the normal operating modes of the system, describe when each mode is
appropriate, and explain generally how mode changes are accomplished. A reference should be
provided to the procedures that cover system operations, including operational mode changes, to the
extent that such procedures exist. A footnote that refers to a particular referenced item in the
appropriate appendix to the SDD may be convenient. This section should then focus on and generally
describe the most frequently-used mode of operations, including routine checks on system
DOE-STD-3024-2011
E-22
performance and performance data logging by the operations staff to verify that the system is
operating normally, including the key parameters and their nominal values. Those surveillance
actions performed by maintenance staff should be identified in Section 4.3.
This section should identify the types of automatic records or logs that are maintained by or for the
system in the central control area, including any equipment status changes that are “alarmed” during
normal operations.
This section should also briefly address conduct of operations as it applies to this particular system.
For example, at shift turnover, certain types of information about how this system is functioning
might be appropriate or required. Then a reference should be provided to the specific procedure that
provides the details for these aspects of the operation of the system.
4.2.4 Off-Normal Operations
This section shall identify off-normal conditions for or during which the system is intended to
operate. Off-normal events range from simple, ordinary events such as the failure of a particular
component, to anticipated system upsets (such as loss of cooling or lubrication, excessive leakage, or
high radiation levels), to unlikely events such as a fire, explosion, or earthquake. For each off-normal
event, this section should identify how the upset would be detected, describe the impact of the event
on functional capability of the system, and, to the extent appropriate, describe the impact on the
facility.
This section should summarize briefly the recovery actions for each type of off-normal condition.
Some facilities use what are called “Alarm Response Procedures” that define pre-planned, reviewed,
and approved actions that operators are to take when particular alarms are activated. Typically, such
procedures will identify each important alarm that requires action, describe what conditions will
cause that alarm to activate, define those few immediate operator actions, and then define the less-
urgent, follow-up actions appropriate to that alarm. This section should provide a reference to the
appropriate documents for recovery actions.
4.2.5 System Shutdown
If the system must be shut down in a particular sequence or with special timing, those system
shutdown actions should be summarized and a reference to the corresponding procedure provided.
4.2.6 Safety Management Programs and Administrative Controls
Section 33
This section should identify the aspects of safety management programs that apply to the system
being described. This discussion should focus on the unique aspects of the application of those
programs (such as radiation control and configuration management) and simply reference the general
programs that apply to many systems at the facility.
This section should identify administrative controls placed on the system and/or its operation, and
reference the associated procedures. If general access to the equipment of the system is restricted in
any way, those restrictions should be identified in general terms.
4.3 Testing and Maintenance
When procedures exist, this section should provide an overview of testing and maintenance activities
so as to enable the reader to gain an understanding of the scope and intent of the approved procedures.
These activities should be described in a general manner that will aid the reader in understanding the
DOE-STD-3024-2011
E-23
detailed procedure steps, their required sequence, and how system maintenance supports facility
operations. This section should identify good practices related to the system that maintenance
personnel have voluntarily adopted. For example, maintenance personnel may have decided that all
battery testing will be performed in accordance with a particular national standard.
4.3.1 Temporary Configurations
Situations under which temporary configurations are used during surveillance or maintenance should
be identified and described in the SDD. The SDD should state the operational limitations on the use
of those configurations and should refer to the applicable governing procedures.
Temporary configurations may be needed to conduct surveillance, testing, inspection, and
maintenance activities properly. For example, it might be necessary to lift leads temporarily so that
the fire deluge system will not be activated during the test of the fire detection system. In most cases,
operational limitations on the use of such temporary configurations may impact system availability.
For example, redundant sets of equipment might not be allowed to be jumpered out, bypassed, or
otherwise rendered out of service at the same time. Another type of limitation might be time
constraints on how long lifted leads, jumpers, bypasses, etc., are permitted to be in use, especially
where operability is a factor. The SDD should define compensatory measures required during the
time the equipment is not operable or is out of service. Another limitation might be special
provisions in procedures to control the use of such temporary configurations adequately, including
removal verifications, especially if the use or misuse of such configurations could affect safety or
availability.
4.3.2 TSR-Required Surveillances
When the system being described is the subject of TSR Surveillance Requirements, the SDD shall
summarize the methods used to meet the requirements in this area (including confirmation that the
acceptance criteria have been met), and refer to the procedures used to implement these requirements.
4.3.3 Non-TSR Inspections and Testing
When the system being described is the subject of non-TSR inspection, testing, or surveillance
requirements, the SDD should summarize the methods used to meet the requirements in this area
(including confirmation that the acceptance criteria have been met), and should provide references to
the implementing procedures.
4.3.4 Maintenance
Section 34
This section is aimed primarily at meeting the needs of maintenance personnel, although it contains
some information that is important to operating personnel. This information is also important to the
Cognizant System Engineer responsible for all aspects of the system, which includes testing and
maintenance actions. This section should summarize the routine actions required by preventive
maintenance procedures and post-maintenance modification testing procedures. This section should
provide references to appropriate maintenance procedures or technical manuals.
4.3.4.1 Post-Maintenance Testing
This section should explain the extent to which a post-maintenance testing program is applied to the
system. It shall identify key performance or acceptance criteria that are required to be satisfied or
verified during post-maintenance testing (for the system to fulfill its functions identified in the
hazards and accident analyses). This section should provide the applicable references to post-
maintenance testing procedures and any additional operability considerations. For many systems,
DOE-STD-3024-2011
E-24
both the TSR and non-TSR inspections and tests will have been described in earlier sections of the
SDD; therefore, those sections should be referenced as appropriate.
4.3.4.2 Post-Modification Testing
In some cases, the maintenance organization also serves as the construction or installation
organization for system modifications. In such cases, care should be taken to ensure that change
activities are recognized as different from maintenance. The SDD should explain the extent to which
a post-modification testing program applies to the system being described. As in the previous section,
both the TSR and non-TSR inspections and tests already may have been described in earlier sections
of the SDD; therefore, those sections should be referenced as appropriate.
4.4 Supplemental Information
Some have found it beneficial to address supplemental topics in the SDD in order to facilitate other
considerations, including the Unreviewed Safety Question process. This section may include the
following topics:
a. Summary of potential system and component failures and reference to any failure
modes and effects analyses (FMEA) or related analyses, failure modes,
probability/likelihood consequences (effects of failures) and mitigative features
b. Margins of safety in the design
c. Optional extra performance capabilities
d. Summary of critical engineering studies and calculations
e. System limitations and precautions
f. Other
DOE-STD-3024-2011
E-25
APPENDICES TO THE SDD
Appendix A: Source Documents
This appendix should contain the bibliographical information for documents that are referenced in the
body of the SDD. Separate appendices may be included for documents of various types, such as
design documents, procurement documents, vendor documents, etc., or a single appendix may be
subdivided into sections that address different document types.
Appendix B: System Drawings and Lists
This appendix should identify the diagrams and drawings and other relevant information provided in
separate documents, tables, or lists associated with or affecting the system being described. These
include physical arrangement diagrams, isometric drawings, installation drawings, P&IDs, functional
control diagrams, process flow diagrams, schematic and one-line diagrams, wiring diagrams, sketches
of particular portions or features of the system, load lists, setpoint tables, and instrument calibration
lists.
Section 35
This appendix should also identify (but not duplicate) master equipment lists, parts lists, Bills of
Materials, and lists showing the hierarchy of drawings that are pertinent to the system being
described.
To avoid unnecessary revisions of the SDD, this tabulation of the system drawings should not include
specific revision numbers/letters or revision dates. Instead, this appendix should state that the most
recently approved version is to be used.
Appendix C: System Procedures
This appendix should contain a listing of the procedures associated with or affecting the system being
described. In a manner similar to the System Drawings appendix, this appendix should avoid specific
revision information. Procedures should be listed in groups according to their general type; for
example, operating procedures, TSR surveillance procedures, and maintenance procedures.
Appendix D: System History
This appendix is optional and may be more appropriately maintained in the CSE System Notebook,
Facility Maintenance History, or other facility record. If included, this appendix should list those
system modifications or changes considered to be of significance, such as those that result in changes
to requirements, bases, TSRs, and setpoints. The maintenance and repair actions considered to be of
major significance should also be identified. Each such modification or change and maintenance or
repair action should be briefly summarized and the appropriate documentation referenced, such as
design change packages or work packages. System history information may be kept in separate
referenced files or systems.
This section should also include applicable lessons learned from testing, start-up, and operations.
DOE-STD-3024-2011
F-1
APPENDIX F: COMPILING TECHNICAL INFORMATION FOR THE
DEVELOPMENT OF SDDS
A key variable in determining the level of effort involved in development of an SDD is the amount of
effort required for locating, screening, and reviewing source documents, and extracting the desired
information from them. The more technical information used, the more useful the resulting SDD will
be. Facility management should establish a plan for collecting and reviewing design information.
This attachment provides information that can help with that plan.
1. AVAILABILITY OF DESIGN INFORMATION
Field experience in both the commercial nuclear industry and the DOE nuclear complex indicates that
some virtually new facilities have already “lost” important design information that once existed, and
that many “existing” facilities, including those dating back to the 1940s, have design information still
on hand or reasonably retrievable. The need to capture the design information when it was produced
was not recognized, and as a result, it may have been simply discarded at the end of the design effort.
The same may be true for modifications to existing facilities. At some new DOE facilities, a
moderate amount of information is on hand but some essential information is no longer available. At
others, a moderate amount of information is on hand, but the reliability or trustworthiness of the
information is questionable. At a few DOE Sites, a vast amount of highly trustworthy information is
available.
For all new Hazard Category 1, 2 or 3 nuclear facilities or for select high hazard facilities for which
this Standard is to be applied, it is important to define, as specific contract deliverables, the data that
should be captured early in the preliminary design stage on a system-by-system basis. This will
ensure that the data is methodically captured and maintained from the beginning.
Section 36
Whether a facility is new or an existing facility is not a significant factor in developing SDDs; rather,
development is affected by the amount of design information needing to be captured, and whether
that information is on-hand or can be retrieved within reasonable efforts.
2. THE DOE-STD-3009 APPROACH
DOE-STD-3009 provides a sound approach to establishing the important technical requirements for
safety SSCs that are used in the development of DSAs to meet 10 CFR 830. That approach involves
a combination of two points: 1) using design information that is immediately available or can be
retrieved through reasonable efforts; and 2) developing new information regarding the functional
requirements as part of the process hazards analysis effort in sufficient detail to support the safety
analysis. Documented engineering judgments (including their bases) can be used to extrapolate
existing information and thereby establish the performance capabilities of the existing systems. The
assumed performance capabilities can often be verified against records of operating experience or by
testing at relatively small costs. These capabilities, once verified to be adequate by analysis and
validated in the field, then become requirements. This approach has technical merit and is suggested
by OSHA in its rulemaking regarding the process hazards analysis program. When sufficient
technical information is not on hand or reasonably retrievable, this second method is recommended.
DOE-STD-3024-2011
F-2
3. DOCUMENT RETRIEVAL
Efforts to retrieve design information have sometimes been limited to searches only for specific types
of information under the perception that such a limitation will lead to cost-effective results. Although
general decisions regarding how far to look for information can be made and are valid, experience has
shown that a priori limiting the search to certain types of information may neither be effective nor
efficient.
Reasonable general limitations can be placed on the search for design information. A recommended
approach is to try to identify the most promising locations and search only those places. Identifying
those locations that are most likely to have the desired information is usually possible. Contacting
long-term technical staff to learn where key documents are should be an early step.
An important management consideration is to know when to stop. To facilitate answering this
question, management must understand the information needed and the types of documents that are
likely to contain the information. Engineers with design experience can usually describe what types
of documents typically are produced for different types of systems and components. The search can
be stopped upon completion of reasonable efforts to retrieve the types of documents that would be
expected to contain the needed information. Compiling all information and data should not be a
requirement to begin the SDD development process. Cost effectiveness may be gained by obtaining
readily available information and data on the system, then developing a draft of the SDD from which
a determination can be made as to any additional information that is needed. Typically, this will
result in a parallel SDD development and information search that supports phased and graded
approaches to the development of an SDD.
4. REVIEWING RETRIEVED DOCUMENTS
The Cognizant System Engineer should ascertain which of the retrieved documents contain
information that is applicable to the current configuration of the facility.
Section 37
A question arises about what to do with documents that are not related to the current SDD task. Some
suggest disposing of the documents or sending them to Records Management. An approach might be
to make a list of the documents found, to be maintained in the System Notebook. Another approach
used by some facilities to establish the initial baseline is to conduct the search/retrieval process for all
the SDD systems as one consolidated task and to keep an inventory of other documents found for
broader future uses. These or other approaches result in an SDD project document list (PDL) for
future reference. Some facilities have chosen to include this PDL as an appendix in the SDD so as to
document and preserve this information. Some facilities have recognized further benefits from a
PDL, such as providing the basis for determining that necessary information/documents for the
system are in the “Master Document List” or in records management for ready retrieval. Maintaining
a PDL may also assist engineers and management in determining when to stop searching for
information.
Having retrieved some documents related to the system, one effective approach is to organize and sort
the documents by system, then by type of document (reports and studies, analysis, calculations,
drawings, specifications, procurement documents), and finally by document date with the most recent
documents on top.
Older records are not likely to be segregated as safety design information and non-safety design
information. Including this non-safety information in the SDD at the same time that safety data is
being captured is cost-effective.
DOE-STD-3024-2011
F-3
5. RESOLVING CONFLICTING INFORMATION
When information in one source document does not agree with information in another source
document, the Cognizant System Engineer may be able to identify information that is outdated and no
longer applicable. However, sometimes the conflicts cannot be easily resolved. In such cases, the
conflict should be formally documented and tracked until it is resolved. Keeping a log of open items
for the SDD for this purpose is recommended.
The open items need to be reviewed to determine if any are safety significant. Safety-significant open
items should be treated as discrepancies within the facility non-conformance program. Also, the
discrepancies need to be reviewed to determine whether they have an impact on the operability of any
systems, or any reportable occurrences. Open items that are not safety-significant but involve critical
information that could have an adverse impact on facility operations also should be formally tracked
to closure.
6. MISSING INFORMATION
With the retrieval of design information completed, a determination should be made regarding what
information may still be missing and if any of that information is truly critical to safety or to effective
and efficient operations. If the missing information is not critical, no more time or money should be
invested in perfecting the data bank. If the missing information is critical, a plan should be developed
to recover that information. In a few cases, calculations or analyses might have to be regenerated.
DOE-STD-3024-2011
G-1
APPENDIX G: APPLICATION OF THE GRADED APPROACH TO
THE DEVELOPMENT OF SDDS
Section 38
Substantial flexibility is allowed for the development of SDDs to address priorities and resources
available to the facility. This appendix addresses the systems for which SDDs may be appropriate
and the application of the graded approach to SDDs, including phased development. The DOE
should provide direction to the contractor via the Contracting Officer if the DOE expects to have
SDDs or FDDs developed for specific systems beyond safety class and safety significant active
systems. If the contract does not require the implementation of this Standard, then the DOE may,
through the Contracting Officer, define a subset (graded approach) of SDDs they wish to see
developed. For new construction, the level of detail and number of SDDs should be defined as part of
the contract deliverables at the beginning of design, with a focus on assuring that DOE has sufficient
information to effectively implement DOE O 420.1B. The graded approach for a new project is to be
defined in the project-specific QA Plan per DOE O 414.1C. Phasing of the development of the SDDs
against the design process should also be defined at the beginning of design. Phasing could be based
on the state of design (e.g., all SDDs initiated but only for those sections that can be supported by the
design state completed), by safety system, or by equipment procurement status.
The use of an enterprise system rather than hard copy documents should be considered and
encouraged for new projects.
1. FACILITY CATEGORIZATION
The graded approach should be applied based on a number of considerations, including the hazard
categorization of the facility (in accordance with DOE-STD-1027) and the function of the system.
Appropriately graded levels of effort could then be established, each of which would provide system
requirements and system description information. At a Hazard Category 1 nuclear facility, the
decision might be, for example, that a facility design description (FDD) will be developed and SDDs
will be developed for all safety and mission- critical systems. At a Hazard Category 2 nuclear
facility, the decision might be, for example, that SDDs will be developed only for safety SSCs. At a
Hazard Category 3 nuclear facility, the decision might be, for example, that separate SDDs will not be
developed, but instead, an FDD will be developed that describes the facility from an overall
perspective and summarizes all the SSCs. Such an FDD would most likely emphasize the system
requirements and system descriptions for each system.
2. FACILITY REMAINING LIFETIME
The useful life of the completed SDD should be long enough to make it worth the resources expended
to develop the SDD. If the remaining lifetime of the facility is less than five years, development of
SDDs may not be considered worthwhile. However, if the facility is required by its safety analysis to
contain a significant source term for a number of years, SDDs are effective to convey needed
information across staff or contract changes. The contractor should formally document the decision
and basis for that decision if SDDs are not developed for Hazard Category 2 nuclear facilities.
3. SSC CLASSIFICATION
The systems within the facility should be classified in accordance with 10 CFR 830. The system
importance classification should be used to determine which systems need to have SDDs developed.
All active safety SSCs should have SDDs developed (safety SSCs include both safety-class SSCs and
safety-significant SSCs). Development of SDDs for passive safety SSCs should be determined and
Section 39
DOE-STD-3024-2011
G-2
documented on a case-by-case basis, depending on the complexity of the passive SSC and the needs
of the facility. Developing SDDs for environmental-protection and mission-critical systems is also
encouraged, especially if the system fulfills a regulatory requirement.
4. GRADING WITHIN AN SDD
When the decision has been made to develop an SDD for a particular system, the graded approach
determines the level of effort to be applied during development. The factor that will have the greatest
effect on the level of effort required to develop an SDD is the complexity of the system involved.
Simple systems might yield an SDD of only a few pages. Complex systems might necessitate many
pages to describe requirements, bases, and operational aspects.
The topics to be addressed in an SDD may be adjusted. The most important active systems would
have SDDs that are the most comprehensive. Less important systems or passive safety systems might
not warrant the cost of developing such comprehensive SDDs. For example, sections of the outline
such as “Operations” (Appendix E, Section 4.2) and “Testing and Maintenance” (Appendix E,
Section 4.3) might be considered for omission. When a section is not included, the author should
provide a brief explanation as to the basis for excluding the information.
Having determined which topics of the outline need to be addressed in an SDD for a particular
system, the next consideration is the level of detail to which a topic should be addressed. For
important systems, a particular topic in the outline may warrant a page or more of discussion. For a
less important system, that same topic may warrant one paragraph or simply a reference to
appropriate procedures. This is particularly pertinent with regard to Section 4 of the SDD.
The graded approach is not used to justify inaccuracies in SDDs. Bad information is worse than no
information. Care should be exercised to ensure that all statements, tables, drawings, and other
information in an SDD are accurate, regardless of the system classification and the graded approach.
5. PHASED APPROACH
In addition to the decisions regarding which systems warrant SDDs and the extent of the content of
particular SDDs, another consideration is whether to schedule or divide the development of those
SDDs into time phases. For example, SDDs for safety-class systems might be developed during the
first year, followed by SDDs for safety-significant systems the second year. The remaining SDDs
would be scheduled for subsequent years. This approach is particularly relevant for existing systems.
The content of the SDDs should be scheduled for development in stages, particularly for new
projects/designs and for major upgrades of existing facilities (e.g., line item upgrades). For example,
the system requirements and bases would be developed for all SDDs early in the project and issued to
the project team. Then, as additional information becomes available during the subsequent design
and construction phases, the SDDs would be updated (and issued) by developing the additional
sections, or further developing sections initiated in prior revisions. Population of particular sections
should be based on when the information for that section is available.
DOE-STD-3024-2011
H-1
APPENDIX H: PREPARATION OF FACILITY DESIGN
DESCRIPTIONS (FDDs)
Section 40
Facility Design Descriptions (FDDs) generally should be prepared using the guidance contained
within this document for SDDs. However, the content of FDDs should focus on facility SSCs (e.g.,
structural features, architectural features, site features), systems that are facility-wide that are not the
subject of an SDD (e.g., potable water system, electrical distribution system), and information that is
common to multiple systems (e.g., acceleration spectra). The limitations section of the FDD should
clearly state the boundaries of information contained within the document.
For some facilities with limited systems, only an FDD should be developed. This particularly should
be considered where the facility does not contain any active SC/SS systems. In other facilities, where
the number of systems is very small, it may be more appropriate to develop only SDDs. No
requirement exists that a facility requires both FDDs and SDDs.
The FDD should be a higher level document than the SDDs and, in many cases, should contain details
on overall facility functions, facility systems that support process systems (e.g., electrical distribution
system) in lieu of placing this information in SDDs. The SDDs should then refer to the FDD for the
higher level functions, requirements, and programs. The FDD should also reference any lower tier
SDDs for further details that are specific to those systems.
The structure of the FDD should be similar to the SDD outline format with a few exceptions. In most
cases, the SDD sections should be placed in the FDD with “facility” replacing “system.” The FDD
should clearly distinguish content of facility SSCs and minor systems not within the scope of SDDs,
such as potable water. Instead of a system diagram in Section 2.3, Basic Operational Overview, the
FDD should contain a simplified facility plan diagram. In addition, in any section discussing
boundaries/interfaces, the FDD should delineate facility SSCs and boundaries/interfaces with any
systems that are in SDDs.
Section 3, Requirements and Bases, of the FDD should contain requirements and bases that apply to
the overall facility such that they need not be repeated in lower tier SDDs. For example,
programmatic requirements, general nuclear criticality safety requirements for facility draining (e.g.,
floor design with sloping), mezzanines, structural columns, and seismic spectra that apply to all SSCs
in the facility would be examples of content ideally placed in the FDD rather than repeated in each
SDD. Many sections in the SDD outline may not apply to the FDD (e.g., Section 3.1.5, Operability)
and may be omitted from the FDD. In Section 3.2.6, human interface requirements and logical
layouts should be included in the FDD. For better division in the FDD, Section 3 may be applied to
the facility and an identical Section 4 may be used for SSCs that are in other systems not covered in
SDDs, such as potable water system.
The last section in the FDD (Section 4 or 5) is the Facility Description. The subsections in this
section should contain, at a minimum: description of facility SSCs, description of
boundaries/interfaces with other SSCs, and description of layout and location. Principles of operation
and description of controls, setpoints, and ranges should be included if applicable.
The appendices in the FDD should include the following, at a minimum:
Appendix A: Source Documents
Appendix B: Facility Drawings
Appendix C: System Design Descriptions
Appendix D: Facility-Level Procedures
Section 41
DOE-STD-3024-2011
H-2
Appendix E: Facility History (including significant facility-wide changes and additional
facility projects)
DOE-STD-3024-2011
Concluding Page 1
CONCLUDING MATERIAL
Project Number: Preparing Activity: Preparing Agent:
EDCO-0001 Office of Nuclear Facility Ms. Ashley Ruocco
Safety Programs (DOE-HS-32)
Review Activities:
Headquarters Offices
National Nuclear Security Administration
Office of Health, Safety and Security
Office of Environmental Management
Office of Nuclear Energy
Office of Science
Office of Management
Site Offices
Ames Area Office
Argonne Area Office
Brookhaven Site Office
Carlsbad Field Office
Chicago Operations Office
Fermi Area Office
Idaho Operations Office
Los Alamos Site Office
Livermore Site Office
Nevada Site Office
NNSA Service Center
Oak Ridge Operations
Office of River Protection
Pantex Site Office
Portsmouth/Paducah Project Office
Richland Operations Office
Savannah River Operations Office
Savannah River Site Office
Sandia Site Office
West Valley Demonstration Project
Y-12 Site Office
External Agency
Defense Nuclear Facilities Safety Board