DOE-STD-1104-2014 Requirements Crosswalk from DOE-STD-1104-2009
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
DOE-STD-1104-2009 to DOE-STD-1104-2014
Requirements Matrix
- 1 -
No. Section/
Page
Number
DOE-STD-1104-2009
Requirement
DOE-STD-1104-2014
Requirements
Comment
Gen DOE-STD-1104-2009 was broadly implemented but
not required.
DOE-STD-1104-2014 will be required by DOE
Order 420.1C, Page Change 1, soon to be approved
(already concurred upon by the program offices and
the Directives Review Board).
DOE-STD-1104-
2014will now be
a required
method. For
more discussion,
see letter from
Moniz to
Winokur,
October 18,
2014.
1 Guiding
Principles
Page Vii
#2
“If a contractor uses a method other than a safe
harbor method from Table 2 of Appendix A of 10
CFR Part 830, per 10 CFR 830.204, the contractor
must obtain DOE approval of the method before
developing the DSA. Likewise, if a contractor uses a
safe harbor method to develop the DSA, but does
not follow the method completely, per 10 CFR
830.204, the contractor must request DOE approval
of the method with the specific deviations noted.”
No corresponding requirement in DOE-STD-1104-
2014.
Section 4.1 [Paragraph 3, Page 11] does provide the
following:
“If a contractor uses a method other than a safe
harbor method from Table 2 of Appendix A of 10
C.F.R. Part 830, per 10 C.F.R. § 830.204, the
contractor is required to obtain DOE approval of the
method. If a contractor uses a safe harbor method to
develop the DSA, but does not follow the method
completely, per 10 C.F.R. § 830.204, the contractor
is required to request DOE approval of the method
used (with the specific deviations noted) in
accordance with DOE-STD-1083-2009, or successor
document.”
These are10
C.F.R. 830
requirements;
they do not have
to be repeated as
requirements in
DOE-STD-1104-
2014.
2 Intro-
duction
Page 1
“This Standard utilizes the verb “must” to specify
requirements in associated rules or DOE Orders or
critical actions in performing the safety basis
document reviews.”
“Throughout this Standard, the word “shall” denotes
actions that are required to comply with this
Standard.” [Foreword #6, Page i]
“Throughout this Standard, the word “shall” denotes
actions that are required to comply with this
“Throughout this
Standard, the
word “shall”
denotes actions
that are required
to comply with
DOE-STD-1104-2009 to DOE-STD-1104-2014
Requirements Matrix
- 2 -
No. Section/
Page
Number
DOE-STD-1104-2009
Requirement
DOE-STD-1104-2014
Requirements
Comment
Standard.” [Introduction, Paragraph 6, Page 1] this Standard.”
[Foreword #5,
Page 1]
3 1.4
Paragraph
6
Pages 7-8
“As stated in 10 CFR 830.202, contractors must
incorporate in the safety basis any changes,
conditions, or hazard controls directed by DOE. The
regulation also states that the SER must document
the basis for approval of the safety basis for the
facility including any conditions of approval.”
No corresponding requirement in DOE-STD-1104-
2014.
Section 3.5 [Paragraph 9, Page 9] does provide the
following:
“As stated in10 C.F.R. § 830.202 (c) (3), contractors
are required to incorporate in the safety basis any
changes, conditions, or hazard controls directed by
DOE. Section 830.207 (d) of the Rule states that ‘A
contractor may not begin operation of the facility or
modification prior to the issuance of an SER in
which DOE approves the safety basis for the facility
or modification.”
These are10
C.F.R. 830
requirements;
they do not have
to be repeated as
requirements in
Section 2
DOE-STD-1104-
2014.
4 No corresponding requirement in DOE-STD-1104-
2009.
“In circumstances where no viable control strategy
exists in an existing facility to prevent or mitigate the
offsite dose consequence of one or more of the
accident scenarios from exceeding the EG, the
cognizant PSO shall serve as the DOE approval
authority and this approval may not be delegated. In
such cases, the approval authority shall obtain
concurrence from the CTA and consult with the
Office of Environment, Health, Safety, and Security
on the technical adequacy of the DSA submittal.”
[3.2, Paragraph 4, Page 5]
New
requirement.
DOE 2010-1
Implementation
Plan issue.
5 No corresponding requirement. “In cases where the SBRT has multiple review team
members and the review is complex (such as for a
new facility or major modification), at least one
member of the SBRT shall meet the requirements of
DOE-STD-1183-2007.” [3.3, Paragraph 4, Page 7]
New
requirement.
Reflects
experience and
lessons learned.
DOE-STD-1104-2009 to DOE-STD-1104-2014
Requirements Matrix
- 3 -
No. Section/
Page
Number
DOE-STD-1104-2009
Requirement
DOE-STD-1104-2014
Requirements
Comment
6 1.4
Paragraph
7
Page 8
“To ensure adequate tracking and closure of
conditions of approval, the DOE site office staff
must:
Verify that contractors have a documented
process for:
o tracking conditions of approval to closure
(including any required compensatory
measures),
o verifying satisfactory closure of the condition
of approval,
o notifying DOE when a condition of approval
has been satisfied, and
o managing any conditions of approval until
they are closed.
Ensure that when a condition of approval is
satisfied, the basis for closure is documented
in the next update of the DSA, and the
closure of the condition of approval is noted
in the DOE approval of that update of the
DSA; and
Periodically assess the closure progress and
status of conditions of approval, as well as
the contractor tracking process for them.”
“To ensure adequate tracking and closure of
conditions of approval, the DOE site office staff
shall:
Verify that contractors have a documented
process for:
o tracking conditions of approval to closure
(including any required compensatory
measures);
o verifying satisfactory closure of the
condition of approval;
o notifying DOE when a condition of
approval has been satisfied; and
o managing any conditions of approval until
they are closed.
Ensure that when a condition of approval is
satisfied, the basis for closure is documented
in the next update of the DSA and/or TSRs,
and the closure of the condition of approval
is noted in the DOE approval of that update;
and
Periodically assess the closure progress and
status of conditions of approval, as well as
the contractor tracking process for them.”
[3.5, Paragraph 10, Page 9]
Comparable.
7 1.4
Paragraph
“These directed changes must be incorporated into
the approved TSRs prior to operation under the
“SER-directed changes shall be incorporated into the
approved TSRs prior to operation under the approved
Comparable.
DOE-STD-1104-2009 to DOE-STD-1104-2014
Requirements Matrix
- 4 -
No. Section/
Page
Number
DOE-STD-1104-2009
Requirement
DOE-STD-1104-2014
Requirements
Comment
8
Page 8
approved safety basis.” safety basis.” [3.5, Paragraph 11, Page 10]
8 No corresponding requirement. “In circumstances where no viable control strategy
Section 3
exists in an existing facility to prevent or mitigate the
consequence of one or more of the accident scenarios
from exceeding the EG, DOE shall verify that
information is included in the DSA, or an attachment
to the DSA, that is consistent with the requirements
described in Section 3.3.1 of DOE-STD-3009-2014”
[4.9, Paragraph 2, Page 18]
New
requirement.
9 No corresponding requirement. “The SBAA for DSAs that include mitigated doses
above the EG shall be at the PSO, at a minimum.
The SBAA shall obtain concurrence from the CTA
and consult with the Office of Environment, Health,
Safety and Security on the technical adequacy of the
DSA submittal.” [4.9, Paragraph 5, Page 19]
New
requirement.
10 2.6
Paragraph
1
Page 13
“While these elements must be addressed in the
DSA, generic descriptions of these institutional
programs should not be duplicated in the DSA if
they can be referenced in Integrated Safety
Management System documents or site-wide
manuals.”
No corresponding requirement.
Section 4.8 [Paragraph 1, Page 17] does provide the
following:
“While these elements are required to be addressed in
the DSA, generic descriptions of these institutional
programs should not be duplicated in the DSA if they
can be referenced in Integrated Safety Management
System documents or in site-wide manuals.”
Rhetorical; not
necessary.
11 2.7
Paragraph
1
Page 14
“A defined closure date or milestone must be
identified in the condition of approval.”
“A defined closure date or milestone shall be
identified in the condition of approval.” [4.10,
Paragraph 1, Pages 19-20]
Comparable.
DOE-STD-1104-2009 to DOE-STD-1104-2014
Requirements Matrix
- 5 -
No. Section/
Page
Number
DOE-STD-1104-2009
Requirement
DOE-STD-1104-2014
Requirements
Comment
12 2.7
Paragraph
5
Page 15
“Fundamentally, the DSA must demonstrate that
proposed activities have been thoroughly described
and analyzed and that the hazards have been
adequately identified. The DSA must establish the
linkage between the individual hazards identified
and the final control set that addresses each hazard.
The functions of the controls that are relied upon for
safety must be clearly documented and
demonstrated to be adequate for the bounded
hazards that they are intended to address. The
selected controls must be documented as capable of
providing the credited safety functions and
appropriately captured in the TSRs.”
No corresponding requirement.
Section 4.10 [Paragraph 5, Page 20] does provide the
following:
“Fundamentally, the DSA is intended to demonstrate
that proposed activities have been thoroughly
described and analyzed and that the hazards have
been adequately identified. The DSA establishes the
linkage between the individual hazards identified and
the final control set that addresses each hazard. The
functions of the controls that are relied upon for
safety are clearly documented and demonstrated to
be adequate for the bounded hazards that they are
intended to address. The selected controls are
documented as capable of providing the credited
safety functions and appropriately captured in the
TSRs.”
Rhetorical; these
are DSA and
SER issues,
covered
elsewhere.
Addressed in
SER Evaluation
Criteria.
13 3.1
Page 16
“Because the TSRs must implement commitments
made in the DSA, approvals and implementation of
both the DSA and TSRs must be coordinated.”
No corresponding requirement.
Section 4
Section 5.1 [Paragraph 1, Page 22] does provide the
following:
“Because the TSRs implement commitments made in
the DSA, approvals and implementation of both the
DSA and TSRs should be coordinated.”
Rhetorical; not
necessary.
14 3.2.2
Page 17
“Safety SSCs must be described in sufficient detail
in a DSA so that their functional requirements are
defined and the bases for TSR requirements are
derived….In any case, safety SSCs must be
addressed specifically in TSR provisions.”
No corresponding requirement.
Section 5.3 [Paragraph 1, 2
nd
bullet, Page 22] does
provide the following:
“Review criteria to assess consistency are provided
below:
Safety SSCs are addressed specifically in
Rhetorical; these
are DSA and
TSR issues,
covered
elsewhere.
Addressed in
SER Evaluation
DOE-STD-1104-2009 to DOE-STD-1104-2014
Requirements Matrix
- 6 -
No. Section/
Page
Number
DOE-STD-1104-2009
Requirement
DOE-STD-1104-2014
Requirements
Comment
TSR provisions.”
(note: the first sentence on describing Safety SSCs
was deleted)
Criteria.
15 3.2.3
Page 17
“When SACs are used, they must be controlled
through the TSR."
No corresponding requirement.
Section 5.3 [Paragraph 1, 4
th
bullet, Page 23] does
provide the following:
“Review criteria to assess consistency are provided
below:
When SACs are used, they are controlled
through the TSR.”
Rhetorical; these
are DSA and
TSR issues,
covered
elsewhere.
Addressed in
SER Evaluation
Criteria.
16 No corresponding requirement. “The basis for approval of the USQ procedure shall
address the expectations from the DOE G 424.1-1B,
Implementation Guide for Use in Addressing
Unreviewed Safety Question Requirements (or
successor document in the site contract).” [6.1,
Paragraph 2, Page 25]
New
requirement;
New section for
completeness to
address all DOE
approvals related
to safety basis.
17 No corresponding requirement. “The bases for approval of the ESS or JCO shall
address the expectations from the DOE Guide G
424.1-1B (or successor document in the site contract)
as described below.” [6.2, Paragraph 4, Page 25]
New
requirement;
New section.
18 No corresponding requirement. “In these cases, DOE shall review and approve the
final categorization based on facility-specific hazard
analysis to confirm that the hazard analysis and final
categorization are accurate.” [6.3, Paragraph 1, Page
26]
New
requirement;
New section.
19 4.0
Paragraph
“The SER clearly states any conditions of approval
that impose additional commitments to which
“The SER for a given facility or operation shall
document: (1) the conduct of an appropriate review
This is the main,
broad SER
DOE-STD-1104-2009 to DOE-STD-1104-2014
Requirements Matrix
- 7 -
No. Section/
Page
Number
DOE-STD-1104-2009
Requirement
DOE-STD-1104-2014
Requirements
Comment
3
Page 18
facility management must adhere beyond those
already documented in the DSA and TSRs.”
of the safety basis document (e.g., PDSA, DSA, or
TSRs); (2) the bases for approving these documents
(see Sections 4, 5, and 6 of this Standard for approval
bases for different safety basis documents); and (3)
any conditions of approval.” [7.1, Paragraph 1, Page
28]
requirement that
requires
appropriate
review against
evaluation
criteria.
20 No corresponding requirement. “In such cases the letter or report shall address the
following:
The sufficiency of the safety basis document
Section 5
for a hazard category 1, 2, or 3 DOE nuclear
facility;
The extent to which a contractor has satisfied
the requirements of Subpart B of 10 C.F.R.
Part 830; and,
The basis for approval by DOE of the safety
basis for the facility, including any
conditions for approval.”
[7.1, Paragraph 10, Page 30]
New requirement
for short-form
SERs.
21 4.3
Bullet 1
Page 20
“For the PDSA, that it provides a reasonable basis
for the preliminary conclusion that the nuclear
facility can be operated safely based on the
following: (1) the nuclear safety design criteria in
DOE O 420.1B have been satisfied; (2) a safety
analysis meeting DOE O 420.1B and DOE-STD-
1189-2008 requirements to support the design has
been performed; and (3) an initial listing is provided
of the safety management programs that must be
developed to address operational safety
considerations.”
No corresponding requirement.
Section 7.2.3 [Paragraph 1, 1
st
bullet, Page 31] does
provide the following:
“For the PDSA, that it provides a reasonable basis for
the preliminary conclusion that the nuclear facility
can be operated safely based on the following: (1)
the nuclear safety design criteria in DOE O 420.1C
(or successor document in the site contract) have
been satisfied; (2) a safety analysis meeting DOE O
420.1C and DOE-STD-1189-2008 requirements to
support the design has been performed; and (3) an
Covered in #35.
DOE-STD-1104-2009 to DOE-STD-1104-2014
Requirements Matrix
- 8 -
No. Section/
Page
Number
DOE-STD-1104-2009
Requirement
DOE-STD-1104-2014
Requirements
Comment
initial listing is provided of the safety management
programs that have been or will be developed to
address operational safety considerations.”
22 4.8
Page 22
“However the safety function of SACs must be
clearly defined so that the decision to use an SAC
rather than a safety SSC can be evaluated.”
No corresponding requirement.
Section 7.2.8 [Paragraph 1, Page 33] does provide
the following:
“The safety function of SACs is clearly defined so
that the decision to use an SAC rather than a safety
SSC can be evaluated.”
Rhetorical; this is
a DSA issue,
covered
elsewhere, such
as safe harbor
standards.
Addressed in
SER Evaluation
Criteria.
23 No corresponding requirement. “Whenever a compensatory measure is needed to
ensure appropriate safety levels are maintained while
a temporary condition of approval is in effect, that
compensatory measure shall be clearly articulated in
the SER. It then becomes part of the facility safety
basis.” [7.2.12, Paragraph 2, Page 34]
Clarification.
New
requirement.
24 No corresponding requirement. “Design basis accidents (DBAs) identified for
new facilities and major modifications shall be
prevented or have mitigated offsite dose
consequences below the EG.” [8.1, Paragraph 3,
Page 35]
New require-
ment. DOE
2010-1 Imple-
mentation Plan
issue. See also
#4 above.
25 No corresponding requirement. “DOE shall document the review of the SDS either
in an SVR or in a letter (with a basis for approval
attached) for approval by the SBAA and the Federal
Project Director.”
New
requirement.
Clarified
expectation,
based on
experience and
lessons learned.
26 No corresponding requirement. “DOE shall review and approve updates of the New
DOE-STD-1104-2009 to DOE-STD-1104-2014
Requirements Matrix
- 9 -
No. Section/
Page
Number
DOE-STD-1104-2009
Requirement
DOE-STD-1104-2014
Requirements
Section 6
Comment
SDS.” requirement.
Clarified
expectation,
based on
experience and
lessons learned.
27 5.2
Paragraph
1
Page 27
“The CSDR must reflect the project configuration
at conceptual design; however, the design at this
phase is not fully defined and the CSDR may (1)
propose more than one possible approach to some
aspects of the design and (2) identify some areas
that will need more research and development at
later stages.”
No corresponding requirement.
Section 8.4 [Paragraph 2, Page 38] does provide the
following:
“As described in DOE-STD-1189, the CSDR reflects
the project configuration at conceptual design;
however, the design at this phase is not fully defined
and so the CSDR may (1) propose more than one
possible approach to some aspects of the design and
(2) identify some areas needing more research and
development at later stages.”
Unnecessary
requirement
statement,
relative to safety
basis
expectations
28 5.2
Paragraph
2
Page 27
“Although some of the decisions and selections may
be preliminary at this phase of design, the CSDR
reviewer must confirm that the following are
adequate and sufficiently conservative to proceed
from the conceptual design phase to the preliminary
design phase:”
“Although some of the decisions and selections may
be preliminary at this phase of design, the CSDR
reviewer shall confirm that the following are
adequate and sufficiently conservative to support
proceeding from the conceptual design phase to the
preliminary design phase:
Hazard categorization (hazard category-1, -2
or -3) of the facility;
Preliminary identification of the facility
DBAs;
Assessment of the need for safety class and
safety significant facility-level safety
Comparable
requirement.
DOE-STD-1104-2009 to DOE-STD-1104-2014
Requirements Matrix
- 10 -
No. Section/
Page
Number
DOE-STD-1104-2009
Requirement
DOE-STD-1104-2014
Requirements
Comment
controls based on the preliminary hazard
analysis, preliminary fire hazard analysis
and analysis of the DBAs;
Application of the principles of the
hierarchy of controls;
Preliminary assessment of the appropriate
natural phenomena hazards (NPH) design
criteria for the facility; and
Compliance with the safety design criteria of
DOE O 420.1C, Facility Safety (or successor
document), or any alternate criteria proposed.”
[8.4, Paragraph 3, Page 38]
29 5.2
Paragraph
4
Page 28
“As part of the review of the CSDR, the reviewer
must:” (followed by list of 14 items)
“As part of the review of the CSDR, the reviewer
shall perform the following review activities:
Assess whether the identified facility level
DBAs appear to be a complete set;
Determine if the safety function/NPH
classifications from Appendices A and B of
DOE-STD-1189-2008 were appropriately
applied;
Assess the adequacy of the preliminary
hazard analysis against the expectations in
Section 4.2 of DOE-STD-1189-2008;
Evaluate the technical adequacy of the basis
of the chosen confinement strategy (i.e.,
active confinement ventilation is preferred
Comparable.
DOE-STD-1104-2009 to DOE-STD-1104-2014
Requirements Matrix
- 11 -
No. Section/
Page
Number
DOE-STD-1104-2009
Requirement
DOE-STD-1104-2014
Requirements
Comment
over passive confinement systems per DOE
O 420.1C, which states that “Alternate
confinement approaches may be acceptable if
a technical evaluation demonstrates that the
alternate confinement approach results in
Section 7
very high assurance of the confinement of
radioactive materials” and includes a
footnote stating that “The safety
classification (if any) of the ventilation
system is determined by the facility
documented safety analysis.”);
Review the risk and opportunity assessment1
to confirm that technical uncertainties related
to safety are identified;
Confirm that the current safety design basis
is conservative and the risk of significant
redesign related to major or costly changes in
safety controls is minimized or properly
documented in the CSDR and addressed as
discussed in items 7 and 8;
Confirm that the CSDR contains a summary
of the risks and opportunities associated with
the safety design basis strategies;
Confirm that the CSDR identifies risk
handling strategies that bound each identified
risk;
Confirm that the hazard analysis is complete
to the degree appropriate for the stage of
DOE-STD-1104-2009 to DOE-STD-1104-2014
Requirements Matrix
- 12 -
No. Section/
Page
Number
DOE-STD-1104-2009
Requirement
DOE-STD-1104-2014
Requirements
Comment
development;
Confirm that the process in DOE-STD-1189-
2008, as tailored in the SDS, was used for
the selection of safety controls at the facility
level;
Evaluate the decisions made with respect to
the safety classification of the safety controls
and associated functions, and adequate
implementation of defense-in-depth;
Ensure that any open Conditions of Approval
from the DOE review of the SDS are
resolved;
Ensure that any safety issues that require
further study are identified in the CSDR;
Confirm that the safety design aspects of the
project support moving ahead to the
preliminary design phase and all DBAs
considered for new facilities have been
prevented or have mitigated offsite dose
consequences below the EG; and,
Evaluate the CSDR to ensure that the hazard
controls were selected consistent with the
principles of the hierarchy of hazard
controls:
passive engineering features;
active engineering features;
administrative controls; and
DOE-STD-1104-2009 to DOE-STD-1104-2014
Requirements Matrix
- 13 -
No. Section/
Page
Number
DOE-STD-1104-2009
Requirement
DOE-STD-1104-2014
Requirements
Comment
personal protective equipment.”
[8.4, Paragraph 4, Page 38]
30 5.3
Paragraph
3
Page 29
“The reviewer of the PSDR must also confirm that
it adequately addresses the following safety
design basis aspects for the preliminary design
phase:”
“The reviewer of the PSDR shall also confirm that it
adequately addresses the following safety design
basis aspects for the preliminary design phase:
The nuclear facility design requirements of
DOE O 420.1C.
A viable design solution (e.g., safety SSCs)
to provide the safety functions assessed to be
necessary by the hazard and accident
analysis, as follows:
o The unmitigated accident
consequence assessment properly
indicates the required functional
classification (i.e., safety class versus
safety significant) and seismic and
other NPH design requirements (i.e.,
the proper seismic design criteria for
seismic design and performance
criteria for other NPH design).
o The analysis of DBAs identifies the
functional requirements that the
safety SSCs and SACs perform and
the conditions (e.g., normal and
accident) under which these
functions are required to be
performed. As discussed in DOE-
STD-1189-2008 Section 4.3, “SACs
should only be selected if engineered
Section 8
Comparable.
DOE-STD-1104-2009 to DOE-STD-1104-2014
Requirements Matrix
- 14 -
No. Section/
Page
Number
DOE-STD-1104-2009
Requirement
DOE-STD-1104-2014
Requirements
Comment
controls cannot be identified or are
not practical.” Where SACs are
included in lieu of an SSC, an
explanation should be provided in
the PDSR for DOE to determine the
adequacy of that rationale. Other
expectations for the discussion of
SACs in the PSDR are included in
Appendix I of DOE-STD-1189-
2008.
o The safety systems can meet the
functional requirements and any
unique technology development that
may be needed has been identified.
Appropriate supplemental design criteria
(DOE O 420.1C, Attachment 3) as specified
for safety SSCs, as follows:
o General requirements for safety class
and safety significant SSCs are
specified (e.g., conservative design
features, design against single
failure, environmental qualification,
safe failure modes, as appropriate).
o Based on the functional
classification and the safety SSC
design function, appropriate codes
and standards are specified and
tailored, as needed, or alternate
codes and standards are identified
and justified.
Descriptions of the technical studies needed
DOE-STD-1104-2009 to DOE-STD-1104-2014
Requirements Matrix
- 15 -
No. Section/
Page
Number
DOE-STD-1104-2009
Requirement
DOE-STD-1104-2014
Requirements
Comment
to complete the safety design.
Safety design risks and risk mitigation
strategies for the final design phase.
Resolution of any open Conditions of
Approval identified in the CSVR.”
[8.4, Paragraph 4, Page 40]
31 5.3
Paragraph
3, 2b
Page 30
“The analysis of DBAs identifies the functional
requirements that the safety SSCs and SACs must
perform and the conditions (e.g., normal and
accident) under which these functions must be
performed.”
No corresponding requirement.
Section 8.5 [Paragraph 3, 2
nd
bullet, 2
nd
sub-bullet,
Page 40] does provide the following:
“The analysis of DBAs identifies the functional
requirements that the safety SSCs and SACs perform
and the conditions (e.g., normal and accident) under
which these functions are required to be performed.”
Rhetorical.
32 5.3
Paragraph
4
Page 30
“The PSDR must demonstrate the adequacy of the
hazard analyses and the selection and classification
of the safety controls, including consideration of the
application of the principles associated with the
hierarchy of controls.”
No corresponding stand-alone requirement.
Section 8.5 [Paragraph 4, Page 41] does provide the
following:
“As described in DOE-STD-1189, the PSDR is
intended to demonstrate the adequacy of the hazard
analyses and the selection and classification of the
safety controls, including consideration of the
application of the principles associated with the
hierarchy of controls.
9
”
Unnecessary
requirement.
Covered by #30.
DOE-STD-1104-2009 to DOE-STD-1104-2014
Requirements Matrix
- 16 -
No. Section/
Page
Number
DOE-STD-1104-2009
Requirement
DOE-STD-1104-2014
Requirements
Comment
33 5.4
Paragraph
1, #3
Page 31
“An initial listing of the safety management
programs that must be developed to address
operational safety considerations.”
No corresponding stand-alone requirement.
Section 8.6 [Paragraph 1, #3, Page 42] does provide
the following:
“An initial listing of the safety management
programs [to] be developed to address operational
safety considerations.”
Unnecessary
Section 9
requirement.
Covered by #35.
34 5.4
Paragraph
2
Page 31
“When a PDSA is required, it must be approved by
DOE before the contract or can procure materials or
components or begin construction, unless DOE
provides relief under the provisions of the Rule.”
“When a PDSA is required, it shall be approved by
DOE before the contractor can procure materials or
components or begin construction, unless DOE
provides relief under the provisions of the Rule.”
[8.6, Paragraph 2, Page 42]
Comparable.
35 5.4
Paragraph
4
Page 32
“The PDSA must identify any changes that were
made to the decisions and commitments in the
PDSR.”
“The review of the PDSA shall confirm that:
The design safety analysis is complete and
demonstrates the adequacy of the design
from the safety perspective. The PDSA does
not need to show the progression of the
design that led to the final choices, only the
final choices and the justification for their
adequacy;
The safety design requirements specified at
the end of the preliminary design have been
met;
The hazards and accident analysis is
consistent with DOE-STD-1189-2008,
Section 4.4;
The description of the final design of the
Comparable.
DOE-STD-1104-2009 to DOE-STD-1104-2014
Requirements Matrix
- 17 -
No. Section/
Page
Number
DOE-STD-1104-2009
Requirement
DOE-STD-1104-2014
Requirements
Comment
facility is adequate with respect to safety
SSCs and safety design features;
Safety SSCs, SACs, and other hazard
controls are identified and their performance
requirements are clearly stated. In addition
to the review consideration presented in
Section 8.4 of this Standard regarding SACs,
expectations for the discussion of SACs in
the PDSA are included in Appendix I of
DOE-STD-1189-2008;
The description of how the selected safety
controls prevent and/or mitigate identified
hazards and accidents is adequate;
The description of how selected safety
controls provide defense-in-depth is
adequate, based on mitigated accident
frequency and on control reliability;
11
The initial list of safety management
programs is complete;
The description of how the nuclear safety
design criteria of DOE O 420.1C (or
applicable version) have been satisfied by the
design is adequate;
Any technical issues that required research or
other data collection to finalize the design
have been resolved;
12
Preliminary approaches to startup and
operations management have been
documented; and
DOE-STD-1104-2009 to DOE-STD-1104-2014
Requirements Matrix
- 18 -
No. Section/
Page
Number
DOE-STD-1104-2009
Requirement
DOE-STD-1104-2014
Requirements
Comment
Any open Conditions of Approval identified
in the PSVR have been resolved. ”
[8.6, Paragraph 5, Page 43]
36 Footnote
11
Page 32
“The technical issue(s) giving rise to the need for
research or other data collection must be identified
in the project.”
No corresponding stand-alone requirement.
Section 8.6 [Footnote 12, Page 43] does provide the
following:
“The technical issue(s) giving rise to the need for
research or other data collection should be identified
in the project Risk and Opportunity Assessment,
including the plan and rationale for resolution of the
issue(s).”
Unnecessary
requirement.
Covered by #35.
37 Footnote
Page 33
“DOE reviewers must evaluate the risk and
opportunity evaluation to ensure that it is robust in
identifying unknowns and potential technical issues
Section 10
related to the results of the hazard analysis;
specifically, the selection of hazard controls.”
No corresponding stand-alone requirement.
Section 8.6 [Footnote 12, Page 43] does provide the
following:
“DOE reviewers should evaluate the risk and
opportunity evaluation to ensure that it is robust in
identifying unknowns and potential technical issues
related to the results of the hazard analysis;
specifically, the selection of hazard controls.”
Unnecessary
requirement.
Covered by #35.
38 5.5.2.7
Paragraph
1
Page 36
“For the CSVR (Conceptual Design Phase), this
section must document how the hazard and accident
analyses are consistent with DOE-STD-1189-2008,
Section 4.2, and follow the format of Appendix H of
that Standard or the format that is defined and
approved in the SDS.”
No corresponding requirement.
Section 8.7.2.7 [Paragraph 1, Page 47] does provide
the following:
“For the CSVR (Conceptual Design Phase), this
section documents how the hazard and accident
analyses are (a) consistent with DOE-STD-1189-
2008, Section 4.2, and (b) follow the format of
Appendix H of that standard, or the format defined
and approved in the SDS.”
Unnecessary
documentation
requirement.
Essential
elements
captured in
CSDR review
criteria.
DOE-STD-1104-2009 to DOE-STD-1104-2014
Requirements Matrix
- 19 -
No. Section/
Page
Number
DOE-STD-1104-2009
Requirement
DOE-STD-1104-2014
Requirements
Comment
39 5.5.2.7
Paragraph
2
Page 36
“For the PSVR (Preliminary Design Phase), this
section must document how the hazard and accident
analyses are consistent with DOE-STD-1189-2008,
Section 4.3 and follow the format of Appendix I of
that Standard or the format that is defined and
approved in the SDS.”
No corresponding requirement.
Section 8.7.2.7 [Paragraph 2, Page 47] does provide
the following:
“For the PSVR (Preliminary Design Phase), this
section documents how the hazard and accident
analyses are (a) consistent with DOE-STD-1189-
2008, Section 4.3 and (b) follow the format of
Appendix I of that standard, or the format defined
and approved in the SDS.”
Unnecessary
documentation
requirement.
Essential
elements
captured in
review criteria.
40 5.5.2.8
Page 36
“This section must identify the designated nuclear
facility hazard category level (hazard category 1, 2
or 3) and assess whether the designated level is
appropriate. This section must be used to address
any issues related to any uncertainties in the nuclear
facility hazard category level and the potential costs
and opportunities if the level is revised at a later
date.”
No corresponding requirement.
Section 8.7.2.8 [Paragraph 1, Page 47] does provide
the following:
“This section identifies the designated nuclear
facility hazard category level (hazard category 1, 2 or
3) and assess whether the designated level is
appropriate. This section addresses any issues
related to any uncertainties in the nuclear facility
hazard category level and the potential costs and
opportunities if the level is revised at a later date.”
Unnecessary
documentation
requirement.
Essential
elements
captured in
review criteria.
41 5.5.2.9
Page 37
“This section must address the identified safety
SSCs in the CSDR or the PSDR, their bases and
their functions, and any issues related to the
identified set.”
No corresponding requirement.
Section 8.7.2.9 [Paragraph 1, Page 48] does provide
the following:
“This section addresses the safety SSCs identified in
Section 11
the CSDR or the PSDR, their bases and their
functions, and any issues related to the identified
set.”
Unnecessary
documentation
requirement.
Essential
elements
captured in
review criteria.
DOE-STD-1104-2009 to DOE-STD-1104-2014
Requirements Matrix
- 20 -
No. Section/
Page
Number
DOE-STD-1104-2009
Requirement
DOE-STD-1104-2014
Requirements
Comment
42 5.5.2.10
Page 37
“This section must address any identified SACs in
the CSDR or the PSDR, their bases and their
functions, and any issues related to the identified
set.”
No corresponding requirement.
Section 8.7.2.10 [Paragraph 1, Page 48] does provide
the following:
“This section addresses any identified SACs in the
CSDR or the PSDR, their bases and their functions,
and any issues related to the identified set.”
Unnecessary
documentation
requirement.
Essential
elements
captured in
review criteria.
43 5.5.2.11
Page 37
“This section must address any issues with the
hazard controls identified in the CSDR or PSDR.”
No corresponding requirement.
Section 8.7.2.11 [Paragraph 1, Page 48] does provide
the following:
“This section addresses any issues associated with
other hazard controls identified in the CSDR or
PSDR.”
Unnecessary
documentation
requirement.
Essential
elements
captured in
review criteria.
44 5.5.2.12
Page 37
“This section must provide the basis for approval of
the design codes and standard(s) identified in
the CSDR or PSDR, including any exceptions to the
design codes and standards listed in DOE O 420.1B,
DOE G 420.1-1, and DOE G 420.1-2. This section
does not constitute an exemption to the
requirements of DOE O 420.1B, which must be
requested separately if needed.”
No corresponding requirement.
Section 8.7.2.12 [Paragraph 1, Page 48] does provide
the following:
“This section provides the basis for approval of the
design codes and standards identified in the CSDR or
PSDR, and identify any exceptions to the design
codes and standards listed in DOE O 420.1C and
DOE G 420.1-1A. This section does not constitute an
exemption to the requirements of DOE O 420.1C,
which are required to be requested separately if
needed.”
Unnecessary
documentation
requirement.
Essential
elements
captured in
review criteria.
DOE-STD-1104-2009 to DOE-STD-1104-2014
Requirements Matrix
- 21 -
No. Section/
Page
Number
DOE-STD-1104-2009
Requirement
DOE-STD-1104-2014
Requirements
Comment
45 5.5.2.13
Page 37
“If the contractor used design criteria other than that
documented in DOE O 420.1B, this section must
document the evaluation of the alternate criteria and
assess the acceptability of those criteria.”
No corresponding requirement.
Section 8.7.2.13 [Paragraph 1, Page 48] does provide
the following:
“If the contractor used design criteria other than
those documented in DOE O 420.1C, this section
documents the evaluation of the alternate criteria and
assess the acceptability of those criteria.”
Unnecessary
documentation
requirement.
Essential
elements
captured in
review criteria.
46 5.5.2.14
Page 37
“This section must document any conditions for
proceeding to the next stage of design. The section
must also document any recommendation that the
project is not ready to proceed to the next phase of
design.”
No corresponding requirement.
Section 8.7.2.14 [Paragraph 1, Page 48] does provide
the following:
“This section documents any conditions for
proceeding to the next stage of design. The section
also documents any recommendation that the project
is not ready to proceed to the next phase of design.”
Unnecessary
documentation
requirement.
Essential
elements
captured in
review criteria.
47 5.5.2.15
Page 37
“This section must summarize the significant issues
in the review and document whether the CSDR or
the PSDR is acceptable.”
No corresponding requirement.
Section 8.7.2.15 [Paragraph 1, Page 48] does provide
the following:
“This section summarizes the significant issues in the
review and document whether the CSDR or the
PSDR is acceptable.”
Unnecessary
documentation
requirement.
Essential
elements
captured in
review criteria.