DOE-STD-3003-2000, Backup Power Sources for DOE Facilities
Functional areas: Backup Power, Power Supplies, Critical Power Supplies, Batteries, Safety Class Equipment, Emergency Power
The purpose of this Standard is to document good engineering practices for the installation, testing, and maintenance of BACKUP POWER SOURCES at DOE facilities.
Unknown Block text
Version history and related documents
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
TS
DOE-STD-3003-2000
January 2000
Superseding
DOE-STD-3003-94
September 1994
DOE STANDARD
BACKUP POWER SOURCES FOR DOE
FACILITIES
U.S. Department of Energy AREA EDCN
Washington, D.C. 20858
DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.
METRIC
This document has been reproduced directly from the best available copy.
Available to DOE and DOE contractors from ES&H Technical Information
Services, U.S. Department of Energy, (800) 473-4375, fax: (301) 903-9823.
Available to the public from the U.S. Department of Commerce, Technology
Administration, National Technical Information Service, Springfield, VA 22161;
(703) 605-6000.
DOE-STD-3003-2000
iii
FOREWORD
1. This Standard is approved for use by the U.S. Department of Energy (DOE). This
Standard is not a DOE Order, and its requirements are not automatically invoked at any
facilities or on any BACKUP POWER SOURCES. This Standard is intended for use by the
operations/field offices or management and operating (M&O) contractors at their discretion.
Activities applying this Standard must tailor the requirements to the specific application as
discussed in 6.3. This Standard may be invoked by contractual documents, procurement
documents, or in the authorization basis for a facility. Unless it is invoked as above, the
contractor will not be assessed or inspected against its requirements. This Standard is also
suitable for voluntary use by engineers responsible for BACKUP POWER SOURCES at DOE
facilities.
2. Acronyms used in this Standard are defined in Section 3 and are therefore not
spelled out at their first occurrence. Terms defined in Section 3 are CAPITALIZED in the text.
3. Beneficial comments (recommendations, additions, deletions) and any pertinent data
that may improve this document should be sent to: DOE Backup Power Working Group, in
care of John Fredlund, DP-45 GTN, U.S. Department of Energy, 19901 Germantown Road,
Germantown, MD 20874-1290. The back page of this document may be copied for this
purpose.
4. This Standard was prepared in cooperation with and using input from the members
of the Backup Power Working Group (BPWG).
The charter of the group is as follows:
The DOE BPWG fosters safe, practical, and effective testing, maintenance, operation, design,
and installation of systems and equipment used to provide backup electrical power at DOE
facilities. The BPWG provides an open forum on standard practices, safety issues, training,
and solutions to problems encountered at DOE facilities. The BPWG promulgates its learning
throughout the DOE complex and industry.
To fulfill its charter, the BPWG will:
* Share practical design and operating experience with BACKUP POWER SOURCES by
promoting a continuing exchange among DOE contractor personnel, Headquarters
(HQ), Operations Offices, and industry.
* Examine existing standards applicable to BACKUP POWER SOURCES and adopt,
endorse, or tailor them for DOE applications.
* Identify and apply techniques to achieve and maintain reliability and availability
commensurate with mission/safety objectives.
* Promote worker safety, public safety, protection of the environment, and the DOE
mission in the application of BACKUP POWER SOURCES.
* Exchange successful and cost-effective management techniques.
DOE-STD-3003-2000
iv
* Identify potential means for coordination of training among DOE facilities.
* Discuss graded approaches for conformance with DOE orders.
Section 2
In the course of meeting this obligation, the BPWG was instrumental in the development and
adoption of this Standard. The BPWG provides unique expertise (by virtue of its involvement in
the development of this Standard and its responsibilities within the organizations maintaining
BACKUP POWER SOURCES) to beneficially impact the reliability of BACKUP POWER
SOURCES through promotion and facilitation of the use of this Standard. For information on
the BPWG, see http://www.dp.doe.gov/CTG/bpwg/bpwg.htm or contact John Fredlund, DP-45,
phone (301) 903-3059.
5. ENGINE GENERATORS, UNINTERRUPTIBLE POWER SUPPLIES, and
STATIONARY BATTERIES are used to provide electrical power to equipment upon loss of the
normal source when either external (GRID) or internal (plant equipment) failures occur. The
need for this backup power ranges from supplying safety class equipment to convenience
only. BACKUP POWER SOURCES may be classified under a number of different authorities.
Some important aspects of the availability of electrical power are derived from public health
and safety, environmental concerns, plant security, costs related to lost production, damage to
products or equipment, critical operating considerations, compliance with Occupational Safety
and Health Administration (OSHA) requirements, and communications. Reliable performance
of the required functions of backup and emergency sources can be ensured through proper
engineering, installation, appropriate testing, and maintenance. This can be seen from a
University of Dayton Research Institute study of diesel generator failures that resulted in
several recommendations to improve diesel generator reliability (see Appendix I).
6. This Standard identifies fundamental criteria, surveillance testing, reporting, and
reliability program considerations, which if properly implemented, should improve and maintain
capable and reliable backup and emergency power sources. Maintenance programs for
BACKUP POWER SOURCES are also required by DOE 4330.4, Maintenance Management
Program.
7. In the process of developing this Standard, industry standards (including those of the
National Fire Protection Association (NFPA), and the Institute of Electrical and Electronics
Engineers (IEEE)) and guidance were reviewed. This Standard incorporates those
requirements and guidance from industry standards considered appropriate for backup power
system equipment important to worker safety and/or the DOE mission at DOE Hazard
Category II facilities. Category I facilities (as defined in DOE STD-1027-92) may place more
stringent requirements on design, maintenance and testing commensurate with the safety
significance of the power source.
8. This 2000 revision of this standard was unanimously supported by users from
several DOE sites. It has been updated and slightly rearranged. Several requirements were
softened based on field experiences. Section 4.1 was changed to take advantage of DOE-
STD-3024. Sections 5.3.1 and 5.4.1 were reworded to take advantage of DOE-SPEC-3018,
DOE-SPEC-3019, and DOE-SPEC-3021.
DOE-STD-3003-2000
v
CONTENTS
PARAGRAPH PAGE
FOREWORD . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . iii
Section 3
1. SCOPE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.1 Applicability . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.2 Purpose . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.3 Background . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
2. APPLICABLE DOCUMENTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
2.1 Government documents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
2.2 Non-Government publications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
3. DEFINITIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
4. GENERAL REQUIREMENTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
4.1 System Design Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
4.2 Conflicting Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
4.3 Control of changes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
4.4 Ownership . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
4.5 User(s) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
4.6 Identification plaque . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
4.7 Maintenance requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
4.7.1 Maintenance records . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
4.7.2 Coordination . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
4.7.3 Centralized Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
4.8 Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
5. DETAILED REQUIREMENTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
5.1 Requirements applicable to all BACKUP POWER SOURCES . . . . . . . . . . . . . . . 8
5.1.1 Internal events . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
5.1.2 External events . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
5.1.3 OUTPUT BREAKERS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
5.1.4 Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
5.1.5 Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
5.2 EG Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
5.2.1 EG capabilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
5.2.2 Qualification of maintenance personnel for EGs . . . . . . . . . . . . . . . . . . 13
5.2.3 EG testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
Section 4
5.3 UPS system requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
5.3.1 UPS capabilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
5.3.2 Maintenance and repair of UPS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
5.3.3 Testing of UPS systems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
5.4 STATIONARY BATTERY system requirements . . . . . . . . . . . . . . . . . . . . . . . . . . 17
5.4.1 Battery system capabilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
5.4.2 Battery maintenance, testing, and surveillance . . . . . . . . . . . . . . . . . . . 18
6. NOTES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
6.1 Intended use . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
DOE-STD-3003-00
vi
6.2 Revision status . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
6.3 Tailoring guidance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
6.4 Subject term (key word) listing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
APPENDIX I . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
APPENDIX II . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
CONCLUDING MATERIAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32
DOE-STD-3003-2000
1
1. SCOPE
1.1 Applicability. This Standard
establishes fundamental requirements and
guidance for BACKUP POWER SOURCES
at DOE facilities.
1.2 Purpose. The purpose of this
Standard is to document good engineering
practices for the installation, testing, and
maintenance of BACKUP POWER
SOURCES at DOE facilities. The term
"BACKUP POWER SOURCES" as used in
this Standard covers both "emergency" and
"backup" power applications. These sources
typically supply loads used to protect health
and safety of the public, workers, and the
environment; and to reduce the
consequences of postulated events involving
nuclear, chemical, or other hazards or having
an adverse impact on the DOE mission. This
Standard applies to design and operating
practices for both permanent and temporary
installations used while permanent power
sources are being serviced. Examples of
BACKUP POWER SOURCES covered by
this Standard are those which supply power
to nuclear safety systems, radiation monitors
and alarms, fire protection systems, security
systems, data processing equipment, and
emergency lighting. The significance of each
individual BACKUP POWER SOURCE
application should be analyzed to determine
the design requirements and classification
levels. See 4.1 for more information on the
significance of BACKUP POWER
SOURCES. This Standard does not provide
criteria to establish the need for or level of
importance of BACKUP POWER SOURCES.
This Standard is not intended and should not
be used as the sole source of information to
develop design requirements for specific
applications. Other requirements such as
those found in DOE Order 420.1, Facility
Safety, may apply to BACKUP POWER
SOURCES depending on their application.
The many appropriate recommended
practices presented in this Standard should
be implemented to maintain the reliability and
availability of BACKUP POWER SOURCES
Section 5
at acceptable levels for both nuclear and
non-nuclear safety applications.
1.3 Background. As a result of
concerns expressed by former Secretary of
Energy James D. Watkins over the number
of incidents where BACKUP POWER
SOURCES failed to provide electrical power
during tests or actual demands, an
Augmented Evaluation Team (AET) was
formed to evaluate the reliability and
availability of BACKUP POWER SOURCES
at DOE DP facilities. The AET conducted a
series of on-site reviews for the purpose of
understanding the design, operation,
maintenance, and safety significance of
emergency and backup power supplies. The
AET found that the quality of programs
related to maintenance of backup power
systems varied greatly among the sites
visited (and often among facilities at the
same site), and identified areas where the
reliability of emergency and backup power
systems should be improved. This Standard
was originally developed to provide a vehicle
for BACKUP POWER SOURCE reliability
improvement to respond to the Secretary's
concern and the findings of the AET.
DOE-STD-3003-2000
2
2. APPLICABLE DOCUMENTS
Unless otherwise specified by contract,
solicitation, or purchase order, the current
issue of the following documents form a part
of this document to the extent specified
herein.
2.1 Government documents.
2.1.1 DOE standards, handbooks,
technical standards lists (TSLs), and
specifications.
DOE-STD-1027-92 - Hazard
Categorization and Accident Analysis
Techniques for Compliance with DOE
5480.23, Nuclear Safety Analysis
Reports
DOE-STD-1073-93 - Guide for
Operational Configuration Management
Program including the Adjunct Program
of Design Reconstitution and Material
Condition and Aging Management
DOE-STD-3024-98 - Content of System
Design Descriptions
DOE-SPEC-3018-96 - Flooded-Type
Lead-Acid Storage Batteries
DOE-SPEC-3019-96 - Valve-Regulated
Type Lead-Acid Storage Batteries
DOE-SPEC-3021-97 - Uninterruptible
Power Supply Systems
DOE-HDBK-1092-98, Electrical Safety
2.1.2 Other Government documents,
drawings, and publications.
DOE O 420.1 - Facility Safety
DOE 4330.4 - Maintenance
Management Program
DOE 5480.23 - Nuclear Safety Analysis
Reports
Federal Specification VV-F-800, Fuel Oil
NRC Publication NUREG/CR 0660 -
Enhancement of On-Site Emergency
Diesel Generator Reliability
NRC Regulatory Guide 1.160 -
Monitoring the Effectiveness of
Maintenance at Nuclear Power Plants
NRC Regulatory Guide 1.9 - Selection,
Design, Qualification, and Testing of
Emergency Diesel Generator Units
Used as Class 1E Onsite Electric
Power Systems at Nuclear Power
Plants
2.2 Non-Government publications.
ANS 59.51 - Fuel Oil Systems for
Safety-Related Emergency Diesel
Generators
ANSI/IEEE Std 944 - IEEE
Recommended Practice for the
Application and Testing of Uninterruptible
Power Supplies for Power Generating
Stations
ASTM D975 - Standard Specification for
Diesel Fuel Oils
ASTM D4057 - Standard Method of
Sampling Petroleum Products
IEEE Std 387 - Standard Criteria for
Diesel-Generator Units Applied as
Standby Power Supplies for Nuclear
Power Generating Stations
IEEE Std 446 - Emergency and Standby
Power Systems for Industrial and
Commercial Applications
IEEE Std 450 - Recommended Practice
for Maintenance, Testing, and
Replacement of Large Lead Storage
Batteries for Generating Stations and
Substations
DOE-STD-3003-2000
3
IEEE Std 484 - Recommended Practice
for Installation Design and Installation of
Vented Lead-Acid Batteries for
Stationary Applications
Section 6
IEEE Std 485 - Recommended Practice
for Sizing Large Lead Storage Batteries
for Generating Stations and
Substations
IEEE Std 762 - Standard Definitions for
Use in Reporting Electric Generating
Unit Reliability, Availability and
Productivity
IEEE Std 1106 - IEEE Recommended
Practice for Installation, Maintenance,
Testing, and Replacement of Vented
Nickel-Cadmium Batteries for Stationary
Applications
IEEE Std 1115 - Recommended
Practice for Sizing Nickel-Cadmium
Batteries for Stationary Applications
IEEE Std 1187 - IEEE Recommended
Practice for Installation Design and
Installation of Valve-Regulated Lead-
Acid Storage Batteries for Stationary
Applications
IEEE Std 1188 - Recommended
Practice for Maintenance, Testing, and
Replacement of Valve-Regulated
Lead-Acid (VRLA) Batteries for
Stationary Applications
NFPA 37 - Standard for the Installation
and Use of Stationary Combustion
Engines and Gas Turbines
NFPA 110 - Standard for Emergency
and Standby Power Systems
NFPA 111 - Standard on Stored
Electrical Energy Emergency and
Standby Power Systems
DOE-STD-3003-2000
4
3. DEFINITIONS
All key terms used in this Standard are
defined below.
3.1 Acronyms used in this Standard.
a. ac - alternating current
b. AET - Augmented Evaluation
Team
c. ANSI - American National
Standards Institute
d. ASTM - American Society for
Testing & Materials
e. BPWG - Backup Power Working
Group
f. C - Centigrade
g. dc - direct current
h. DOE - Department of Energy
i. DP - Defense Programs
j. EG - ENGINE GENERATOR
k. g - grams
l. HQ - Headquarters
m. IEEE - Institute of Electrical &
Electronics Engineers
n. kw - kilowatt
o. M&O - management and
operating
p. mm - millimeters
q. NCR - Nonconformance Report
r. NRC - Nuclear Regulatory
Commission
s. NFPA - National Fire Protection
Association
t. OSHA - Occupational Safety and
Health Administration
u. RCA - Radiologically Controlled
Area
v. RWP - Radiation Work Permit
w. STD/Std - Standard
x. UPS - UNINTERRUPTIBLE
POWER SUPPLY
3.2 Backup Power Source. Power
source used to supply electrical power when
the normal source is unavailable. For
simplicity, this Standard uses the term
"backup" as an all-encompassing term.
"Emergency" is generally used only when the
power source is required for nuclear safety or
to ensure personnel safety.
3.3 Continuous rating. Maximum
continuous power output the EG can
maintain in the service environment without
necessitating deviation from the
manufacturer's recommended scheduled
maintenance.
3.4 Design Requirements. As defined
by DOE-STD-1073.
3.5 Droop mode. Mode in which the EG
speed is governed as a monotonic function
of engine load, used when operating in
parallel with the GRID to avoid instability
problems.
3.6 Engine generator. Independent
electrical power supply unit consisting of an
internal combustion engine (diesel, gasoline)
directly coupled to an electrical generator
with associated instrumentation, controls,
protective features, and auxiliary systems.
3.7 Equalizing charge. A charge
applied to a battery, which is greater than the
normal float charge and is used to completely
DOE-STD-3003-2000
5
restore the active materials in the cell,
bringing the cell FLOAT VOLTAGE and the
specific gravity of the individual cells back to
"equal" values.
3.8 Float voltage. A continuous voltage
supplying a low current from a battery
charger applied to a battery in the standby
mode to make up for internal losses and
maintain the battery in a fully charged state.
Section 7
3.9 Grid. Offsite and/or onsite
interconnected electrical power distribution
system.
3.10 Hot restart. Restart of an EG from
its continuous duty equilibrium temperature.
3.11 Isochronous mode. Mode of
operation of an EG whereby it establishes its
own operating speed to maintain the correct
frequency over the load range capacity of the
EG.
3.12 Load breaker. Breaker that feeds
and protects a load, located between the
power source bus and the load.
3.13 Output breaker. Breaker located
between the BACKUP POWER SOURCE's
output terminals and the bus feeding loads,
intended to protect the BACKUP POWER
SOURCE from various fault conditions and to
provide a means to connect and disconnect
the source from its load.
3.14 Performance Discharge Test. Test
that measures the existing capacity of a
battery, to be compared to its rated capacity.
The usual units of capacity are ampere-
hours.
3.15 Short-time rating. Output rating
(typically 110%) of an EG that can be
sustained for a specified time in a specified
period of operation without necessitating
deviation from normal scheduled
maintenance (usually 2 hours in 24, per IEEE
Std 387).
3.16 Standby conditions. Normal
equilibrium status of an EG ready to receive
a start signal, either cold start or the
conditions maintained by a keep-warm and
continuous lubrication system.
3.17 Stationary Battery. A system
consisting of a group of battery cells
(connected in series, parallel, or combination)
normally operated in parallel with a
charger(s) and a load.
3.18 Synchronization. Bringing one ac
power source of the same nominal frequency
as another into the same frequency and
phase angle of the other in order to avoid
excessive current flow when paralleling two
ac sources.
3.19 Uninterruptible power supply. A
system intended to provide a continuous
source of power, without delay or transients,
upon degradation or failure of the normal
source of power
DOE-STD-3003-2000
6
4. GENERAL REQUIREMENTS
4.1 System Design Description. New
BACKUP POWER SOURCE installations
shall be described in a system design
description according to DOE-STD-3024.
Owners of existing BACKUP POWER
SOURCE installations should consider
preparing a system design description using
DOE-STD-3024 as guidance. Consideration
should include the safety application of the
installation, its importance to DOE's mission,
and the potential consequences of failure (for
example, excessive costs or delays).
When identifying the system functions of a
BACKUP POWER SOURCE, the “System
Functions” section of the system design
description should address the effects of
both normal and BACKUP POWER
SOURCE failures, any need for electric
power for safe shutdown of the facility, and
prevention or mitigation of credible accidents.
The following list gives samples of bases that
may be identified in the “Requirements and
Bases” section of the system design
description.
* Legally required by Local, State and
Federal (Codes and Rules).
* Necessary to prevent release of
materials (radioactive or toxic) harmful
to the public and/or the environment.
* Necessary to protect plant/building
occupants from serious injury or health
effects.
* Necessary for plant security.
* Necessary to prevent damage to
equipment or products (loss of heating,
loss of refrigeration, fire.)
* Necessary to minimize lost production.
* Necessary for plant communications.
* Necessary to maintain equipment for
restoring normal power.
Section 8
The following list gives examples of
requirements that may be addressed in the
“Requirements and Bases” section of the
system design description.
* Load lists with load power requirements
and load functions;
* Load profile/sequence for various
abnormal or accident conditions;
* Method of load transfer or connection to
normal offsite power;
* Reliability or availability;
* Protective features; and
* Equipment control and protective
setpoints.
4.2 Conflicting Requirements. This
Standard does not relieve the contractor from
contractual or other mandatory requirements.
4.3 Control of changes. Modifications
to system design, installation, or
documentation shall be under the auspices of
the facility's formal change control program.
DOE-STD-1073-93 provides guidance for a
facility change control program.
4.4 Ownership. A single specific
organization or individual/position should be
identified as the "owner" for each BACKUP
POWER SOURCE. Typically the "owner" is
the one having possession of equipment and
control of its operation. The owner shall have
the responsibility and authority for ensuring
that appropriate maintenance and testing
activities are performed to sustain equipment
reliability and availability. The owner should
be cognizant of all users and of the types
and safety classifications of all loads on the
power sources. The owner should ensure
that all users are apprised of the types and
classifications of all other users' loads and
the scheduling, problems, and
maintenance/repair/testing activities on
BACKUP POWER SOURCES. Owners
should cooperate with maintenance
organizations in scheduling maintenance
activities. The owner should get concurrence
from the user in the scheduling of all
maintenance/repair/testing activities relative
to the BACKUP POWER SOURCES on
which the user depends.
4.5 User(s). A user is considered to be
a specific organization or individual/position
that uses or depends on the BACKUP
DOE-STD-3003-2000
7
POWER SOURCE. The owner is often one
of the users. Each user should ensure that
the owner is aware of the types and safety
classification of all the user's loads on the
power source.
4.6 Identification plaque. A plaque or
other permanent sign should be located at
the BACKUP POWER SOURCE identifying
the equipment, the owner and the user(s).
4.7 Maintenance requirements.
BACKUP POWER SOURCES shall be
maintained in accordance with DOE 4330.4,
manufacturer’s recommendations, and the
detailed requirements in Section 5. At least
two persons should always be present when
working on backup electrical power systems.
Refer to DOE-HDBK-1092, federal, state,
and local policies for safety practices that
may apply.
4.7.1 Maintenance records. All repairs,
maintenance, and tests for BACKUP
POWER SOURCES shall be documented
and records maintained.
4.7.2 Coordination. Maintenance
organizations should obtain authorization
from users prior to conducting
maintenance/repair/test activities on
BACKUP POWER SOURCES. Scheduling of
maintenance activities should be coordinated
with owners.
4.7.3 Centralized Maintenance. Sites or
facilities should consider whether to establish
centralized maintenance of BACKUP
POWER SOURCES.
4.8 Testing. BACKUP POWER
SOURCES shall be tested in accordance
with Section 5. Detailed step-by-step
procedures shall be provided for performing
testing and surveillance activities. The
procedures shall include the appropriate
information specified in Section 5. Any test
that demonstrates equipment being tested
does not meet a DESIGN REQUIREMENT
shall constitute a failure. Performance data
should be recorded for all tests and actual
Section 9
demands, including tests from standby mode,
monthly/weekly testing, loss of normal power
simulations, and the like. Performance data
should not be recorded for maintenance
troubleshooting activities.
DOE-STD-3003-2000
8
5. DETAILED REQUIREMENTS
5.1 Requirements applicable to all
BACKUP POWER SOURCES. The following
requirements are applicable to ENGINE
GENERATORS, UNINTERRUPTIBLE
POWER SUPPLIES, and STATIONARY
BATTERIES:
5.1.1 Internal events. The BACKUP
POWER SOURCE shall have the capability
to perform its required function over the
expected range of environmental and load
conditions independent of the normal
sources of power. The environmental
considerations shall include the effects of
anticipated operating conditions and failed
plant equipment that may have an adverse
impact on the ability of the BACKUP POWER
SOURCE to perform its function.
5.1.2 External events. The BACKUP
POWER SOURCE, associated distribution
systems, and necessary support systems,
shall be protected against those events likely
to produce a loss of normal power. Examples
of such events are hurricanes (high winds),
tornadoes, floods, ice storms, lightning, fire,
and seismic events. The level of protection
should be related to the expected frequency
and consequences of total loss of ac power
due to the particular event.
5.1.3 OUTPUT BREAKERS. OUTPUT
BREAKER protection and LOAD BREAKER
protection shall be coordinated in accordance
with NFPA 110. A fault on an individual load
or circuit should not trip the BACKUP
POWER SOURCE'S OUTPUT BREAKER.
OUTPUT BREAKERS should have an
interrupt rating greater than or equal to the
maximum available fault current at its
location. OUTPUT BREAKERS should be
located such that a fire at the BACKUP
POWER SOURCE will not damage the bus
feed circuit downstream of the OUTPUT
BREAKER. This should prevent a fire at the
BACKUP POWER SOURCE from causing
the loss of ability to feed loads from the
normal source.
5.1.4 Maintenance. A corrective
maintenance and preventative maintenance
program for the BACKUP POWER SOURCE
and its supporting subsystems shall be
established in accordance with DOE 4330.4.
The program should be based on the
inspection activities, intervals, and parts
replacement periods recommended by the
manufacturer. The program should take into
consideration the type of service to which the
BACKUP POWER SOURCE is subjected (for
example, continuous duty or standby service
with the number of expected demands/year).
The program inspection and replacement
intervals may be adjusted based on
documented experience with the particular or
similar equipment. The level of detail and
rigor applied in a maintenance program
should be appropriate to the significance of
the BACKUP POWER SOURCE'S failure to
function under loss of normal power
conditions. This may result in graded
requirements for maintenance varying from
repair-on-failure to manufacturer-
recommended periodic maintenance, or other
based on documented experience and failure
analysis.
5.1.4.1 Management control. For any
maintenance program to be effective,
maintenance priority must be established by
all management levels. Management
objectives and control of maintenance
activities shall conform to DOE 4330.4 with
particular emphasis as follows:
a. Management shall define the
goals, organizational structure,
and lines of authority and
responsibility for the maintenance
program.
b. Management shall assign the
responsibility for the development
of a program and procedures for
the implementation of
maintenance, and approve the
developed program.
Section 10
DOE-STD-3003-2000
9
c. Management shall ensure
adequate training to qualify
maintenance personnel.
d. Management shall identify
performance indicators and
criteria to be utilized to measure
equipment, systems, and
personnel effectiveness in
maintenance activities. (Additional
guidance to be used in formulating
performance goals may be found
in NRC Regulatory Guide 1.160.)
e. Management shall periodically
evaluate the effectiveness of the
maintenance program
(recommended minimum
frequency - 18 months).
5.1.4.2 Qualification of maintenance
personnel. DOE 4330.4 provides
requirements for qualification and training of
maintenance personnel. The required level of
qualification of maintenance personnel
depends on the level and type of involvement
in maintenance activities. Important aspects
such as safety practices, failure analysis,
inspection, control adjustments, testing,
calibration, disassembly, and parts
replacement require appropriate training and
experience. Training should include specific
manufacturer's operating and maintenance
manuals and the plant procedures to be
followed when performing testing and
maintenance as well as specific training on
identical or similar equipment to be
maintained. When maintenance is provided
by an offsite contractor, that contractor's
personnel shall have equivalent training and
qualification.
5.1.4.3 Maintenance records.
Maintenance activities shall be documented
and records maintained and utilized. DOE
4330.4 provides requirements for records.
Maintenance records provide the
performance history of a BACKUP POWER
SOURCE and its associated support
systems. They are also used to establish
parts replacement intervals that will reduce
the potential for failure when a loss of normal
power occurs. Maintenance records provide
essential information for evaluating the
effectiveness of the maintenance program.
The maintenance records should be
comprehensive and well organized to
facilitate ready retrieval of information for
analysis. The following should be included in
the maintenance records as appropriate:
* All inspection and maintenance
activities
* Start Reliability (IEEE Std 762
definition)
* All failures, during either testing or
operation, or during walkdowns
* Failure analysis and identified cause(s)
* Corrective action(s)
* Out-of-service time
* All part replacements
* Modifications
* Critical or selected operating
parameters (for trending)
5.1.4.4 Maintenance Data. A set of
operating data should be recorded
periodically according to manufacturer's
recommendations. The data should be
recorded for standard operating conditions.
This data is used to determine trends in
operating performance as a basis for
predictive maintenance actions, and is a
ready reference for maintenance and
manufacturer personnel in servicing the
BACKUP POWER SOURCE.
5.1.5 Testing. The requirements below
shall be applied to all testing of BACKUP
POWER SOURCES.
5.1.5.1 Test Procedures. Test
procedures for BACKUP POWER SOURCES
shall include acceptance criteria, review and
approval blocks for critical steps,
prerequisites, precautions, and other sections
to record the information identified in 5.1.5.2.
An example of a maintenance/test procedure
with associated data sheets is included in
Appendix II.
DOE-STD-3003-2000
10
Section 11
5.1.5.2 Test records. All test activities
shall be recorded and records retained. The
records should identify the date, time, names
of test personnel, type of test procedure
conducted, "as found" and "as left"
conditions, values of monitored parameters,
length of test, unusual conditions, test results
(comparison of data to criteria), and
description of any failures for each BACKUP
POWER SOURCE. Failures shall be defined
in terms of the BACKUP POWER
SOURCE'S documented requirements. Test,
operating, and maintenance logs for all
BACKUP POWER SOURCES should be in
one comprehensive document or computer
data base readily retrievable and available to
maintenance and operating organizations
responsible for BACKUP POWER
SOURCES. Preferably, the document should
be kept at the facility or site level. The
identity of information (data) related to each
BACKUP POWER SOURCE should be
preserved.
5.2 EG Requirements. This section
covers the EG and those associated systems
necessary for its functioning. It does not
include the electrical network to which it is
attached beyond the generator OUTPUT
BREAKER. An EG unit includes the engine,
generator, starting system, automatic and
manual controls, lubricating oil system,
cooling water system (if not self-contained,
up to the supply valves), starting energy
source (if not dedicated, from the connection
points on the unit), fuel supply system, and
generator OUTPUT BREAKER (refer to
IEEE-387 Std, Figure 1). Other components
are necessary for reliability and the continued
operation of the EG and are discussed in this
Standard. For the purposes of determining
an EG unit failure, however, they should be
excluded.
Automatic transfer devices are often part of a
Backup Power System. Their purpose is to
automatically transfer loads between the
normal power source and the BACKUP
POWER SOURCE upon loss or restoration
of the normal power source. Information on
transfer device features can be found in
NFPA 110 and IEEE Std 446.
NFPA 37 should be used for new EG
installations and those portions of existing
equipment and installations that are changed
or modified. Appendix I provides several
recommendations to improve diesel
generator reliability that should be considered
when modifying existing or developing new
designs.
5.2.1 EG capabilities. Consideration of
environmental, load, and other design factors
at the specific location of the EG shall be in
accordance with NFPA 110. The following
paragraphs apply when specifying
requirements for EGs to ensure their
functional performance.
5.2.1.1 Environmental and load
conditions. The EG shall have the capability
to perform its required functions over the
specified range of conditions during and
subsequent to the loss of normal power.
These conditions shall have documented
operating ranges and performance indicators
and shall include the following:
a. Temperature of the EG and
necessary auxiliaries including
expected ambient extremes and
temperature rise due to the EG
operation at maximum loading
b. Combustion air quality (range of
atmospheric pressure,
temperature, humidity, and
impurities)
c. Auxiliary equipment extremes and
quality (electrical, lubrication,
water)
d. Type and quality of fuel
e. Expected operating cycles and
hours for the design lifetime (this
should include periodic testing,
estimated troubleshooting, and
loss of power demands)
DOE-STD-3003-2000
11
Section 12
f. The load profile (the time
sequence and duration of load
application) including the change
in load currents resulting from the
extremes of allowable voltage and
frequency variations. To the
extent practical, the application of
loads should be at known time
intervals. The loading sequence
shall ensure that random loads
cannot occur in a manner to
overload the EG. "Permissive," as
opposed to "demand," start
signals shall be evaluated to
ensure the loading profile is not
compromised and to identify
random loading problems.
Automatic loading may be limited
to the necessary safety or other
important loads.
g. Conditions of load transfer
needed between the normal
source and EG (unloaded bus,
automatic SYNCHRONIZATION,
manual SYNCHRONIZATION)
and including consideration of
change between ISOCHRONOUS
and DROOP MODE of operation
h. Potential effect of failures or
inadvertent actuation of
equipment such as water spray
from fire protection equipment.
Refer to NFPA 110 for additional
guidance.
5.2.1.2 Starting and loading. The EG
shall be capable of starting, accelerating, and
loading within the time required by the
demands of the equipment/system being
supplied. This requirement is discussed in
IEEE Std 387. Voltage and frequency shall
be maintained during the loading sequence
such that equipment will operate without
malfunction. Typically, the frequency should
be > 57 Hz and voltage > 75% of nominal.
Subsequently, the steady-state operating
voltage and frequency to the loads should be
within the manufacturer's guaranteed
equipment ratings for continuous operation,
typically ± 10% and ± 2% respectively. The
EG system full load shall be within the
CONTINUOUS RATING of the EG. The EG
shall have the capability to handle the load
power factor during loading and steady-state
operation. SHORT-TIME RATING overload
specifications shall not be exceeded.
5.2.1.3 Engine cooling. The EG should
be provided with a self-contained cooling
system. If self-cooling is not available, the EG
shall be able to operate without overheating
damage or trip for the time required to
activate an auxiliary cooling system to ensure
EG cooling. Refer to NFPA 110 for additional
guidance.
5.2.1.4 HOT RESTART. EGs should
have the capability for immediate HOT
RESTART upon shutdown at full load
temperature conditions (after it has operated
at full load for at least 2 hours).
5.2.1.5 EG ratings. Most EGs will have
continuous and overload ratings. Typical EGs
will have more than one overload rating.
These ratings shall accommodate any
overload transient that occurs during
sequence loading of equipment or a
momentary overload that could occur through
manual action during testing. The light- and
no-load rating shall accommodate the
starting and loading sequence. If the EG
must be operated under light load longer
than manufacturer's specifications, the
manufacturer shall be consulted as to what
precautions to take to rectify the accumulated
detrimental effects of low-load operation
and/or how to prevent such detrimental
effects. Refer to IEEE 387 for additional
guidance regarding light loading.
5.2.1.6 Vibration. Critical speeds
associated with excessive vibrational
stresses shall not occur within ± 5% of the
normal operating speed of the machine.
Refer to IEEE Std 387 for additional
guidance.
DOE-STD-3003-2000
12
5.2.1.7 Overspeed. The engine
overspeed resulting from a SHORT-TIME
RATING load rejection shall not cause
moving parts to fail nor the engine to trip. The
overspeed trip device setting shall protect the
unit from damage. Refer to IEEE Std 387 for
additional guidance.
Section 13
5.2.1.8 Automatic operation. If the EG
is required to operate separately in DROOP
and ISOCHRONOUS MODES, and the
voltage regulator is required to accommodate
paralleled and nonparalleled operation, the
EG controls for each of these control
systems should automatically revert to the
appropriate mode of operation upon an
automatic demand signal. The need for this
feature should be assessed based on the
significance of unavailability during testing,
considering manual action could be taken to
place the unit in a condition where it could
then respond. There shall be protective
features to protect an EG from an overload
that may occur during a loss of normal power
when the EG is operating in parallel with the
GRID.
5.2.1.9 Control. The EG may have
automatic and/or manual control capability.
Automatic control should include automatic
start on a demand signal and automatic
adjustment of speed and voltage to a ready-
to-load condition. Manual control shall be
available to allow operator intervention as
needed. To prevent personal injury, an
engine start signal shall not override any
manual non-operating modes used for repair
or maintenance. NFPA 110 and IEEE Std
387 provide additional guidance. Most EG
bus designs incorporate an undervoltage
relay that will trip and may block closure of
the breaker feeding from the normal power
source to the EG bus. Features should be
incorporated to allow easy restoration of the
GRID if the EG fails during a test in which the
GRID source is disconnected. Where
necessary for equipment protection,
especially motor-driven loads with low inertia,
controls for breakers and automatic switches
should be provided to ensure that neither the
ENGINE GENERATOR nor the driven loads
can be damaged by out-of-phase transfer
between normal and backup sources under
both emergency and test conditions.
5.2.1.10 Surveillance features. A
surveillance system/program should be
provided to monitor the status of the EG for
the various modes (operating, test, standby,
lockout/maintenance). For important
applications (necessary to mitigate/prevent
consequences of process accidents) where
an EG is unable to perform its design
function (when an essential auxiliary/support
system is inoperable as well as during
maintenance or other lockout conditions),
indication of the inoperable status should be
provided. Sufficient information should be
provided to allow any required remote action
to manually start, load/unload, or trip the EG.
Where the EG is normally controlled from a
remote location, a common trouble alarm
may be provided at the remote location for
conditions that cannot be rectified from the
remote location.
5.2.1.11 Monitored systems. EG
systems should be provided with sufficient
instrumentation to measure and display the
variables indicative of proper operation and
to provide alarm signals for abnormal and trip
conditions. These systems include the
engine, start system (battery or air),
generator, exciter or voltage regulator,
cooling system, fuel supply system,
lubricating system, speed governor,
combustion air system, and the EG breaker.
Included in the various parameters that may
be monitored are: pressure, temperature,
flow, level, frequency/speed, current, voltage,
power, volt-amperes, power factor, and
contact positions.
5.2.1.12 Protective features. Features
shall be provided to protect the EG against
damage- or failure-inducing events. Such
features shall cause immediate shutdown of
the EG upon exceeding the trip level. Alarms
of a protective trip actuation should be
provided at the appropriate location. NFPA
110 provides guidance on equipment safety
indications and shutdowns using a graded
Section 14
DOE-STD-3003-2000
13
approach. Protective features should be able
to be periodically tested and the trip
instrumentation and controls should be
periodically calibrated. The capability to block
protective trips during an actual emergency
condition should be considered. Alternatively,
independent indicators with coincident trip
logic could be considered. The following is a
list of typical equipment safety indications
and shutdowns; use may vary with
importance and power source application:
* Low lubrication oil pressure
* Engine overspeed
* Generator phase current differential
* Generator overcurrent
* Cooling water pressure
* High engine temperature (typically
cooling water temperature downstream
of the EG)
* High vibration
* Low turbocharger oil pressure
* High crankcase pressure
* Reverse power (during operation in
parallel with GRID or other sources)
* Failure to start after normal cranking
time
* Emergency stop
Some protective trip functions should never
be bypassed. Trips such as engine
overspeed, generator phase current
differential, reverse power, and emergency
stop should always cause EG shutdown.
These trips are indicative of faults or failures
that render the EG incapable of supplying its
loads, and may cause equipment damage if
left unchecked.
5.2.2 Qualification of maintenance
personnel for EGs. Specific qualification for
EG maintenance personnel should include
the following subjects:
a. Diesel and/or gasoline engine
fundamentals (as appropriate).
b. Testing and maintenance
practices for EGs.
c. Safety precautions for engine-
driven generators.
5.2.3 EG testing. EG installations shall
accommodate periodic testing during
operation of the plant (or process) and during
shutdown. When operation of facility
processes does not allow such a test, they
may be performed on a less frequent basis
during planned maintenance or shutdown
periods. To the extent practical, the EG
system test demands should duplicate actual
demands. Simulation of loss of power should
exercise the circuits that sense power loss
and initiate automatic start, and cause
OUTPUT BREAKER closure and transfer
device operation. Instrument sensor design
and location should permit in-place
inspection and calibration. Alarm and status
indication of important modes and
parameters should be included.
Communications should be established
between the local test station and the normal
operating area to allow test personnel to
inform operators of EG test status and
condition. Operating data should be recorded
at the beginning and end of the test and at
regular intervals during the test.
5.2.3.1 Periodic testing during facility
operation. EGs for operating facilities shall be
periodically tested according to a
documented schedule to demonstrate their
ability to start and accept required loads. To
avoid unnecessary and premature
degradation of the EG, manufacturer's
recommendations should be followed in
regard to prelubrication, acceleration,
loading, and unloading. An EG start from
normal STANDBY CONDITIONS (fast start
test) shall be performed annually or
semiannually if not done during the periodic
test. Other engine starts should follow
manufacturer's recommendations for
prelubrication and/or other warmup
procedures to minimize mechanical stress
and wear. (The use of these slow start tests
is more important for larger machines.) The
following should be performed at least once
per month, unless otherwise specified by the
manufacturer or surveillance requirements:
Section 15
DOE-STD-3003-2000
14
a. Record the as-found conditions,
including coolant and lubricant
levels, and the identity of the test
personnel.
b. Verify that the EG starts and
accelerates to operating rpm in
(the required value) seconds.
Generator voltage and frequency
shall be (required value ± 10%)
volts and (60 ± 1.2) Hz within
(required value) seconds.
c. Verify that the starting system
disengages properly (if an
indication is provided).
d. Verify that fuel tank levels (fuel
storage tank, day tank, and
engine tank) are within
specifications.
e. Remove accumulated water from
fuel tanks and oil/water separator.
f. Verify that the fuel transfer pump
system starts and that fuel is
being transferred from the storage
tank to the day and engine-
mounted tank (if present).
g. Verify EG can accept loads up to
90% of the CONTINUOUS
RATING and operate for 1 hour
(time should consider
manufacturer's
recommendations). This may be
done using normal loads, a load
bank, or by synchronizing to the
offsite GRID if this capability is
available. If a load bank is
routinely used, a dedicated
connection should be provided.
The value of 90% is used to
provide margin to avoid
inadvertent overloading. If this is
not feasible, the test loading
conditions provided by NFPA 110
may be substituted.
5.2.3.2 Diesel fuel tests. A program
shall be established for maintaining the
quality of fuel. Long-term storage of fuel
requires proper selection, proper storage
conditions, and monitoring of fuel properties
prior to and during storage. ANS 59.51 and
ASTM D975 provide guidance for maintaining
the quality of fuel for diesel generators. Fuel
shall be procured according to the
requirements of Federal Specification VV-F-
800, ASTM D975, or the diesel
manufacturer's specifications if it is more
restrictive. The program shall establish
criteria for periodic testing and for the
disposition of fuel not meeting the
appropriate specifications. Procedures for
periodic sampling can be found in ASTM
D4057. In addition to periodic testing, water
should be periodically drained from the fuel
tank. The fuel should be kept cool. The tank
should be kept full to minimize breathing and
reduce exposure to air. These measures will
reduce the rate of buildup of condensation
water, fungi, bacteria, and oxidation
products.
5.2.3.3 Gasoline fuel tests. Gasoline is
considerably more reactive than diesel fuel
and highly susceptible to deterioration during
long-term storage. The best practice is to
plan storage capacity and fuel use to avoid
prolonged storage. The volatile nature of
gasoline dictates that quantities on site be
kept to the minimum necessary and all
standard precautions be taken to reduce the
potential for explosion and fire. The same
actions should be taken as with diesel fuel
(periodic draining of water condensate from
the storage tank; keeping the tank full to
reduce fuel exposure to air and minimize
moisture intake; and keeping the fuel cool to
slow oxidation, fungi, and bacteria rates).
5.2.3.4 Battery surveillance tests. Most
EGs used in backup applications at DOE
facilities use batteries to provide the initial
energy source for the control, start, and field
flashing power necessary to bring the unit to
operating conditions. A degraded battery
may result in failure of the BACKUP POWER
SOURCE to perform. Batteries require
DOE-STD-3003-2000
15
monitoring, periodic maintenance, and
charging to ensure their readiness to
perform. Refer to 5.4 for information on
maintenance and related activities for
ensuring reliable battery operation.
Section 16
5.2.3.5 Infrequent tests. Infrequent
tests are performed on EGs to verify machine
capabilities other than start and load that
need not be demonstrated on a monthly
basis or that cannot be performed during
plant operation. Users shall be appropriately
notified before performing disruptive tests.
The following are typical EG tests that should
be performed on an 18-month basis or during
plant maintenance periods or shutdown as
the plant design and the safety analysis
necessitates. The EG test program should be
tailored to include the following tests as
pertinent to the specific EG application. The
testing in b., c., and e. may be accomplished
using a load bank, or by synchronizing to the
offsite GRID if this capability is available. If a
load bank is routinely used, a dedicated
connection should be provided.
a. Perform manufacturer's inspection
procedures specified for this
interval for an EG used in standby
service.
b. Verify the capability of the EG to
reject a load of greater than or
equal to (largest single load) kW
while maintaining engine speed
less than or equal to nominal
speed plus 75% of the difference
between nominal speed and the
overspeed trip setpoint, or 15%
above nominal, whichever is less.
The voltage and frequency
excursion should not cause
damage or misoperation of loads.
c. Verify capability of the EG to
reject a load of (90 - 100% of
CONTINUOUS RATING) kW
without tripping on overspeed.
d. Perform a loss-of-power test that
simulates the loss of normal
power to the EG buses and:
1) Verify that the buses that will
be powered by the EG
deenergize and loads shed,
as required.
2) Verify EG auto-starts and, if
required, auto-loads the
connected system loads
within any required load
timing sequence. Verify
frequency and voltage are
maintained within
manufacturer's specifications
for connected loads for both
transient and steady-state
conditions.
If the EG is manually loaded,
perform manual loading as
normally done for the specific EG
application.
e. Perform an endurance test that
will demonstrate that the EG
operates (typically for 8 to 24
hours) at 90 - 100%
CONTINUOUS RATING and, if
installation permits, load power
factor. If a short-time rating is
provided, it is desirable to test the
unit at this load during the 8 to 24-
hour period. If the connected load
is above the CONTINUOUS
RATING but within the SHORT-
TIME RATING, the unit should be
operated at this load for no longer
than the time specified for the
short-time rating. The generator
voltage and frequency shall be
(required value ± 10%) volts and
(60 ± 1.2) Hz throughout the
duration of the load test. After the
test is complete, shut the unit
down and within 5 minutes
demonstrate the ability of the unit
to HOT RESTART and load to 90-
100% of its CONTINUOUS RA-
DOE-STD-3003-2000
16
TING for a minimum of 5 minutes.
The HOT RESTART test may be
performed independently of the
endurance and load test provided
the EG is at full temperature.
f. Where the system accommodates
parallel operation of the EG with
the GRID system for the purpose
of live bus transfer of loads or for
testing, the ability to synchronize
and transfer between these
sources should be demonstrated.
This is unnecessary if done during
periodic tests.
g. For systems where the bus
undervoltage relay trips the GRID
source breaker, the capability to
restore the GRID circuit to the EG
bus should be demonstrated.
Section 17
5.2.3.6 Test failure. When recording
test results, a failure should be recorded if
the EG fails to start, accelerate, reach
nominal voltage and frequency, accept the
rated load within and for the time required, or
otherwise fails to satisfy the specified
acceptance criteria. Test success and failure
data should be used to determine whether
performance (reliability) goals are being met.
Refer to IEEE Std 762, NRC Reg. Guide 1.9,
and NRC Reg. Guide 1.160 for guidelines.
5.3 UPS system requirements. UPSs
are used to supply an uninterrupted source of
power to important instrumentation and
control systems for loss-of-normal-power
conditions. They are also used to provide
continuous, quality power for systems
sensitive to disturbances occurring in an
electrical power distribution system caused
by switching, faults, or power transfer. UPS
designs include various combinations of
rectifier/charger, battery transfer and bypass
switches, and an inverter. Rotary UPSs are
not covered by this Standard.
5.3.1 UPS capabilities. The
specification of requirements for the UPS
shall include the sizing (based on the load
and duration of the load) of the unit, the type
of power required by the load (frequency,
voltage), the system configuration
(redundancy, transfer features), protective
features, limitations of available ac power,
limitations of available dc sources, short-
circuit capability, required controls,
instrumentation, and alarms. Refer to
ANSI/IEEE Std 944 and DOE-SPEC-3021 for
guidance and criteria for these and other
factors to be considered in developing the
bases of a UPS system. ANSI/IEEE Std 944
and DOE-SPEC-3021 shall be used to
develop the bases and requirements of UPS
systems with respect to specification of
service conditions (environmental),
specification of UPS system requirements,
and specification of design test requirements.
Environmental conditions exceeding the
values in ANSI/IEEE Std 944 should be
identified and equipment specifically qualified
to these different conditions. Refer to
guidance and criteria in NFPA 111 for the
development of bases and specifications for
transfer devices to be used with UPS
designs. DOE-SPEC-3021 should be used to
develop and document the specification for
new UPS installations.
5.3.2 Maintenance and repair of UPS.
The maintenance program should take into
consideration the type of service to which the
equipment is subjected (duty cycle,
chemicals, dust, heat), manufacturer's
recommendations, and trending.
5.3.2.1 Qualification of maintenance
personnel for UPSs. Specific qualification for
UPS systems maintenance personnel should
include the following:
a. Fundamentals of electrical and
electronic design of UPSs
b. Testing and maintenance
practices for UPS systems
c. Safety precautions for UPS
systems
DOE-STD-3003-2000
17
5.3.2.2 Routine inspections and
servicing of UPS systems. UPS systems
should be checked externally daily. The UPS
should be checked for evidence of problems
by evaluating meter readings and detrimental
environmental problems (heat, moisture,
chemicals). Less frequent activities such as
internal cleaning, filter replacement, checking
electrical connections for tightness, and
calibration of instruments shall be done
according to manufacturer's recommend-
ations or at least every 18 months. This
interval may be adjusted according to
documented operating experience.
Section 18
5.3.3 Testing of UPS systems. A UPS
in its standby or normal operating mode may
not demonstrate many of the various features
that may be required to function during
emergency conditions such as a loss-of-
power or equipment failure. Depending on
the design of the UPS system, the following
tests should be performed:
a. Light-load Test - Verify inverter
voltage & frequency remains
within specified limits. Verify
proper operation of control
switches & meters.
b. SYNCHRONIZATION Test -
Measure the rate of change of
inverter frequency while a
reference frequency is attenuated.
Concurrently measure the inverter
voltage. (only required when
synchronization with alternate
source is a design feature)
c. AC Input Failure Test - Disconnect
the input power source(s) or
shutdown the rectifier on-line to
verify that the dc source can
indeed instantly sustain the critical
loads. Verify inverter voltage &
frequency remains within specified
limits.
d. AC Input Return Test -Restore the
input power source(s) or
reactivate the rectifier on-line to
verify that the rectifier can
instantly sustain the critical loads
and re-charge batteries (if used).
Verify inverter voltage & frequency
remains within specified limits.
e. Transfer Test - (For UPS systems
which use a Static Bypass Switch)
Cycle the UPS to and from the
bypass source, measuring
transients, maximum & minimum
voltages and transfer times.
Simulated failures may be
needed.
f. Rated Full-Load Test - Loads
(equivalent to the full-rated load)
shall be applied to the output of
the UPS at the extreme ranges of
ac and dc input voltages for rated
duration.
g. Output-Voltage Balance Test -
Measure inverter phase-to-phase
& phase-to-neutral voltages and
angles while symmetrical loads
are applied. Measure inverter
phase-to-phase &
phase-to-neutral voltages and
angles during the transition from
no-load to an imbalanced full load.
h. Harmonic-Components Test -
measure harmonic content in the
output voltage for rated linear and
nonlinear load conditions.
The tests above correspond to tests
recommended by ANSI/IEEE Std 944 and
should be performed according to
manufacturer's recommendations or on at
least an 18-month interval. UPS batteries
shall be maintained and tested in accordance
with 5.4.
5.4 STATIONARY BATTERY system
requirements. A STATIONARY BATTERY
system is a direct current (dc) standby power
system consisting of a group of two or more
cells connected together electrically in series
or parallel, or combination. A system includes
DOE-STD-3003-2000
18
all switchgear and distribution equipment
necessary to provide quality voltage and
current as required by the connected load.
The battery is normally in full float operation
where it is connected in parallel with a
charger and the load, and where the charger
supplies the normal dc load plus any self-
discharge or charging current, or both,
required by the battery. The battery will
supply power to the load upon loss of ac
power to the charger, failure of the charger,
or when the load exceeds the charger output.
STATIONARY BATTERIES are commonly
used for standby service in industrial control,
electric substation control circuits, UPSs, and
communication system service. The following
subsections provide requirements and
information for STATIONARY BATTERIES,
including their maintenance and testing.
Section 19
5.4.1 Battery system capabilities. The
specification of requirements for
STATIONARY BATTERIES shall include
battery load (load profile), voltage, time
period, environment, and installation. DOE-
SPEC-3018 or DOE-SPEC-3019 should be
used to develop and document the
specification for new lead-acid battery
installations.
5.4.1.1 Battery sizing. Battery load
profiles and sizing shall be developed in
accordance with IEEE Std 485 (for lead-acid
batteries) or IEEE Std 1115 (for nickel-
cadmium batteries). This includes type of
load, nature of the load (transient and
steady-state values), timing of application of
loads, length of time for each load and
overall time needed for battery operation.
IEEE Std 485 and IEEE Std 1115 provide
detailed instructions on how to treat various
types of loads and construct a load profile.
Other factors involved in assessing proper
battery size include: maximum system
voltage, minimum acceptable voltage, and
battery duty cycle. Cells may be connected in
series or series-parallel combinations to
arrive at the desired voltage and battery
capacity. Refer to IEEE Std 485 or IEEE Std
1115 as appropriate for detailed guidance on
assessing cell and battery size (number and
capacity of cells), and for information on the
treatment of design margin and the various
associated factors to assess whether sizing
is adequate.
5.4.1.2 Installation. The following
factors shall be addressed for an acceptable
battery installation: vibration, temperature,
ventilation for hydrogen offgassing and heat
removal, local heat sources, power source
location, mounting rack (support, insulation,
and grounding), seismic needs, containment
for flooded lead acid batteries,
instrumentation, and alarms. Refer to IEEE
Std 484 (Vented Lead-Acid), IEEE 1106
(Nickle-Cadmium), or IEEE Std 1187 (Valve-
Regulated Lead-Acid) for detailed guidance
on battery installation. Refer to IEEE Std 450
(lead-acid), IEEE Std 1106, IEEE 1187, or
IEEE 1188 for acceptance testing.
Manufacturer's recommendations should be
followed, if more limiting, for all batteries.
5.4.2 Battery maintenance, testing, and
surveillance. Batteries shall be monitored,
periodically maintained, and properly charged
to ensure their readiness to perform. Many
types of batteries, if allowed to sit without a
charger, will internally discharge, often with
irreversible cell degradation. For these types
of batteries, it is important to maintain proper
charging FLOAT VOLTAGE during standby.
Due to inherent differences between cells,
FLOAT VOLTAGE and specific gravity values
will vary from cell to cell over time. If cell
FLOAT VOLTAGES and/or specific gravity
values are allowed to remain in an unequal
condition for extended periods of time, cell
sulfation will result. To overcome this
problem, periodic EQUALIZING CHARGE
must be applied to equalize cell voltages and
specific gravities. Manufacturer's
recommendations should be followed in
regard to EQUALIZING CHARGE. When
performing an EQUALIZING CHARGE, care
should be taken to assure the charger
voltage does not exceed the voltage rating of
the loads connected during the equalize
charge. Batteries are rated at a temperature
of 25 �C. Higher temperatures will improve
capacity at high discharge rates but
DOE-STD-3003-2000
19
Section 20
significantly reduce battery life. Lower
temperatures have a significant effect in
reducing battery capacity. Typical battery
types for standby service are lead-acid
(calcium, antimony), pure lead (generally a
"round cell"), or nickel-cadmium. IEEE Std
1106 provides criteria and guidance for
nickel-cadmium batteries similar to that
provided in IEEE Std 450 for lead-acid
batteries. Manufacturers will provide
necessary information on the care,
precautions, charging, and treatment of
specific batteries including during periods of
storage.
5.4.2.1 Routine maintenance and
surveillance of lead-acid batteries. Routine
inspections and corrective actions for
problems found during surveillance and
testing shall be in accordance with IEEE Std
450 or IEEE 1188, as applicable. Manufactur-
ers also provide recommended routine main-
tenance practices that should be considered
in the care of batteries. NFPA 110 provides
guidance on a graded approach to battery
maintenance and surveillance. In addition,
TABLE I provides an example of good
practices for surveillance and testing of lead-
acid cells. Adjustments to (increase or
decrease) the intervals in TABLE I should be
based on experience and manufacturer's
recommendations. Refer to IEEE Std 1106
for maintenance, inspection, and corrective
actions for nickel-cadmium batteries.
5.4.2.2 Periodic load tests for batteries.
The only real measure of a battery's capacity
and capability to provide power to its required
load is derived from the performance of two
different tests. One of these is called the
PERFORMANCE DISCHARGE TEST, and
the other is called the Service Test. The
PERFORMANCE DISCHARGE TEST
indicates the existing capacity of the battery
expressed as a percent of the rated capacity.
This provides an indication of the remaining
useful life of the battery. The Service Test is
an as-found test that demonstrates the ability
of the battery to carry its required load for the
required time period (duty cycle). These two
tests are the best indicators of a battery's
ability to perform its function. In order to
perform the Service Test, the load profile
(duty cycle) for the battery must be known.
During the performance of these tests, the
battery will be unavailable for duty due to
significant discharge. These tests should only
be performed under conditions when the
unavailability of the battery is acceptable, or
provisions should be made for an alternate
source to be temporarily connected to the
loads for the duration of the test and
recharging of the battery. Intervals,
procedural instructions, and criteria for the
Performance and Service Tests for lead-acid
batteries shall be in accordance with IEEE
Std 450 or IEEE 1188. The schedule and
procedures for battery capacity tests for
nickel-cadmium batteries shall be in
accordance with IEEE Std 1106.
Replacement criteria for nickel-cadmium cells
shall be in accordance with IEEE Std 1106.
Battery replacement criteria for lead-acid
cells shall be in accordance with IEEE Std
450.
DOE-STD-3003-2000
20
Subject (Note 3) Values (Note 1) Period
Battery Terminal Voltage (typical 60
cell battery)
(129-130.2) volts PbSb
(130.2-135) volts PbCa
monthly
Electrolyte Level Between fill lines (distilled
water only)
monthly
Cell Float Voltage
(Pilot cell)
(2.15-2.17) volts PbSb
(2.17-2.25) volts PbCa
monthly
Cell Float Voltage
(All cells)
(2.15-2.17) volts PbSb
(2.17-2.25) volts PbCa
quarterly
Specific Gravity
(Pilot cell)
1.215 ± 0.010 monthly
Section 21
Specific Gravity
(All cells)
1.215 ± 0.010 quarterly
Cleanliness and Corrosion Check (Note 2) monthly
Resistance Measurement Cell to Cell
and Terminal Connections
< 20% above the value
when new or after cleaning
retorquing bolts
yearly
Battery Capacity Test
(PERFORMANCE DISCHARGE TEST)
> 80% of capacity (Note 5) 5 years
Battery Load Test
(Service Test)
Design load and duration
with adequate voltage
yearly
(Note 4)
Note 1 Values outside these ranges indicate action is necessary to restore the parameter
to within the specified values.
Note 2 Battery cleaning should be done with baking soda and water with clear water rinse--
no other cleaning materials shall be used.
Note 3 All manufacturer's safety precautions should be observed when working on
batteries.
Note 4 Not required where battery is for engine generator only and not other loads. The
periodic monthly start of the engine generator is a load test. Load tests should be
done in as-found condition.
Note 5 Battery capacity (performance discharge) test is used as a battery age indicator.
Initially, battery should be fully charged, temperature near 25 �C, and terminals
clean. See IEEE Std 450 for times the battery capacity test should be performed.
TABLE I. Typical Lead-Acid Battery/Cell Surveillance and Tests
DOE-STD-3003-2000
21
6. NOTES
(This section contains information of a general or explanatory nature that may be helpful,
but is not mandatory.)
6.1 Intended use. This Standard is not a DOE Order, and its requirements are not
automatically invoked at any facilities or on any BACKUP POWER SOURCES. This Standard
is intended for use by the operations/field offices or M&O contractors as desired. It may be
invoked by contractual documents, procurement documents, or in the authorization basis for a
facility. Unless it is invoked as above, the contractor cannot be assessed or inspected against
its requirements. This Standard is also suitable for voluntary use by engineers responsible for
BACKUP POWER SOURCES at DOE facilities.
6.2 Revision status. A specific revision of this Standard should only be invoked and used
when required by contractual considerations. In all other cases, the most current revision
should be assumed to be used.
6.3 Tailoring guidance. For applications that are not related to nuclear safety, use of this
Standard should be tailored based on the relative importance of the power source to safety of
the public, the environment, operating personnel, and the facility. Procurement documents
invoking this Standard should tailor the requirements contained herein to suit the particular
procurement. Contractual or authorization basis documents invoking this document must
specify assessment or inspection criteria appropriate to the application.
6.4 Subject term (key word) listing. The following listing of subject terms (keywords) is
provided so that this document may be found during retrieval searches.
Backup power
Emergency power
Diesel generator
ENGINE GENERATOR
UNINTERRUPTIBLE POWER SUPPLY
STATIONARY BATTERIES
DOE-STD-3003-2000
22
APPENDIX I
Considerations to Improve Diesel Generator Reliability
NRC publication NUREG/CR 0660, Enhancement of On-Site Emergency Diesel Generator
Reliability, was developed from a comprehensive study of diesel generator problems and
installations. The document made a number of recommendations to improve diesel generator
reliability. The following were selected for consideration by DOE facilities:
Section 22
1. Provide refrigerated air dryers between the air compressor and air storage tank to
reduce detrimental effects of entrained moisture causing rust and pipe scale that result in
damage to air start motors.
2. Diesel generator room air quality is often poor; this can be overcome by providing
dust-tight covers for relays and contactors or by providing filters for static inverters to protect
field flashing contacts. Room ventilation should be taken from about 6 m above the ground to
reduce intake of local dust.
3. Provide training for those personnel operating and maintaining specific diesel
generators.
4. Provide prelubrication for all engine starts (except true auto-start) for 3 - 5 minutes
(longer per manufacturer's recommendation) to reduce potential for engine bearing wear.
5. Provide an electric fuel pump that starts upon engine auto-start signal and shuts off
when engine is up to speed.
6. Mount instruments and controls in a separate floor-mounted panel independent of
the EG (minimizes vibration effects on instruments and controls).
DOE-STD-3003-2000
23
APPENDIX II
EXAMPLE PROCEDURE
FLOODED LEAD-ACID BATTERY (IDENTIFICATION NO. _______) MONTHLY
MAINTENANCE
Date/Time Started: _____________ / _____ :_______ a.m./p.m.
This procedure is authorized by Work Request No. ___________ .
Battery Location: ____________________
Battery Identification No. ____________________
PURPOSE
The purpose of this procedure is to provide instructions for performing monthly
maintenance and checks on the XXX volt lead acid (battery identification).
FREQUENCY
Monthly, except when the quarterly or annual maintenance is performed.
REFERENCES
* Site Safety Manual
* IEEE Std 450, IEEE Recommended Practice for Maintenance, Testing, and
Replacement of Large Lead Storage Batteries for Generating Stations and
Substations.
* Battery manufacturer _______________(manual)
* Technical Standard - (Plant Standards)
* Technical Specification - (Identification Number)
* Specific Battery Equalizing Charge Procedure
GENERAL LIMITATIONS AND PRECAUTIONS
"WARNING! Failure to complete this procedure correctly in its entirety and within the frequency
specified may result in operation outside the requirements of the Technical Standards or,
ultimately, the Technical Specifications."
1) A Nonconformance Report (NCR) is required for any nonconforming equipment or test
failure that has been identified during the performance of this procedure, unless the
corrective actions are authorized by this procedure.
2) Electrical Supervision shall be notified of any abnormal condition discovered while
performing this procedure.
3) Readings shall be taken under normal float conditions. Specific gravity readings are not
meaningful during charge or following the addition of water.
DOE-STD-3003-2000
24
INFORMATION
1) The battery consists of XX cells of the lead-calcium type, Battery Model
XXXXXXXXXXXXXXX. Battery terminal voltage is XXX Vdc (nominal) and specific
gravity is 1.215 (nominal) at 25 �C. Charging float voltage is XXX-XXX Vdc.
2) Pilot cell selection shall be directed by Electrical Supervision at least annually, or as
often as deemed necessary by the periodic review of cell data, to ensure that the
selected pilot cell(s) are representative of the overall battery condition.
TOOLS/INSTRUMENTS/MATERIALS
* Voltmeter with an accuracy range of better than ± .008 Vdc.
Instrument I.D. # __________ Calibration Expiration Date ________
Section 23
* Hydrometer. Range: 1.180 - 1.310
Instrument I.D. # __________ Calibration Expiration Date ________
* Glass thermometer. Range: 0 - 65 �C
Instrument I.D. # __________ Calibration Expiration Date ________
* Density Meter, minimum accuracy .0025 specific gravity
Instrument I.D. # __________ Calibration Expiration Date ________
* Electrolyte level gauge/ruler
* Acid neutralizing agent (120 g bicarbonate of soda to 1 liter of clean water)
* Clean rags or paper towels
* No-Ox-Id grease
* Brush, stiff plastic bristles
* Distilled water
AUTHORIZATION
An authorized Work Request is required.
SAFETY PRECAUTIONS
1) Follow applicable Site and Area Safety Rules for work on batteries.
2) Obtain an approved Work Clearance Permit per Site Safety Manual before initiating
any work on batteries.
3) The use of personal protection articles such as acid-resistant gloves, apron, face
shield, and goggles is required.
4) Electrolyte is highly corrosive and extreme care is required during handling.
5) Use only non-conductive/insulated/non-sparking tools in the battery room.
6) Do not smoke or use open flames, do not cause arcing in the vicinity of the battery.
7) All metallic objects such as jewelry (rings, bracelets, necklaces) must be removed
before working on batteries.
8) Neutralize static buildup just before working on battery by having personnel contact
nearest effectively grounded surface.
9) Ensure entrance and exit from the battery area is unobstructed.
10) Verify availability of currently inspected and operable (portable or stationary) water
facilities for rinsing eyes and skin in case of acid spill.
11) A Radiation Work Permit (RWP) is required for all work in a Radiologically Controlled
Area (RCA).
DOE-STD-3003-2000
25
12) For safety reasons, a person shall not work alone. At least two persons (Two Man Rule)
must always be present when working on electrical power systems.
PROCEDURE
A. PREPARATION
CHECK
1) Read the following PROCESS SIGNIFICANCE statement:
Statement of battery function and significance .... ____
2) Check to ensure that this is the latest approved revision of this procedure. ____
3) Confirm each Instrument has a current calibration sticker and record the
information in the Instrument/Tool Report (No._____) attached to this
procedure and in the TOOLS/INSTRUMENTS/ MATERIALS Section of this
procedure. ____
4) Obtain an authorized Work Request (No._____) and record the number on
Page 1 and Data Sheet 1 of this procedure. ____
5) Obtain an approved Work Clearance Permit (No._____) per Site Safety
Manual. ____
6) Confirm that the Battery Room ventilation system is operating. ____
7) Confirm with Operations that the battery has been on normal float voltage
(XXX-XXX Vdc) for at least 72 hours since the conclusion of the last
equalization charge and subsequent return to float voltage. If not on float
charge, notify (Operations and Electrical) supervision. ____
Section A completed by __________________ /____________________________
(signature) (print name)
Date/Time Completed ______________ /_______ :_______ a.m./p.m.
DOE-STD-3003-2000
26
B. INSPECTION AND CLEANING
1) Check the battery cells for cracks and leakage of electrolyte. ____
2) If cell cracks and leakage of electrolyte are found, note the location in the
Comments section of Data Sheet 1, complete an NCR, and notify Electrical
Supervision promptly. ____
3) Check the intercell and terminal connections for corrosion. ____
4) If any cell connections are corroded:
Section 24
a) Neutralize the corrosion with a neutralizing agent. ____
b) Remove corrosion with stiff plastic bristled brush and clean rags. ____
c) Note the location in the Comments section of the Data Sheet 1. ____
NOTE: Use water only as a cleaning agent; do not use hydrocarbon-type cleaning
agents or strong alkaline cleaning agents that may cause containers and
covers to crack or craze.
5) Clean the battery and rack:
a) Remove electrolyte spillage with clean rags and a neutralizing agent. ____
b) Remove dirt from cells and rack using clean cloths dampened with
clean water. ____
6) If protective grease was removed from intercell and terminal connections
during cleaning, apply a light coat of No-Ox-Id grease to the affected
terminal.
Section A completed by __________________ /____________________________
(signature) (print name)
Date/Time Completed ______________ /_______ :_______ a.m./p.m.
DOE-STD-3003-2000
27
C. BATTERY AND CHARGER CHECK
NOTE: Data from applicable Step(s) in this section shall be recorded on Data
Sheet 1.
1) Check and record Battery Charger voltage (as found) and current meter
readings from the dc distribution panel meters. ____
2) Take and record the Battery Room ambient temperature.
Acceptance Criteria: Temperature recorded correctly.
(15 �C to 35 �C) ____
3) Check and record the battery (as found) terminal voltage, using a digital
voltmeter and reading at the battery terminals.
CAUTION: Do not allow charger output to exceed XX amps.
____
4) If battery terminal voltage is outside the XXX to XXX volt range, adjust the
charger to obtain XXX to XXX volts and record the battery terminal voltage
(as left).
Acceptance Criteria: Adjustment made and readings (as left) correctly
recorded. (XXX-XXX Vdc) ____
5) Check and record the charger (As Left) voltage and current meter readings
from the dc distribution panel.
Acceptance Criteria: Readings recorded correctly.
(XXX-XXX- Vdc) (� X amps)
NOTE: A table providing manufacturer's correction factors for determining corrected
specific gravity (corrected for temperature and level) should be provided with
procedure.
____
6) Take and record the following Pilot cell parameters:
- Pilot cell number
- Hydrometer reading (HYD)
- Pilot cell temperature (TEMP) and temperature correction factor
- Electrolyte level (LEVEL) and level correction factor
- Pilot cell voltage (VOLTS). ____
Completed by _________________ /___________________ Date_______
(signature) (print name)
7) Inspector shall verify that the values obtained are correct and that
acceptance criteria are met in Steps C.1 through C.6.
Verified by __________________ /____________________ Date_______
(signature) (print name)
DOE-STD-3003-2000
28
8) Correct the hydrometer reading for level and temperature and enter on Data
Sheet 1 as specific gravity. ____
9) Measure and record the electrolyte level (as found) for each cell. Read from
the bottom of the electrolyte High Level line.
Above line: Add; Below line: Subtract.
Completed by _________________ /___________________ Date_______
(signature) (print name)
10) Inspector shall verify the values obtained in Steps C.8 and C.9.
Verified by __________________ /____________________ Date_______
(signature) (print name)
11) If any cell's electrolyte level is below the Low level mark, add distilled water
to those cells to the High level mark, and place on equalize charge per
Battery Equalize Procedure immediately after completion of this procedure. ____
12) Measure and record the electrolyte level (as left) for each cell. Read from
the bottom of the electrolyte High Level line.
Above line: Add; Below line: Subtract.
Section 25
Completed by _________________ /___________________ Date_______
(signature) (print name)
13) Inspector shall verify that the Acceptance Criterion in Step C.12 was met.
Verified by __________________ /____________________ Date_______
(signature) (print name)
Section C completed by __________________ /____________________________
(signature) (print name)
Date/Time Completed ______________ /_______ :_______ a.m./p.m.
DOE-STD-3003-2000
29
D. RETURN TO CUSTODIAN
1) Clean work area and remove tools and special equipment. ____
2) List the number here of each Nonconformance Report (NCR) prepared for
any nonconforming condition identified during the performance of this work:
__________________________________________________
3) Notify Operations Shift Supervisor that this procedure is complete.
____
Section D completed by __________________ /____________________________
(signature) (print name)
Date/Time Completed ______________ /_______ :_______ a.m./p.m.
DOE-STD-3003-2000
30
DATA SHEET 1
Work Request No. ____________________ Battery No. __________________
C.1) Meter readings: _____ volts _____ amps, as found
C.2) Battery Room temperature _____�C (15 �C to 35 �C)
C.3) Battery terminal voltage _____ V, as found
C.4) Battery terminal voltage _____ V (XXX-XXX V), as left
C.5) Meter readings _____ volts (XXX-XXX Vdc) ____ amps (� X amps), as left
C.6) & C.7) Pilot Cell data:
CELL NO. HYD TEMP.(�C)/
TEMP.COR
R. FACTOR
LVL. (mm)/
LVL. CORR.
FACTOR
SPECIFIC
GRAVITY
(1.215)
VOLT
(2.13 -
2.38)
/ /
COMMENTS:
___________________________________________________________________
___________________________________________________________________
___________________________________________________________________
___________________________________________________________________
___________________________________________________________________
___________________________________________________________________
___________________________________________________________________
___________________________________________________________________
___________________________________________________________________
___________________________________________________________________
DOE-STD-3003-2000
31
DATA SHEET 1 (Continued)
Work Request No. ____________________ Battery No. __________________
CELL ELECTROLYTE LEVEL
No. AS FOUND AS LEFT
-----------------------------------
1 ___________ ___________
2 ___________ ___________
3 ___________ ___________
4 ___________ ___________
5 ___________ ___________
6 ___________ ___________
7 ___________ ___________
8 ___________ ___________
9 ___________ ___________
10 ___________ ___________
11 ___________ ___________
12 ___________ ___________
13 ___________ ___________
14 ___________ ___________
15 ___________ ___________
16 ___________ ___________
17 ___________ ___________
18 ___________ ___________
19 ___________ ___________
20 ___________ ___________
21 ___________ ___________
22 ___________ ___________
23 ___________ ___________
24 ___________ ___________
25 ___________ ___________
26 ___________ ___________
27 ___________ ___________
28 ___________ ___________
29 ___________ ___________
30 ___________ ___________
CELL ELECTROLYTE LEVEL
No. AS FOUND AS LEFT
-----------------------------------
31 ___________ ___________
32 ___________ ___________
33 ___________ ___________
34 ___________ ___________
Section 26
35 ___________ ___________
36 ___________ ___________
37 ___________ ___________
38 ___________ ___________
39 ___________ ___________
40 ___________ ___________
41 ___________ ___________
42 ___________ ___________
43 ___________ ___________
44 ___________ ___________
45 ___________ ___________
46 ___________ ___________
47 ___________ ___________
48 ___________ ___________
49 ___________ ___________
50 ___________ ___________
51 ___________ ___________
52 ___________ ___________
53 ___________ ___________
54 ___________ ___________
55 ___________ ___________
56 ___________ ___________
57 ___________ ___________
58 ___________ ___________
Completed by ______________________ /________________________ Date____________
(signature) (print name)
DOE-STD-3003-2000
32
INTENTIONALLY BLANK
DOE-STD-3003-2000
CONCLUDING MATERIAL
Review Activity (Original Revision): Preparing Activity:
DOE Field Offices DOE-DP-45
DP AL
EE CH Project Number:
EH ID
EM NV EDCN-0002
ER OR
FE RL
FM SF
HR SR
NE Fernald
NN Golden
PO
RW
National Laboratories
BNL
LLNL
LANL
ORNL
PNL
SNL
Area Offices
Amarillo
Kirtland
Los Alamos
Princeton
Rocky Flats
Operations Offices
Idaho
Nevada
Oakland
Oak Ridge
Richland
U.S. DEPARTMENT OF ENERGY
DOCUMENT IMPROVEMENT PROPOSAL
(Instructions on Reverse)
DOE F 1300.3
(01-94)
1. Document Number 2. Document Title
3a. Name of Submitting Organization
3b. Address (Street, City, Zip Code)
4. Type of Organization (Mark one)
5. Problem Areas (Attach extra sheets as needed.)
a. Paragraph Number and Wording
b. Recommended Wording
c. Reason/Rationale for Recommendation
6. Remarks
7a. Name of Submitter (Last, First, MI) 7b. Work Telephone Number (Include Area Code)
7c. Mailing Address (Street, City, State, Zip Code) 8. Date of Submission
OMB Control No.
1910-0900
OMB Burden Disclosure
Statement on Reverse
Other (Specify: )
Manufacturer
User
Vendor
Printed with soy ink on recycled paper
DOE F 1300.3
(01-94)
OMB Control No.
1910-0900
INSTRUCTIONS: In a continuing effort to improve the U.S. Department of Energy (DOE) Technical Standards, this form is
provided for use in submitting comments and suggestions for improvements. All users of DOE Technical Standards are
invited to provide suggestions. This form may be detached, folded along the lines indicated, taped along the loose edge (DO
NOT STAPLE) mailed to the address indicated or faxed to (615) 574-0382.
1. The submitter of this form must complete blocks 1 through 8.
2. The Technical Standards Program Office (TSPO) will forward this form to the Preparing Activity. The Preparing Activity will
reply to the submitter within 30 calendar days of receipt from the TSPO.
NOTE: This form may not be used to request copies of documents, nor to request waivers, deviations, or clarification of
specification requirements on current contractors. Comments submitted on this form do not constitute or imply authorization
to waive any portion of the referenced document(s) or to amend contractual requirements.
Section 27
Public reporting burden for this collection of information is estimated to average 30 minutes per response, including the time
for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and
reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of
information, including suggestions for reducing this burden, to Office of Information Resources Management Policy, Plans,
and Oversight, Records Management Division, HR-422 - GTN, Paperwork Reduction Project (1910-0900), U.S. Department
of Energy, 1000 Independence Avenue, S.W., Washington, DC 20585; and to the Office of Management and Budget (OMB),
Paperwork Reduction Project (1910-0900), Washington, DC 20503.
OMB Burden Disclosure Statement
U.S. Department of Energy Technical Standards Program Office
c/o Performance Assurance Project Office
P.O. Box 2009, Bldg. 9201-3
Oak Ridge, Tennessee 37831-8065
FOREWORD
1. SCOPE
2. APPLICABLE DOCUMENTS
3. DEFINITIONS
4. GENERAL REQUIREMENTS
5. DETAILED REQUIREMENTS
6. NOTES
APPENDIX I
APPENDIX II
A. PREPARATION
B. INSPECTION AND CLEANING
C. BATTERY AND CHARGER CHECK
D. RETURN TO CUSTODIAN
CONCLUDING MATERIAL