DOE-STD-3006-2010, Planning and Conducting Readiness Reviews
Functional areas: Readiness Reviews, Readiness Assessments, Startup Notification Reports
This Standard provides standardized methods and approaches for planning and conducting RRs. This Standard also provides guidance for preparation of exemption requests in accordance with DOE O 251.1C. DOE O 425.1D requirements for RRs apply both to responsible contractors and to DOE. Supersedes DOE-STD-3006-2000.
Version history and related documents
Supersedes
Earlier documents this one replaced.
Related documents
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
DOE-STD-3006-2010
________________________
Superseding
DOE-STD-3006-2000
June 2000
DOE STANDARD
PLANNING AND CONDUCTING
READINESS REVIEWS
U.S. Department of Energy AREA OPER
Washington, D.C. 20585
DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.
TS
This document has been reproduced directly from the best available copy.
Available to DOE and DOE contractors from ES&H Technical Information Services,
U.S. Department of Energy, (800) 473-4375, fax: (301) 903-9823.
Available to the public from the U.S. Department of Commerce, Technology Administration,
National Technical Information Service, Springfield, VA 22161; (703) 605-6000.
DOE-STD-3006-YR
i
CONTENTS
FOREWORD................................................................................................................................. 1
1 SCOPE, PURPOSE, AND ORGANIZATION ..................................................................... 2
1.1 Scope. ............................................................................................................................... 2
1.2 Purpose. ............................................................................................................................ 2
1.3 Organization of the Standard. .......................................................................................... 3
2 DEFINITIONS ........................................................................................................................ 4
3 OVERVIEW OF THE READINESS REVIEW PROCESS ............................................. 13
3.1 History and Purpose of Readiness Reviews. .................................................................. 14
3.2 Differences Between Operational Readiness Reviews and Readiness Assessments. .... 14
3.3 Determining the Level of Readiness Review and Contents of the Startup Notification
Report....................................................................................................................... 15
3.4 Core Requirements. ........................................................................................................ 16
3.5 Focus and Sequence of Contractor and DOE Readiness Reviews. ............................... 16
3.6 DOE Headquarters and Field Line Management Oversight Responsibilities. .............. 18
3.7 Approval to Start Up or Restart Nuclear Operations. .................................................... 18
4 DETERMINING THE SCOPE AND THE LEVEL OF THE READINESS REVIEW 19
5 STARTUP NOTIFICATION REPORTS ........................................................................... 25
6 ACHIEVING READINESS ................................................................................................. 28
7 ROLES AND RESPONSIBILITIES ................................................................................... 28
7.1 Contractor Line Management. ....................................................................................... 28
7.2 DOE Field Element Line Management. ......................................................................... 30
7.3 DOE Headquarters Line Management, including Oversight Organizations. ................ 32
7.4 Office of Health, Safety and Security. ........................................................................... 32
7.5 Readiness Review Team Leader. ................................................................................... 32
7.6 Readiness Review Team Members. ............................................................................... 34
Section 2
8 OPERATIONAL READINESS REVIEWS ....................................................................... 35
8.1 Plan of Action. ............................................................................................................... 35
8.2 Operational Readiness Review Implementation Plan. ................................................... 41
8.3 Implementation Plan Format.......................................................................................... 42
8.4 Conduct of Operational Readiness Reviews. ................................................................. 45
8.5 Contractor Operational Readiness Reviews. .................................................................. 48
8.6 Readiness to Proceed Memorandum. ............................................................................. 50
8.7 DOE Action Following Receipt of the Readiness to Proceed Memorandum. ............... 51
8.8 DOE Operational Readiness Reviews. .......................................................................... 52
8.9 Documentation of Operational Readiness Review Results. .......................................... 52
8.10 Prestart and Post-Start Findings. .................................................................................... 57
8.11 Corrective Action Plans. ................................................................................................ 57
8.12 Operational Readiness Review Follow-up Activities. ................................................... 58
8.13 Action Tracking and Closure Methodology. ................................................................. 59
DOE-STD-3006-YR
ii
8.14 DOE Line Management Oversight of the Operational Readiness Review Process. ...... 59
8.15 Independent Oversight Organizations. ........................................................................... 61
8.16 Authorization to Start Operations. ................................................................................. 61
9 READINESS ASSESSMENTS ............................................................................................ 61
9.1 Plan of Action. ............................................................................................................... 62
9.2 Readiness Assessment Implementation Plan. ................................................................ 68
9.3 Conduct of Readiness Assessment ................................................................................. 72
9.4 Unsuccessful Readiness Assessments. ........................................................................... 73
9.5 Contractor Readiness Assessments. ............................................................................... 75
9.6 Readiness to Proceed Memorandum. ............................................................................. 76
9.7 DOE Action Following Receipt of the Readiness to Proceed Memorandum (For use
Section 3
when DOE is the SAA). ........................................................................................... 78
9.8 DOE Readiness Assessments. ........................................................................................ 78
9.9 Documentation of Readiness Assessment Results. ........................................................ 79
9.10 Prestart and Post-Start Findings. .................................................................................... 82
9.11 Corrective Action Plans. ................................................................................................ 83
9.12 Readiness Assessment Follow-up Activities. ................................................................ 84
9.13 Action Tracking and Closure Methodology. ................................................................. 84
9.14 DOE Line Management Oversight of the Readiness Assessment Process. ................... 85
9.15 Independent Oversight Organizations. ........................................................................... 87
9.16 Authorization to Resume Operations. ............................................................................ 87
10 EQUIVALENCIES AND EXEMPTIONS ......................................................................... 87
APPENDIX 1. RECOMMENDED APPLICATION OF THE GRADED APPROACH
IN READINESS REVIEW PLANNING ................................................................................. 1-1
APPENDIX 2. EXPECTATIONS FOR CORE REQUIREMENTS (CRs) ................... 2-1
APPENDIX 3. READINESS REVIEW WRITING GUIDE ........................................... 3-1
DOE-STD-3006-YR
iii
This page is intentionally blank.
DOE-STD-3006-2010
1
FOREWORD
1. This Department of Energy (DOE) technical standard is approved for use by all DOE
Components and their contractors.
2. DOE technical standards, such as this Standard, do not establish requirements. However, all
or part of the provisions in a DOE standard can become requirements under the following
circumstances:
a. They are explicitly stated to be a requirements in a DOE requirement documents; or
b. The organization makes a commitment to meet a standard in a contract or in an
implementation plan or program plan required by a DOE requirements document.
Throughout this Standard, only the word “must” is used to denote actions which are required
to be performed to assure adequate implementation of the Order. This Standard cannot
create or imply, directly or indirectly a requirement that is not in the Order. Every effort has
been made to minimize “directive” type of statements which could be interpreted as
requirements. However, as mentioned above, only “must” statements denote Order
requirements, regardless of the grammatical structure.
3. Comments in the form of recommendations, pertinent data and lessons learned that may
improve this document should be sent to:
Michael Hillman
Office of Nuclear Safety Policy and Assistance
Office of Nuclear Safety, Quality Assurance and Environment
Office of Health, Safety and Security
U.S. Department of Energy
Washington, DC, 20585-0019
michael.hillman@hq.doe.gov
DOE-STD-3006-2010
2
1 SCOPE, PURPOSE, AND ORGANIZATION
1.1 Scope.
Section 4
Department of Energy (DOE) Order (O) 425.1D, Verification of Readiness to Startup or
Restart Nuclear Facilities, specifies the conditions and circumstances under which a
Readiness Review (RR) is required as part of a new start or restart process. This Standard
provides standardized methods and approaches for planning and conducting RRs. This
Standard also provides guidance for preparation of exemption requests in accordance with
DOE O 251.1C. DOE O 425.1D requirements for RRs apply both to responsible
contractors and to DOE. Accordingly, the methods and approaches provided in this
Standard are applicable to both contractors and DOE.
1.2 Purpose.
This Standard describes acceptable methods and approaches for meeting the RR
requirements of DOE O 425.1D. Specifically this Standard describes methods and
approaches for:
1. determining the type of RR that is appropriate to the specific facility startup consistent
with the history, hazards, and complexity of the facility being started up or restarted;
2. developing the Startup Notification Report (SNR) which documents the results of the
process for determining the type of readiness;
3. conducting the RR, including development of the Plan of Action (POA) and
Implementation Plan (IP), selection of team members, and performance and
documentation of the RR;
4. achieving readiness; and,
5. providing examples of process deliverables to include a writing guide and suggested
processes for achieving readiness.
The requirements in DOE O 425.1D are only applicable to startup or restart of Hazard
Category 1, 2, or 3 nuclear facility, activity or operation. This Standard provides
acceptable methods and approaches for meeting the specific requirements of that Order.
The methods and approaches provided in this Standard may be useful to line managers
regarding the startup or restart of radiological facilities or non-nuclear facilities in
accordance with the requirements of DOE O 430.1A. DOE line managers are encouraged
to consider the methods and approaches in this Standard when developing requirements or
procedures for startup or restart of radiological or non-nuclear facilities.
DOE-STD-3006-2010
3
1.3 Organization of the Standard.
1.3.1 Overview of the Readiness Review Process.
This section provides a history and sequential summary of the actions, responsibilities,
decisions, and documents associated with the Operational Readiness Review (ORR) and
Readiness Assessment (RA) processes. It is organized starting with the type of RR
required, development of RR plans, achieving readiness, and conduct and reporting of RRs.
This section also contains general information for gaining an understanding of the
principles and the expectations of the ORR or RA processes.
1.3.2 Determining the Scope and the Level of Readiness Review Required.
This section discusses the expectations for determining the level of RR required whenever
a nuclear facility is being started or restarted. It contains expectations for the
considerations to be included in the process as well as the attributes that should be included
in the contractor and DOE procedures that define the process.
1.3.3 Startup Notification Reports.
This section discusses the expectations and requirements for preparing, submitting, and
approving SNRs. The discussion includes the expectations for the contents of the SNR as
well as the attributes of the contractor and DOE procedures for development, review, and
approval of the SNR.
Section 5
1.3.4 Achieving Readiness.
This section discusses the processes and considerations for achieving readiness in a
planned, efficient, and predicable manner. Although the focus and purpose of DOE O
425.1D and this Standard are to verify that readiness has been achieved to commence
nuclear operations, the ability to successfully implement the Order and Standard is
dependent on the adequacy of contractor processes for achieving readiness.
1.3.5 Roles and Responsibilities.
This section discusses the roles and responsibilities for the processes and activities required
by the Order and Standard. It describes the activities of DOE and contractor line
management and oversight organizations as well as the RR Team Leader and team
members. The requirements for individual expectations are further discussed in the
specific sections of the Standard in which the tasks are discussed.
1.3.6 Conduct of Operational Readiness Reviews.
This section provides the detailed processes and methods for planning and conducting an
ORR, and is arranged by the time sequence of events associated with the ORR. The
discussion includes a description of the required documentation, including a recommended
content and format. It also discusses the actions required of line management, the ORR
DOE-STD-3006-2010
4
Team Leader, and team members to accomplish the process, including the actions needed
to resolve deficiencies and grant final approval to start nuclear operations.
1.3.7 Conduct of Readiness Assessments.
This section describes the detailed processes and methods for planning and conducting an
RA, and is arranged by the time sequence of events associated with the RA. The
discussion includes a description of the required documentation, including a recommended
content and format. It also discusses the actions required of line management, the RA
Team Leader, and team members to accomplish the process, including the actions needed
to resolve deficiencies and grant final approval to start nuclear operations.
1.3.8 Exemptions.
For information on processing exemptions, see DOE Order 251.1A: Directive System
1.3.9 Appendices.
The Appendices contain detailed information useful to the individual team members or line
managers to assist in preparing the documents required during the ORR or RA process:
• Appendix 1 discusses the recommended use of the graded approach to assist in
defining the scope of the RR.
• Appendix 2 contains guidance to clarify the intended scope and review approaches
associated with several Core Requirements (CRs) that have caused confusion in the
past.
• Appendix 3 is a writer’s guide containing information and examples of required or
recommended forms and document content. It is intended to assist team members in
developing required documents and in documenting their activities and findings.
2 DEFINITIONS
This section defines the terms used in DOE O 425.1D and this Standard. The description or
discussion concerning the terms may be expanded or more specific than definitions found in
other DOE documents. However, the uses of them in this Standard are consistent with
definitions provided in other DOE documents. All definitions used in Section 3 of 10 CFR
Part 830, Nuclear Safety Management, apply and are included in this listing for convenience
and clarity. Definitions from Section 3 of 10 CFR 830 are indicated by an asterisk (*).
Where compliance with any section of this standard is required, the terms defined in this
section should be used as defined in this section without alteration.
Section 6
• Administrative Controls (AC)*: The provisions relating to organization and
management, procedures, recordkeeping, assessment, and reporting necessary to ensure
safe operation of a facility.
DOE-STD-3006-2010
5
• Authorization Agreement (AA): Documented basis between DOE and the contractor
for high-hazard nuclear facilities (Hazard Categories 1 and 2) that incorporates the
results of DOE’s review of the contractor’s proposed authorization basis for a defined
scope of work. The AA contains key terms and conditions (i.e., controls and
commitments) under which the contractor is authorized to perform work. Any changes
to these terms and conditions require DOE approval.
• Authorization Basis (AB)*: Safety documentation supporting the decision to allow a
process or facility to operate. Included are corporate operational environmental
requirements as found in regulations and specific permits, and, for specific activities,
work packages or job safety analyses.
• Breadth: The set of CRs and the physical boundaries evaluated by the ORR or RA team
during the RR. The breadth is specified in the POA by line management.
• Core Requirement (CR): A fundamental area or topic evaluated during an ORR or RA
to assess whether a facility can be operated safely.
• Criteria and Review Approach Document (CRAD): This document lists the criteria that
the technical experts (team members) plan to use to evaluate and describes the
objective evidence that is gathered to determine whether the criteria have been met.
The review approach consists of evaluating a sampling of documents,
hardware/systems, people, and performance. CRADs are a key component of the
Implementation Plan (IP) for the RR.
• Depth: The depth of a review relates to the level of analysis, documentation, or action
by which a review objective is assessed. The depth to which different review
objectives are assessed may vary within an individual RR. Depth could vary from a
simple records review to a detailed assessment that includes a review of all records, all
references, and all involved individuals and physical spaces. The POA establishes the
breadth of the review and broadly describes the desired depth. The CRADs, part of the
IP, translate the POA description of the depth into practical terms of what is intended
be reviewed and by what approach.
• Design Feature*: The design features of a nuclear facility specified in the Technical
Safety Requirements (TSRs) that, if altered or modified, would have a significant
effect on safe operation.
• Directed Shutdown: An unscheduled termination of program operations or activities
directed by contractor management, local DOE officials, or by DOE Headquarters.
• Document*: Recorded information that describes, specifies reports, certifies, requires,
or provides data or results.
• Documented Safety Analysis (DSA)*: Documented analysis of the extent to which a
nuclear facility can be operated safely with respect to workers, the public, and the
DOE-STD-3006-2010
6
environment, including a description of the conditions, safe boundaries, and hazard
controls that provide the basis for ensuring safety.
• Environmental Restoration Activities*: The processes by which contaminated sites and
facilities are identified and characterized and by which contamination is contained,
treated, or removed and disposed.
Section 7
• Finding: Nonconformance with a stated requirement that represents either: (1) a
systematic failure to establish or implement an adequate program or control; or (2) a
significant failure that could result in unacceptable impact on the safety of personnel,
the facility, the general public, or the environment during nuclear operations.
• Fissionable Material*: A nuclide capable of sustaining a neutron-induced chain
reaction (e.g., uranium-233, uranium-235, plutonium-238, plutonium-239, plutonium-
241, neptunium-237, americium-241, or curium-244).
• Graded Approach*: The process used to determine the level of analysis,
documentation, and actions necessary to comply with a requirement that is
commensurate with: (1) the relative importance to safety, safeguards, and security; (2)
the magnitude of any hazard involved; (3) the lifecycle stage of a facility; (4) the
programmatic mission of a facility; (5) the particular characteristics of a facility; (6) the
relative importance of radiological and non-radiological hazards; and (7) any other
relevant factor.
• Hazard*: A source of danger (i.e., material, energy source, or operation) with the
potential to cause illness, injury, or death to a person or damage to a facility or to the
environment (without regard to the likelihood or credibility of accident scenarios or
consequence mitigation).
• Hazard Category (HC): The consequences of releases of radioactive or hazardous
material are evaluated as required by 10 CFR 830 and classified by the following
Hazard Categories:
a. Category 1 – The hazard analysis shows the potential for significant offsite
consequences.
b. Category 2 – The hazard analysis shows the potential for significant onsite
consequences.
c. Category 3 – The hazard analysis shows the potential for only significant localized
consequences.
DOE-STD-1027-92, Hazard Categorization and Accident Analysis Techniques for
Compliance with DOE Order 5480.23, Nuclear Safety Analysis Reports, Change Notice
1, contains additional information on methods and criteria for determining Hazard
Categories.
• Hazard Controls*: Measures to eliminate, limit, or mitigate hazards to workers, the
public, or the environment, including:
DOE-STD-3006-2010
7
a. physical, design, structural, and engineering features;
b. safety structures, systems, and components (SSCs);
c. safety management programs (SMPs);
d. TSRs; including SACs and,
e. other controls necessary to provide adequate protection from hazards.
• Implementation Plan (IP): The procedural document by which the RR is conducted.
This document implements the scope and direction approved in the POA and defines
the depth of the review. Sections 8.2 and 9.3 describe the contents, preparation, and
use of the IP.
• Independent Verification Review (IVR): A formalized verification of the completeness
and adequacy of the implementation of the safety basis (DSA and TSRs) for a nuclear
facility. The IVR process is defined in local procedures. A successful IVR, including
the resolution of all pre-start issues, may be a prerequisite to the start of an RR as
defined in DOE O 425.1D.
• Interruption: A cessation of facility program work required to perform scheduled
activities (such as programmatic or equipment adjustments, reactor refueling,
maintenance, surveillance, tests, inspections, or safety upgrades) or for programmatic
reasons unrelated to the facility’s ability to operate, such as a funding shortfall, is a
planned interruption. Local procedures should define the review requirements for
planned interruptions or shutdowns.
Section 8
• Limiting Condition for Operation (LCO)*: The limit that represents the lowest
functional capability or performance level of safety SSCs required for safe operations.
• Limiting Control Settings (LCSs)*: The settings on safety systems that control process
variables to prevent exceeding a safety limit.
• Major Modification*: A modification to a DOE nuclear facility that substantially
changes the existing safety basis for the facility. This is not the same as a Substantial
Modification. See the definition for Substantial Modification below.
• Management Self Assessment (MSA): A quality process planned and accomplished by
line management to assist in achieving readiness. The process, while not required by
DOE O 425.1D or this Standard is an important element in ensuring readiness to start
nuclear operations and thus achieve readiness to conduct the RR required by DOE O
425.1D.
• New Nuclear Facility: This is a reactor or a nonreactor nuclear facility where an
activity is initiated for or on behalf of DOE that includes any related area, structure,
facility, or activity to the extent necessary to ensure proper implementation of the
requirements established in 10 CFR 830. The term refers to an entire new facility (or
conversion of an existing non-nuclear facility to a nuclear mission) devoted to the
operation and maintenance of a new program activity, which is generally covered by a
unique DSA.
DOE-STD-3006-2010
8
• Non-reactor Nuclear Facility*: Those facilities, activities, or operations involve, or will
involve, radioactive and/or fissionable materials in such form and quantity that a
nuclear or a nuclear explosive hazard potentially exists to workers, the public, or the
environment. This excludes accelerators and their operations and activities involving
only incidental use and generation of radioactive materials or radiation such as check
and calibration sources, use of radioactive sources in research and experimental and
analytical laboratory activities, electron microscopes, and X-ray machines.
• Nuclear Facility*: Reactor and non-reactor nuclear facilities where an activity is
conducted for or on behalf of DOE that includes any related area, structure, facility, or
activity to the extent necessary to ensure proper implementation of the requirements
established by 10 CFR 830.
• Nuclear Operations: As used in this Standard, Nuclear Operations means nuclear
facilities, operations, and/or activities that fall within the scope of DOE O 425.1D
• Operating Limits*: The limits required to ensure the safe operation of a nuclear facility,
including limiting control settings and limiting conditions for operation.
• Plan of Action (POA): The document prepared by line management that describes the
scope of the RR, the prerequisites to be met to begin the RR, and the proposed Team
Leader for the RR. The contractor and DOE both prepare POAs for their respective
RRs (in some instances as specified in the SNR, a DOE RA may not be required).
Both contractor and DOE POAs when required are submitted to the Startup Approval
Authority (SAA) for approval. The designated RR Team Leader(s) develops their IP
from the approved POA.
• Preliminary Documented Safety Analysis (PDSA)*: Documentation prepared in
connection with the design and construction of a new DOE nuclear facility or a major
modification to a DOE nuclear facility that provides a reasonable basis for the
preliminary conclusion that the nuclear facility can be operated safely through the
consideration of factors such as:
Section 9
1) the nuclear safety design criteria to be satisfied;
2) a safety analysis that derives aspects of design that are necessary to satisfy the
nuclear safety design criteria; and,
3) an initial listing of the safety management programs needed to address operational
safety considerations.
• Prerequisites (PR): A set of specific, measurable actions or conditions identified in the
contractor and DOE POAs that are to be completed prior to the start of the respective
ORR or RA. At minimum, prerequisites are identified for each of the applicable Core
Requirements of DOE O 425.1D.
• Process*: A series of actions that achieves an end or result.
DOE-STD-3006-2010
9
• Program Work: Work in a reactor or non-reactor nuclear facility that is accomplished
to further the goals of the facility mission or the program for which the facility is
operated. Program work may include D&D or Environmental Restoration activities
when that is the mission of the facility. Program work is not accomplished when an
operational facility is shut down. Program work does not include work that would be
required to maintain the facility in a safe shutdown condition, minimize radioactive
material storage, or accomplish modifications and correct deficiencies required before
program work can resume.
• Quality*: The condition achieved when an item, service, or process meets or exceeds
the user’s requirements and expectations.
• Quality Assurance*: All those actions that provide confidence that quality is achieved.
• Quality Assurance Program (QAP)*: The overall program or management system
established to assign quality assurance responsibilities and authorities, define policies
and requirements, and provide for the performance and assessment of work.
• Radiological Facility: A nuclear facility that is less than nuclear hazard category 1, 2,
or 3. DOE O 425.1D does not apply to radiological facilities.
• Reactor*: An apparatus that is designed or used to sustain nuclear chain reactions in a
controlled manner, such as research, test, and power reactors, critical and pulsed
assemblies, and any assembly that is designed to perform subcritical experiments that
could potentially reach criticality. Unless modified by words such as containment,
vessel, or core, refers to the entire facility, including the housing, equipment, and
associated areas devoted to the operation and maintenance of one or more reactor
cores.
• Record*: A completed document or other medium that provides objective evidence of
an item, service, or process.
• Readiness Assessment (RA): A review conducted to determine a facility’s readiness to
start up or restart when an ORR is not required.
• Readiness Review (RR): A review conducted to determine readiness to start up or
restart a nuclear facility, activity, or operation. There are two types of RRs: ORRs and
RAs.
• Readiness to Proceed (RTP) Memorandum: The formal document submitted by the
contractor certifying the conclusion that the facility is prepared to start or resume
nuclear operations. The contractor RR final report and finding closure packages or
corrective action plans, along with the appropriate endorsements, are attached to the
RTP.
• Restart: The resumption of program work. Restarts requiring an RR can occur in
operating facilities if the process to be resumed meets RR requirements. A restart RR
DOE-STD-3006-2010
10
in accordance with DOE O 425.1D may be required even if the same program work is
ongoing in another portion of the operating facility.
Section 10
• Safety Basis (SB)*: The DSA and hazard controls that provide reasonable assurance
that a DOE nuclear facility can be operated safely in a manner that adequately protects
workers, the public, and the environment.
• Safety-Class Structures, Systems, and Components*: Those SSCs, including portions
of process systems, whose preventive or mitigative function is necessary to limit
radioactive hazardous material exposure to the public, as identified by the DSA.
• Safety Evaluation Report (SER)*: The report prepared by DOE to document.
1) The sufficiency of the DSA for a Hazard Category 1, 2, or 3 nuclear facility;
2) The extent to which a contractor has satisfied the requirements of 10 CFR 830
Subpart B; and,
3) The basis for approval by DOE of the safety basis for the facility, including any
conditions for approval.
• Safety Limits (SL)*: The limits on process variables associated with those safety-class
physical barriers (generally passive) that are necessary for the intended facility function
and that are required to guard against the uncontrolled release of radioactive materials.
• Safety Management Program*(SMP): A program designed to ensure that a facility is
operated in a manner that adequately protects workers, the public, and the environment
by covering an area such as quality assurance, maintenance of safety systems,
personnel training, conduct of operations, inadvertent criticality protection, emergency
preparedness, fire protection, waste management, or radiological protection of workers,
the public, and the environment.
• Safety Management System (SMS)*: An integrated safety management system
established consistent with 48 CFR 970.5223-1.
• Safety-Significant Structures, Systems, and Components*: The SSCs that are not
designated as safety-class SSCs, but whose preventive or mitigating function is a major
contributor to defense in depth or worker safety as determined in the safety basis.
• Safety Structures, Systems, and Components (SSC)*: Both safety-class and safety-
significant SSCs.
• Scope: The overall magnitude of the RR, as defined by the physical breadth and depth
of the facilities and equipment to be started, the breadth of CRs selected, and the depth
of evaluation of these CRs during the RR. The POA defines the scope of the RR when
it establishes the breadth and broadly describes the desired depth.
DOE-STD-3006-2010
11
• Service*: The performance of work, such as design, manufacturing, construction,
fabrication, assembly, decontamination, environmental restoration, waste management,
laboratory sample analyses, inspection, nondestructive examination and testing,
environmental qualification, equipment qualification, repair, installation, or the like.
• Shutdown: (1) A situation in which a reactor is taken subcritical, either manually or
automatically, to a safe shutdown condition; (2) a condition in which a nonreactor
nuclear facility, activity, or operation ceases; or (3) a condition in which a
programmatic nuclear activity ceases (but the structure containing the activity may
remain operational, i.e., not shut down). In a shutdown condition, a facility must still
meet all applicable TSRs and environmental, safety, and health requirements.
Section 11
• Short Interruption: A cessation of program work required to perform scheduled or
unscheduled activities (such as programmatic or equipment adjustments, reactor
refueling, maintenance, surveillance, tests, inspections, or safety upgrades) or for
programmatic reasons unrelated to the facility’s ability to operate, such as a funding
shortfall, for which adequate plans pre-exist that ensure a safe restart without the need
for a formal RR. Local procedures define the circumstances that are considered short
interruptions and the requirements for restart authorization.
• Specific Administrative Control (SAC). An administrative control is designated as a
SAC if (1) it is identified in the documented safety analysis as a control needed to
prevent or mitigate an accident scenario, and (2) it has a safety function that would be
safety significant or safety-class if the function were provided by an SSC. Examples
are discrete operator actions, combustible loading program limits, and hazardous
material limits protecting hazard analyses or facility categorization. (SACs are not
programmatic administrative controls included in TSRs.) (DOE-STD-1186-2004)
• Startup Authorization Authority (SAA): The line manager who is designated in
accordance with DOE O 425.1D, section 4.b to authorize the start of nuclear operations
when all requirements of the Order have been met. The SAA may range from a senior
contractor line manager to the Secretary of Energy. For each startup or restart, the
SAA is designated in the SNR.
• Startup Notification Report (SNR): A quarterly report (or at a periodicity as designated
by the PSO) by each responsible contractor to identify nuclear facility new starts and
restarts scheduled in the next year. The report identifies the facility and, based on the
criteria in DOE O 425.1D, specifies whether an ORR or a RA is required. The SNR
also identifies the SAA and updates previously provided information.
• Startup or Restart Plan: The management plan developed by the responsible contractor
that describes the process of deliberate, controlled operations the contractor intends to
follow after authorization to start nuclear operations following an RR. Appendix 2
contains additional information on the suggested content of a startup plan.
• Substantial Process, System or Facility Modification: A modification that requires that
DOE conduct an RA following completion of the contractor’s readiness activities.
DOE-STD-3006-2010
12
DOE O 425.1D requires that local site implementing procedures must provide a
process for determining when a modification is substantial based on the impact of the
changes to the safety basis and the extent and complexity of changes, whether or not
these changes resulted in a positive Unreviewed Safety Question (USQ). Contractor
and DOE local procedures for determining the level of readiness should include a
process for determining whether a substantial modification has occurred. Items to be
considered when making the determination should include:
o the number and significance of operational process changes necessary to
accommodate the modification;
o the number of procedure changes and the difficulty or significance of the
process changes to which the procedures apply;
o changes to the process controls, limits, and instrumentation;
o the necessary level of training or retraining of operational and oversight staff to
introduce the modification;
Section 12
o the significance of the changes to the DSA and TSRs, with emphasis on the
operational aspects of the changes; and,
o the level of operational process change and complexity of operational activities.
A change that meets one or more of the following criteria should be evaluated using local
procedures to determine whether it meets the criteria for a Substantial Process Change:
1) Alters the footprint of an existing Hazard Category 1, 2, or 3 facility with the
potential to adversely impact one or more credited safety functions of the existing
facility;
2) Introduces a new hazard not previously analyzed that requires a revision to the
Hazards Analysis.
Or if the change:
1) Requires the expansion of work into an existing area of a facility that is not
currently within the Safety Basis for that facility;
2) Requires a structural addition to an existing building or structure that is designed to
house hazardous activities or operations and that should require a new or revised
Safety Basis;
3) Involves environmental remediation activities in a new geographic area, structure,
or building, provided that the work can reasonably be expected to encounter
quantities of nuclear materials that would require designation as a Hazard Category
2 nuclear facility per DOE-STD-1027-92, Change Notice 1;
DOE-STD-3006-2010
13
4) Requires deactivation, decommissioning, or demolition of a facility or activity
within a facility.
• Surveillance Requirement (SR)*: A requirement relating to testing, calibration, or
inspection to ensure that the necessary operability and quality of safety SSCs and the
supporting systems required for safe operations are maintained, that facility operation
is within safety limits, and that LCSs and LCOs are met.
• Technical Safety Requirements* (TSR): The limits, controls, and related actions that
establish the specific parameters and requisite actions for the safe operation of a
nuclear facility; and, as appropriate for the work and the hazards identified in the
facility DSA, includes safety limits, operating limits, surveillance requirements,
administrative and management controls, use and application provisions, and design
features, as well as a bases appendix.
• Unplanned Shutdown: An interruption of an activity or operation at a facility for which
adequate procedures do not pre-exist that would permit safe restart of the facility
without the conduct of a readiness review.
• Unreviewed Safety Question (USQ)*: A situation where:
1) the probability of occurrence, the consequences of an accident, or the malfunction
of equipment important to safety previously evaluated in the DSA could be
increased;
2) the possibility of an accident or malfunction of a different type than those
previously evaluated in the DSA could be created;
3) a margin of safety could be reduced; or,
4) the DSA may not be bounding or may be otherwise inadequate.
• Unreviewed Safety Question Process*: The mechanism for keeping a safety basis
current by reviewing potential USQs, reporting USQs to DOE, and obtaining approval
from DOE prior to taking any action that involves a USQ.
• Vital Safety Systems (VSS). Vital safety systems are safety-class systems, safety-
significant systems, and other systems that perform an important defense-in-depth
safety function.(DOE-STD-1073-2003)
3 OVERVIEW OF THE READINESS REVIEW PROCESS
Section 13
This section provides the background and overview of the process for verifying readiness
to start up or restart nuclear operations within DOE nuclear facilities. DOE O 425.1D
establishes the requirements for verifying readiness. This Standard provides guidance on
approaches and methods that are acceptable for implementing the requirements of the
Order, and includes information that clarifies and expands on requirements included in the
Order.
DOE-STD-3006-2010
14
3.1 History and Purpose of Readiness Reviews.
The Readiness Review process was developed to provide a high degree of confidence that
new and restarted DOE nuclear facility operations will be conducted as intended by the
design and safety basis. A graded independent review approach is used. Independence
was deemed necessary to avoid conflicts of interest that could compromise reviewer ability
to objectively determine the status of the proposed operation.
The Readiness Review process was modeled after Naval Nuclear Propulsion and Nuclear
Regulatory Commission programs and processes. Reviews are based on records review,
observation of equipment and operations, and interviews of relevant personnel. In certain
cases, two reviews are required (contractor and Federal) due to the current degree of
confidence in contractor assurance systems.
Prior to the formal RR process, the method for DOE to authorize the commencement of
new nuclear operations was unclear. Both extremes of readiness verification were possible.
Cursory reviews would raise safety issues while open-ended, extensive reviews could
continue indefinitely introducing significant delay and expense to DOE programs.
The RR process identified in this Standard addresses those issues by providing a well
defined process. Future improvements in contractor assurance programs may warrant
future streamlining of the RR process.
3.2 Differences Between Operational Readiness Reviews and Readiness Assessments.
Readiness reviews required by DOE O 425.1D are grouped into two types: ORRs and RAs.
The differences between an ORR and an RA involve the scope of the review. The scope
incorporates the breadth and depth of the review and includes the processes, personnel, and
equipment being assessed as well as the nuclear SMPs. The scope of a review is defined
by the physical or geographic limits of the review, encompassing the systems, facilities,
and operations being started, and the CRs that include the SMPs and describe the
geographic attributes that must be assessed (see the discussion of CRs in section 3.4
below). If the geographic limits are accurately defined and all CRs fully evaluated, the
assumption of DOE O 425.1D is that all elements necessary for determining readiness to
start nuclear operations should have been evaluated. The fundamental assumption is that
the ORR scope includes all of these elements. In specific cases discussed in DOE O
425.1D and later in this Standard, some CRs may be excluded following a recent
satisfactory independent review.
In the case of the RA, the assumption is that only selected elements need to be evaluated to
verify readiness to start or restart nuclear operations. The RA assumes that identified
elements of the nuclear safety management infrastructure are in a known condition that is
satisfactory to support the nuclear operation to be started; therefore, they need not be
reevaluated. The scope of the RA should be carefully defined to evaluate those elements
that are unique to the operation being started or restarted and to exclude those elements for
which there is reason to believe that existing conditions support the nuclear operation being
started. In reality, each RA may have a unique scope that may be as comprehensive as an
Section 14
DOE-STD-3006-2010
15
ORR or as limited as a simple checklist of a few specific items. The scope of the ORR or
RA is defined in the POA, which is prepared by line management and approved by the
SAA.
As discussed above, in some cases, both the contractor and DOE conduct RRs. In cases
when an ORR is required, the contractor and DOE always conduct ORRs. The DOE ORR
may not start until the contractor ORR has been completed, the identified findings are
resolved or addressed by an approved corrective action plan, and a formal Readiness to
Proceed Memorandum has been submitted to DOE. In the case of an RA, there is more
flexibility as to whether it is conducted by a contractor only, jointly (when approved), or
independently by both the contractor and DOE. The type of RA and its sequencing should
reflect the unique operational circumstances as well as the experience and demonstrated
competence of the individual contractor as viewed by the SAA.
The DOE RR is different from a properly executed contractor RR because it assesses the
adequacy and accuracy of the contractor RR. Because the contractor RR should provide
the substantial basis for acceptance of readiness, the DOE RR should assess the scope of
the contractor RR and should include verification by sampling contractor results (e.g.,
verifying the conduct of operations by walking down procedures, observing normal and
off-normal operations or training evaluations, and quizzing personnel on training material).
The DOE RR should place significant emphasis on the effectiveness of the contractor’s
preparations through demonstrations of such activities as normal operations, abnormal
events, and emergency drills. Additionally, the DOE RR should assess the readiness of the
responsible DOE line organization to safely oversee operations and the effectiveness of
coordination among organizations. Note that in some situations discussed later in this
standard, a DOE RR may not be required.
3.3 Determining the Level of Readiness Review and Contents of the Startup Notification
Report.
DOE O 425.1D requires that every startup or restart of a nuclear facility, operation, or
activity be evaluated to determine the required level of RR. For routine resumption of a
facility, operation, of activity after a short interruption, if approved contractor operational
procedures are used no additional RR is required. For conditions that meet DOE Order
section 4.a.2.b, an ORR must be conducted. For all other startups or restarts, an RA is
required.
As noted earlier, an RA may be as comprehensive as an ORR or as simple as a checklist.
The contractor may conduct a single RA, joint RA (when approved), or conduct an RA
followed by a second conducted by DOE. The contractors and DOE are required to
develop processes by which they assess the projected startups and restarts to determine the
level of RR that is required. As discussed later in this Standard, the methodology used for
making the determination should be formal and deliberate. All startups and restarts of
nuclear operations must be considered.
Each quarter (or on a periodicity as defined by the PSO) the contractor is required to
prepare and submit an SNR to its immediate DOE Line Management that identifies all
DOE-STD-3006-2010
16
Section 15
startups or restarts requiring a RR. Projecting ahead at least one year, the SNR must
propose the level of RR and identify the SAA. The SNR must contain adequate
information about each operation and facility to support and defend the recommendations
being made. DOE Line Management (HQ and Field) approves their respective activities of
the SNR for which they are the SAA. Contractors and DOE should develop procedures for
the preparation and content of the SNR. A later section in this Standard provides detailed
expectations for the processes to develop, review, approve, and maintain the SNR.
3.4 Core Requirements.
DOE O 425.1D specifies 17 CRs that must be considered when planning each ORR/RA
(14 for contractor ORRS/RAs and three additional CR for DOE ORRs/RAs). As stated in
the Order: “These CRs verify the readiness of personnel, procedures, programs, and
equipment within the scope of the RR to safely start nuclear operations.” The fundamental
assumption is that if the programs, operations, equipment, and facilities within the physical
or geographic scope of the RR are shown to meet all of the elements of the CRs, readiness
to start nuclear operations within the facility has been achieved. It is essential that
personnel associated with planning and achieving readiness, as well as those responsible
for planning and conducting RRs, have a clear understanding of the CRs and how they
relate to readiness to start or restart nuclear operations. In aggregate, the CRs should focus
the RR on the following broad functional areas:
• implementation of SMPs to fully and effectively support the nuclear facility and
nuclear operations within the scope of the RR;
• implementation and maintenance of appropriate nuclear safety basis documentation
that has been prepared and approved in accordance with the requirements of 10 CFR
830 Subpart B for the nuclear facility, including all nuclear operations within the scope
of the RR;
• physical readiness of the systems and equipment within the scope of the RR;
• personnel readiness and operational proficiency, including emergency and abnormal
alarm response for all nuclear operations within the scope of the RR; and.
• readiness of DOE to oversee contractor nuclear operations within the scope of the RR.
The full breadth and depth of every CR may not be required in every situation to verify
readiness to start nuclear operation; therefore, it is important that the RR process
recognizes the need to tailor or exclude some parts or all of some CRs. Line management
tailors the scope of CRs in the POA. Detailed processes and considerations for developing
the POA are described in a later section of this Standard.
3.5 Focus and Sequence of Contractor and DOE Readiness Reviews.
This section provides a summary of the normal sequence of events and deliverables of the
RR process. It is required that the contractor and DOE have formal procedures to direct the
DOE-STD-3006-2010
17
process. DOE Field Line Management must concur with the contractor’s procedures. The
times and durations in this discussion are suggested to permit the RR process to proceed
efficiently with minimum impact on the critical path to the start of nuclear operations.
Section 16
The RR process starts upon the determination that a nuclear facility, activity, or operation
is to be started or restarted. At that time, the level of the review is determined and the
startup is added to the SNR. At least six months before the projected date for achieving
readiness, contractor line management should prepare the POA. The POA describes the
scope of the RR, lists prerequisites for achieving readiness, and proposes the RR Team
Leader. The contractor POA should be submitted four to six months prior to the projected
start of the RR.
If DOE is also required to conduct an RR, a DOE POA must also be prepared. The DOE
POA must describe the scope of the RR, prerequisites for the DOE RR, and the proposed
RR Team Leader.
While it is recognized that the specified timing for preparation of the POA may not always
be possible, this timing should be the stated goals of the local procedures. This timing for
submission of the POAs permits adequate time for review, comment and approval while
not inhibiting the ability of the Team Leader to prepare the IP from an approved POA.
Upon approval, the POA is provided to the approved Team Leader to prepare for the RR.
The Team Leader assembles a review team to assist in the preparation of the IP, which
includes the CRADs that the team members use to conduct the review. Together, the
CRADs incorporate the complete review scope specified in the POA. The IP specifies the
methodology for conducting the review and the process and format for documenting the
review.
As a part of achieving readiness, the contractor may conduct a management self-
assessment. Contractor efforts to achieve readiness may be conducted in accordance with a
project management plan, or other project management document. Such management
documents should include all elements of the RR scope specified in the POA. Similarly,
DOE Line Management achieves readiness to oversee contractor operations. A
management self-assessment of DOE Line Management, including management programs
to oversee contractor operations, may also be appropriate.
When the contractor has achieved readiness to start or restart a nuclear facility, activity, or
operation within the scope of the RR, a formal declaration of readiness is provided and the
Team Leader is directed to conduct the review. When a DOE RR is required, the
declaration of readiness (the Readiness to Proceed Memorandum) for the DOE RR is not
submitted until after the contractor RR, and planning for resolution of all identified
findings, are complete.
The RR team conducts the review when the declaration of readiness is received and when
directed by the SAA. The RR Team Leader submits the final report to the SAA as a basis
for approving the startup or restart. The SAA should issue the final report to line
management. Identified findings are designated by the review team as prestart
DOE-STD-3006-2010
18
(i.e., requiring resolution before the start of nuclear operations) or post-start (i.e., can be
corrected after startup or restart of nuclear operations). Line management is responsible for
developing corrective action plans to resolve the findings and determining when the
findings are resolved. Development of acceptable corrective action plans for post-start
findings must be completed before the SAA grants authorization to start or restart nuclear
operations.
3.6 DOE Headquarters and Field Line Management Oversight Responsibilities.
Section 17
Verifying readiness to startup or restart nuclear operations in DOE nuclear facilities is an
important element in the defense-in-depth process to ensure safety of nuclear operations.
As a result, DOE O 425.1D specifies numerous oversight responsibilities of the processes
by DOE Field and DOE Headquarters Line Management.
DOE Field Line Management must prepare implementing procedures and concur with
contractor implementing procedures in accordance with the Contractor Requirements
Document (CRD) in DOE O 425.1D. DOE Line Management (including DOE
Headquarters, in some instances), must review and approve the SNR. DOE Field Element
Line Management should ensure that all required elements are included in these process
documents. Process documentation such as SNRs, POAs, IPs, and RR final reports must
be provided to the appropriate PSO via the appropriate line management chain of
command. The PSO provides these documents to the appropriate CTA, as well as the
Office of Health, Safety and Security (HSS) for information and oversight action as
appropriate.
As part of the process for granting authorization to start nuclear operations within the
nuclear facility, the adequacy of corrective actions should be assessed. DOE Field Line
Management must evaluate the adequacy of the contractor’s actions for achieving
readiness. DOE Headquarters Line Management must oversee DOE Field processes for
verification of readiness to start up and restart nuclear facilities, in accordance with DOE O
226.1A, Implementation of Department of Energy Oversight Policy.
3.7 Approval to Start Up or Restart Nuclear Operations.
The end result of the process for verifying readiness to start up or restart nuclear facilities is
the authorization to start nuclear operations within the nuclear facility. DOE O 425.1D
specifies the SAA who can grant authorization to start nuclear operations. The SAA also
approves the SNR and the POA, and directs the start of the RR. If no DOE RR is required,
the SAA may be a contractor manager. In such a situation, the SAA is designated by the
SNR, which is always approved by a DOE official.
Following completion of the required RR, the team prepares a report that makes a
recommendation as to the readiness of the nuclear facility to start nuclear operations. In
most cases, the report includes prestart findings that must be resolved before nuclear
operations can be authorized to start. Formalized processes are required to evaluate the
findings and plan their resolution. When the corrective action plans are developed and
approved and the prestart findings are resolved, the SAA authorizes the start of nuclear
DOE-STD-3006-2010
19
operations within the nuclear facility. In situations when the SAA is a DOE line manager,
the contractor submits a Readiness To Proceed Memorandum following completion of the
contractor RR, develops corrective action plans for the findings from the RR, and resolves
all prestart findings with the possible exception of a short list of open issues that must be
resolved prior to the start of nuclear operations.
After the Readiness to Proceed Memorandum has been submitted, DOE conducts a RR if
required or authorizes the startup or restart of the nuclear facility, activity, or operation
once the items on the list of open issues are resolved. When the contractor is the SAA, the
contractor line management provides formal documentation to the SAA, which should
include the RR report, a corrective action plan to address the findings, and certification that
all prestart findings are resolved. With that documentation submitted and accepted, the
contractor SAA can authorize the start of nuclear operations.
Section 18
The SAA authorizes the start or restart of the nuclear facility, activity or operation. In most
instances, a startup plan to full operations is suggested. A Startup Plan should provide a
formalized and structured initial operation. Compensatory measures, including increased
supervisory oversight, may be defined. Final equipment testing may be completed if actual
materials are required to be used for the testing. The details of the initial startup period are
defined in the Startup Plan that is evaluated through review and observation of
implementation during the RR (CR 11).
4 DETERMINING THE SCOPE AND THE LEVEL OF THE READINESS REVIEW
DOE O 425.1D requires that the contractor evaluate the need to perform a RR prior to
startup and restart of all nuclear facilities, activities, or operations. This requires that a
decision be made as to the requirement for a RR for every startup of a nuclear facility,
activity, or operation whether following a weekend shutdown, following a major
modification, or starting a new facility. The Order recognizes that for resumption of
operations following a short interruption for which approved operating procedures with
appropriate attributes are applicable, no additional RR is required. However, the contractor
should have a documented decision process for determining the requirement for, and the
level of, the RR. Contractors and DOE must have approved procedures that describe the
processes by which all requirements of the Order must be accomplished.
DOE O 425.1D also requires that, on a quarterly basis (or at a frequency as specified by the
PSO) the contractor prepare and submit for DOE approval an SNR that lists each projected
startup of a nuclear facility for which a RR is required. For each startup listed in the SNR,
the level of RR should be specified with sufficient information to justify the recommended
review level. A part of the process for gaining the necessary information upon which a
recommendation can be made is to determine the unique aspects of the startup. The details
of the situation surrounding individual startup or restart should provide a basis for making a
recommendation as to the level of the RR, as well as the scope of the RR. The SNR must
also recommend the identification of the SAA, which may also be based on the scope and
type of RR. Detailed discussions of the requirements and contents of the POA and SNR
are provided later in this Standard.
DOE-STD-3006-2010
20
Readiness reviews required by DOE O 425.1D are grouped into two types: ORRs and RAs.
The differences between an ORR and an RA involve the scope of the review. The scope
incorporates the breadth and depth of the review and includes the processes, personnel, and
equipment being assessed as well as the nuclear SMPs and the depth or comprehensiveness
of the evaluation of each individual SMP. The scope of a review may be defined by the
physical or geographic limits of the review, encompassing the systems, facilities, activities,
or operations being started or restarted, and the CRs that include the SMPs and describe the
geographic attributes that must be assessed (see the discussion of CRs in paragraph 3.4.
above). If the geographic limits are accurately defined and all CRs fully evaluated, the
assumption of DOE O 425.1D is that all elements necessary for determining readiness to
start nuclear activities or operations have been evaluated. The fundamental assumption is
that the ORR scope includes all of these elements. In specific cases discussed in DOE O
425.1D and later in this Standard, it is possible to exclude some CRs following a recent
satisfactory independent review.
Section 19
In the case of the RA, the assumption is that only selected elements need to be evaluated to
verify readiness to start or restart a nuclear facility, activity, or operation. The RA assumes
that identified elements of the nuclear safety management infrastructure are in a known
condition that is satisfactory to support the nuclear operation to be started; therefore, they
need not be reevaluated. The scope of the RA is carefully defined to evaluate those
elements that are unique to the operation being started or restarted and to exclude those
elements for which there is reason to believe that existing conditions support the nuclear
facility, activity, or operation being started or restarted. In reality, each RA has a unique
scope that may be as comprehensive as an ORR or as limited as a simple checklist of a few
specific items. The scope of the ORR or RA is defined in the POA, which is prepared by
line management and approved by the SAA.
As discussed above, in some cases, both the contractor and DOE conduct independent RRs.
In cases when an ORR is required, the contractor and DOE always conduct ORRs. The
DOE ORR may not start until the contractor ORR has been completed, the identified
findings are resolved or addressed by an approved corrective action plan, and a formal
Readiness to Proceed Memorandum has been submitted to DOE. In the case of an RA,
there is more flexibility as to whether it is conducted by a contractor only, jointly (when
approved), or a contractor and DOE and its sequencing.
The specific elements and processes of the site procedures vary according to the history
and culture of the site as well as the level of maturity of the startup processes. However,
there are some attributes and considerations that should be included in every site’s
procedures and processes for determining the scope and level of RR:
A. Every startup must be considered. A process should be in place to permit site line
management to determine which startups meet the criteria to utilize approved operating
procedures. The process must consider the length of the shutdown. Operator
proficiency and the degree to which that proficiency is maintained should be
considered. The process should also consider the details of any maintenance
performed and the reliability of post-maintenance retest procedures and documentation.
Also, the process should consider any other changes that have occurred during the
DOE-STD-3006-2010
21
shutdown such as physical or procedure modifications. The process should identify the
person authorized to make the determination, the documentation required, and the
process for overseeing results.
B. The determination that a restart does not require a RR should include the following
considerations:
o The restart can be conducted utilizing contractor-approved operating procedures
that provide specific direction for operating systems and equipment during
normal operations. The procedures should verify that systems are properly
aligned and prepared to start or restart the facility, activity, or operation.
Maintenance procedures and work packages should be demonstrated to be
complete as a part of verifying readiness to start or restart the facility, activity,
or operation. Appropriate preoperational checks should be part of the
contractor-approved operating procedures that provide the specific direction for
operating systems, and.
o The restart is a resumption of routine operations after a short interruption such
as maintenance activities governed by existing maintenance procedures or
process.
Section 20
The determination as to whether the last condition is met should include the following
in aggregate:
1) The interruption is less then than six months for Hazard Category 1 facility, and
less then than twelve months for Hazard Category 2 and 3 facilities.
2) All maintenance work should be clearly defined in work packages; post-
maintenance testing was thorough and completed with satisfactory results. All
work packages should be verified to be complete and closed or evaluated and
determined not to affect the ability to resume safe operations.
3) Operating staff turnover.
4) Modifications that have been accomplished during the shutdown period which
require process procedure changes or substantive safety basis changes should be
considered. Process changes that are complex, procedure changes that require
new or significantly different operator actions, changes to safety basis that
require new controls, new hazards and hazard controls, and first time startup of
new systems are examples of modifications that should normally require a RR.
5) The number and significance of updates to the safety basis should be considered
when making the determination that no RR is required.
6) Changes to operational procedures should be limited to a number and criteria
specified in local implementing procedures. The local procedures should require
consideration of the significance and complexity of the changes and the
underlying processes. For any procedures that are changed, all implementation
training should be completed and documented for all members of the operational
and support staff.
DOE-STD-3006-2010
22
o If required by local procedures, the process should retain any necessary
documents or records that will allow a Facility Representative or other
designated DOE representative to identify restarts or startups which the
contractor process determined to not require a RR.
C. For every startup or restart that requires a RR, site procedures and processes that form
the bases for the contractor’s recommendation of the required level of RR should
include the following attributes:
[Note: When the startup or restart clearly meets one of the criteria for conducting an
ORR, it may still be useful to evaluate the following areas to assist in defining the
scope of the ORR and the preparation of the POA. In some instances, it may not be
clear whether the criteria for an ORR have been met. A possible situation is when a
new mission is introduced into a nuclear facility but the DSA and TSR are changed
only to accommodate the new mission. In that situation, it may be necessary to
evaluate the degree to which the new mission utilizes the existing infrastructure to
determine whether a full-scope ORR is appropriate. The fact that the DSA and TSRs
were only changed rather than completely replaced should not immediately preclude
consideration of the need for an ORR.]
1. Hazard Category of Facility or Area where Startup or Restart should be Performed.
Identify the Hazard Category as it currently is defined for the facility, building, or
area in which work is intended to be started or restarted. Identify the Hazard
Category of the activity being started or restarted in an existing facility or area.
2. Startup or Restart Safety Basis Impacts. If there is an updated or revised safety
Section 21
basis associated with the startup, identify the magnitude of the changes. If a change
to the safety basis has not been made, evaluate the activity as it is currently planned
against the effective safety basis using the USQ process. If changes to safety basis
documents should be needed, the elements of the activity should be described that
drive these changes and the anticipated approach to making the changes.
3. Startup or Restart Hazards. Identify and evaluate the important hazards associated
with the facility, activity or operation being started or restarted. Identify and
evaluate the nature of the hazards and the likelihood of their occurrence, compare
them with existing hazards, and indicate whether or not they are new to the site,
facility, building, or area in which the startup or restart is intended to be conducted.
Hazards to be considered that affect the risk or consequences of the nuclear activity
being started or restarted should include non-routine, industrial, chemical,
radioactive, nuclear criticality, and nuclear material hazards.
4. Startup or Restart Complexity. The impacts of expected safety basis changes
should be considered. Identify and evaluate the complexity of the startup or restart.
Items to be evaluated include whether significant changes to equipment or
processes are needed in order to support the activity being started or restarted. The
number and complexity of procedures that require changes or development and any
required training and qualification changes should be considered.
DOE-STD-3006-2010
23
5. Control Changes Needed to Support Startup or Restart. Identify and evaluate the
nature of the changes to existing controls or new controls needed to conduct the
activity or process that is being started or restarted. This attribute should consider
the complexity of new or modified controls such as whether multiple new or
modified TSR-level controls are required associated with the addition of safety-
class or safety-significant equipment or significant modifications to existing TSRs.
6. Status of SMPs. Evaluate the nature of changes required for each SMP to support
the startup or restart. Each SMP should be considered individually with a listing of
the changes or actions necessary to achieve readiness to commence nuclear
operations. The aggregate effect of the SMP status should be considered when
determining the level of RR.
7. Prior Startup or Restart Experience. Identify and evaluate any facility, building, or
area where the same or similar activities or operations have been performed.
Information that is helpful to evaluate includes similarities with existing equipment,
hazards, procedures, training, qualification, and processes. It is also important to
include the time between the startup of the first and second similar facilities. The
greater the time since the original RR, the less credit that should be taken for
conditions that were evaluated during the original RR.
8. Justification for Recommended Review Level. Based on the evaluation of the
preceding attributes, determine a recommendation for the level of RR. Justification
should be provided for the recommended level, connecting the recommended level
to the attributes described above. DOE O 425.1D is specific as to the conditions
that require an ORR. In most cases, it is clear when these conditions are met and an
ORR is recommended. When the circumstances of the startup do not meet the
criteria for an ORR, an RA is normally required unless the conditions for a routine
restart are met. When an RA is indicated, the level of the RA should be determined
by analyzing the information gathered.
Section 22
9. Determination when a DOE RA is Required. In selected situations, DOE O 425.1D
requires both a contractor and a DOE RA. In the remainder of situations when an
RA is required, the specific conditions of the startup and the site situation should be
evaluated to determine whether a DOE RA is required. The unique aspects of each
startup discussed above should be considered when making the determination as to
whether a DOE RA is required in addition to the contractor RA. An additional
consideration should be the record of the site contractor and individual facility
management in successfully achieving readiness to start nuclear operations and the
accuracy of the subsequent contractor RRs. The overall confidence of DOE site
management in the site contractor’s processes, execution, and past record should be
an important consideration in the decision whether to require a DOE RA. Only
during a DOE RA or joint RA (when approved) should the DOE site management
processes and personnel to oversee contractor operations be verified. Therefore, the
decision to not require a DOE RA should be reached when it can be confidently
DOE-STD-3006-2010
24
shown by other means that the DOE Site Management programs and processes to
oversee contractor operations are current, compliant, and effective. As noted later,
when a DOE RA is not required and DOE is the Startup Authorization Authority,
DOE Field Element Line Management must verify readiness to oversee contractor
operations before the Start of nuclear operations is authorized.
10 Recommendation of the SAA. Site procedures should include a process to identify
the appropriate recommendation of the SAA. Contractor procedures should discuss
which Contractor Line Manager positions may be proposed as SAA. In every case,
the SAA should be a senior operational line manager who is not directly responsible
(i.e., one or more line managers are “between” the proposed SAA and the manager
of the facility) for the facility in which the RR is to occur.
D. The process by which contractors determine the appropriate RR should contain the
following attributes:
1. Consistent Implementation. The process should be accomplished by a trained,
dedicated management organization such as a startup group or startup manager.
The process should ensure consistent RR level determination across a site.
2. Structured Documentation is Used and Maintained. Site readiness procedures
should provide checklists or decision guides to maintain consistency throughout the
process. These procedures must be concurred with by the local DOE office.
3. Identify levels of RA. If local procedures include provisions for predetermined
levels of RAs, they should indicate whether a DOE RA is required and identify the
contractor organization responsible for conducting the RA. The procedures may
specify that a checklist tailored to the specific startup or restart as prepared by the
RA Team Leader is an acceptable Implementation Plan. The options chosen by the
site contractor and accepted by DOE local office should be documented in the
procedures, and the process as to how the decision is reached should be clear.
4. Specify Feedback and Improvement Mechanisms for the Process. Site procedures
should include a provision for oversight and assessment by the contractor line as
well as independent oversight. Site records of the process should support and
enable routine oversight by both contractor and DOE organizations.
Section 23
5. Process to Identify Routine Restarts not Requiring a RR. Site processes should
include provisions for determining that a restart meets the criteria for using
approved operating procedures. Site procedures should include a process for
making a determination in an uncertain situation and provide for documenting the
basis for decisions that support no RR. The records of these determinations should
be available for routine review by contractor and DOE oversight personnel.
6. Basis for the Readiness Review POA. The contractor process should require that
the scope of the POA reflect the issues and changes identified and documented
DOE-STD-3006-2010
25
during the process for determining the level of RR. The documentation developed
during the determination process could be a reference or attachment to the POA to
justify the proposed scope.
E. DOE Field Element Line Management must develop procedures that define the
processes to be utilized to implement the responsibilities of this Order. The following
actions and responsibilities should be included:
1. DOE Line Management must concur with the contractor procedures. The DOE
processes should discuss the mechanism for obtaining this concurrence and the
management personnel who recommend or provide the concurrence.
2. DOE must approve (if acceptable) the contractor proposals submitted in the SNR.
The DOE processes should discuss how this approval should occur and identify the
management personnel who recommend or provide the approval. The DOE
procedure should discuss how the adequacy of the processes and personnel should
be determined.
3. DOE should have a process for determining the scope of DOE RRs (when required)
that uses the results of the contractor determination of the required review level. In
particular, DOE must include the three DOE-specific CRs unless a specific basis is
provided as to why the CRs need not be included in the RR.
4. DOE processes should specify the considerations and the basis for the decision as to
whether a DOE RA should be required.
5. DOE Field Element Line Management must review and concur with contractor
procedures for implementing the requirements of the CRD. DOE Field Element
Line Management must ensure that the contractor properly implements the
requirements of the CRD of the Order. Specific elements of DOE oversight must
include the elements in DOE O 425.1D Section 4.g.(2).
6. DOE should establish a formal process to evaluate, endorse, and approve contractor
readiness program documents, including the SNR, POA, corrective action plans and
closure packages, and Readiness to Proceed Memorandum.
Many sites have developed and successfully used procedures, checklists, and
decision strategies to support determination of the requirement for, and level of,
RRs. Examples of these procedures are available on the DOE Readiness Review
website.
5 STARTUP NOTIFICATION REPORTS
The responsible contractor must submit an SNR in accordance with approved contractor
procedures, or change to an existing SNR, that identifies all known facility, activity, or
operation new starts and restarts for which a RR is required. The report identifies the
facility and specifies whether an ORR or RA is required to verify readiness to commence
DOE-STD-3006-2010
26
Section 24
or resume operations. The remarks should describe the basis for the recommended actions
based on the requirements in DOE O 425.1D. For the SNR to be an effective tool for
managing the startup and restart process and ensuring agreement in the process between the
contractor and DOE, the required, approved implementing procedures governing these
reports should contain the following elements:
A. The SNR updates the previous quarter’s information for startups and restarts that have
not yet occurred and adds information for each startup or restart that has been identified
since the last report. The SNR must project startups and restarts at least one year
ahead. The purpose is to establish early, and at the appropriate level, the startup
authorization authority and the appropriate RR methodology for the startup or restart.
Changes late in the process routinely lead to delays and additional problems.
B. Information that is mandatory and suggested to be included in the SNR for each startup
or restart is listed in Table 5.1. This information allows DOE to make a timely and
informed decision, and confirms that the requirements are understood and
implemented.
C. Each SNR must be reviewed and approved by the DOE Field Element Manager. When
the SNR contains some startups or restarts for which the SAA resides within the PSO
or the Office of the Secretary, the Field Element Manager should approve those
startups or restarts for which he/she is the SAA and provide a recommendation
regarding approval, and forward the SNR to the PSO via correspondence for approval
of those startups for which Headquarters is the SAA. This ensures agreement at the
appropriate level for the startup decision, thus reducing the possibility of last-minute
changes of direction, which may be quite costly.
D. Each SNR, including the Field Element approval and/or recommendations, must be
forwarded to the PSO, site Lead Program Secretarial Officer or Cognizant Secretarial
Officer (CSO), as appropriate. The PSO or CSO forwards these documents onto the
appropriate Central Technical Authority (CTA), and HSS for information. The
individual site and Headquarters procedures should determine the processes for SNR
review and comment.
E. Contractor RR activities to start or restart operations requiring an ORR or RA must not
commence until DOE has approved the proposed RR method and SAA. Every nuclear
startup or restart for which DOE O 425.1D requires a RR must be included in the SNR.
Other routine resumptions of operations may be conducted without a RR using normal
contractor startup or restart procedures if such specific procedures are in place.
Contractor routine procedures must not be developed to avoid a properly scoped RA.
F. If a startup or restart requiring a RR is identified that is not listed on the current SNR
that might occur before submittal of the next periodic SNR, an updated SNR should be
submitted to ensure timely agreement on the details of the RR process for that startup
or restart.
DOE-STD-3006-2010
27
G. To ensure that the SNR contains all the information required by the Order in a
manageable and consistent format, contractor procedures should require that the SNR
include the information listed in Table 5-1:
TABLE 5-1 Information to be Included in the SNR
*- mandatory items
Index Item Description
1. SNR Unique
Identifier
This identifier should contain:
• DOE Secretarial Office operationally responsible for this SNR item;
• DOE Field Element that approves the SNR (note that this can be a
Section 25
Headquarters organization);
• Contractor;
• Fiscal year of initial submittal on the SNR; and
• Sequential number for the specific item on the SNR for that fiscal year.
For example: NA-YSO-B&WY12-2007-001
2. Facility and
Hazard Category*
The physical location where the startup or restart is intended to take place
along with its Hazard Category. This may be a specific building, a complex
of various buildings, or a transportation vehicle. It should be designated at
the same level as the safety basis that applies apply to the startup or
restart.
3. Short Title A brief descriptive sentence describing the startup or restart in general
terms.
4. Date of Last
Operation*
For restarts only, this is the date nuclear operations were last performed in
the location where they are intended to be restarted.
5. Reason for Non-
Operation*
The reasons the facility or activity is not operational (e.g., lack of program
work, maintenance, outage, safety concerns, event, new process)
6. Projected Startup
Date*
The month and year that the startup or restart is projected to be authorized
for operation. Specific annotation should be included if the date has
changed from the previous estimate and the reason for the change. The
explanation may be included with other comments in Block 11.
7. Projected date
for submittal of
POA*
The month and year when the contractor POA is intended to be submitted.
This action should occur four to six months prior to the start of the RR.
8. Proposed Type of
RR*/ Justification
for proposed
type of RR*
The type of readiness verification proposed (i.e., ORR or RA). Also
indicate whether a DOE RR is required or recommended. Provide the
basis for why the proposed RR is appropriate. This should be as specific
as possible to facilitate DOE review and approval
9. Proposed Startup
Authorization
Authority *
The specific position that is proposed to authorize the startup or restart
after successful completion of the readiness verification.
10. Approval Status This entry reflects that the particular SNR item has either been previously
approved or that it is being submitted for DOE approval. It may also be
used to indicate that the specific item has been completed, in which case it
would be removed from the next update.
11. Description &
Comments
A description of the startup or restart including hazards, complexity, and
impacts on items such as the safety basis. This should consider
classification elements and a classified supplement may be used if needed.
DOE-STD-3006-2010
28
Index Item Description
The intent is to provide sufficient information to allow for DOE approval of
the SNR item. Comments may include such items as the current status
(e.g., testing, training, management self-assessment (MSA), RA, or ORR)
and the basis for changes such as the projected startup date.
12. Contact The name, phone, number, e-mail address, or other means to reach the
person most knowledgeable of the details of the startup or restart.
6 ACHIEVING READINESS
The responsibility for achieving a state of readiness to safely conduct nuclear operations
resides solely with the line management of the facility or programmatic line management.
The CRs described in DOE O 425.1D provide a summary of the critical issues that should
be considered in preparation for operations. In general terms, readiness applies to the areas
of personnel (e.g. training, proficiency, numbers), equipment (safety and process systems),
and safety management programs (e.g. safety basis implementation, operational formality,
maintenance, ISM, quality).
Section 26
For complex projects, it is useful for the project to formally map the CRs to specific actions
that are intended to meet the CRs. Required actions can then be scheduled as part of the
project plan so that an integrated plan exists to achieve readiness as the project nears
completion.
DOE O 425.1D provides requirements for specific prerequisite actions to take to improve
the likelihood of a successful startup or restart. Establishing these prerequisites and
verifying their completion guide the process of achieving readiness as well as contribute
greatly to its success. A critical success factor is the rigor with which line management
determines that the prerequisites have been met and readiness has been achieved. A robust
line readiness verification or MSA program that is part of or in addition to the site Quality
Assurance (QA) Management Assessment requirements may be a key element in the
ability to determine that readiness has been achieved.
Achieving readiness to start nuclear operations is not specifically within the scope of DOE
O 425.1D and this Standard. Rather, the purpose is to verify that readiness has been
achieved to start nuclear operations. However, experience has shown that unless the
contractor clearly understands the important elements of planning and achieving readiness,
the contractor’s RRs may not be successful. It is therefore important to discuss the
important elements of a process for planning and achieving readiness in this Standard.
When the process is understood and followed, the probability of a successful and timely
RR is increased.
7 ROLES AND RESPONSIBILITIES
7.1 Contractor Line Management.
Contractor line management should plan for and achieve readiness to conduct nuclear
operations. The prior section provide some lessons learned and successful practices for
DOE-STD-3006-2010
29
achieving readiness and should be considered for incorporation into the processes and
procedures.
DOE O 425.1D requires that contractor line management must develop procedures to
define the processes that must be used to implement the responsibilities of this CRD.
These procedures must be submitted to DOE Line Management for concurrence.
Contractor line management roles and responsibilities, as specified in DOE O 425.1D
should be further defined in the contractor procedures to include the following:
• Identify each startup and restart of a nuclear facility and propose the level of RR
required, in accordance with contractor procedures discussed above.
• Prepare and submit to its immediate DOE Line Management a quarterly SNR (or a
frequency as specified by the PSO) that includes each startup or restart for which a RR
is required.
• In order to ensure adequate preparation for the RR, contractor procedures should
suggest that six months prior to the projected date for starting the RR, a POA should be
prepared and submitted.
• Support the Team Leader who is approved in the POA to lead the RR; make the Team
Leader available; make available and support the selected team members, and support
the preparations for the RR as requested by the Team Leader.
• Verify that readiness has been achieved by verifying that all prerequisites from the
POA have been met, all punch-list items have been resolved to support operations, and
that all actions from the project management plan for achieving readiness have been
satisfactorily completed. This action may frequently be accomplished through use of
an MSA process.
Section 27
• When readiness to start nuclear operations has been achieved, submit a formal written
statement to senior contractor management stating that readiness has been achieved and
requesting that the contractor RR be started. Any open items that require resolution
prior to starting nuclear operations must be identified; this should be a short and
manageable list. Contractor line management has verified that the preparations for
startup or restart have been completed with the exception of a manageable list of open
prestart issues. The prestart issues must have a well defined schedule for closure to
allow the Contractor’s ORR team to review the closure process.
• Direct the contractor RR to start and support it as necessary.
• To optimize the conduct of the RR, contractor management should: track the progress
of the RR. Recognize and resolve issues and problems as they occur. Provide
knowledgeable counterparts to each RR team member. Gather information from the
counterparts that should enable management to respond to issues and inadequacies
identified during the RR. Acknowledge that support for the RR should be a full-time
DOE-STD-3006-2010
30
job for the facility management team and assigned counterparts to achieve optimum
success.
• Resolve findings identified during the RR in a competent and thorough manner.
Prepare comprehensive corrective action plans to resolve pre-start and post-start
findings. Assign adequate resources to accomplish the actions identified in the
corrective action plans. Thoroughly review the actions committed to and verify that all
actions were completed. Senior management should be involved in the process of
closing out findings identified during the RR.
• If DOE is the SAA, prepare the Readiness to Proceed Memorandum and forward to
DOE with all required enclosures.
• If DOE conducts a RR, support that review as discussed above.
• When the SAA authorizes the start of nuclear operations, commence operations in
accordance with the provisions of the startup plan (see Appendix 2 for additional
guidance concerning startup plans). Follow the sequence of deliberate operations and
oversight identified in the startup plan until proficiency has been gained and the hold
points of the startup plan have been met, at which time full and unrestricted operations
may be appropriate.
• Track and complete the corrective action plans for post-start findings from the
contractor and DOE RRs.
• Evaluate process results to identify lessons learned and improvements that may be
appropriate for future startup efforts.
7.2 DOE Field Element Line Management.
DOE Field and Headquarters Line Management must prepare procedures that define
processes for implementing the requirements of DOE O 425.1D. The procedures should
assign responsibilities to individuals having competence commensurate with their assigned
responsibilities. Other sections of this Standard provide expectations and attributes of the
procedures.
DOE Field Element Line Management must review and concur with contractor procedures
for implementing the CRD requirements in DOE O 425.1D and must ensure that the
contractor properly implements CRD requirements. Key elements of an oversight program
must include:
• Ensuring that the contractor prepares and submits quarterly SNRs that accurately
reflect all required RRs;
• Ensuring that the contractor develops a POA that adequately defines the scope of the
RR;
DOE-STD-3006-2010
31
Section 28
• Ensuring that the contractor POA specifies the appropriate prerequisites for
commencing the contractor RR;
• Evaluating the qualifications of contractor RR team members;
• Evaluating the adequacy of the contractor RR;
• Verifying that the contractor RR final report adequately describes the review and
contains sufficient detail to support its conclusion regarding startup or restart;
• Ensuring that the contractor and DOE have satisfactorily resolved all pre-start findings
identified during the RRs prior to startup or restart of the facility; and
• Ensuring that the contractor and DOE have developed and implemented approved
corrective action plans for post-start findings;
DOE Elements should achieve and verify their readiness to oversee the contractor
operations that are being started or restarted. DOE oversight programs should be assessed
and updated as necessary. DOE Field Element endorsement of the contractor Readiness to
Proceed Memorandum should document its conclusion that it is ready to conduct this
oversight. Additional responsibilities can include:
• approval or endorsement of the SNR;
• preparation of a POA for the DOE RR;
• review and approval or endorsement of, the contractor POA;
• routine oversight of the contractor processes for achieving readiness;
• oversight of the contractor RR;
• achieving readiness for DOE to oversee contractor operations;
• approval of contractor corrective action plans for findings from DOE RRs;
• verifying closure of findings from the contractor and DOE RRs;
• evaluation and endorsement to the SAA of the contractor Readiness to Proceed
Memorandum when the SAA is a DOE official; and,
• oversight of initial contractor operations, with particular emphasis on compliance, and
with the limitations and compensatory measures specified in the approved contractor
startup plan.
DOE-STD-3006-2010
32
7.3 DOE Headquarters Line Management, including Oversight Organizations.
DOE Headquarters organizations must develop procedures that define the mechanisms by
which they oversee the RR process. These procedures describe the flow of process
documentation to Headquarters for review and approval. Headquarters roles and
responsibilities should be clearly defined in these procedures.
DOE Headquarters Line Management oversee DOE Field processes to verify readiness to
start up and restart nuclear facilities in accordance with DOE O 226.1A, Implementation of
Department of Energy Oversight Policy, DOE O 425.1D, and the provisions of this
Standard.
DOE O 425.1D, Section 5.b specifies that DOE independent oversight of the ORR process
is HSS’s responsibility. To ensure that startups and restarts of DOE nuclear facilities
proceed in a timely fashion, it is incumbent upon the contractors, Field Element Managers,
and Secretarial Officers to ensure that the PSO, site Lead PSO or CSO, as appropriate, the
CTAs, and HSS are provided with appropriate documentation to review throughout the
process. In its role of independent oversight, HSS may provide comments to these
organizations in a timely fashion to ensure that concerns are addressed with minimal
impact on the startup and restart schedule.
7.4 Office of Health, Safety and Security.
In addition to the general Departmental responsibilities specified in DOE M 411.1-1C,
Safety Management Functions, Responsibilities, and Authorities Manual (FRAM), HSS
exercises independent oversight of the startup and restart process for nuclear facilities.
This responsibility specifically entails the following:
Section 29
• In coordination with the PSO, may perform independent reviews of startup and restart
activities as appropriate and provides results of these reviews to the PSO/CSOs for
resolution.
• Reviews and comments as appropriate on the PSO, Field Element, and contractor
procedures for startup or restart of nuclear facilities and provides results of these
reviews to the PSO/CSOs for resolution.
• Provides timely reviews and comments on SNRs, contractor and DOE POAs, IPs, and
final reports for startup or restart of nuclear facilities.
7.5 Readiness Review Team Leader.
The RR Team Leader is nominated by line management in the POA and approved by the
SAA. The roles and responsibilities of the Team Leader are the same for ORRs and RAs.
The qualifications for the RR Team Leader should include:
• technical familiarity with the activities and functional areas being reviewed;
• previous performance-based review experience or training;
DOE-STD-3006-2010
33
• demonstrated leadership and managerial skills, including seniority in relation to the
members of the RR team, to permit smooth management of the RR team; and
• RR experience or formal training; and,
• knowledge of facility, activity or operation.
The Team Leader and Senior Advisor must not be from offices assigned direct line
management responsibility for the work being reviewed. Any exceptions require approval
of the startup authorization authority.
The extent of the Team Leader’s responsibilities may require that he or she be formally
released from other duties. The RR Team Leader should keep management informed of
the team’s progress and findings.
The RR Team Leader is responsible for managing and conducting the RR process. The
Team Leader selects the RR team members to conduct the RR. The information in the RR
POA guides the Team Leader in defining the areas requiring inclusion and the number of
team members needed. The ORR Team Leader must determine and document the
qualifications of the team members and their freedom from a conflict of interest in the
areas they are assigned to review. Appendix 3 includes an example form for use in
consolidating the required information.
Team member qualifications must be determined and documented by the Team Leader.
The Team Leader must document the team members’ freedom from a conflict of interest in
area that they are assigned.
Each team member must meet the minimum qualification requirements, as discussed in the
team member section.
The Team Leader is responsible for the following activities, each of which is discussed in
more detail in later sections.
• Ensure that the team prepares the IP in accordance with the scope (breadth and depth)
defined in the POA. RR team members and senior members assist in developing the
IP.
• Approves the RR IP. Although copies are provided to line management and DOE
Headquarters for information, the responsibility for approving the IP rests solely with
the Team Leader.
• Executes the RR in accordance with the IP Manages the preparation, approves and
submits the RR final report. Sections 8.9 and 9.10 discuss this report.
Note that DOE-HDBK-3012, Guide to Good Practices for ORRs (ORR), Team Leader’s
Guide, provides information useful to a RR Team Leader in preparing for and conducting
an ORR or RA. The handbook contains discussion on suggested processes for preparation
and conduct of the review. It also contains a lessons-learned section that is a compilation
DOE-STD-3006-2010
34
Section 30
of the lessons learned from conducting RRs. The Handbook is a useful guide for both
experienced Team Leaders and those with less experience. Additional information to assist
the Team Leader in preparing for the ORR is available on the DOE Readiness Review
website.
7.6 Readiness Review Team Members.
Readiness reviews teams are comprised of individuals representing disciplines as necessary
or as appropriate. Team members are individually chosen by the Team Leader. The Team
Leader should ensure their backgrounds demonstrate technical competence and experience
in all subject areas and SMPs within the scope of the review. The RR team should be
technically competent to assess all functional areas and CRs defined in the POA. The
number of members should be determined by the scope of the RR and the size and
complexity of the facility.
Each team member should meet the following minimum qualification requirements:
• Technical knowledge of the area assigned for evaluation. The knowledge should
include experience working in the technical area.
• Knowledge of performance-based assessment processes and methods. This knowledge
may be gained through experience as an auditor or inspector or through training that is
evaluated as acceptable by the Team Leader.
• Facility-specific information that may be gained through a combination of required
reading and facility tours and presentations.
• Independence, in that no team member may review his or her own work or work for
which he or she was the responsible manager.
• Ability to commit the necessary time and effort to fully support the RR schedule. The
Team Leader should interact with each prospective team member’s management to
gain support for the commitment to the RR team (i.e., the team member’s management
commits to the team member’s full support of the RR). It is critical to the success of
the RR that the managers of the team members provide for this level of support for the
RR. The Team Leader should recognize this requirement when selecting the team
members.
Team members are responsible for assessing the adequacy of readiness by conducting
reviews in selected areas important to the safe startup or resumption of operations. The
team members should assist the Team Leader, and senior members if applicable, in
defining the depth of review in their assigned areas; documenting the criteria and review
approach for their assigned areas, subject to approval by the Senior Advisors and the Team
Leader; attending team meetings to coordinate activities with other team members;
documenting their own activities, findings, and conclusions in a manner specified by the
Team Leader and the Senior Advisors; and concurring with the content of RR final report
DOE-STD-3006-2010
35
in the areas for which they were responsible. If necessary, any differing opinions should be
addressed in the report
Representatives from operations, environment and regulatory compliance, safety,
engineering, technical, and quality assurance organizations on site, but not directly
responsible for the conduct or supervision of the work being reviewed, may be selected as
team members. An individual’s knowledge of the particular systems, processes, safety
documentation, or facility, as well as knowledge of the RR process, should be considered
in determining his or her fitness as a member of the team.
Team members should be able to conduct a broad range of tasks, including, but not limited
to, the following:
Section 31
• Developing or providing input to the CRAD for the functional area to which he or she
is assigned;
• Reviewing as-built drawings and other applicable procedures and documents;
• Compiling supporting documentation to prepare for and conduct the RR;
• Determining whether the activity complies with applicable environmental requirements
and Federal and state laws and regulations;
• Conducting the review in accordance with the criteria and performance objectives in
the IP or as assigned by the Team Leader;
• Concurring with the determination of readiness to commence nuclear operations and
the conclusions presented in the RR report in the team members area of assessment;
• Submitting completed certification documentation for review and approval; including
preparing supporting or special reports;
• Working with other RR team personnel to ensure timely resolution of the unresolved
questions and concerns;
• Assisting, the Team Leader and senior members in preparing the final report, as
requested.
8 OPERATIONAL READINESS REVIEWS
8.1 Plan of Action.
For new starts and restarts requiring an ORR, the responsible contractor must indicate in
the SNR its intent to conduct an ORR and briefly describe the proposed process.
Approximately six months before the projected date for the contractor’s ORR, the
contractor should prepare and submit for approval the ORR POA. This timing is
recommended in order that the ORR process can proceed in an efficient manner that does
not impact the schedule of readiness. In the event that the requirement for an ORR is
DOE-STD-3006-2010
36
identified less than four months before the estimated start, the POA should be expeditiously
developed, reviewed, and approved so that the ORR schedule is maintained.
The POA must provide the proposed ORR scope, the prerequisites for starting the ORR
and, the proposed Team Leader. The POA should also provided the ORR schedule,
including estimated start date and duration, and any other information required by DOE O
425.1D and information unique to the proposed ORR.
The POA is prepared by line management and describes the breadth of, and the
prerequisites for, the ORR. The POA is the document in which line management describes
what must be evaluated by the ORR, based on the extent of the activities involved in the
resumption or startup. Through the process of the POA, the proper authority within DOE
concurs with or approves the planning for the ORR. The ORR process is then conducted in
accordance with the POA.
The POA is submitted to the designated SAA for review and approval. If the SAA resides
with DOE, the contractor’s POA should be submitted to the cognizant DOE Line
Management. DOE Line Management shall forward the contractors POA to the SAA with
its recommendation for disposition. A copy of the proposed POA is provided to the PSO,
the site Lead Program Secretarial Officer or CSO, as appropriate, the appropriate CTA, and
HSS for information and action in accordance with the individual office’s implementing
procedures for DOE O 425.1D.
The level of detail in each POA varies with the complexity of the facility and the
operations or activity being started or restarted. The level of detail should be adequate to
justify to a skeptical reviewer the decisions being proposed. The detail should be adequate
for preparers, reviewers, and the Team Leader to defend the decisions being made. In
addition, the POA contains the details of the intended scope of the ORR that guides the
development of the IP and ultimately the ORR. Through the level of detail in the POA,
line management proposes, and the SAA approves, the specific areas that are intended to be
reviewed, the desired depth of the review, and the areas that line management have
determined require a lesser or no review.
Section 32
When the POA lacks the necessary level of detail for the scope, the ORR team has no
choice except to apply the most comprehensive scope to the IP and the ORR. The
unintended result is an increase in the time and effort required to conduct the ORR, forcing
the evaluation of areas that DOE and contractor line management have agreed do not
require additional review.
In general, the POA should be very specific as to the systems, programs, processes, and
equipment within the scope of the ORR. Also, the POA should discuss the level of detail
expected of each CR. In the case of CR 1, each SMP within the scope of the ORR, along
with the appropriate breadth and depth of the review, is identified. For example, the review
of a specific SMP may require only the implementation of the program within a specific
process or system. In other cases, it may be appropriate to review the entire SMP from the
contract requirement through implementation mechanisms and its implementation within
the facility. In each case, the POA should provide the specificity so that the IP reflects the
DOE-STD-3006-2010
37
appropriate scope approved by the SAA. The POA also specifies the prerequisites for
starting the ORR and identifies the proposed ORR Team Leader.
DOE O 425.1D allows omitting all or part of a CR in the scope of the ORR. To utilize this
provision, a prior successful, independent and timely review should have occurred within
12 months unless justification can be made for a longer period. Justification may include a
robust, ongoing management and independent assessment program (criteria 9 and 10 of a
compliant 10 CFR 830.120 Quality Assurance program) of the subject that could extend
the baseline provided by the independent review. For the review to be independent, it must
have been accomplished by an independent assessment organization or team. Examples
include previous RRs, Integrated Safety Management System (ISMS) verifications,
comprehensive program audits, and external assessments that are sufficiently
comprehensive to provide assurance as to the status of the particular program being
considered.
The contractor ORR POA should provide the starting point for the DOE POA. The DOE
POA should include prerequisites that ensure the readiness of DOE programs and
personnel to oversee contractor operation.
The DOE ORR POA includes in the breadth all areas appropriate to the responsible
contractor POA and a thorough review of the DOE management organization to determine
its capability to oversee the facility operations to be started or restarted. The DOE ORR
POA should include prerequisites, Team Leader designation, breadth of the DOE ORR,
estimated schedule and duration, and additional information required by DOE O 425.1D.
The DOE POA is formally submitted to the appropriate SAA by cognizant line
management. Once approved, the DOE POA is provided by the SAA to the PSO, the site
Lead Program Secretarial Officer or CSO, as appropriate, the appropriate CTA, and HSS
for information. The SAA shall provide a copy of the POA to the ORR Team Leader.
Each POA contains the following elements:
• Name of the Facility or Activity Being Started: The name should be specific to the
facility or activity being evaluated and started or restarted. For example, if a single
process within a building is to be restarted, the facility name would be the process
name. On the other hand, if the process encompasses several buildings and an area, the
name would be the encompassing process name.
Section 33
• Description of Facility or Activity: This should include buildings, systems, and
processes included in the startup or restart. The description is instrumental in defining
the scope of the review. For example, if most support functions and procedures are
outside the boundary of the facility being started up, the ORR scope should focus on
interfaces with existing programs. This section of the POA should define the physical
scope of the ORR. The physical scope may include systems, structures, or processes.
• Identification of the Responsible Contractor: This should be the contractor who
certifies readiness of the facility to operate. It is normally the contractor who submits
the contractor POA.
DOE-STD-3006-2010
38
• Designation of Action as a New Start or Restart: This should be the identification as to
whether the facility is being started for the first time or being restarted. It is reasonable
that a new process within an existing building would be a new startup. Resumption of
a process after an extended period of no operation would most reasonably be a restart.
• New Start Discussion: The following elements or details about the facility or process
should be included to support or create the basis for the recommended decisions:
a. hazard categorization for new facilities and the basis for their designation;
b. status of the DSA and TSRs. The discussion should indicate whether there is a
new or revised DSA and TSR, the status of implementation, and when the latest
IVR was performed to ensure adequacy and completeness. Any re-verifications
should also be discussed; and
• Restart Discussion: If the action is a restart of an existing facility or process, the
following information should be provided to support the follow-on decisions:
a. hazard categorization of the facility when restarted and the basis for determination
(e.g., criticality, explosive, chemical, environmental). In the event that no formal
hazard categorization has been made, a discussion of the relative hazard may be
appropriate;
b. cause of the shutdown;
c. duration of the shutdown;
d. repairs accomplished during the shutdown period;
e. modifications accomplished during the shutdown period and their effect on the
approved safety basis;
f. any anticipated process changes following restart; and,
g. status of the DSA and TSRs, including a history of IVRs or other verification
reviews.
8.1.1. Proposed scope of the ORR.
This is intended to be a key section of the POA. The breadth is the top-tier CRs, and
should be derived starting with the CRs listed in DOE O 425.1D and the physical scope
in the facility description. In order to justify not performing evaluation of a core
requirement, or portion thereof, the POA may reference a timely, independent review
that addressed a core requirement in a technically satisfactory manner, provided the
review being referenced determined the requirements were successfully implemented.
The breadth of the DOE POA should consider the results of the contractor ORR as well
as DOE management and oversight programs.
The discussion of the ORR scope in the POA supports the development in the IP of the
depth of each aspect of the ORR. In support of this function of the POA, and to ensure
maximum understanding regarding the intention of the SAA as to what may be
reviewed, care and attention to detail are important in developing this section. The
DOE-STD-3006-2010
39
Section 34
scope should start with a clear discussion of the physical or geographic scope of the
ORR. A clear definition of the SSCs and the individual processes or activities within
the scope of the ORR should be provided. Experience indicates that clarity may be best
achieved when each CR is discussed individually.
The POA must include justification for any CRs that are not included in the ORR. For
the CRs that are included, the discussion should clearly describe the detail or depth to
which each is to be reviewed. In some cases, only the interface with site infrastructure
programs may need to be included. In other cases, the entire site-wide program may be
evaluated. The basis or rationale for the scope of each CR being included in the ORR
should be discussed to ensure that the IP reflects the expectations of line management
as approved by the SAA.
The discussions should include reference to site-wide as well as facility-specific
reviews that provide a basis for the ORR. Evaluations such as previous ORRs, ISMS
verifications, independent DOE or contractor reviews, or similar reviews may reduce
the necessary depth of review for individual CRs. Similarly, the recent history of the
facility, site, or activity may be important in defining the level of detail or depth of
individual portions of the review. Conditions such as recent occurrences,
investigations, or systemic issues identified within the site may be the basis for an
increase in the breadth or depth of the review of individual CRs.
8.1.2. ORR Prerequisites.
Defining the prerequisite conditions to be met by facility management prior to the start
of the ORR (appropriate for both the contractor and DOE ORRs) is intended to be an
important element of a successful ORR. The process that the contractor uses to achieve
readiness, through management actions and confirming readiness through the ORR
process should be reflected in the prerequisites.
The contractor POA prerequisites must address each CR contained in the CRD of DOE
O 425.1D. The DOE POA prerequisites must address each CR that applies to DOE as
well as the overall prerequisites that the contractor ORR has been completed. The DOE
POA prerequisites must address the readiness of DOE management and Field Element
programs and assigned personnel who monitor facility operations. Adequate detail
should be included to permit an understanding of the programs and personnel that are
considered essential to provide adequate oversight of the facility or process for startup
or restart.
The prerequisite section of both the contractor and DOE ORR POAs should refer to
specific items such as a project management plan, a readiness self-assessment plan, a
compliance assessment program, safety documentation such as the DSA and TSRs
(including any IVR that demonstrated satisfactory implementation), or environmental
assessments or impact studies. The DOE POA should contain specific prerequisites
that, when completed, provide confidence that DOE is ready to oversee contractor
operations that are about to be started or restarted. The prerequisites must be described
in terms of specific measurable items.
DOE-STD-3006-2010
40
In aggregate, the prerequisites provide assurance that the contractor and DOE have
achieved readiness to start nuclear operations within the facility and that the
infrastructure programs are sufficiently robust and mature to ensure that readiness to
conduct nuclear operations is achieved and maintained
Section 35
8.1.3. Estimated ORR Start Date and Duration.
The ORR start date is for planning purposes only and should be the best estimate.
Identification of a date is not to infer that the ORR is schedule-driven rather than
readiness-driven. The DOE ORR estimated start dates, as well as the contractor ORR
schedule, should be provided for information in the contractor POA to assist DOE
management in planning for the DOE ORR.
8.1.4. Proposed ORR Team Leader.
The POA must identify a qualified Team Leader who should be a senior employee with
adequate experience and knowledge to effectively lead the evaluation of the facility.
The basis for the qualifications should be summarized in the POA and include:
• technical familiarity with the activities and functional areas being reviewed;
• previous performance-based review experience or training;
• demonstrated leadership and managerial skills, including seniority in relation to the
members of the RR team, to permit smooth management of the RR team; and
• RR experience or formal training; and,
• knowledge of facility, activity or operation.
The Team Leader and Senior Advisor must be independent; neither must be from
offices assigned direct line management responsibility for the work being reviewed:
any exceptions require approval of the startup authorization authority. The appointment
of the Team Leader is approved by the SAA when the overall POA is approved.
8.1.5. Senior Advisors.
Senior Advisors are recommended for both contractor and DOE ORRs with a complex
scope or within a complex facility. In many instances, Senior Advisors may not be
needed, particularly if the Team Leader has significant ORR experience. On other
occasions, a single Senior Advisor to assist the Team Leader may be appropriate; or,
for particularly complex or controversial ORRs of high-hazard facility, activity, or
operation, as many as three Senior Advisors may be advisable. The qualifications for
Senior Advisors may be included in the POA. However, whether or not identified by
the POA, the Team Leader has the prerogative to select a Senior Advisor. For most
DOE-STD-3006-2010
41
ORRs, a Senior Advisor may be a critical assistant to the Team Leader.
8.1.6. Official to Approve the Start of the ORR and Approve Startup or Restart of the
Facility, Activity, or Operation.
For the DOE ORR, this is the SAA designated in the approved SNR. Designation of
the SAA is made in accordance with the requirements of DOE O 425.1D. For the
contractor ORR, the official designated to approve the start of the ORR should be a line
manager senior to the manager responsible for achieving overall readiness to start
operations.
8.1.7. Reviewers’ Approval.
The individuals who prepared and reviewed the document should be identified by name
and title.
8.1.8. Distribution.
This is a listing of the individuals and organizations who should receive copies of the
POA following its approval. Individuals who have either responsibilities or interests in
the new start or restart process are listed. The approved ORR POA forms the basis for
ORR activity in the restart or startup process and should therefore be distributed to all
interested individuals and organizations.
8.1.9 Approve the Plan of Action.
Line Management submits the POA to the SAA for approval. The POA must be
approved by the SAA.
8.2 Operational Readiness Review Implementation Plan.
Section 36
The IP is the plan for conducting the ORR. It should include the checklists, evaluation
criteria, review methodology, qualification requirements for team members, and reporting
expectations, as necessary, to efficiently execute and report the results of the ORR.
The IP must be developed by the ORR team and approved by the Team Leader. It should
be provided to contractor and DOE Line Management for information. The usual process
should be for the Team Leader to develop an initial draft of the IP that is then reviewed and
tailored by the individual team members.
The IP defines the ORR scope to be consistent with the breadth and conditions of the
startup or restart, as described in the approved POA and provides the depth of the intended
review. If a previous timely ORR has been completed for the facility being reviewed, the
IP and subsequent ORR should place emphasis on the operations that have changed since
the last review and the effectiveness of the corrective actions developed to address the
findings.
DOE-STD-3006-2010
42
The approved POA is provided to the ORR Team Leader, who then identifies the necessary
team membership to conduct the ORR. The Team Leader, with the assistance of the team,
develops the IP consistent with the breadth defined in the ORR POA and the specific
facility involved. The IP must include CRADs based on the scope defined in the POA.
The IP for the DOE ORR should reflect that the DOE ORR is different from a properly
executed contractor ORR. The DOE ORR should assess the adequacy and accuracy of the
contractor ORR. Because the contractor ORR provides the substantial basis for acceptance
of readiness, the DOE ORR should assess the scope of the contractor ORR and should
sample contractor results (e.g., verify conduct of operations by walking down procedures,
observe normal and off-normal operations or training evaluations, quiz personnel on
training material). The DOE ORR should place significant emphasis on the effectiveness
of the contractor’s preparations through conducting demonstrations of normal operations,
abnormal events, and emergency drills. Additionally, the DOE ORR should assess the
readiness of the responsible DOE line organization(s) to oversee the safe management of
operations and the effectiveness of coordination among organizations.
The IP is intended to document not only the process the team uses to conduct the review,
but also is intended to define the rationale for that process. In documenting the process, the
team may evaluate the selection of criteria and review approaches, the procedures that it
uses to develop findings and conclusions, and the criteria to be applied to categorize
findings as prestart and post-start. The IP provides for evaluating the breadth and depth of
the ORR.
The IP should be sufficiently detailed to provide information to management and guidance
to the ORR team members. The team preparing the IP should have a thorough
understanding of the facility and its associated issues. Onsite facility visits and interviews
may be required before the IP can be adequately developed and finalized.
The IP should be provided by the Team Leader to appropriate oversight and higher-level
DOE management before the DOE ORR begins.
8.3 Implementation Plan Format.
The following format is recommended. Alternative formats may be specified in local
procedures so long as they include the required items and lead to a successful ORR result.
Section 37
• Introduction and Background: The introduction should describe the activity that is
intended to be reviewed and the reason for shutdown (if a restart). The background
section describes the basic process, hazards, and issues associated with the activity to
be reviewed.
• Purpose: This section should describe the reasons why the review is being conducted
and provides the basic insights for the defined scope of the review.
DOE-STD-3006-2010
43
• Scope: This section should describe the scope that defines the physical and
administrative boundaries of the facility, justifies those defined boundaries, and
supports function reviews relative to each of the following:
o Plant and equipment readiness;
o Management and personnel readiness; and
o Management programs (e.g., procedures and plans) readiness.
The scope section should describe the approved scope from the approved POA. Each
breadth element (core requirement) required by the POA must be incorporated into the
IP. The depth to which each scope element is evaluated is specified and quantified by
the IP criteria and review approaches (CRADs) to be consistent with the discussion in
POA.
The scope (CRADs) defines the physical scope, including facilities, systems, and
processes. In addition, it should describe the level of review of the various site
infrastructure SMPs that comprise the site ISMS.
• Prerequisites: The IP should summarize the prerequisites for starting the ORR,
including those specified in the POA. The team should not develop the prerequisites,
but they should understand them and may use them in developing the criteria and lines
of inquiry for the individual CRADs.
• Review Approach: This section should define the generic approach by which the
review is conducted and provides an introduction to the ORR process. The ORR
CRADs should be discussed in this section. The methodology for classifying findings
as prestart and post-start should be defined here, as should the method for report
preparation. The CRADs may be included as an appendix to the IP.
The reviews conducted by each team are guided by CRADs, which are grouped into
functional areas. The ORR Team Leader should select the functional areas and their
groupings. The selections should be based on the ORR scope and the expertise of the
team members.
CRADs are used in the IP to establish the depth of the ORR and provide guidance to
the ORR team members. As such, the quality of these documents significantly impacts
the overall quality of the ORR. CRADs are the bases used to evaluate the CRs of an
ORR. The CRs of an ORR include the 17 CRs from DOE O 425.1D (14 of which
apply to the contractor ORR), as well as any additional CRs specific to the particular
ORR. Each CR is evaluated based on the criteria established. The criteria should be as
specific and objective as possible.
The CRADs should provide the means by which the graded approach is applied to the
scope of the ORR. The areas that are significant to the startup or the shutdown should
be assessed in greater depth than other areas. For example, if, during a maintenance
shutdown, a system was modified or a new system was added, the training, procedures,
documentation, and safety basis for the new system should be reviewed exhaustively.
DOE-STD-3006-2010
44
Another system in that same facility that did not undergo modification would receive a
less comprehensive review that would involve a sampling of the training and
procedures associated with the system.
Section 38
For example, the team could interview 20 percent of the qualified operators of
unmodified systems to assess their level of knowledge, and a larger percentage for
operators of modified or new systems. In a shutdown that was caused by a DSA or
TSR or safety limit violation due to a personnel error, the training and qualification
program for the facility should be assessed in detail, while safety basis implementation
would need a less comprehensive assessment. For a new high-hazard facility, the depth
of the review should be complete in all areas. For a restart of a low-hazard facility, the
review should be focused on the areas significant to the startup or shutdown, with the
remaining core areas addressed to a lesser extent via less extensive criteria. In general,
the discussion in the POA guides the level of detail in any particular review area.
The Objective in each CRAD should include all, or selected portions, of one or more
CRs. The IP must include all CRs as specified in the POA. This ensures that all CRs
are addressed regardless of the approach used in developing the criteria. The criteria
that address the CR or portion of a CR should follow, and be related clearly to, these
requirements. Each criterion, should be a statement of the specific actions or attributes
the team member(s) use to make a judgment as to the readiness of the site, facility, or
process to operate in this specific area.
The Review Approach section of the CRAD should describe the documents to be
reviewed, the personnel to be interviewed, and the shift evolutions, including tours and
walkdowns, to be observed that enable the team to reach a conclusion as to whether the
criteria have been met. The final portion of the CRAD should include any references
DOE Orders, Standards, or site-specific requirements against which the preceding
criteria are to be assessed. The alpha-numeric identification methodology chosen for
the ORR implementation plan should represent a logical “work breakdown structure”
chosen to describe the entire ORR effort so that all elements can be related back to the
core requirements for safe operation of the facility. Examples are presented in the
writing guide in Appendix 3.
The initial criterion in each CRAD for the DOE ORR may be an assessment of the
adequacy of the contractor ORR in the Objective section. The Review Approach
section for the DOE ORR should include an evaluation of the contractor ORR,
including the final report, the corrective action plans, and the finding closure reports.
Interviews with members of the contractor ORR team may also be specified in the
Review Approach, as well as a sampling of the contractor ORR field work.
The effectiveness and completeness of the ORR may depend in large measure on the
quality of the CRADs. A critical element in developing each CRAD is the thoughtful
input by the team member who use it. It is thus important that the ORR team members
be selected early and that they actively participate in developing the IP. Additional
DOE-STD-3006-2010
45
discussion concerning the development of CRADs, as well as example CRADs, is
included in Appendix 3, the Writing Guide.
• ORR Preparations: This section describes any preparations, including pre-visits and
document reviews, for example, that may be undertaken prior to the onsite review. A
discussion of qualifications and training considerations for ORR team members may
appear here.
Section 39
• ORR Process: This section describes how the ORR is intended to be conducted.
Subjects include the sequence of activities from the initial in-briefing through the final
out-briefing, including record reviews, interviews, and operational demonstrations.
The section should discuss the conduct of team meetings, the overall decision process,
and developing the final report. Some discussion may be appropriate as to how
evolutions and upsets should be conducted and observed.
• Administration: This section should describe the mechanism for ORR-related
meetings, correspondence, communications, and team structure. The ORR team
composition, organization, interface requirements, and any oversight groups and DOE
organizations to be involved in the review should be discussed in this section.
• Reporting and Resolutions: This section should detail the methods that the ORR team
should use to report review results.
• Schedule: This section should include a discussion of the proposed schedule for any
preparation, previsits, the onsite review, report preparation, and closeout.
• Appendices: The Appendices should include the CRADs that the team members
should use. The Appendices may also include reporting forms, writing guides, team
resumes, and other sections that would be appropriate to append. The Appendices to
this Standard, as well as the Team Leader’s Guide and DOE Readiness Review web
site, contain information and examples that may be useful during development of the
Appendices for the ORR IP.
8.4 Conduct of Operational Readiness Reviews.
The purpose of the ORR is intended to examine the aspects of the activity under review and
to ensure that the equipment, procedures, and personnel associated with the activity are
ready for startup and safe operation. The ORR is also intended to verify that the site
infrastructure, including the SMPs, ensures that the status of readiness to safely conduct
nuclear operations should be sustained throughout the operating cycle.
The ORR is a performance-based assessment that includes observing and documenting the
responses of operating and support program personnel to normal and off-normal events as
demonstrated by drills, preoperational tests, and exercises. In addition, field assessments
should be conducted to verify that field configurations match the applicable supporting
documentation. The ORR team should also conduct interviews with personnel, including
management, to evaluate their readiness to conduct operations. The IP guides the
evaluations.
DOE-STD-3006-2010
46
The ORR team must verify that the approved requirements documentation is in place and
the procedures, personnel, equipment, and systems support the requirements. The RR
process is not intended to be used to approve the foundation documentation such as a
Safety Basis.
Critical to the establishment of operational requirements are formal agreements between
the operating contractor and DOE that delineate these requirements. These are generally in
the form of a contract section J attachment, which is required by the DEAR for nuclear
facilities. The DEAR includes requirements that govern the safe operations of a facility.
The listing of these requirements is frequently described as Contract List A (laws and
regulations) and List B (DOE directives).
Section 40
The team should perform a systematic review of the facility’s compliance with these
requirements. In many situations, a recent verification of implementation of the contract’s
requirements documents into site manuals of practice is available. In those situations, it is
only necessary for the ORR team to verify implementation of the site manuals of practice
in the facility or activity being evaluated. These requirements should be verified by the
operating entity to have been implemented in the facility, or DOE-approved compensatory
measures put in place during the period of implementation. DOE should approve the
compensatory measures and the implementation period if needed.
Prior to the ORR starting, DOE Line Management has received a Readiness to Proceed
Memorandum from the responsible contractor certifying that the facility, activity, or
operation is ready for startup or restart and this has been verified by the contractor ORR.
As DOE O 425.1D states, it may be appropriate for the ORR team to observe events
significant to the startup process before the ORR begins. Experience indicates that the
events meeting this criterion are emergency management exercises initiated in the facility
within the scope of the ORR. Because it is difficult to plan and schedule emergency
management exercises during an ORR, it is appropriate for the ORR teams (both contractor
and DOE) to observe the exercise when it occurs. When this situation occurs, it is
important that the DOE and contractor ORR team members maintain independence of their
observations and conclusions which are included in the individual ORR reports.
For the observation to be a valuable contribution to the ORR, the exercise should have the
initiating event within the facility being started, all emergency management documentation
for the facility should be complete, and personnel should be trained in emergency
management procedures. It is not normally possible to meet these criteria more than a
month or two before readiness is achieved to start the ORR. In very unusual
circumstances, there may be other unique events that should be observed by the team
before the ORR begins. This may include a one-time, high-risk test of a component or
system within the scope of the ORR or a complex, integrated test sequence. However,
normally it is adequate for the ORR team to review the results of the testing. Since the
testing is normally not accomplished by operations personnel and not conducted in a
manner to demonstrate formality of operations or personnel capabilities, direct observation
of such testing is of little value towards demonstration of readiness to start nuclear
operations.
DOE-STD-3006-2010
47
Unsuccessful ORRs
The assumption of the ORR process is that before it commences, readiness to start nuclear
operations has been essentially achieved and that the ORR team can recommend
authorization to start operations when the prestart findings have been resolved. However,
in rare instances, the number or magnitude of the findings may be such that the team is
unable to conclude that resolving the findings may lead to a condition of readiness to start
nuclear operations. Such a conclusion recognizes that because the ORR process is
executed through sampling, some important elements of readiness may not be evaluated
because of findings that have been identified. For example, if the TSRs are not fully
implemented, it is not possible to assess the adequacy of the individual implementation
mechanisms. In another example, if the training and qualification requirements were not
adequately defined, it may not be possible to determine the adequacy of the knowledge and
competence of the operating personnel since they had not received appropriate training.
However, there is no firm definition as to when an ORR should be stopped. All facts and
issues should be evaluated to determine an answer to the question of whether the ORR
team is convinced that readiness has been achieved and whether nuclear operations can be
safely started when the identified prestart findings are resolved.
Section 41
The ORR team should not casually reach its decision to stop an ORR or reach an
unsatisfactory conclusion, but should instead carefully consider all of the facts that led to
its conclusion. The basis for the team’s decision should be supported with specific issues
and examples
In general, there are two situations that could arise. In the first situation, the team identifies
many areas in which numerous issues are identified, which leads the team to a conclusion
that the ORR is unsatisfactory and should be repeated. The repeat ORR can commence
after line management implements corrective actions to address the identified issues and
recertifies readiness to start nuclear operations. It may be appropriate to develop a new
POA and IP for the repeat ORR or simply repeat the ORR using the same POA and IP.
In the second situation, many functional areas of the ORR are adequately prepared to
support nuclear operations; however, deficiencies are identified in some important
functional areas to the extent that it was not appropriate to simply identify findings to be
corrected. In such a case, it may be appropriate to complete the ORR for the functional
areas that are ready to support nuclear operations and finalize the report in those functional
areas. For the inadequate functional areas, the ORR may be suspended until the deficient
functional areas are remediated. If the option to suspend the ORR is chosen and agreed to
by the SAA, the interim report should provide line management general information
concerning the areas of inadequacy, but not a punch-list upon which they should focus all
attention. Once line management has fully evaluated the areas of inadequacy and taken
corrective actions to bring them into a state of readiness to support nuclear operations, the
ORR may be resumed in the deficient functional areas.
The Team Leader and the SAA should be aware of the possibility of an unsuccessful ORR
and decide how it should be handled. Because the Team Leader works for the SAA, who
DOE-STD-3006-2010
48
directed the start of the ORR, suspending the ORR should only occur with the SAA’s
agreement. If the SAA does not agree, the team is obligated to complete the ORR and
determine that readiness to start nuclear operations has not been achieved, in which case
repeating the ORR is the only alternative.
Some organizations within DOE believe that it is never appropriate to suspend and restart
an ORR and that if an ORR cannot be completed, the entire process should be repeated.
However, in cases where an ORR can be satisfactorily completed in some functional areas,
it may be appropriate to take credit for the functional areas that were satisfactory and grade
the POA accordingly. The decision to take credit for the successful portions of the initial
ORR should be weighed carefully against time constraints and any changes that have taken
place since the first ORR. In every case, there should be close coordination and agreement
between contractor line management, DOE Field Line Management, and the SAA who
must approve the POA for the second ORR.
8.5 Contractor Operational Readiness Reviews.
Contractor procedures governing the conduct of ORRs should include a provision that,
prior to commencing, line management must certify in writing that all prerequisites
specified in the POA have been met. A manageable list of open items may exist, as
discussed below, at the time the contractor ORR starts.
Section 42
Once contractor line management has determined that readiness has been achieved by
meeting all of the prerequisites specified in the approved contractor ORR POA, the ORR
must be conducted and reported in accordance with the contractor ORR IP. The contractor
must formally declare readiness before the ORR begins. A formal Readiness to Proceed
Memorandum must be prepared by contractor line management only when readiness to
start operations has been achieved and the prerequisites specified in the POA have been
met. The results of the line management MSA or other type of assessment, including
resolution of identified issues, should be included with the declaration of readiness to start
the contractor ORR.
The contractor must commence its ORR only when the approved prerequisites have been
completed. However, there may be events that occur before the ORR begins, such as
periodic emergency preparedness drills or complex system testing, when the ORR team
may monitor the event when it occurs rather than wait until the review begins. This early
review is appropriate. The activity should be documented in the ORR final report. It may
also be appropriate for the ORR team to conduct pre–ORR activities necessary to gain the
familiarization, understanding, and qualification necessary to prepare the ORR IP and
conduct the ORR prior to prerequisites being met.
Qualified personnel in the necessary functional areas conduct ORRs. The number of team
members varies with the scope of the ORR and the size and complexity of the facility. The
Team Leader and Senior Advisor must not be from offices assigned direct line
management responsibility for the work being reviewed by the startup or restart authority.
All ORR team members should have demonstrated assessment expertise in addition to
DOE-STD-3006-2010
49
technical expertise. ORR team members must not review their own work or that for which
they are responsible.
The sequence and methodology for the ORR is described in the IP. Additional guidance
for the preparation and conduct of the ORR is provided in DOE-HDBK-3012, Guide to
Good Practices for Operational Readiness Reviews (ORR), Team Leader's Guide. In
general, ORRs include a pre-visit by the team to become familiar with the site and the
physical scope of the ORR. Administrative requirements such as access and safety training
should be completed. When line management has determined that readiness to start
nuclear operations has been achieved, the ORR Team Leader should be directed by the
SAA to start the actual ORR.
The ORR should take no more than two weeks, with four to six days of actual field work.
The sequence of activities should normally start with record reviews, followed by
operational demonstrations and upset response demonstrations, and concluding with
interviews. The final report should be developed during and following the ORR. Factual
accuracy should be verified as the report is being finalized, with the goal of providing the
final report at the out-briefing at the end of the two-week ORR period. This timeline is
important for several reasons: the need to expeditiously start operations, controlling the
extent of the review, and recognizing that the team members have other work assignments
that are suspended during the period of the ORR. Many years of experience have
demonstrated the effectiveness of this controlled timeline to accomplish a satisfactory ORR
and determine readiness to start nuclear operations.
Section 43
ORR evaluations should place particular emphasis on the SSCs that are important to
nuclear safety (relevant to public and worker safety and health) or of particular importance
to the safety of the planned nuclear operation of the activity. The results of these
evaluations should be included in the final report.
DOE or Field Element personnel should observe and evaluate the contractor ORR process.
It is therefore important that the ORR process be open and well-defined to permit DOE
oversight. Team meetings should be informative for the benefit of the team as well as for
DOE. Interviews and record reviews, as well as evolutions and drills, should be scheduled
in a manner that fosters openness. The ORR Team Leader should coordinate with DOE
oversight personnel to facilitate their observation and evaluation of the contractor ORR.
Documentation of the methodology, criteria, and results of the contractor ORR is important
to the credibility of the review and the foundation for the follow-on DOE ORR. The value
of the review depends in large part on the thoroughness of the ORR and the adequacy of its
scope (breadth and depth). Section 8.4 and Appendix 3 of this Standard provide additional
guidance on recording the results of the ORR.
Once the contractor ORR process has been completed, the contractor must develop a
corrective action plan. The plan should provide the methodology and the schedule for
resolving the findings. Prior to issuing the Readiness to Proceed Memorandum to DOE,
indicating that readiness to start nuclear operations has been achieved, a manageable list of
open prestart issues may exist provided they have a well-defined schedule for closure.
DOE-STD-3006-2010
50
DOE must not begin its ORR until the contractor’s Readiness to Proceed Memorandum has
been received.
8.6 Readiness to Proceed Memorandum.
The Readiness to Proceed Memorandum is the formal communication from the contractor
to DOE stating that the facility has been brought to a state of readiness to start or restart
nuclear operations. The Memorandum is a prerequisite to the DOE ORR. The Field
Element should use the contents of the Readiness to Proceed Memorandum, coupled with
its own routine management understanding of the status of the facility, as a basis for the
recommendation or decision to commence the DOE ORR.
The contractor ORR final report should be an enclosure to the Readiness to Proceed
Memorandum. The Readiness to Proceed Memorandum indicates the status of resolution
of prestart findings and a corrective action plan for post-start findings. The DOE line
management shall forward the Readiness to Proceed Memorandum onto the SAA with
evaluation of the readiness of the contractor to startup or restart of the facility, activity or
operation. In addition, the DOE Line Management must also certify its readiness to
oversee the contractor’s activates related to the startup or restart of the facility, activity or
operation in question.
The Readiness to Proceed Memorandum should not be submitted until all actions required
for startup or restart have been completed, with the exception of a manageable list of open
prestart items that have a well-defined plan and schedule for closure. There should be no
unresolved issues in the path to closure of these prestart items.
If there is an excessive number of open items at the time the Readiness to Proceed
Memorandum is submitted to DOE, the initial conclusion is that contractor management
and ORR processes were not successful. The DOE ORR should not start until the situation
is resolved.
Section 44
The following items provide guidance on the acceptability of the open prestart items at the
time the contractor submits the Readiness to Proceed Memorandum:
• Each open pre-start issue shall be identified in the Readiness to Proceed Memorandum.
• In determining how many open items are acceptable, line management should
understand that every functional area should be sufficiently well developed in its
elements to permit its evaluation in the ORR. For example, one or more open items
indicating that a key program has not yet been developed and implemented should not
be acceptable because the functional area could not be adequately reviewed in the
ORR. Such an open item should be acceptable only if the key program were to be
fully established before the ORR is complete.
• Each open item must be addressed in a corrective action plan. An open item such as
“the required environmental permits have not been requested or approved” would not
be acceptable because many other facility procedures and activities are potentially
impacted by the corrective actions to the identified open item. The schedule for
DOE-STD-3006-2010
51
completion of the corrective action plan should be consistent with the timing for the
completion of the ORR so that the ORR may evaluate the corrective action plan and
the progress in completing the planned activities.
In summary, the open items should be few in number, well-defined with a well defined
corrective action plan, able to be completed on a schedule consistent with the ORR
schedule, and not of such a nature to preclude an adequate review of any specific area by
the ORR.
8.7 DOE Action Following Receipt of the Readiness to Proceed Memorandum.
DOE Operations or Field Element Line Management should review the submitted
Readiness to Proceed Memorandum, which involves verifying the accuracy of the included
information, evaluating the completeness of the open items listing, and determining
whether the corrective actions and time estimates are realistic.
DOE Field Element Line Management responsible for overseeing contractor operations
must prepare an endorsement to the Readiness to Proceed Memorandum before forwarding
it to the SAA. The DOE Line Management endorsement should discuss two important
elements:
• DOE Field Element Line Management’s assessment of the readiness of the contractor
to commence operations. This assessment should be based on the day-to-day
observation of contractor activities and an assessment of the adequacy of the contractor
ORR and the associated corrective actions.
• Readiness of DOE Field Element Line Management to oversee contractor operations
following startup, including meeting prerequisites and CRs in the DOE POA. The
basis for the conclusion, including the results of any DOE Line Management self-
assessments conducted in anticipation of startup, should be included in the
endorsement.
DOE Field Element Line Management must forward the Readiness to Proceed
Memorandum to the SAA with a recommendation as to whether the memorandum should
be accepted and the DOE ORR begun as scheduled, or whether additional information or
action is needed from the contractor or additional actions should be taken by DOE Field
Element Line Management. SAA makes the determination to proceed or not to proceed
with the ORR.
Section 45
Following the DOE Field Element Line Management review, the Readiness to Proceed
Memorandum should be either returned to the contractor with identified comments or
forwarded recommending approval to start the DOE ORR. Each DOE management
endorsement should identify programs and personnel positions that have been verified as
ready to support facility operations, indicate how the evaluation was accomplished, and
specify the actions taken to achieve the state of readiness to oversee operations. The
acceptable Readiness to Proceed Memorandum is forwarded to the SAA for approval.
DOE Field Element or Headquarters implementing procedures may also require the RTP to
be provided to other organizations for information.
DOE-STD-3006-2010
52
The Readiness to Proceed Memorandum with its enclosures and endorsements should be
retained as a part of the facility, activity, or operation startup or restart record, as well as
the ORR final report and associated documentation as specified in local documentation
control procedures. Experiences and lessons learned in managing the Readiness to Proceed
Memorandum and process should be included in the lessons learned section of the ORR
final report.
8.8 DOE Operational Readiness Reviews.
The DOE ORR must not commence until the contractor has reported in writing its
readiness to commence operations Following receipt of the Contractor Readiness to
Proceed Memorandum, the Field Element Manager or designee may concur with the
contractor’s readiness, must verify DOE management readiness, including meeting the
DOE prerequisites in the DOE POA, and may recommend to the SAA that the DOE ORR
commence.
The prerequisites for starting a DOE ORR must be specified in the DOE POA, as required
by DOE O 425.1D. The specifics vary with each ORR, but the basic principle is that the
DOE ORR should not commence until management has determined the facility is ready to
operate, including readiness of the DOE Field Office to oversee contractor operations.
When directed by the SAA, the DOE ORR must be conducted in accordance with the IP
prepared by the team and approved by the Team Leader. The DOE ORR team conducts
and prepares the final report in accordance with the IP. The DOE ORR should include a
detailed review of the contractor ORR and other performance assessments in accordance
with the approved scope. Following completion of the DOE ORR and resolution of
prestart findings, DOE management may recommend to the SAA that startup approval be
granted.
The DOE ORR team should assess the technical and managerial qualifications of those in
the DOE Field Element responsible for providing direction and guidance to the contractor,
including Facility Representatives. A similar review should be made of the qualifications
of contractor personnel responsible for facility operations.
In most cases, a key element of the DOE ORR is a detailed review of the methods and
results of the contractor ORR. The results, including corrective actions, should be assessed
for adequacy and effectiveness. The DOE ORR team should conduct additional detailed
assessments to verify the findings of the contractor ORR and review areas that may not
have received an adequate review in the contractor ORR. The DOE ORR should not
duplicate the contractor ORR; it is intended that the DOE ORR validate the accuracy and
completeness of the contractor ORR and verify the readiness of the DOE line organization
to oversee the contractor nuclear operations within the scope of the ORR.
Section 46
8.9 Documentation of Operational Readiness Review Results.
The final product of the ORR process is the ORR final report, which documents not only
findings and conclusions, but the process by which they were developed. The ORR final
DOE-STD-3006-2010
53
report should form the basis for senior management decisions, including startup or restart
approval, and should therefore accurately reflect the conditions found during the ORR.
The ORR final report is intended to document the logic of the review and convey the
results of the review. It should provide a summary of review activities and confirmation
that the criteria and review approaches detailed in the IP were followed, with explanations
for any deviations. It should also contain enough detail that the reader can follow the
review logic of the ORRs, traceable from the POA to the IP to the ORR findings.
The ORR final report should document the effectiveness of the facility’s operational
readiness preparation, the contractor ORR, and the readiness of the facility to proceed with
startup or restart. The final report should also provide information concerning the
readiness of the management system (both the contractor and DOE) to oversee and manage
the facility, activity, or operation. If deficiencies exist, the ORR final report should clearly
define those, as well as the inadequacies that should be addressed before and after startup.
The final report should also address deficiencies identified and corrected during the course
of the review.
The validity and defensibility of ORR results should depend largely on the thoroughness
with which the process and the observations are documented. The final report should be
clear as to what was evaluated and the methodology used during the evaluation.
Final Report Format.
DOE O 425.1D provides some minimum content requirements of the ORR report. It does
not, however, provide the format. The following is a suggested format derived from a
composite of past DOE ORR final reports. A synopsis of each section is contained below.
• Title Page: The cover and title page should state the subject and the date of the
ORR. The report cover should not contain any extraneous information, data,
graphics, or pictures.
• Signature Page: This page should contain the signatures of all team members,
signifying their agreement as to the report content and conclusion in the areas to
which they were assigned. In the event all team member signatures cannot be
obtained due to logistical considerations, the Team Leader should gain their
concurrence via fax or telephone and sign for them.
• Executive Summary: The Executive Summary should be a one- to three-page
synopsis of the review, findings, and the conclusion as to whether the team believes
readiness has been achieved. The Executive Summary should introduce information
and direct the reader to those portions of the report that provide more detail on the
information. Some suggested points for the Executive Summary include:
o a brief synopsis of the review activity, which provides information
concerning the team’s evaluation of readiness;
o the management system’s adequacy to oversee the operation;
DOE-STD-3006-2010
54
o a summary evaluation of the adequacy of the ORR preparation (and possibly
the ORR program); and,
o a synopsis of the significant problems and strengths.
• Table of Contents: A Table of Contents should be provided to facilitate a review of
the report. The Table of Contents should identify, with page numbers, all sections
and subsections of the report, illustrations, charts, and appendices.
Section 47
• Introduction: The Introduction should provide information and background
regarding the facility being reviewed, the reasons for shutdown (if a restart), the
purpose of the ORR, and the scope of the evaluation. Other information that should
be provided includes a brief discussion of:
o the overall objectives of the evaluation;
o the review process and methodologies used in the review;
o the team composition; and,
o definitions applicable to the review.
• ORR Evaluation: This section should provide an overall evaluation of readiness,
followed by individual functional area summaries. For each functional area, the
summary should, in one page or less, discuss the CRs and provide conclusions as to
the readiness of the functional area to safely support proposed operations.
Conclusions as to the readiness of hardware, personnel, procedures, and the
management system that controls each functional area should be addressed,
including key issues. Findings identified at any point in the ORR are to be included
in the ORR Final Report and formally addressed for resolution and closure
regardless of any interim actions which may be taken by line management to address
such deficiencies. The evaluation should discuss the prestart and post-start findings
associated with the review and provide a conclusion as to the readiness of the
facility to begin operation within the scope of that specific functional area.
The detailed results of each CRAD should be included in a comprehensive write-up
in the evaluation form (Form 1). The form should describe how the CRAD
evaluation should be accomplished and the results of the evaluation. An evaluation
should be made of each criterion in the CRAD to discuss whether it was met or not
met. The level of detail in the Form 1 should be such that a knowledgeable
individual who did not observe the ORR can understand the methodology of the
review and the basis for the results. Any deficiencies identified during the course of
the evaluation of the CRAD should be discussed in the Form 1 write-up. When
deficiencies rise to the level of Findings, they should be indicated on the Form 1 and
should be the basis for a Finding form (Form 2).
The Appendix 3 writing guide provides examples of Forms 1 and 2. Also the DOE
Readiness Review website contains recent examples of final reports. The Functional
Area summary should roll up the results of the review as discussed in the Forms 1
and 2 applicable to the functional area. A critical success factor for ORRs should be
the Team Leader’s providing examples to the team of acceptable formats for the
DOE-STD-3006-2010
55
forms and the prepared forms containing the information from the CRADs.
Appendix 3 and the Team Leaders’ Handbook contain additional information on
accomplishing and managing the process of reporting the results of the ORR.
Any deviations from the IP should be discussed, along with the reasons for the
deviations, and the alternative actions that were taken to compensate, if necessary.
Because the ORR Evaluation section provides the basis for the determination of
readiness for each CR, it should discuss not only the deficiencies found during the
review, but should also discuss those positive aspects that affected the
determination. In addition, the ORR final report should also identify as
Opportunities for Improvement those items that are not findings; but that, if
addressed, would lead to excellence in operations. The detailed documentation to
support the conclusions may be included in an appendix consisting of the individual
CRAD or Lines of enquiry with the accompanying Assessment Forms. See
Appendix 3 for additional details.
Section 48
• Status of Requirements: The ORR final report must state whether the facility has
established the following:
o an agreed-upon set of requirements for governing safe operations of the
facility, activity or operation;
o that this set of requirements has been formalized with DOE through the
contract or other enforceable mechanism;
o that these requirements have been appropriately implemented in the facility,
activity or operation, or appropriate compensatory measures, formally
approved by DOE, are in place during the period prior to full implementation;
and that,
o in the opinion of the DOE ORR team, adequate protection of the public health
and safety, worker safety, and the environment will be maintained.
• Implementation of ISMS: The core requirements, in aggregate, should address
many of the core functions and guiding principles of Integrated Safety Management
(ISM). The final report should include a statement regarding the Team Leader’s
assessment of the adequacy of the implementation of those functions and principles
which were addressed by the ORR at the facility undergoing the review. This
should not be direction or inference that any additional review be added to the ORR
process to address ISM. Only to the extent that the ISM processes are visible in the
established review should they be evaluated and commented on.
• Lessons Learned: Each ORR final report must contain a section on lessons learned
to be used by both contractor and DOE to improve the ORR process. These lessons
should provide information on problems encountered by the review team,
adequacies or inadequacies concerning the review, design, and implementation,
expertise, or any other relevant factors or information that may be used by future
review teams.
DOE-STD-3006-2010
56
The ORR must also identify lessons learned applicable to similar facilities. Lessons
learned in areas such as operations, procedures, design, or documentation may also
be identified. The ORR team must include these lessons learned in the report as
well. Facility management or DOE management is then responsible for
promulgating these lessons in accordance with established procedures. The ORR
final report may be issued before the lessons learned section is written to avoid
delays in issuing the report. However, each ORR report must contain a lessons-
learned section, as required by DOE O 425.1D.
• Dissenting Professional Opinions: The ORR process provides an opportunity for
team members to submit dissenting professional opinions which should be
documented and appended to the final report. There must be a provision for
differing professional opinions if agreement cannot be achieved.
While the team should strive to reach a consensus concerning all aspects of the
review, DOE recognizes that professional judgment does not always allow for
complete agreement. In cases of disagreement, the Team Leader makes the final
recommendation concerning the disposition of the finding or concern. However,
discussion of all aspects of the finding should be provided in the final report to
provide the SAA with all relevant information on which to base his or her decision.
If a team member feels that aspects of his or her opinions have not been adequately
represented, that member should file a dissenting professional opinion. The written
report of the dissenting professional opinion is appended to the ORR final report for
review by the SAA.
Section 49
• Appendices: Appendices are intended to provide data that support the final report.
Data that should be considered for appendices include:
o the IP*;
o the CRADs*;
o a listing of the team members and their resumes*;
o the POA*
o Evaluation of criteria (Forms 1);
o the Prestart Findings summary (Forms 2); and,
o the Post-start Findings summary (Forms 2).
The asterisked items may be referenced but not included in the final report
and maintained with the readiness records.
• Distribution: A SSA provides a copy of the final report to the cognizant DOE Line
Management. DOE Line Management provides the report to cognizant contractor
line management for action.
DOE-STD-3006-2010
57
8.10 Prestart and Post-Start Findings.
Findings should be defined as follows:
• Nonconformance with a stated requirement that represents either:
o a systematic failure to establish or implement an adequate program or
control; or
o a significant failure that could result in unacceptable impact on the safety of
personnel, the facility, the general public, or the environment during nuclear
operations.
During the ORR the team may identify individual deficient conditions. Frequently, the
deficient conditions, when evaluated together, may reflect a programmatic or
implementation weakness that is of concern and require corrective action to ensure that
operations are conducted safely when started (prestart finding), or requires corrective
action to mitigate longer-term concerns or programmatic deterioration (post-start finding).
As discussed above, findings should be discussed on Form 1 and documented on Form 2.
The rollup or individual deficient conditions should be identified as findings. One of the
important tasks of the team should be to identify the significant findings that impact the
adequacy of programmatic support or indicate inadequate implementation of important
operational conditions. It is always possible to identify individual deficiencies. The
challenge may be to determine when a group of seemingly minor individual issues is
indicative of a more systemic issue that should be identified as a finding.
The IP should provide a standardized method for identifying findings using the
requirements identified within the criteria. Each finding should be clearly described,
providing examples of the individual issues that comprise the finding. The finding should
describe what is deficient, provide the reference to the requirement with which it is
deficient, and be written in a manner permitting corrective action to resolve it.
Each finding should be identified as to whether or not, it must be resolved prior to startup
of operations. Criteria for arriving at this opinion should be published or referenced in the
IP. It may also be appropriate to identify the level of management (i.e., contractor, DOE
Field, or DOE Headquarters) at which the finding should be closed. While the ORR team
may assist management in reviewing the action taken on a finding, responsibility for its
resolution should reside with line management. Form 2s should further discuss identified
findings.
8.11 Corrective Action Plans.
The contractor and DOE must prepare corrective action plans for all findings identified as
applicable. The DOE and contractor implementing procedures should specify the process
and format for evaluating and documenting findings. Form 3, described in Appendix 3
writing guide, may provide the required documentation to describe corrective actions and
close the finding. The action plan should contain the following elements:
Section 50
DOE-STD-3006-2010
58
• The finding, as written in the report submitted by the ORR team, and whether the
finding is a prestart or post-start finding.
• A detailed proposed action plan for addressing the deficiencies identified in that
finding. The proposed action plan should evaluate any overall programmatic
deficiencies related to a specific finding that could lead to similar occurrences and
include actions to address these deficiencies. For findings identified during the
DOE ORR, DOE must approve the contractor’s proposed corrective action plan.
• The proposed dates when the actions are intended to be completed. If the corrective
actions for a finding are phased, the dates for each phase should be detailed.
• If it is a post-start finding, a description of the risks and mitigating actions or
compensatory measures, if any, to be taken during the interim that are intended to
reduce the risks to an acceptable level before final corrective action. DOE Line
Management should verify that the corrective action plan has been entered into the
appropriate assurance program issues management system.
• If some corrective actions for prestart findings would occur after the startup of
operations, the risks and mitigating factors or compensatory measures should be
clearly identified. The actions that are required prior to the startup of operations
must be completed and closed with a final closure package, as discussed below,
before operations can be started.
Findings and associated corrective actions for the contractor and DOE ORRs should be
entered and managed via the site corrective action or action tracking processes.
8.12 Operational Readiness Review Follow-up Activities.
The ORR process continues beyond the completion of the ORR and the finalizing of the
report. Several actions may require the participation of the Team Leader and team
members. The Team Leader should notify all team members of future involvement
concerning closeout briefings, interpretation (and possible justification) of findings, review
of corrective action plans for adequacy, and review of final closure actions. It should be
clearly understood that line management is solely responsible for resolving findings and
accepting the corrective action plan and the adequacy of the corrective actions. However,
since the team members are most familiar with the details of the findings, line management
may request members of the team to assist during the process for closing findings. It
should be clear that line management should not defer to the team on deciding on the
adequacy of the corrective action plans or the corrective actions actually taken.
The Team Leader should coordinate any follow-up meetings, which include closeout
meetings with the affected facility and line management, team debriefings, and
presentation of the report to DOE and contractor upper management. The Team Leader
may be required by the Secretarial Officer or other appointing authority to present the team
report to upper DOE management. Presentations may be required to internal or external
DOE-STD-3006-2010
59
interested groups as well. In addition, it may be appropriate for the Team Leader to
recommend an organization to verify proper closure of individual prestart findings.
8.13 Action Tracking and Closure Methodology.
Section 51
Monitoring and verifying the satisfactory closure of prestart findings from both the
contractor and DOE ORRs is a line management responsibility. The ORR Team Leader
and team members may be requested to assist in verifying or resolving prestart findings.
DOE O 425.1D defines elements of the required process to close ORR prestart findings.
This is accomplished by developing a closure package that is reviewed and verified by
DOE Line Management for findings from the DOE ORR. These procedures should be
documented either in a facility-wide process for issues management tracking or the specific
implementation of the requirements of DOE O 425.1D. Closure packages should contain
the following information:
• The finding, taken verbatim from the original report, identified as a prestart or post-
start finding.
• The actions proposed in the action plan developed, submitted, and approved with
the original completion schedule.
• A brief description of the corrective actions taken, reasons for concluding that
closure has been achieved, and objective evidence supporting closure. The
referenced documents or objective evidence illustrating the corrective actions and
the dates of the actions should also be included.
• Signatures of the appropriate line management, as defined by the site procedures or
within the ORR IP. A draft closure form is provided as Form 3, ORR Finding
Resolution Form, in Appendix 3.
• DOE verification (DOE ORR findings, at a minimum) of the adequacy and
completion of the corrective actions.
8.14 DOE Line Management Oversight of the Operational Readiness Review Process.
Throughout the ORR process, various Headquarters, Field Element, and external oversight
organizations may become involved in the process. To ensure that proper liaison occurs,
documentation from each step in the process should be provided to the appropriate internal
and external oversight groups for information and comment. In most cases, the
documentation is provided after approval by the appropriate management official. It
should be stressed, however, that all information should be provided in a timely manner if
all organizations are to execute their responsibilities without delaying critical steps in the
process. Frequent liaison should occur between management and oversight organizations
at each level, both internal and external, to ensure that all responsibilities and commitments
are fulfilled. Transmittal of DOE documents to agencies outside of DOE should follow
established procedures.
DOE-STD-3006-2010
60
DOE Field Element personnel should observe and evaluate the contractor ORR process.
The ORR process should be open and defined to permit DOE oversight. Team meetings
should be informative for the benefit of the team as well as DOE oversight. Interviews,
record reviews, evolutions, and drills should be scheduled in a manner to support openness.
The ORR Team Leader should coordinate with DOE oversight personnel to facilitate their
responsibility for observing and evaluating the contractor ORR.
The following items are a compilation of the required and recommended responsibilities of
the DOE Field Offices in executing the new start and the restart ORR processes.
• Review and approve, or review and forward for approval, the contractor ORR POA.
• Provide day-to-day oversight of the contractor’s activities to achieve and verify
readiness to conduct operations, including a review of the contractor ORR report
and prestart finding closure plans and closure documentation. Through this day-to-
day oversight, DOE Field Element Line Management provide knowledgeable
recommendations concerning the contractor’s actions and proposals.
Section 52
• Review, and take appropriate action on, the contractor Readiness to Proceed
Memorandum. If the Operations or Field Element Manager is the SAA, he or she
grants authority to conduct the DOE ORR. For other new starts and restarts, the
DOE Field Element Manager forwards the Readiness to Proceed Memorandum to
Headquarters recommending that the DOE ORR be started when it is satisfied that
the facility is ready to be operated safely, Field Element Line Management
personnel are ready to oversee contractor activity, and DOE oversight processes and
procedures are in place.
• DOE Field Element Line Management responsible for oversight of contractor
operations shall prepare an endorsement to the Readiness to Proceed Memorandum
when forwarding it to the SAA, even when the SAA is the DOE Field Element
Manager. The DOE Line Management endorsement should contain two important
elements:
o a discussion of DOE Line Management’s assessment of the contractor’s
readiness to commence operations. This assessment should be based on the
day-to-day observation of contractor activities and an evaluation of the
adequacy of the contractor ORR and associated corrective actions; and
o concurrence with the status of prestart findings and a recommendation to the
appropriate decision official to authorize startup or restart after the DOE
ORR is complete and all prestart findings are closed. In cases when the
Element Manager is the designated SAA, he or she must authorize the
startup or restart.
DOE Prestart Findings Closure Process. Evaluate the contractor’s prestart
finding closure process and verify closure of DOE ORR prestart findings as
designated by the SAA. To verify closure, support may be requested from
DOE-STD-3006-2010
61
the DOE ORR Team Leader or team members; however, closure verification
remains a line management responsibility. DOE Line Management verifies
the adequacy of corrective action plans for all findings from the DOE ORR.
See Section 7 above for additional discussion on the roles and responsibilities of DOE Line
Management and oversight organizations.
8.15 Independent Oversight Organizations.
DOE O 425.1D, Section 5.b specifically indicates that DOE independent oversight of the
ORR and ORR process is the responsibility of HSS. To ensure that the startups and restarts
of DOE nuclear facilities proceed in a timely fashion, it is incumbent upon the contractors,
Field Element Managers, and Secretarial Officers to provide the appropriate review
documentation to the PSO, Site Lead PSO or CSO, the appropriate CTA, and HSS
throughout the process. It is also incumbent upon HSS to provide comments to these
organizations in a timely fashion to ensure that their concerns are addressed with minimal
impact on the startup or restart schedule.
HSS. In addition to the general Departmental responsibilities specified in DOE M 411.1-
1C and the DOE FRAM, HSS exercises independent oversight of the startup and restart
process for nuclear facilities. This responsibility entails the following:
• In coordination with the PSO, performing independent reviews of startup and restart
activities as appropriate and providing the results of these reviews to the CSOs for
resolution.
• Reviewing and commenting as appropriate on the PSO, Field Element, and
contractor procedures for startup or restart of nuclear facilities and providing the
results of these reviews to CSOs for resolution. Reviewing and commenting on
SNRs, contractor and DOE POAs, IPs, and ORR final reports.
Section 53
8.16 Authorization to Start Operations.
When the DOE ORR is complete, all prestart findings are resolved, and satisfactory
corrective action plans are prepared for post-start findings, DOE Line Management concurs
on the satisfactory status of prestart and post-start findings and should recommend that the
SAA authorize the start of operations. The designated SAA reviews the results of the
contractor and DOE ORRs and, when satisfied with the status of all prestart and post-start
findings, approves startup of nuclear operations. In cases when the Field Element Manager
is the designated SAA, he or she authorizes the Startup of nuclear facility, activity, or
operations and may inform the designated secretarial officer as required by local and
Headquarters implementing procedures.
9 READINESS ASSESSMENTS
The majority of RRs that are planned and accomplished to meet the requirements of DOE
O 425.1D are RAs. The scope and complexity of RAs may range from a simple checklist,
if local procedures permit, to a scope that approximates that of an ORR. This section of the
DOE-STD-3006-2010
62
Standard discusses the processes for planning and conducting an RA. The discussion refers
to or defers to the tailored processes in the local procedures for the planning and conduct of
RAs. Local implementing procedures for RAs should provide detailed processes and
expectations for the unique aspects of RAs permitted in the order such as use of checklists
and parallel accomplishment of contractor and DOE RAs. Both of these situations are
identified in the following sections but detailed processes are not defined. The detailed
processes should be developed in local procedures prior to using a POA/IP checklist to
conduct an RA.
Section 4 of this standard discusses the recommended process to be followed by the
contractor and DOE to determine the level and scope of the RR. A critical aspect of the
process is the expectation that the contractor and DOE develop implementing procedures to
formalize and guide these processes. The implementing procedures must describe the
process for evaluating the startup to decide on the type of RR required. The process should
address a number of elements that form the basis for determining the level of the required
RR. In addition, when the process leads to a determination that an RA is the appropriate
level of RR, there should also be a determination as to whether DOE needs to conduct an
RA in addition to the contractor. A properly documented determination provides
information that should be considered when developing the scope of the RA. That scope is
documented in the RA POA. When a DOE RA is required, the DOE and contractor
processes for determining the level of an RR should provide the information necessary to
define the scope of the DOE RA as well.
9.1 Plan of Action.
The POA provides the proposed RA scope, the prerequisites for starting the RA and the
proposed RA Team Leader. The POA should include, the RA schedule, including the
estimated start date and duration and other information unique to the proposed RA. The
contractor’s POA is reviewed by the Field Element Manager or designee and approved or
forwarded to the designated SAA with a recommendation for approval. When the
contractor is the SAA, the approved POA must be provided to the DOE Field Element for
information. DOE O 425.1D specifies that the POA may be as simple as a checklist or as
comprehensive as that for an ORR. If the approved format for the RA POA differs from
that for an ORR, the format, minimum contents, and manner of usage should be
specifically discussed in the approved contractor and DOE implementing procedures. DOE
O 425.1D specifies that the POA must define the scope and prerequisites and identify the
Team Leader for the RA. Local procedures should also reflect these requirements.
Section 54
Standing RA checklists may be used to provide the framework and guide for scoping and
tailoring the RA for the specific startup or restart. Every RA POA should be prepared that
accurately specifies the required RA scope and tailoring consistent with the unique
conditions and situations associated with the specific startup or restart. Contractor
procedures should establish a goal that the POA should be prepared approximately six
months prior to the projected start date for the RA. When the need for an RA is identified
less than six months prior to the projected start date, the POA should be prepared as soon
as possible so as to avoid the RA process from impacting the schedule for determination of
readiness.
DOE-STD-3006-2010
63
As specified in DOE O 425.1D, the RA POA must define an adequate scope to fully
describe the intent of the RA. The evaluation that was used to determine that an RA was
the appropriate level of RR should be used in defining the RA scope. The scope should
provide a detailed description of the activities, operations, structures, and process systems
and equipment being started or restarted. Each CR listed in DOE O 425.1D must be
evaluated for inclusion in the scope of the RA. The POA must justify the exclusion of any
CR that may not be assessed during the RA. The level of detail provided in the
justification should be commensurate with the complexity of the review and of the
operation such that an independent reader would reasonably be expected to draw the same
conclusion. The basis for not including a CR may be that no changes have occurred during
the shutdown and that confidence has been maintained in the adequacy of the program or
function within the scope of the startup or restart.
Another example that supports excluding a CR is when the SMP was previously
determined to be satisfactory and implementation within the facility being restarted did not
change (e.g., the change in the activity would not require a review of the CR, as the SMP
functions are adequate for the new activity and did not change). The explanation needs to
be brief but meaningful, and acceptable to the SAA. Some CRs may be included, but
tailored to more fully describe the total scope of the RA.
The development of the scope must be based, in part, on the status of, and changes to, the
facility, operating procedures, safety basis documents, hazards, operational conditions, and
personnel. For example, many SMPs may be included only to the degree necessary to
determine that the site SMP processes were adequately implemented within the scope of
the RA. The POA must include a prerequisite section that defines the prerequisites for
declaring readiness to start nuclear operations. The prerequisites must, at a minimum,
address each CR that is within the scope of the RA. Clarity in the discussion of the manner
in which the CR should be tailored is important to ensure that the RA IP accurately reflects
the intended scope of the RA.
The POA is submitted to the designated SAA for review and approval. If the SAA resides
with DOE, the contractor’s POA should be submitted to the cognizant DOE Line
Management. DOE Line Management shall forward the contractors POA to the SAA with
its recommendation for disposition. A copy of the proposed POA is provided to the PSO,
the site Lead Program Secretarial Officer or CSO, as appropriate, the appropriate CTA, and
HSS for information and action in accordance with the individual office’s implementing
procedures for DOE O 425.1D.
Section 55
The level of detail in each POA varies with the complexity of the facility and the situation
under which the activity is being started or restarted. As a rule of thumb, the level of detail
should be adequate to justify to a skeptical reviewer the overall scope being proposed,
including the tailoring of each CR. The detail should be adequate to defend the decisions
being made to preparers, reviewers, and the SAA.
In cases where a DOE RA is to be conducted. Following receipt of the contractor POA, the
DOE Line Management organization prepares a DOE RA POA for each nuclear facility
new start and restart for which a DOE RA is required. The contractor POA should provide
DOE-STD-3006-2010
64
the starting point for the DOE POA. The DOE POA must include prerequisites that ensure
readiness of DOE programs and personnel to oversee contractor operations. Prerequisites
in the DOE POA should also ensure that the contractor RA process has been completed in
accordance with the approved site processes and procedures. When a DOE RA would be
conducted in parallel with the contractor RA, the DOE POA must specify the prerequisites
for starting the DOE RA. The DOE POA should also discuss the purpose of conducting
the RAs in parallel and the expectations for DOE RA Team’s performance in the conduct
of the parallel DOE RA.
The DOE RA POA should include in its breath all areas appropriate to the responsible
contractor POA and a thorough review of the DOE management organization to determine
its capability to oversee the facility, activity, or operation to be started or restarted. The
DOE RA POA should include prerequisites, Team Leader designation, breadth of the DOE
RAs, estimated schedule and duration, and additional information required by DOE O
425.1D. The DOE POA is formally transmitted via management to the appropriate SAA.
Once approved, the DOE POA is provided to the PSO, the site Lead PSO or CSO, as
appropriate, the appropriate CTA, and HSS for information.
Each POA should contain the following elements.
• Name of the Facility, Activity, or Operation Being Started: The name should be
specific to what is to be evaluated and started. For example, if a single process within a
building is being started or restarted, the facility name is the process name. On the
other hand, if the process encompasses several buildings and an area, the name would
be the encompassing process name.
• Description of Facility, Activity or Operation: This should include buildings, systems,
and processes included in the startup or restart. The description may be instrumental in
defining the scope of the review. For example, if most support functions and
procedures are outside the boundary of the facility being started up, the RA scope
focuses on interfaces with existing programs. This section of the POA should define
the physical scope of the RA. The physical scope may include systems, structures, or
processes.
• Identification of the Responsible Contractor: This should be the contractor who
certifies readiness of the facility, activity, or operation to operate. It is normally the
contractor who submits the contractor POA.
• Designation of Action as a New Start or Restart: This should be the identification as to
whether the facility, activity, or operation is being started for the first time or being
restarted. It is reasonable that a new process within an existing building would
constitute a new startup. Resumption of a process after an extended period of no
operation would most reasonably be a restart.
Section 56
• New Start Discussion: The following elements or details of the facility, activity, or
operation should be included to support or create the basis for the recommended
decisions:
o Hazard categorization of the new facility and the basis for its designation; and
DOE-STD-3006-2010
65
• Restart Discussion. If the action is a restart of an existing facility, activity, or
operation, the following information should be provided to support the follow-on
decisions. This information should be available from the determination that an RA was
the appropriate level of RR:
o hazard categorization of the facility, activity, or operation when restarted and
the basis for determination. In the event that no formal hazard categorization
has been made, a discussion of the relative hazard may be appropriate;
o the cause of the shutdown;
o the duration of the shutdown;
o repairs accomplished during the shutdown period;
o modifications accomplished during the shutdown period and their effect on the
approved safety basis;
o any anticipated process changes following restart; and,.
o status of the DSA & TSR, including a history of IVRS or other reviews as
applicable
9.1.1 Proposed Scope of the Readiness Assessment.
This should be a key section of the POA. The scope should be developed starting with
the CRs listed in DOE O 425.1D and the physical scope in the facility, activity, or
operation description. The discussion should support the decision to eliminate or tailor
any CRs, as discussed above. The DOE POA scope should include the scope of the
contractor RA and address DOE management and oversight programs.
The discussion of the scope of the RA in the POA supports the development of the IP for
each functional area. Attention to detail should be particularly important in developing
the scope to ensure that the all involved individuals and organizations have a complete
understanding of the areas to be reviewed.
The scope should start with a clear discussion of the physical or geographic scope of the
RA. A clear definition of the SSCs, as well as the individual processes or activities
within the scope of the RA, should be provided to ensure the proper focus of the RA.
Experience indicates that clarity can be best achieved when each CR is discussed
individually.
The discussion should include justification for any CRs that are excluded in the RA. For
the remaining CRs, the discussion should clearly describe the detail or depth to which
each is to be reviewed. In some cases, only the interface with site infrastructure
programs may need to be included. In other cases, the entire site-wide program may need
to be evaluated.
The discussions should refer to site-wide and facility-specific reviews that provide a basis
for the RA. Evaluations such as previous RAs, ISMS verifications, independent DOE or
contractor reviews, IVRs, or similar reviews may reduce the necessary depth of review
DOE-STD-3006-2010
66
for individual CRs. Similarly, the recent history of the facility, site, or activity may be
important in defining the level of detail or depth of individual portions of the review.
Conditions such as recent occurrences, investigations, or systemic issues identified within
the site may form the basis for an increase in the breadth or depth of the review of
individual CRs. The final scope should be consistent with the evaluation that was
documented when the level of RR was determined.
Section 57
When a parallel Contractor and DOE RA has been approved in the SNR, the discussion
of the scope of the DOE RA should include the expectations of performance of the DOE
RA team to ensure independent evaluation of readiness.
9.1.2 Readiness Assessment Prerequisites.
Prerequisites provide line management, the contractor, and DOE with criteria as to when
the activity is ready for startup or restart. The contractor POA prerequisites must address
each CR contained in DOE O 425.1D within the scope of the RA. The DOE POA
prerequisites should address the readiness of DOE management and Field Element
programs and assigned personnel who monitor facility operations. The DOE POA
prerequisites should also address the completeness and adequacy of the contractor RA
process.
Adequate detail should be included to permit an understanding of the programs and
personnel considered essential to adequately oversee the facility or process for startup or
restart. The prerequisites section of both the contractor and DOE RA POAs may refer to
specific items such as a project management plan, a readiness self-assessment plan, a
compliance assessment program, safety documentation such as DSAs and TSRs,
including recently completed IVRs, if possible, or environmental assessments or impact
studies, if they were required to achieve readiness to commence nuclear operations. The
prerequisites must be described in terms of specific measurable activities that must be
accomplished before the RA begins in order to ensure that readiness has been achieved to
start nuclear operations.
The prerequisites for starting an RA vary with each RA, but the basic principle is that the
contractor RA must not commence until management has determined that the facility is
ready to operate. The DOE RA must not commence until the contractor submitted the
Readiness to Proceed Memorandum certifying its readiness to commence operations and
until DOE management is ready to oversee operations. The prerequisites specified in the
POAs may refer to, for example, phases of the startup process, conditions of the project
management plan, specific consent or compliance agreements, or IP status to quantify the
method for achieving readiness. Prerequisites should be specific and verifiable. The
DOE POA should contain specific prerequisites that, when completed, provide
confidence that DOE is ready to oversee contractor operations that are about to be started.
As noted above, when the SNR approves a parallel contractor and DOE RA, the
prerequisites in the DOE POA should be clear and specific as to what conditions must be
met to start the DOE RA. The prerequisites should consider both the status of the facility
readiness and the readiness of the DOE Field Element to oversee contractor operations.
DOE-STD-3006-2010
67
In the situation of a parallel RA, it may be appropriate for DOE Field Element to consider
the status of the contractor MSA or similar verification processes when determining
readiness to start the DOE RA.
9.1.3 Estimated Readiness Assessment Start Date and Duration.
The estimated start date is for planning purposes only. Identifying a date should not infer
that the RA start is schedule-driven rather than readiness-driven. The DOE RA estimated
start dates, as well as the contractor RA schedule, should be provided for information in
the contractor POA to assist DOE Line Management in planning for the DOE RA.
9.1.4 Proposed Readiness Assessment Team Leader.
Section 58
The POA must identify a qualified Team Leader who should be a senior employee with
adequate experience and knowledge to effectively lead the evaluation of the facility. The
basis for the qualifications should be summarized in the POA and include:
• technical familiarity with the activities and functional areas being reviewed;
• previous performance-based review experience or training;
• demonstrated leadership and managerial skills, including seniority in relation to the
members of the RR team, to permit smooth management of the RR team;
• RR experience or formal training; and,
• knowledge of facility, activity or operation.
The Team Leader and Senior Advisor must be independent; neither must be from offices
assigned direct line management responsibility for the work being reviewed: any
exceptions require approval of the startup authorization authority. The appointment of the
Team Leader is approved by the SAA when the overall POA is approved. The
appointment of the Team Leader is approved by the SAA upon approval of the RA POA.
9.1.5 Senior Advisors.
Senior Advisors are recommended for contractor and DOE RAs with a complex scope or
within a complex facility. In many instances, Senior Advisors may not be needed,
particularly if the Team Leader has significant RA experience. On other occasions, a
single Senior Advisor may be appropriate to assist the Team Leader; or, for particularly
complex or controversial RAs of high-hazard facilities, as many as three Senior Advisors
may be advisable. The qualifications for the Senior Advisor may be included in the
POA. However, it is also within the prerogative of the Team Leader to select Senior
Advisors if he or she deems it appropriate.
9.1.6 Official to Approve the Start of the Readiness Assessment and Approve Startup or
Restart of the Facility.
The start of the DOE RA is directed by the SAA, who is identified in the approved SNR
in accordance with the requirements of DOE O 425.1D. For the contractor RA, the
DOE-STD-3006-2010
68
official designated to direct the start of the RA should be a line manager senior to the
manager responsible for achieving overall readiness to start operations.
9.1.7 Reviewers’ Approval.
The individuals who prepared and reviewed this document should be listed by name and
title. Their signature certifies that they should have reviewed the document and
recommend approval by the SAA.
9.1.8 Distribution.
This is a listing of the individuals and organizations that should receive copies of the
POA following its approval. These entities have either responsibilities or interests in the
new start or restart process. The approved POAs form the basis for RA activity in the
restart or startup process. They should therefore be distributed to all interested
individuals and organizations. When the SAA is a contractor official, the approved POA
must be forwarded to the local DOE Line Management. DOE Line Management must
distribute the POA to the PSO, the site Lead PSO or CSO, as appropriate, the appropriate
CTA and HSS for information.
9.1.9 Approve the Plan of Action
Line management submits the POA to the SAA for approval. The POA must be
approved by the SAA.
9.2 Readiness Assessment Implementation Plan.
The approved POA should be provided to the designated RA Team Leader. The Team
Leader identifies the team members who must conduct the RA. The Team Leader, with the
assistance of the team, develops the IP consistent with the breadth defined in the RA POA
and the facility involved. The IP must identify all of the necessary criteria and review
approaches so that the team can determine whether readiness to safely start up and operate
the specified facility has been achieved.
Section 59
DOE O 425.1D specifies that the IP may be as simple as a checklist or as comprehensive as
that for an ORR. If the approved format for the RA IP differs from that for an ORR, the
format, minimum contents, and manner of usage should be specifically discussed in the
approved contractor and DOE implementing procedures. DOE O 425.1D specifies that the
IP must be developed by the RA team and that it must reflect the scope of the RA defined
in the approved POA. Local procedures should also reflect this requirement. Every RA IP
should be a document that accurately incorporates the RA scope and tailoring reflected in
the approved POA.
The IP defines the RA depth in a manner consistent with the scope and conditions for
startup or restart, as reflected in the approved POA. If a previous timely RA was
completed for the facility being reviewed, the RA POA should so indicate, and the IP and
subsequent RA should stress the operations that have changed since the last review as well
as the effectiveness of corrective actions for any findings.
DOE-STD-3006-2010
69
The RA is conducted by a team of experts chosen by the Team Leader to ensure that,
collectively, they can address all of the facets of operations to be reviewed. Management
should also be supportive of team members’ release from their current duties to support the
RA. The number of members may be determined by the scope of the RA and the size and
complexity of the facility.
A key responsibility of the Team Leader is selecting the team members based on their
qualifications. Each team member should have the qualifications discussed in section 7.6.
The Team Leader must determine and document the team members’ qualifications. This
information should normally be provided through individual resumes, required reading, and
training records. Appendix 3 includes an example form for consolidating the required
information.
The roles and responsibilities of the Team Leader and the team members are more
completely discussed in section 7.5 and 7.6 above.
The IP should not only document the process the team uses to conduct the review, but
should also define the rationale for that process. The documentation should include the
selection of criteria and review approaches and the criteria for categorizing findings as
prestart or post-start. The IP must reflect the breadth of the RA as described in the POA.
DOE O 425.1D specifies that the IP may range from a simple checklist to a review
approach as comprehensive as that of an ORR. Local implementing procedures should
specify the IP format. The IP should include all of the information discussed below that is
relevant to the specific RA. The IP must be prepared by the team and approved by the
Team Leader. The IP must reflect the specific scope and tailoring for the RA provided in
the approved POA. The IP should be provided by the Team Leader to the SAA before the
RA begins. Contractor line management must forward the RA IP to local DOE Line
Management for information.
The IP should provide sufficient detail to serve as both information to management and
guidance to the RA team members. Predevelopment onsite facility visits and interviews
may be required before the IP can be adequately developed. The following sections are
suggested. The information below should be included as applicable for the RA, regardless
of the format specified by the local implementing procedures.
9.2.1 Format for Implementation Plan.
Section 60
• Introduction and Background: The Introduction should describe the activity that
should be reviewed and the reason for shutdown (if a restart). The Background
section should provide background information concerning the basic process,
hazards, and issues associated with the activity to be reviewed.
• Purpose: Describes the reasons for the review and provides the basic insights for the
defined scope of the review.
DOE-STD-3006-2010
70
• Scope: The scope defines the physical and administrative boundaries of the facility,
justifies the defined boundaries, and supports a functional review relative to each of
the following:
o plant and equipment (hardware) readiness;
o management and personnel readiness; and,
o SMP (e.g., procedures, plans) readiness.
The Scope section of the IP should reflect the approved scope from the approved POA.
Each scope element required by the POA must be incorporated into the IP. The depth to
which each scope element is evaluated is specified and quantified by the IP criteria and
review approaches (CRADs), consistent with the discussion in the approved POA.
• Prerequisites: The IP should summarize the prerequisites specified in the approved
POA. It should not be the responsibility of the RA team to develop the prerequisites,
but they should understand them because of their usefulness in developing lines of
inquiry for the individual CRADs. This section of the IP should also include the
prerequisites that are the responsibility of the team or Team Leader in preparing to
conduct the RA.
• Review Approach: This section should define the generic approach by which the
review may be conducted and provides an introduction to the RA process. The RA
CRADs should be defined by the processes described in this section. The means for
classifying findings as prestart and post-start should be defined here, as well as the
method for report preparation, finding resolution, and methods of closure. In the
event that checklists or other locally approved methods for defining the lines of
inquiry other than CRADs may be used, the approved method may be described in
this section.
The reviews conducted by each RA team are guided by CRADs, which may be grouped
into functional areas. The selection of functional areas and the specific groupings should
be decided by the RA Team Leader. The selections should be based on the scope of the
RA and the expertise of the team members.
CRADs are the documents used in the IP to establish the depth of the RA and provide
guidance to the RA team members. As such, the quality of these documents has a
significant impact on the overall quality of the RA. CRADs are the bases used to
evaluate the CRs of an RA. The CRs of an RA include the 17 CRs of the DOE O
425.1D, as well as any additional CRs specific to the RA that were specified in the
approved POA. Each CR is evaluated based on the established criteria. The criteria
should be specific and as objective as possible.
The development of the CRADs is the means through which the graded approach is
applied to the scope of the RA. Those areas significant to the startup or to the shutdown
should be assessed to a greater extent than other areas. For example, if, during a
maintenance shutdown, a system was modified or a new system was added, the training,
procedures, documentation, and safety basis for that new system should be thoroughly
DOE-STD-3006-2010
71
Section 61
reviewed. Another system in that same facility that did not undergo modification would
receive a less comprehensive review (i.e., this review could consist of a sampling of the
training and procedures associated with the system).
In another example, 20 percent of the qualified operators of unmodified systems could be
interviewed to assess their level of knowledge, whereas the percentage could be higher
for modified or new systems. In a shutdown that was caused by a DSA or TSR violation
due to a personnel error, the training and qualification program for the facility should be
assessed in detail, while the implementation of the safety basis itself would need a less
comprehensive assessment. For a new, high-hazard facility, the depth of the review
should be complete in all areas. For a restart of a low-hazard facility, the review should
focus on the areas significant to the startup or shutdown, with the remaining core areas
addressed to a lesser extent via less extensive criteria. In general, the discussion in the
POA guides the level of detail in any particular review area.
Each CRAD should address a CR or some portion of the CR. This ensures that all CRs
are addressed by criteria, regardless of the approach used in developing the criteria. The
criterion should clearly and fully address the CR or portion of a CR to which it is
ascribed. Each criterion should be a statement of the specific attributes the team member
evaluates to reach a conclusion as to the readiness of the site, facility, or process to
operate in this specific area.
The next section of the CRAD should be the Review Approach. This section should
describe the documents to be reviewed, the personnel to be interviewed, and the shift
evolutions, including tours and walkdowns, to be observed that lead to the conclusion as
to whether the criteria have been met. The final portion of the CRAD should include any
references — DOE Orders, mandatory Standards, or site-specific requirements — against
which the preceding criteria are to be assessed. The alpha-numeric identification
methodology chosen for the RA implementation plan should represent a logical “work
breakdown structure” chosen to describe the entire RA effort so that all elements can be
related back to the core requirements for safe operation of the facility. The Appendix 3
writing guide contains some examples of CRAD identifications.
The depth of the evaluation specified by the CRADs or through local procedures and
defined lines of inquiry may be unique. The critical and consistent goal is that the review
approaches are adequate to fully evaluate the scope defined in the POA and that they are
sufficiently detailed to allow a knowledgeable observer to understand the intentions for
the RA and agree that the scope specified in the POA is fully addressed.
• RA Preparations: This section should describe any preparations, including team pre-
visits and document reviews, which may be undertaken prior to the RA. A discussion
of qualifications and training considerations for RA team members could appear here.
• RA Process: This section should describe how the RA should be conducted, including
the sequence of activities from the initial in-briefing through the final out-briefing.
The section should discuss the record reviews, interviews, operational
demonstrations, team meetings, and the overall decision-making process. The
DOE-STD-3006-2010
72
Section 62
processes for development of the final report should be included. Some discussion
may be appropriate as to how evolutions and upsets should be conducted and
observed. This section may paraphrase or summarize the RA process in the approved
local implementing procedures.
• Administration: This section should describe the mechanism for RA-related
meetings, correspondence, communications, and team structure. The RA team
composition, interface requirements, any oversight groups, and DOE organizations to
be involved in the review should be discussed in this section.
• Reporting and Resolutions: The section should detail the methods that the RA team
would use to report review results.
• Schedule: This section should include a discussion of the proposed schedule for any
preparation, the previsit, the onsite review, report preparation, and closeout.
• Appendices: The Appendices should include the specific CRADs or other checklists
or lines of inquiry used to conduct the individual assessments. The Appendices may
also include reporting forms, a writing guide, team resumes, and other sections
appropriate to stand alone in an appendix. The appendices of this Standard, as well as
the Team Leader’s Guide and the DOE Readiness Review website, may contain
information and examples that may be useful during development of the appendices
for the IP.
9.3 Conduct of Readiness Assessment
The scope of the RA may not include all core requirements discussed below. In a situation
where the POA excludes some CRs, those elements are not evaluated.
The purpose of the RA should be to examine the aspects of the activity under review and to
ensure that the equipment, procedures, and personnel associated with the activity are ready
for startup and safe operation. In addition, the RA should verify the adequacy of the SMP
infrastructure to ensure that the readiness conditions to start nuclear operations are
maintained through the operating cycle.
The RA should be a performance-based assessment that includes observing and
documenting the responses of operating and support program personnel to normal and off-
normal events as demonstrated by drills, preoperational tests, evolutions, and exercises. In
addition, field assessments should be conducted to verify that field configurations match
the applicable supporting documentation. The RA team should also conduct interviews
with personnel, including management, to evaluate their readiness to conduct operations.
The scope and extent of the evaluations must conform to the scope specified in the POA
that has been accurately reflected in the IP.
The RA must verify that the necessary requirements documentation is in place and
adequately supported by procedures, personnel, equipment, and systems. It is not a
requirement that the RA process approve the foundation documentation, only to verify that
it is complete, approved, and implemented as required by the CRs of DOE O 425.1D.
DOE-STD-3006-2010
73
Critical to the establishment of operational requirements are formal agreements between
the operating contractor and DOE, generally in the form of contracts. Part of the contract
includes the requirements governing the safe operations of the facility. These are normally
identified as List A and List B in the contract section J attachments.
The implementation of the contract requirements for programs that should be within the
scope of the IP should be noted by the RA team member reviewing the programs.
Section 63
Typically an RA should not commence until line management certifies that readiness to
start nuclear operations has been achieved. However, as DOE O 425.1D states, it may be
appropriate for the RA team to observe events significant to the startup process before the
RA begins. Experience indicates that the events meeting this criterion would be emergency
management exercises initiated in the facility within the scope of the RA. Because it is
difficult to plan and schedule emergency management exercises during an RA, it may be
appropriate for the RA teams (both contractor and DOE) to observe the exercise when it
occurs.
For the observation to be a valuable contribution to the RA, the exercise should have the
initiating event within the facility being started, all emergency management documentation
for the facility should be complete, and personnel should be trained in emergency
management procedures. It may not be possible to meet these criteria more than a month
or two before readiness is achieved to start the RA. In very unusual circumstances, there
may be other unique events that should be observed by the team before the RA begins.
This could include a one-time, high-risk test of a component or system within the scope of
the RA or a complex, integrated test sequence. However, normally it is adequate for the
RA team to review the results of the testing. Since the testing is normally not
accomplished by operations personnel and not conducted in a manner to demonstrate
formality of operations or personnel capabilities, direct observation of such testing is of
little value towards demonstration of readiness to start nuclear operations.
9.4 Unsuccessful Readiness Assessments.
The assumption of the RA process is that before it commences, readiness to start nuclear
operations has been essentially achieved and that the RA team can recommend
authorization to start operations when the prestart findings have been resolved. However,
in rare instances, the number or magnitude of the findings may be such that the team is
unable to conclude that resolving the findings would lead to a condition of readiness to start
nuclear operations. Such a conclusion recognizes that because the RA process is executed
through sampling, some important elements of readiness may not be evaluated because of
findings that have been identified. For example, if the TSRs are not fully implemented, it
is not possible to assess the adequacy of the individual implementation mechanisms. In
another example, if the training and qualification requirements were not adequately
defined, it may not be possible to determine the adequacy of the knowledge and
competence of the operating personnel since they had not received appropriate training.
However, there is no firm definition as to when an RA should be stopped. All facts and
issues should be evaluated to determine an answer to the question of whether the RA team
DOE-STD-3006-2010
74
is convinced that readiness has been achieved and whether nuclear operations can be safely
started when the identified prestart findings are resolved.
The RA team should not casually reach its decision to stop an RA or reach an
unsatisfactory conclusion, but instead carefully consider all of the facts that led to its
conclusion. The basis for the team’s decision should be supported with specific issues and
examples. The guidance and counsel of the Senior Advisor may be invaluable.
Section 64
In general, there are two situations that could arise. In the first situation, the team identifies
many areas in which numerous issues are identified, which leads the team to a conclusion
that the RA is unsatisfactory and should be repeated in full. The repeat RA may commence
after line management implements corrective actions to address the identified issues and
recertifies readiness to start nuclear operations. It may be appropriate to develop a new
POA and IP for the repeat RA or simply repeat the RA using the same POA and IP.
In the second situation, many functional areas of the RA are adequately prepared to support
nuclear operations; however, deficiencies are identified in some important functional areas
to the extent that it was not appropriate to simply identify findings to be corrected. In such
a case, it may be appropriate to complete the RA for the functional areas that are ready to
support nuclear operations and finalize the report in those functional areas. For the
inadequate functional areas, the RA may be suspended until the deficient functional areas
are remediated. If the option to suspend the RA is chosen and agreed to by the SAA, the
interim report should provide line management general information concerning the areas of
inadequacy, but not a punch list upon which they should focus all attention. Once line
management has fully evaluated the areas of inadequacy and taken corrective actions to
bring them into a state of readiness to support nuclear operations, the RA may be resumed
in the deficient functional areas.
The Team Leader and the SAA should be aware of the possibility of an unsuccessful RA
and decide how it should be handled. Because the Team Leader works for the SAA, who
directed the start of the RA, suspending the RA should only occur with the SAA’s
agreement. If the SAA does not agree, the team is obligated to complete the RA and
determine that readiness to start nuclear operations has not been achieved, in which case
repeating the RA is the only alternative.
Some organizations within DOE believe that it is never appropriate to suspend and restart
an RA and that if an RA cannot be completed, the entire process should be repeated.
However, in cases where an RA can be satisfactorily completed in some functional areas, it
may be appropriate to take credit for the functional areas that were satisfactory and grade
the POA accordingly. The decision to take credit for the successful portions of the initial
RA should be weighed carefully against time constraints and any changes that have taken
place since the first RA. In every case, there should be close coordination and agreement
between contractor line management, DOE Field Line Management, and the SAA who
must approve the POA for the second RA
DOE-STD-3006-2010
75
9.5 Contractor Readiness Assessments.
Contractor procedures governing the conduct of RAs should include a provision that, prior
to commencing, line management must verify in writing that all prerequisites specified in
the POA have been met. A manageable list of open items may exist, as discussed below, at
the time the contractor RA starts.
Once contractor line management has determined that readiness has been achieved by
meeting all of the prerequisites specified in the approved contractor RA POA, the
contractor formally declares readiness through the Readiness to Proceed Memorandum, and
then the RA must be conducted and reported in accordance with the contractor IP.
Section 65
The contractor must commence its RA only when the approved prerequisites have been
completed. However, there may be events that occur before the RA begins, such as
periodic emergency preparedness drills or complex system testing, when the RA team may
monitor the event when it occurs rather than wait until the review begins. This early
review is appropriate. The activity should be documented in the RA final report. It may be
also appropriate for the RA team to conduct pre–RA activities necessary to gain the
familiarization, understanding, and qualification necessary to prepare the RA IP and
conduct the RA prior to prerequisites being met.
The sequence and methodology for the RA should be described in the IP. Additional
guidance for the preparation and conduct of the RA is provided in DOE-HDBK-3012,
Guide to Good Practices for Operational Readiness Reviews (ORR), Team Leader's Guide.
The final report should be developed during and following the RA. Examples of forms for
the final report are included in the writing guide in Appendix 3. Final reports can be
viewed on the DOE Readiness Review website.
The overall responsibility of the RA team is to examine the aspects of the activity under
review and assure themselves, management, and DOE that the equipment, procedures,
personnel and infrastructure programs, including SMPs associated with the activity, are
ready for startup and safe conduct of nuclear operation.
RA evaluations should place particular emphasis on the SSCs that are important to nuclear
safety (relevant to public and worker safety and health) or of particular importance to the
safety of the planned nuclear operation of the activity. The results of these evaluations are
included in the final report.
DOE Field Element personnel should observe and evaluate the contractor RA process. The
RA process should be open and well-defined to permit DOE oversight. Team meetings
should be informative for the benefit of the team as well as for DOE. Interviews and
record reviews, as well as evolutions and drills, should be scheduled in a manner that
fosters openness. The Team Leader should coordinate with DOE oversight personnel to
facilitate their observation and evaluation of the contractor RA.
Documentation of the methodology, criteria, and results of the contractor RA is important
to the credibility of the review and the foundation for the follow-on DOE RA. The value of
DOE-STD-3006-2010
76
the review depends in large part on the thoroughness of the RA and the adequacy of its
scope (breadth and depth). Section 9.4 and Appendix 3 of this Standard provide additional
guidance on recording the results of the RA.
9.6 Readiness to Proceed Memorandum.
9.6.1 When SAA Resides with Contractor
If the SAA resides with the contractor, the contractor RA team shall develop a final
report in accordance with the site’s implementing procedures and forward it to the SAA.
Upon approval of the SAA, the final report is provided to responsible line management
for use in developing a corrective action plan that provides the methodology and the
schedule for resolving the findings. The SAA will also provide a copy of the final report
to the local DOE Field Element.
For RA where the SAA resides with the contractor, the contractor shall carry out the
applicable parts of 9.4 through 9.9.
Upon completion of pre-start corrective action, line management will issue a Readiness
to Proceed Memorandum to the SAA, who will then make a determination on authorizing
the restart in accordance with section 9.11.
Section 66
The Readiness to Proceed Memorandum should not be submitted until all actions
required for startup or restart have been completed, with the exception of a manageable
list of open prestart items that have a well-defined plan and schedule for closure. There
should be no unresolved issues in the path to closure of these prestart items.
9.6.2 When SAA Resides with DOE
If the SAA resides with DOE, the contractor RA team shall develop a final report in
accordance with the site’s implementing procedures and forward it to the applicable
contractor line management.
Once the contractor RA process has been completed, the contractor must develop a
corrective action plan that provides the methodology and the schedule for resolving the
findings. Prior to issuing the Readiness to Proceed Memorandum to DOE, the contractor
must resolve all prestart findings and prepare the action plan, including schedule of
completion for the remaining findings.
The Readiness to Proceed Memorandum is the formal communication from the
contractor to DOE stating that the facility has been brought to a state of readiness to start
or restart nuclear operations. The Memorandum is a prerequisite to the DOE RA. The
Field Element should use the contents of the Readiness to Proceed Memorandum,
coupled with its own routine management understanding of the status of the facility, as a
basis for the recommendation or decision to commence the DOE RA.
DOE-STD-3006-2010
77
9.6.3 Contents of the Readiness to Proceed Memorandum
The contractor RA final report should be an enclosure to the Readiness to Proceed
Memorandum. The Readiness to Proceed Memorandum indicates the status of resolution
of prestart findings and a corrective action plan for post-start findings. If applicable, the
DOE Line Management endorsement to the Readiness to Proceed Memorandum should
state that the conclusions reached by the contractor RA support the recommendation in
the endorsement.
The Readiness to Proceed Memorandum should not be submitted until all actions
required for startup or restart have been completed, with the exception of a manageable
list of open prestart items that have a well-defined plan and schedule for closure. There
should be no unresolved issues in the path to closure of these prestart items.
If there are an excessive number of open items at the time the Readiness to Proceed
Memorandum is submitted to the SAA, the initial conclusion is that contractor
management and RA processes were not successful. In case where a DOE RA is to be
conducted, the DOE RA should not start until the situation is resolved. The submittal
should be delayed until there are no open items that would prevent authorization to start
nuclear operations. In the situation when the contractor is the SAA, a copy of the
complete RTP including all enclosures should be provided to the DOE Field Element
Manager.
The following provide guidance on the acceptability of the open prestart items at the time
the contractor submits the Readiness to Proceed Memorandum:
• Each open item prerequisite to commencing facility operations should be identified
in the Readiness to Proceed Memorandum.
• In determining how many open items are acceptable, it should be recognized by
line management that every functional area should be sufficiently well developed
in its elements to permit its evaluation in the RA. For example, one or more open
items indicating that a key program has not yet been developed and implemented
would not be acceptable because the functional area could not be adequately
reviewed in the RA. Such an open item would be acceptable only if the key
program were to be fully established before the RA is complete.
Section 67
• Each open item should be explicitly addressed in a corrective action plan. An open
item such as “the required environmental permits have not been requested or
approved” would not be acceptable because many other facility procedures and
activities are potentially impacted by the corrective actions to the identified open
item. The schedule for completion of the corrective action plan should be
consistent with the timing for the completion of the RA so that the RA may
evaluate the corrective action plan and the progress in completing the planned
activities.
DOE-STD-3006-2010
78
In summary, the open items should be few in number, well-defined with a well defined
corrective action plan, able to be completed on a schedule consistent with the RA
schedule, and not of such a nature to preclude an adequate review of any specific area by
the RA.
9.7 DOE Action Following Receipt of the Readiness to Proceed Memorandum (For use when
DOE is the SAA).
DOE Operations or Field Element Line Management should review the submitted
Readiness to Proceed Memorandum, which involves verifying the accuracy of the included
information, evaluating the completeness of the open items listing, and determining
whether the corrective actions and time estimates are realistic. In addition, the Operations
or Field Element must verify that DOE is ready to oversee facility operations as specified
in DOE O 425.1D, which requires that DOE Line Management, up to the SAA, document
in writing their readiness to oversee operations.
DOE Field Element Line Management forwards the Readiness to Proceed Memorandum to
the appropriate DOE Line Manager with a recommendation as to whether the
memorandum should be accepted and the DOE RA scheduled, or whether additional
information or action is needed from the contractor or additional actions should be taken by
DOE Field Element Line Management.
The Readiness to Proceed Memorandum with its enclosures and endorsements should be
retained as a part of the facility restart record, as well as the RA final report and associated
documentation. Experiences and lessons learned in managing the Readiness to Proceed
Memorandum and process should be included in the lessons learned section of the RA final
report.
DOE Line Management responsible for overseeing contractor operations should prepare an
endorsement to the Readiness to Proceed Memorandum before forwarding it to the restart
authority, even when the SAA is at the local DOE Field Office. The DOE Line
Management endorsement should discuss two important elements:
• DOE Line Management’s assessment of the readiness of the contractor to commence
operations. This assessment should be based on the day-to-day observation of
contractor activities and an assessment of the adequacy of the contractor RA and the
associated corrective actions.
• Readiness of DOE Line Management to oversee contractor operations following
startup, including meeting prerequisites and CRs in the DOE POA. The basis for the
conclusion, including the results of any DOE Line Management self-assessments
conducted in anticipation of startup, should be included in the endorsement.
9.8 DOE Readiness Assessments.
When the approved SNR requires a separate DOE RA, the following principles should be
followed:
DOE-STD-3006-2010
79
Section 68
• The DOE RA should not commence until DOE has received the contractor’s Readiness
to Proceed Memorandum, signifying its readiness to commence operations, and until
DOE management is ready to oversee operations. In the event local procedures
provide for parallel DOE and contractor RAs, the procedures should provide clear
direction as to how and when the DOE RA is authorized to start.
• The prerequisites for starting an RA must be specified in the DOE POAs, as required
by DOE O 425.1D. The specifics vary with each RA, but the basic principle is that the
RA must not commence until management has determined that the facility is ready to
start or resume nuclear operations.
• The prerequisites identified in the POAs may refer to phases of the startup process,
conditions of the project management plan, specific consent or compliance agreements,
IVRs, or IP status in order to quantify the method for demonstrating that readiness has
been achieved. Prerequisites should be specific and verifiable. The DOE POA should
contain specific prerequisites that, when completed, provide assurance that DOE is
ready to oversee contractor operations that are about to be started or resumed.
When directed by the SAA, the DOE RA should be conducted and reported in accordance
with the DOE IP that reflects the review scope specified in the approved POA. The DOE
RA team conducts the RA and prepares the final report in accordance with the IP. The
DOE RA should include a detailed review of the contractor’s RA and other performance
assessments in accordance with the approved scope. Following completion of the DOE
RA, resolution of prestart findings, and development of acceptable corrective action plans
for post-start findings, DOE management should recommend to the SAA that startup
approval be granted.
The DOE RA should include an assessment of the technical and managerial qualifications
of those in the DOE Field organization who are responsible for oversight, direction, and
guidance to the contractor, including Facility Representatives. A similar review should be
made of the qualifications of contractor personnel responsible for facility operations.
In most cases, a key element of the DOE RA is a detailed review of the methods and results
of the contractor’s RA. The results, including corrective actions, should be assessed for
adequacy and effectiveness of the contractor’s RR process. The DOE RA should conduct
additional selected detailed assessments to verify the findings of the contractor RA and
review areas that may not have received an adequate review in the contractor RA. The
DOE RA should not be intended or desired to duplicate the contractor RA.
9.9 Documentation of Readiness Assessment Results.
The final product of the RA process is the RA final report, which documents not only
findings and conclusions, but the process by which they were developed. Findings
identified at any point in RA are to be included in the final report and formally addressed
for resolution and closure regardless of any interim actions which may be taken by line
management to address such deficiencies.
DOE-STD-3006-2010
80
The RA final report should be the basis for senior management decisions including startup
or restart approval, and should therefore accurately reflect the conditions found during the
RA.
Section 69
The RA final report should document the logic of the review and conveys the results of the
review. It should provide a summary of review activities and confirmation that the criteria
and review approaches detailed in the IP were followed, with explanations for any
deviations. It should also contain enough detail that the reader can follow the review logic
of the RAs, traceable from the POA to the IP to the RA findings.
The RA final report should document the effectiveness of the facility’s operational
readiness preparation, the contractor RA, and the readiness of the facility to proceed with
startup or restart. The final report should also provide information concerning the
readiness of the management system (both the contractor and DOE) to oversee and manage
the facility, activity, or operation. If deficiencies exist, the RA final report should clearly
define those, as well as the inadequacies that should be addressed before and after startup.
The validity and defensibility of RA results should depend largely on the thoroughness
with which the process and the observations are documented. The final report should be
clear as to what was evaluated and the methodology used during the evaluation.
9.9.1 Final Report Format.
DOE O 425.1D provides requirements for the content of the RA report. The order does
not provide the format. For consistency purposes across a site, the format for check list
type RAs should be specified in site implementing procedures. For RAs with more
substantial scope, the following is a suggested format derived from a composite of past
DOE RA final reports. A synopsis of each section is contained below.
• Title Page: The cover and title page should state the subject and the date of the RA.
The report cover should not contain any extraneous information, data, graphics, or
pictures.
• Signature Page: This page should contain the signatures of all team members,
signifying their agreement as to the report content and conclusion in the areas to which
they were assigned. In the event all team member signatures cannot be obtained due to
logistical considerations, the Team Leader should gain their concurrence via fax or
telephone and sign for them.
• Executive Summary: The Executive Summary should be a one- to three-page synopsis
of the review, findings, and the conclusion as to whether the team believes readiness
has been achieved. The Executive Summary should introduce information and direct
the reader to those portions of the report that provide more detail on the information.
Some suggested points for the Executive Summary include:
o a brief summary of the review activity that provides information concerning
the team’s evaluation of readiness;
DOE-STD-3006-2010
81
o the management system’s adequacy to oversee the operation;
o a summary evaluation of the adequacy of the RA preparation (and possibly the
RA program); and.
o a synopsis of the significant problems and strengths.
• Table of Contents: A Table of Contents should be provided to facilitate a review of the
report. The Table of Contents should identify, with page numbers, all sections and
subsections of the report, illustrations, charts, and appendices.
• Introduction: The Introduction should provide information and background regarding
the facility being reviewed, the reasons for shutdown (if a restart), the purpose of the
RA, and the scope of the evaluation. Other information that should be provided
includes a brief discussion of:
Section 70
o The overall objectives of the evaluation;
o The review process and methodologies used in the review;
o The team composition; and
o Definitions applicable to the review.
• RA Evaluation: This section provides an overall evaluation of readiness, followed by
individual functional area summaries. For each functional area, the summary should,
in one page or less, discuss the CRs and provide conclusions as to the readiness of the
functional area to safely support proposed operations. Conclusions as to the readiness
of hardware, personnel, procedures, and the management system that controls each
functional area should be addressed, including key issues. The evaluation should
discuss the prestart and post-start findings associated with the review and provide a
conclusion as to the readiness of the facility to begin operation within the scope of that
specific functional area.
Any deviations from the IP should be discussed, along with the reasons for the
deviations, and the alternative actions that were taken to compensate, if necessary.
Because the RA Evaluation section provides the basis for the determination of
readiness for each CR, it should discuss not only the deficiencies found during the
review, but should also discuss those positive aspects that affected the determination.
In addition, the RA final report should also identify as Opportunities for Improvement
those items that are not findings; but that, if addressed, would lead to excellence in
operations. The detailed documentation to support the conclusions may be included in
an appendix consisting of the individual CRADs, checklists, or other lines of enquiry
with the accompanying Assessment Forms. See Appendix 3 for additional details.
• Lessons Learned: Each RA final report should contain a section on lessons learned to
be used by both contractor and DOE to improve the RA process. These lessons should
provide information on problems encountered by the review team, adequacies or
inadequacies concerning the review, design, and implementation, expertise, or any
other relevant factors or information that may be used by future review teams.
DOE-STD-3006-2010
82
The RA must also identify lessons learned applicable to similar facilities. Lessons
learned in areas such as operations, procedures, design, or documentation may also be
identified. The RA team must include these lessons learned in the report as well.
Facility management or DOE management should be responsible for promulgating
these lessons in accordance with established procedures. The RA final report may be
issued before the lessons learned section is written to avoid delays in issuing the report.
However, each RA report must contain a lessons-learned section, as required by DOE
O 425.1D.
• Dissenting Professional Opinions: The RA process provides an opportunity for team
members to submit dissenting professional opinions which should be documented and
appended to the final report.
While the team should strive to reach a consensus concerning all aspects of the review,
DOE recognizes that professional judgment does not always allow for complete
agreement. In cases of disagreement, the Team Leader should make the final decision
concerning the disposition of the finding or concern. However, discussion of all
aspects of the finding should be provided in the final report to provide the SAA with all
relevant information on which to base his or her decision.
Section 71
If a team member feels that aspects of his or her opinions have not been adequately
represented, that member should file a dissenting professional opinion. The written
report of the dissenting professional opinion should be appended to the RA final report
for review by the SAA.
• Appendices: Appendices provide data that support the final report. Data that should
be considered for appendices include:
o the IP*;
o the CRADs*;
o a listing of the team members and their resumes*;
o the POA*
o Evaluation of criteria (Forms 1);
o the Prestart Findings summary (Forms 2); and,
o the Post-start Findings summary (Forms 2).
The asterisked items may be referenced but not included in the final report and should
be maintained with the readiness records.
9.10 Prestart and Post-Start Findings.
Findings should be defined as nonconformance with a stated requirement that represents
either:
o a systematic failure to establish or implement an adequate program or control; or,
DOE-STD-3006-2010
83
o a significant failure that could result in unacceptable impact on the safety of
personnel, the facility, the general public, or the environment during nuclear
operations.
During the RA, it is expected that the team should identify individual deficient conditions.
Frequently, the deficient conditions, when evaluated together, may reflect a programmatic
or implementation weakness that is of concern and requires corrective action to ensure that
operations are conducted safely when started (prestart finding), or requires corrective
action to mitigate longer-term concerns or programmatic deterioration (post-start finding).
As discussed above, findings should be discussed on Form 1s and documented on Form 2.
The rollup or individual deficient conditions should be identified as findings. One of the
important tasks of the team is to identify the significant findings that impact the adequacy
of programmatic support or indicate inadequate implementation of important operational
conditions. It may be possible to identify individual deficiencies. The challenge should be
to determine when a group of seemingly minor individual issues are indicative of a more
systemic issue that should be identified as a finding.
The IP or local approved procedures also should provide a standardized method for
identifying findings using the requirements identified within the criteria. Each finding
should be clearly described, providing examples of the individual issues that comprise the
finding. The finding should describe what is deficient, provide the reference to the
requirement with which it is deficient, and be written in a manner permitting corrective
action to resolve it. Each finding should be identified as to whether or not, in the opinion
of the RA team leadership, it should be resolved as a prerequisite to startup of operations.
Criteria for arriving at this opinion should be published in the IP. It may also be
appropriate to identify the level of management (i.e., contractor, DOE Field, or DOE
Headquarters) at which the finding should be closed. While the RA team may assist
management in reviewing the action taken on a finding, responsibility for its resolution
should reside with line management. Form 2, which is discussed in the writing guide in
Appendix 3, further discusses identified findings.
9.11 Corrective Action Plans.
Section 72
The contractor and DOE must prepare corrective action plans for all findings identified in
their respective RAs. The DOE and contractor implementing procedures should specify the
process and format for evaluating and documenting findings. Form 3, described in
Appendix 3 writing guide, may provide the required documentation to describe corrective
actions and close the finding. The action plan should contain the following elements:
• The finding, as written in the report submitted by the RA team, and whether the
finding is a prestart or post-start finding.
• A detailed proposed action plan for addressing the deficiencies identified in that
finding. The proposed action plan should evaluate any overall programmatic
deficiencies related to a specific finding that could lead to similar occurrences and
include actions to address these deficiencies. For findings identified during the DOE
RA, DOE must approve the contractor’s proposed corrective action plan.
DOE-STD-3006-2010
84
• The proposed dates when the actions should be completed. If the corrective actions
for a finding are phased, the dates for each phase should be detailed.
• If it is a post-start finding, a description of the risks and mitigating actions or
compensatory measures, if any, to be taken during the interim that should reduce the
risks to an acceptable level before final corrective action. DOE Line Management
should verify that the corrective action plan has been entered into the appropriate
quality program issues management system.
• If some corrective actions for prestart findings would occur after the startup of
operations, the risks and mitigating factors or compensatory measures should be
clearly identified. The actions that are required prior to the startup of operations must
be clear and closed with a final closure package, as discussed below, before
operations can be started.
Findings and associated corrective actions for the contractor and DOE RAs should be
entered and managed via the site corrective action or action tracking processes.
9.12 Readiness Assessment Follow-up Activities.
The RA process should not end with the completion of the RA and the finalizing of the
report. Several actions may require the participation of the Team Leader and team
members. The Team Leader should notify all team members of future involvement
concerning closeout briefings, interpretation (and possible justification) of findings, review
of corrective action plans for adequacy, and review of final closure actions.
It should be clearly understood that line management is solely responsible for resolving
findings and accepting the corrective action plan and the adequacy of the corrective
actions. However, since the team members are most familiar with the details of the
findings, line management may request members of the team to assist during the process
for closing findings. It should always be clear that line management should not defer to the
team on deciding on the adequacy of the corrective action plans or the corrective actions
actually taken.
The Team Leader should be prepared to coordinate any follow-up meetings, which include
closeout meetings with the affected facility and line management, team debriefings, and
presentation of the report to DOE and contractor upper management. The Team Leader
may be required by the Secretarial Officer or other appointing authority to present the team
report to upper DOE Line Management. Presentations may be required to internal or
external interested groups as well. In addition, it may be appropriate for the Team Leader
to recommend an organization to verify proper closure of individual prestart findings.
Section 73
9.13 Action Tracking and Closure Methodology.
Monitoring and verifying the satisfactory closure of prestart findings from both the
contractor and DOE RAs is a line management responsibility. DOE O 425.1D defines
elements of the required process to close RA findings. Closure packages should contain
DOE-STD-3006-2010
85
the following information:
• The finding, taken verbatim from the original report, should be identified as a prestart
or post-start finding.
• The actions proposed in the action plan should be developed, submitted, and
approved with the original completion schedule.
• A brief description of the corrective actions taken, reasons for concluding that closure
has been achieved, and objective evidence supporting closure should be provided.
The referenced documents or objective evidence illustrating the corrective actions and
the dates of the actions should also be included.
• Signatures of the appropriate line management, as defined by the site procedures or
within the RA IP should be included. An example closure form is provided as Form
3, RA Finding Resolution Form, in Appendix 3.
• DOE verification for DOE RA findings, of the adequacy and completion of the
corrective actions should be provided.
9.14 DOE Line Management Oversight of the Readiness Assessment Process.
Throughout the RA process, various Headquarters, Field Element, and external oversight
organizations may become involved in the process. To ensure that proper liaison occurs,
documentation from each step in the process should be provided to the appropriate internal
and external oversight groups for information and comment. In most cases, the
documentation should be provided after approval by the appropriate management official.
It should be stressed, however, that all information should be provided in a timely manner
if all organizations are to execute their responsibilities without delaying critical steps in the
process. Frequent liaison should occur between management and oversight organizations
at each level, both internal and external, to ensure that all responsibilities and commitments
are fulfilled. Transmittal of DOE documents to agencies outside of DOE should follow
established procedures.
DOE Field Element personnel should observe and evaluate the contractor RA process. The
RA process is open and defined to permit DOE oversight. Team meetings should be
informative for the benefit of the team as well as DOE oversight. Interviews, record
reviews, evolutions, and drills should be scheduled in a manner to support openness. The
RA Team Leader should coordinate with DOE oversight personnel to facilitate their
responsibility for observing and facilitating the contractor RA.
The following items are a compilation of the required and recommended responsibilities of
the Field Elements in executing the new start and the restart RA processes. Some of these
actions may not be required in situations when the contractor is designated in the SNR as
the SAA. In all cases, however, DOE should exercise adequate oversight of the RA
DOE-STD-3006-2010
86
process to ensure that the approved procedures are followed and the desired outcome is
achieved.
• Review and approve, or review and forward for approval, the contractor RA POA.
• Provide day-to-day oversight of the contractor’s activities to achieve and verify
Section 74
readiness to conduct operations, including a review of the contractor RA report and
prestart finding closure plans and closure documentation. Through this day-to-day
oversight, Element Line Management provides knowledgeable recommendations
concerning the contractor’s actions and proposals. Day-to-day oversight enables
Field Element staff to provide a defensible recommendation on the contractor’s
Readiness to Proceed Memorandum.
• For cases where SAA resides with the DOE, review, and take appropriate action on,
the contractor Readiness to Proceed Memorandum. If the Operations or Field
Element Manager is the SAA, he or she grants authority to conduct the DOE RA. For
other new starts and restarts, the contractor forwards the Readiness to Proceed
Memorandum to Headquarters recommending that the DOE RA be started when it is
satisfied that the facility is ready to be operated safely, Field Element Line
Management personnel is ready to oversee contractor activity, and procedures are in
place.
• For cases where SAA resides with the DOE, DOE Field Element Line Management
responsible for oversight of contractor operations should prepare an endorsement to
the Readiness to Proceed Memorandum when forwarding it to the SAA. The DOE
Line Management endorsement should contain two important elements:
o a discussion of DOE Line Management’s assessment of the contractor’s readiness
to commence operations. This assessment should be based on the day-to-day
observation of contractor activities and an evaluation of the adequacy of the
contractor RA and associated corrective actions; and,
o concurrence with the status of prestart findings and a recommendation to the
appropriate decision official to authorize startup or restart after the DOE RA is
complete and all prestart findings are closed. In cases when the Field Element
Manager is the designated SAA, he or she must authorize the startup or restart and
should inform the Secretarial Officer.
• DOE Prestart Findings Closure Process. Evaluate the contractor’s prestart finding
closure process and verify closure of DOE RA prestart findings as designated by the
SAA. To verify closure, support may be requested from the DOE RA Team Leader
or team members; however, closure verification remains a line management
responsibility. DOE Line Management verifies the adequacy of corrective action
plans for all findings from the DOE RA.
DOE-STD-3006-2010
87
See Section 7 above for additional discussion on the roles and responsibilities of DOE Line
Management and oversight organizations.
9.15 Independent Oversight Organizations.
DOE O 425.1D, Section 5.b specifically indicates that DOE independent oversight of the
RA and RA process is the responsibility of HSS. To ensure that the startups and restarts of
DOE nuclear facilities proceed in a timely fashion, it is incumbent upon the contractors,
Field Element Managers, and Secretarial Officers to provide the appropriate review
documentation to the PSO, site Lead PSO or CSO, the appropriate CTA, and HSS
throughout the process. It is also incumbent upon HSS to provide comments to these
organizations in a timely fashion to ensure that their concerns are addressed with minimal
impact on the startup or restart schedule.
HSS. In addition to the general Departmental responsibilities specified in DOE M 411.1-
1C, the DOE FRAM, HSS exercises independent oversight of the startup and restart
process for nuclear facilities. This responsibility entails the following:
Section 75
• In coordination with the PSO, performing independent reviews of startup and restart
activities as appropriate and providing the results of these reviews to the CSOs for
resolution.
• Reviewing and commenting on SNRs, contractor and DOE POAs, IPs, and RA final
reports.
9.16 Authorization to Resume Operations.
In cases where the SAA resides with the contractor. Upon completion of Readiness
Assessment activities, including resolution of all prestart findings, and satisfactory
corrective action plans are prepared for post-start findings, and a Readiness to Proceed
Memorandum has been received, the SAA my grants permission to start or resume
operations.
In cases where the SAA resides with DOE. Upon completion of Readiness Assessment
activities, receipt of the contractor’s Readiness to Proceed Memorandum, DOE Line
Management concurrence on the satisfactory status of prestart and post-start findings. DOE
Line Management should forward the contractor’s Readiness to Proceed Memorandum to
the SAA with a recommendation on authorizing the restart or startup of operations or
activities. The SAA should inform appropriate Secretarial Officer of their final decision.
10 EQUIVALENCIES AND EXEMPTIONS
DOE O 425.1D specifies that the exemption provisions of DOE O 251.1C, Departmental
Directives Program are applicable.
DOE-STD-3006-2010
1-1
APPENDIX 1. RECOMMENDED APPLICATION OF THE GRADED APPROACH IN
READINESS REVIEW PLANNING
For the purposes of this Appendix, the graded approach is defined as the process by which the
readiness determination is adjusted in the scope of detail required and magnitude of resources
needed to be commensurate with the facility’s potential impact on safety, environmental
compliance, safeguards and security, and its programmatic importance, including the present and
future missions. The graded approach is commensurate with:
• The importance to safety, safeguards, and security;
• The magnitude of any hazard involved;
• The lifecycle stage of a facility;
• The programmatic mission of a facility;
• The particular characteristics of a facility;
• The cause and circumstances of the facility shutdown;
• Complexity of the weapons-related or research activity; and
• Other relevant factors.
All RRs consider the minimum set of Core Requirements (CRs) and any additional requirements
as deemed necessary for an adequate review (breadth). A recent independent, successful,
comprehensive review may be used as justification for eliminating a CR from the breadth of the
RR. Additional justification may be provided in the POA to justify the elimination or tailoring
of additional CRs. With respect to RR planning, a graded approach should be applied to
determine the level of detail (i.e., the depth). The combination of breadth and depth forms the
scope of the RR. Proper application of the graded approach is essential to conducting a
successful RR. The supporting principle governing the use of the graded approach is that
knowledgeable personnel should analyze the factors surrounding the start or restart, determine
the depth of the review needed, and appropriately document this determination. Precise
documentation facilitates communication with knowledgeable outside officials that the proper
level of review has been conducted and that readiness to operate has been accurately verified.
The scope of a RR cannot be determined using a cookbook or formulaic approach. Identifying
the appropriate depth of a review requires knowledgeable people who identify relevant topics
based on their experience, the facility characteristics, the facility operating environment, the
operating and support organizations’ capabilities, and the risks associated with the proposed
startup or restart. The Scope discussion in the approved POA provides a basis for determination
of the depth of the review of individual criteria or CRs. Criteria and Review Approach
Documents (CRADs) are developed for each CR, specifying the appropriate level of detail.
Section 76
The following factors and their implications should be considered in developing the depth of
either an operational RR or a RA and should be considered when applicable in preparing the
POA:
DOE-STD-3006-2010
1-2
• Physical modifications to the facility: Any modification should be assessed for its potential
effect on facility hazards and risks, on the facility safety basis as documented in the
Documented Safety Analysis (DSA) and associated Technical Safety Requirements (TSRs),
on facility procedures, and on the need for personnel to be trained on the reconfiguration. In
addition, the integrity of the facility design baseline may need to be verified.
• Procedural changes: Changed or new procedures should be reviewed to determine if they
have been adequately verified and validated, if the operators have been adequately trained on
the modified procedures, and if the procedures at the workstations clearly reflect the changes.
• Personnel changes: Continuity of the operations team should be assessed to determine if a
significant loss of experienced personnel has occurred and been adequately mitigated.
Training and qualification of new and reassigned personnel should be verified.
• Length of shutdown: There is a characteristic loss of operator familiarity with normal facility
operations that increases with the length of the shutdown. If the shutdown is unusually long,
requalification of the operators may be necessary. There are also physical processes (e.g.,
corrosion, radioactive decay, evaporation) that may become important following an extended
outage. The longer the outage and the more complex the activity during the outage, the more
rigorous the review should be to identify unanticipated changes.
• Overall hazard characteristics of the facility: The nature of the hazards and the environment
associated with a facility or process are major factors in determining the depth of the RR.
For example, the depth of an RR for a facility that handles small quantities of tritium gas may
not be as complex as one that handles large quantities of plutonium.
• The complexity of the activity: The size and complexity of the facility or process being
reviewed drives the rigor and complexity of the RR. The depth of the review requires that
reviewers be able to comprehend and evaluate the criteria. The number of criteria developed
should be based on the size and complexity of the facility or process.
• A new process or facility versus the restart of an existing activity: A significantly new
process would involve verification of training and qualification of workers and new
procedures without any significant reference points available onsite. This should ensure the
RR to be more comprehensive than that for a process that has a significant experience base
onsite.
• The programmatic significance of subsequent operations: A facility or process that is
intended for long-term programmatic operations should require a more comprehensive
review in some specific areas than would a temporary operation.
• Introduction of new hazards: The proposed facility evolution should be evaluated for
potential new hazards. While some new hazards may be obvious, a critical review is needed
to identify subtle new hazards introduced by the startup of new facilities or modification to
existing facilities. Modifications made to improve operations in one aspect may
unexpectedly introduce hazards in a different area.
Section 77
• Increase in existing hazards or risks: Modifications to the facility, personnel, or procedures
should be evaluated for their potential to increase the hazard level (e.g., by increasing the
inventories of hazardous materials) or the hazard potential (e.g., by introducing a new
mechanism for the release of hazardous materials).
• Operating history of the facility: The record of operational reliability (e.g., reliability during
most recent operation) may identify issues to be addressed in the proposed RR. Additionally,
the nature of the facility or process transition to standby or shutdown status should be
considered. A shutdown resulting from systemic safety concerns may need greater RR depth
DOE-STD-3006-2010
1-3
than would a shutdown in response to an individual safety concern (i.e., a TSR violation,
potential inadequacy in the safety analysis (PISA), lack of program work or similar non-
safety-related causes).
• Confidence in site-wide programs and infrastructure: Even if the proposed startup or restart
does not directly involve changes to site programs (e.g., emergency preparedness, site fire
response, environmental monitoring), it may be prudent to evaluate these in an RR unless
recent reviews have shown them to be acceptable. Startup or restart of a facility is
problematic within a significantly flawed site infrastructure. Conversely, a strong record of
implementing DOE requirements (e.g., conduct of operations) should allow for a justifiable
reduction in depth in that area of the RR.
• Issues raised through other internal or external reviews: The RR may need to verify that
previously raised issues have been adequately addressed. These issues may be facility-
specific or may relate to the site infrastructure within which the facility operates. Previous
RRs, Integrated Safety Management System (ISMS) verifications, or periodic site inspections
or assessments may be sources of information as to conditions at the site and the facility.
The facility’s experiences in implementing the corrective actions and lessons learned may
also provide a valuable perspective for determining the depth of the RR. Caution should be
exercised in utilizing previous inspections as justification for eliminating a topic or limiting
the breadth of review. The adequacy of any previous review to be used in this manner should
be equivalent in all respects to the review that would have been conducted during the RR.
• DOE O 425.1D requires that RR final reports document lessons learned. Such lessons may
assist in determining the depth of future RRs. Previous reviews may highlight issues to be
considered or may provide the justification for doing a less detailed review if recent reviews
and restart experience can be cited.
• The extent to which the facility or process has been evaluated or operated using the standards
and level of excellence in the RR: In applying the graded approach, the extent to which the
facility has utilized or been evaluated against the current nuclear safety standards should be
considered. A facility that has operated successfully using the DOE nuclear safety standards
may require a less extensive RR depth.
DOE-STD-3006-2010
2-1
APPENDIX 2. EXPECTATIONS FOR CORE REQUIREMENTS (CRs)
Section 78
Since the formal inception of the Readiness Review (RR) Program, lessons learned have been
generated. Through review of these lessons learned, it has been noted that some of the CRs need
further explanation to properly communicate the expectations contained therein. Specifically,
CR 13, regarding implementation of established requirements, has generated confusion from
both a preparation and an evaluation perspective. CR 11 has generated confusion from a
preparation standpoint. Further details regarding these CRs are provided below.
CR 13 states,
(13) Formal agreements between the operating contractor and DOE have been established
via the contract or other enforceable mechanism to govern the safe operations of the
facility.
A systematic review of the facility’s conformance to these requirements has been
performed.
These requirements have been implemented in the facility, or compensatory measures are
in place during the period of implementation. The compensatory measures and the
implementation period are approved by DOE.
This requirement was established to verify that there were adequate contract requirements,
frequently identified as contract List A and List B, to ensure the safety of nuclear operations.
The requirement includes implementation of the established requirements at the facility.
Organizations have misinterpreted this requirement to be fulfilled through the completion of the
Standards/Requirements Identification Document (S/RID) or Work Smart Standards Processes or
the existence of a List A and List B. While the completion of the program elements is certainly
prerequisite to the proper controls being established in the facility, the facility-level
implementation of the contract requirements is the issue of primary concern. The procedures and
direction for floor-level operations should implement the established requirements agreed to by
DOE and the operating contractor through the S/RID, Work Smart Standard, List A or B, or
other acceptable program. The existence and adequacy of these procedures and direction at the
floor level should be verified by line management prior to startup or restart and confirmed by the
ORR or RA team during the review by their observation of floor-level operations. The
Integrated Safety Management (ISM) initiative and the verification of implementation of the
approved Integrated Safety Management System (ISMS) have increased the confidence in the
adequacy of the contract requirements. It is therefore appropriate, in verifying CR 13, to look to
the adequacy of ISMS implementation verifications and re-verifications as evidence of the
adequacy of the implementation of the requirements. A re-verification by the RR team is not
normally necessary if there is strong evidence of adequacy through ISMS verifications, re-
verifications, or the contractor annual ISMS assessment report. At most, it may be appropriate to
verify inclusion of the site implementing mechanisms at the facility or process level.
DOE-STD-3006-2010
2-2
CR 11 states,
(11) An adequate startup or restart program has been developed that includes plans for
graded operations and testing after startup or resumption to simultaneously confirm
operability of equipment, the viability of procedures, and the performance and knowledge
of the operators.
The plans should indicate validation processes for equipment, procedures, and operators
after startup or resumption of operations including any required restrictions and
additional oversight.
Section 79
Compensatory measures required during the approach to full operations are described.
This requirement was established to provide direction for the period following the RR and the
startup or restart of the facility. It is recognized that since operations are not authorized prior to
and during the RR, actual operations may not be fully validated by a line manager or evaluated
by an RR team. Hence, to some degree (greater for a more complex facility), operators may be
operating equipment, using procedures, and handling the hazards for the first time immediately
following the startup or restart. It is appropriate to establish additional controls, support, and
oversight for the initial period following the startup, which is often called the “deliberate
operations” phase. Review of the plans for these deliberate operations provide the RR team with
an opportunity to judge the complexity of the remaining startup or restart activities, determine
the controls to be exercised, and provide an appropriate recommendation to the Startup
Authorization Authority (SAA) without having seen these events.
Likewise, the responsible line manager gains confidence that operators, procedures, and
equipment have achieved the requisite readiness to conduct work safely. Some sites have
provided guidelines for establishing startup or restart controls that accomplish the objectives
outlined above. An example of these guidelines is included here for informational purposes. It
is appropriate to note that the level of detail and magnitude of the Startup Plan depends largely
on the complexity of the activity that is being started or restarted and the degree to which
operations can be demonstrated before hazards are introduced. If the majority of operations can
be conducted and demonstrated during the preparation and review processes, the Startup Plan
may include those operations that could not be demonstrated, or that may be conducted for the
first time with the hazard present. Alternatively, for an operation where most of the preparation
should be done through walkthroughs and tabletop exercises, the Startup Plan would necessarily
be more extensive. In all cases, it is appropriate that the controls specified in the Startup Plan be
demonstrated during the RR. The required compensatory oversight and recordkeeping should
also be demonstrated. In short, all elements of the Startup Plan should be evaluated in the
facility during the RR.
Guidelines for Developing the Startup or Restart Plan
The Startup or Restart Plan should provide for a controlled, deliberate approach to achieving
safe, unrestricted facility nuclear operations. Other plans and schedules affecting startup or
restart should be summarized in the Startup or Restart Plan so that the startup or restart plan is a
complete standalone document that clearly delineates the graded, systematic approach to full
operations. The Plan should detail implementation of management and facility activities
DOE-STD-3006-2010
2-3
necessary to achieve full operations, not simply describe established programs. A key element
involves the participation of qualified management personnel in evaluating initial operations
testing. As such, the Plan should include specific management observer responsibilities. The
following paragraphs provide further guidance on developing the Startup or Restart Plan.
A. Identification of facility management observers necessary for initial operations
oversight
Section 80
1. List the management personnel assigned to conduct initial operational evaluations
of the graded operations testing, including summary-level duties, responsibilities,
and shift staffing requirements (specific duties and responsibilities should be
listed in the remaining sections of the Plan), indicating the duration of the initial
operational evaluations. Include recordkeeping expectations and the specific
qualifications required of each individual.
B. Equipment operability
1. Identify and describe the integrated tests planned and required to confirm
operability of equipment during initial operations. Include the purpose and a
summary of the testing acceptance criteria.
2. List management responsibilities for approving the commencement of testing and
management observer oversight of test performance. Include management
approval requirements for key events or progression to the next phase of testing.
3. Provide a summary-level schedule that clearly illustrates the systematic approach
to full operations.
C. Procedure viability
1. Identify and describe the mechanism for verifying the viability of procedures
during actual performance, including requirements for management observer
participation in the first-time execution of procedures.
2. Summarize the process for procedure changes resulting from the identification of
inadequacies in the Field. Include any provisions for increased procedure revision
support during the initial execution of procedures.
D. Operator Performance
1. Identify and describe the mechanism for real–time, in-plant management observer
evaluations of operator performance to verify the adequacy of operator training.
2. Identify and describe the established mechanism for remediating any identified
weaknesses.
DOE-STD-3006-2010
3-1
APPENDIX 3. READINESS REVIEW WRITING GUIDE
Introduction
The process for determining the operational readiness of Department of Energy
(DOE) facilities is complex, involving many technical and management issues at
each specific facility or site. Readiness Reviews (RRs) should be accomplished
by experienced, dedicated people and conducted with sufficient rigor and
discipline so the Departmental leadership and independent oversight groups have
confidence in the results and recommendations by the RR team for startup or
restart.
RRs are assumed to be open to public scrutiny. In addition, results from these
reviews may form the basis for improvements at DOE facilities. For these
reasons, it is essential that team members substantiate their observations in
writing, factually, accurately, and in such a way as to make clear the details of
observed strengths and weaknesses. RR final reports should be of the highest
technical accuracy and quality.
The documentation used to guide the RR should also be complete and
comprehensive to ensure that its scope, as specified by the Startup Authorization
Authority (SAA) in the POA, is fully and accurately reflected in the
Implementation Plan (IP) that guides the RR. Each IP is unique, reflecting the
scope specified in the POA and the mix of skills and experience of the individuals
on the RR team. This Writing Guide provides examples of Criteria and Review
Approach Documents (CRADs), but the CRADs for a specific RR are tailored to
reflect the scope and the skills of the individuals on the RR team. The IP is
prepared and approved by the RR Team Leader with the assistance of the RR
team.
Section 81
This Guide is intended to assist team members in preparing for the RR,
documenting their activities and findings, and preparing the final report. DOE O
425.1D provides for flexibility in the IP for a Readiness Assessment (RA), which
may be as simple as a checklist or as complex as the IP for a full-scope
Operational Readiness Review (ORR). DOE O 425.1D further requires that local
procedures be developed and approved to define the processes by which the
requirements in the Order are met. If local processes are different from those
described in this Standard, they should be documented in the approved local
procedures.
CRADs
CRADs are the documents used in the IP to establish the depth of the RR and
provide guidance to the RR team. As such, the quality of these documents
significantly impacts the overall quality of the RR. The CRADs form the basis
for evaluating the CRs, which are derived from the 17 CRs listed in DOE O
DOE-STD-3006-2010
3-2
425.1D. Each CR is evaluated based on the established criteria. The criteria
should be specific and as objective as possible.
The graded approach is applied to the scope of the RR through the CRADs. The
areas that are significant to the startup or shutdown should be assessed to a greater
extent than other areas. For example, if, during a maintenance shutdown, a
system was modified or a new system was added, the training, procedures,
documentation, and safety basis for the new system should be reviewed
comprehensively. Another system in that same facility that did not undergo
modification would receive a less comprehensive review that could consist of a
sampling of the training and procedures associated with the system.
For example, the team could interview 20 percent of the qualified operators of
unmodified systems could be interviewed to assess their level of knowledge, and
a larger percentage for operators of modified or new systems. In a shutdown that
was caused by a Documented Safety Analysis (DSA) or Technical Safety
Requirement (TSR) violation due to a personnel error, the training and
qualification program for the facility should be assessed in detail, while safety
basis implementation would need a less comprehensive assessment. For a new,
high-hazard facility, the depth of the review should be complete in all areas. For
a restart of a low-hazard facility, the review should be focused on the areas
significant to the startup or shutdown, with the remaining core areas addressed to
a lesser extent, via less extensive criteria. In general, the discussion in the plan-
of-action may guide the consideration that results in the level of detail in any
particular review area.
The Objective in each CRAD includes all, or portions, of one or more CRs. All
CRs that are within the approved scope should be included within one or more
Objectives. The criteria in the CRAD are developed so that the criteria reflect the
Objective. This ensures that all CRs are addressed regardless of the approach
used in developing the criteria. The criteria that address the CR or portion of a
CR included within the Objective should follow, and be related clearly to, these
requirements. Each criterion, then, is a statement of the specific actions or
attributes the team members use to make a judgment as to the readiness of the
site, facility, or process to operate in this specific area.
Section 82
The assumption is that if all criteria in a CRAD are met, the objective is met. If
all objectives are met, readiness to start nuclear operations has been verified.
However, it is not true that if individual criteria are not met, the Objective cannot
be met; nor is it always the case that if an Objective is not met, readiness has not
been achieved. The determination as to whether an objective is met or readiness
has been achieved must be made by the RR team based on the body of evidence
and information developed during the RR. The experience and technical
competence of the RR team is critical to ensure the determination of meeting an
objective or readiness is accurate. The discussion on findings and conclusions
DOE-STD-3006-2010
3-3
appears in the body of the Standard. The requirement reference should be
included with each criterion which is the basis for evaluation of the criteria.
The Review Approach section of the CRAD describes the documents to be
reviewed, the personnel to be interviewed, and the shift evolutions, including
tours and walkdowns, to be observed that enable the team to reach a conclusion as
to whether the criteria have been met. The final portion of the CRAD should
include any references — DOE Orders, mandatory standards, or site-specific
requirements — against which the preceding criteria are to be assessed.
Because every RR is different, the scope of the evaluation specified by the
CRADs is unique. The following examples are by no means inclusive, serving
merely to demonstrate CRADs previously deemed appropriate in specific
situations. If site experience leads to a different format or content for the CRAD
in the IP, it should be reflected in the approved local implementing procedures.
Sample CRADs.
The sample CRADs are taken from actual RRs. In some cases, explanatory notes
are added to provide clarification when following the examples in developing
CRADs for future RRs. Including contract references with each criterion is
appropriate for future use.
The DOE Readiness Review website contains examples of additional
documentation associated with RRs, including POAs, IPs, and final reports. The
website also contains lessons learned and other relevant information on the RR
program. This website should be reviewed frequently, particularly before
developing an IP. The DOE Readiness Review website also contains current IPs.
Experience also indicates that each IP is unique to accurately reflect the specific
details of the RR.
The CRADs that follow are samples from actual IPs. In some cases, the content
has been modified to show a particular methodology or process for developing the
CRAD. Some additional points:
• The objectives of the CRADs should reflect the complete scope of the RR as
specified in the POA.
• Each criterion should include the reference in terms of a contract requirement
or a site-specific implementing mechanism. The references should be as
specific as possible.
• The naming of functional areas is at the discretion of the team. In many
instances, the functional areas reflect the skill set of the individual reviewers.
• Each CRAD should be designed to be reviewed by a single team member.
Multiple team members assigned to a single CRAD may increase the
difficulty of completing the RR and the final report.
DOE-STD-3006-2010
3-4
RADIATION PROTECTION (RP)
(from the Tritium Extraction Facility (TEF) ORR)
(Note: Unique names for Functional Areas are not specified. Names chosen
by the Team Leader may reflect the skills of the assigned team member)
Section 83
OBJECTIVE
RP.1: Site Contractor line management has established radiation protection safety
management programs (SMPs) to ensure the safe accomplishment of work:
• The contract requirements for the SMPs have been flowed down into facility-
specific procedures;
• SMP implementing procedures have been effectively implemented in support
of the facility;
• Sufficient number of qualified personnel are available to effectively
implement the SMPs;
• An adequate number of facilities and equipment is available to ensure that
SMP support and services are adequate for safe facility operations.
The Site Contractor program for management and control of on-site transportation of
radioactive materials in support of TEF activities is effectively implemented. The
program requirements and processes have been updated to reflect TEF requirements.
Adequate personnel, facilities, and equipment are available to support TEF requirements.
The Site Contractor plan for verifying the adequacy and integrity of the structural
radiation shielding for TEF is adequate (Core Requirements 1, 20). (For this RR,
additional CRs associated with transportation were added)
CRITERIA
1. The Site Contractor Radiation Protection Program has been effectively implemented
in support of the full scope of TEF operations, including bioassays, the As Low As
Reasonably Achievable (ALARA) principle, radiological work permits (RWPs),
survey requirements, and decontamination (10 CFR 835, Radiation Protection
Program for 10 CFR 835, Occupational Radiation Protection).
2. Assessments of program elements are performed (Site Contractor Manual, RADCON
Internal Audit Program), including those listed below. The results of the assessments
are evaluated and issues are resolved. The assessments confirm the adequacy of the
radiation protection program in support of TEF activities.
• Boundary control stations and access controls,
• Routine surveys and monitoring (both airborne and surface),
• Survey records and maps,
• Bioassay baseline and continuing monitoring processes and records.
DOE-STD-3006-2010
3-5
3. An adequate number of radiation protection program personnel, including
radiological control technicians, radiation control engineers, and support technicians,
are assigned and available to support TEF activities (10 CFR 835, Site Contractor
RadCon Manual).
4. Instrumentation in support of TEF activities is appropriate, adequate inventory is
provided, calibrations are current, and source checks are performed as required (10
CFR 835, Site Contractor RadCon Manual).
5. Packaging and Transportation (P&T) program requirements necessary to support TEF
have been incorporated into the Site Contractor program. The P&T program includes
compliant provisions to transport Tritium-Producing Burnable Absorber Rods
(TPBARs) from K Area to TEF. The Site Contractor and the Savannah River Site
Office (SRSO) have assessed the adequacy of the implementation of the P&T
program elements required to support TEF. Program requirements include P&T of
both radioactive waste and TPBARs (DOE O 460.1B, DOE O 460.2A,
Standards/Requirements Identification (SRID)).
6. TEF radioactive waste management procedures and processes are compliant with the
Site Contractor Radioactive Waste Management Program. Adequate personnel,
facilities, and equipment are available to support TEF radioactive waste management
processes and activities. The Site Contractor has assessed the adequacy and
compliance of the TEF radioactive waste management processes. Issues have been
resolved, and the program has been assessed as adequate to support TEF operations
(DOE O 435.1C, SRID).
Section 84
7. The TEF Project Plan for verifying the adequacy and integrity of the structural
radiation shielding is adequate (10 CFR 835, TEF contract commitment).
8. The Site Contractor demonstrates adequate preparation to implement the project plan
for verification of the adequacy and integrity of the structural shielding:
• Adequate personnel are assigned and trained to implement the Plan;
• Maps and survey points are prepared. Survey points have been identified and
marked. Adequate survey equipment is available and calibrated;
• Operations staff and management are adequately trained on the details of the
program, including operational methodology, hold points, limits, and expected
outcomes (DOE Order 5480.19, 2S Manual).
APPROACH
Document Review:
• TEF Contractor ORR (CORR) final report sections concerning this functional area.
• Site Contractor assessment records associated with the radiation protection program,
material packaging and transportation programs, radioactive waste management
programs, and the structural shielding test program as they apply to TEF operations
and activities.
DOE-STD-3006-2010
3-6
• Site Contractor Manual, Radiation Protection Program Plan
• TEF RWPs
• Work packages related to TEF activities for which radiological controls are
appropriate
• DSA
• TSRs
• Contamination Control Plan
• ALARA review documentation
• Bioassay plans and results
• Routine assessments and oversight of RadCon program implementation in support of
TEF
• TEF radiation protection program equipment calibration data
• TEF shielding verification program plan, including implementing procedures and
documentation; checklists, grids, and training documentation.
• P&T plans and procedures for movement of TPBARs from K Area to TEF
• Site Contractor P&T program documentation in support of TEF
• Site Contractor Radioactive Waste Management Program documentation in support
of TEF
Interviews:
• TEF RadCon lead
• TEF Facility Manager
• P&T Manager responsible for TEF
• TEF Work Control Lead
• Work planners who support TEF
• Test Engineer responsible for shielding integrity test
• Selected TEF operational and testing personnel
Observations:
• TEF operational demonstrations
• Operational demonstration of packaging and transportation of TPBARs from K Area
storage to the TEF TPBAR storage area
• RadCon equipment calibration procedures
• Boundary Control Stations
• Routine and special radiation and contamination surveys
DOE-STD-3006-2010
3-7
EMERGENCY MANAGEMENT (EM)
OBJECTIVE
EM.1: The Site Contractor Emergency Management Program has been updated to
include activities involving the Tritium Extraction Facility (TEF) within the requirements
of the safety basis documentation. Adequate facilities and equipment are available to
ensure that emergency management activities in support of TEF can be performed as
required. Adequate numbers of emergency management personnel are assigned and
trained to support emergency operations. An Emergency Drill and Exercise Program,
including program records, has been established, implemented, and demonstrated during
the Contractor Operational Readiness Review (CORR) (Core Requirements 1, 10).
CRITERIA
1. Site Contractor, Savannah River Site Office (SRSO), Site Emergency Response
Procedures, checklists, and EALs have been updated to reflect TEF operations (DOE
O 151.1C, DOE G 151.1-1A).
2. Sitewide emergency training and emergency exercises demonstrate adequate
capability to respond to emergency events at TEF (DOE O 151.1C).
Section 85
3. The Emergency Management Program has adequate numbers of trained personnel
and adequate equipment to respond and manage emergency events at TEF (DOE O
151.1C).
4. The Site Contractor Emergency Management Program has had periodic assessments
and reviews by internal and independent groups. Issues that were identified were
tracked to completion and formally resolved (DOE O 151.1C).
5. The Emergency Planning Hazards Assessment (EPHA) has been updated to reflect
TEF. (DOE O 151.1C)
APPROACH
Document Review:
• TEF CORR final report sections associated with emergency management and
emergency exercises
• EM Organization Program Description
• DOE O 151.1C, Comprehensive Emergency System Management
• DOE G 151.1-1A, Emergency Management Fundamentals and the Operational
Emergency Base Program
• Approved TEF EPHA and Emergency Plan
• TEF Emergency Plan Implementing Procedures
• TEF Emergency management checklists, Emergency Action Levels (EALs),
accountability records, and similar emergency response documents
• Site emergency management procedures that include TEF
• Emergency exercise response reports and records
DOE-STD-3006-2010
3-8
• Assessment Reports and issues management records for emergency management
Interviews
• TEF Facility Manager
• TEF Supervisor and workers/operators
• Emergency Preparedness Functional Manager with TEF responsibilities
Observations
• TEF-related Emergency Exercise (may occur during CORR)
• TEF shift operations and shift turnover with emphasis on consideration of emergency
preparedness.
• Shift turnover at Emergency Response Center with responsibility for TEF
DOE-STD-3006-2010
3-9
OPERATIONS (OP)
OBJECTIVE
OP.1: The formality and discipline of operations at the Tritium Extraction Facility (TEF)
for operations and support personnel are adequate to conduct work safely, and programs
are implemented to maintain this formality and discipline. Approval and accomplishment
of work, including operations, is accomplished with a satisfactory level of formality and
controls, including line management responsibility for safety, plan of the day, procedures,
job-related briefings, worker involvement, and Facility Manager control of all work
within the facility for which he or she is responsible.
Sufficient numbers of qualified personnel are available to conduct and support
operations.
The level of knowledge of managers, operations, and operations support personnel is
adequate based on reviews of examinations and examination results, observation of
operations, and interviews with managers operating and operations support personnel
(Core Requirements 1, 4, 6, 13, and 15).
CRITERIA
1. TEF has a DOE-approved Conduct of Operations (COO) Matrix that has been fully
and effectively implemented (DOE Order 5480.19).
2. Performance of conduct of operations is observed to be adequate (i.e., log keeping,
shift turnover, timely orders, equipment labeling, operational formality, review of
surveillance) (DOE Order 5480.19, Site Contractor Manual).
3. A structured assessment program of implementation of COO is planned and
accomplished, documented, corrective actions established and tracked to completion
(DOE P 450.4, DOE O 226.1A, 10 CFR 830.120).
4. Conduct of Operations commitments from the Technical Safety Requirements (TSRs)
have been effectively implemented (TSRs, DOE Order 5480.19).
5. Workers follow procedures, work control documents, and other implementing
Section 86
methods. When procedures cannot be followed, work is stopped until they are
corrected (DOE P 450.4, DOE Order 5480.19, Site Contractor Manual).
6. Sufficient numbers of trained and qualified personnel are available to meet minimum
staffing requirements and support operations (Documented Safety Analysis (DSA)
and TSRs, DOE Order 5480.20A).
7. The level of knowledge of managers, operations, and operations support personnel
associated with TEF operations is adequate to permit safe operations (This criterion
DOE-STD-3006-2010
3-10
will also be evaluated by other functional areas but documented in OP.1) (DOE Order
5480.19, Chapter XIII, DOE Order 5480.20A, Chapters 1-5).
APPROACH
Document Review:
• TEF Contractor Operational Readiness Review (CORR) final report sections
associated with the adequacy of the formality of operations
• Field Element-approved Conduct of Operations Applicability Matrix that includes
TEF operations
• TEF implementing processes and procedures for each applicable element of conduct
of operations
• ConOps management assessment results
• Operational documentation associated with conduct of operations, such as logs,
checklists, shift turnover records, daily orders, and standing orders
• Training and qualification records, including examination results as necessary to
verify an adequate number of personnel and satisfactory levels of knowledge
• SRSO operational awareness documentation associated with formality of operations.
Interviews
• TEF Facility Manager
• TEF Field operational supervisors
• Selected functional support staff assigned to support TEF activities
• Craft personnel who support TEF
• TEF Facility Representative
Performance Observations
• TEF operational demonstrations, including preshift briefings and post-activity
debriefs
• Observation of emergency and operational drills
• Routine facility operations, including shift turnover and surveillance activities
• TEF facility walkdown
DOE-STD-3006-2010
3-11
OPERATIONS (OP)
OBJECTIVE
OP.2: Adequate and accurate procedures and safety limits are in place for operating the
Tritium Extraction Facility (TEF) process systems and utility systems. The procedures
include necessary revisions for all modifications that have been made to the facility.
Facility processes ensure that only the most current revision to each procedure is in use
(Core Requirement 9).
CRITERIA
1. There are adequate and correct procedures, processes, and other work control
documents in place to implement the applicable elements of DOE Order 5480.19.
(DOE Order 5480.19, Chapter XVI, Contractor Requirements Document (CRD) in
DOE O 433.1A, 10 CFR 830.120).
2. Site Contractor procedure development processes require that procedures that direct
or guide TEF operations and operations support are developed and verified to be
accurate prior to use. Adequate training is required prior to use to ensure personnel
understand and can follow the procedures (DOE Order 5480.19; DOE O 433.1A).
3. A structured assessment program of implementation of COO is planned and
accomplished, documented, corrective actions established and tracked to completion
(evaluation in conjunction with OP.1) (DOE Order 5480.19, DOE P 450.4, DOE O
226.1A).
4. Site Contractor processes require that procedures be updated and verified whenever
facilities or requirements to which the procedure applies changes (DOE O 433.1A, 10
CFR 830.120, DOE Order 5480.19).
5. A process is in place to maintain configuration control to ensure only the most current
Section 87
document is in use. (DOE Order 5480.19, DOE O 433.1A, 10 CFR 830.120).
6. Workers follow procedures, work control documents and other implementing
methods. When procedures cannot be followed, work is stopped until they are
corrected (DOE Order 5480.19, Site Contractor Manual).
APPROACH
Document Review:
• TEF Contractor Operational Readiness Review (CORR) final report sections
concerning procedure development, use, and control.
• Site-Office approved TEF Conduct of Operations Applicability Matrix
• Selected TEF operational, surveillance, and maintenance procedures, preferably
incident to use in the facility
• Site Contractor procedure development and maintenance process documents
DOE-STD-3006-2010
3-12
• Site Contractor Manual
• ConOps Management Assessment
• Training records associated development and use of operational procedure.
documents as necessary
• Operational drill and upset program records including record of accomplishment,
scenarios, and post drill critiques and lessons learned.
• SRSO operational awareness and oversight records that reflect awareness of TEF
procedure development and use.
Interviews:
• TEF Facility Managers
• TEF Field Supervisors
• Selected functional support staff who support TEF operations
• Craft personnel who work at or in support of TEF
• TEF Facility Representative
Observations:
• TEF operational demonstrations
• TEF maintenance and surveillance procedures
• TEF procedure development, including field verification and validation activities
• Observation of emergency and operational drills
• Routine facility operations, including shift turnover and surveillance activities
DOE-STD-3006-2010
3-13
OPERATIONS – STARTUP PLAN (OP)
OBJECTIVE
OP.3: An adequate startup or restart program has been developed for the Tritium
Extraction Facility (TEF) that includes plans for graded operations and testing after
startup or resumption to simultaneously confirm operability of equipment, the viability of
procedures, and the performance and knowledge of the operators.
The plans should indicate validation processes for equipment, procedures, and operators
after startup or resumption of operations including any required restrictions and
additional oversight.
Compensatory measures required during the approach to full operations are described
(Core Requirement 11).
CRITERIA
1. The Startup Plan (SUP) has been developed and approved (DOE O 425.1D, DOE-
STD-3006-2010).
2. The SUP reflects deliberate, controlled actions, including criteria for escalation and
exit from the Plan requirements (DOE O 425.1D, DOE-STD-3006-2010).
3. Management oversight has been specifically required in the Plan. Specific
expectations for management oversight are defined. Hold points are specified. (DOE
O 425.1D, DOE-STD-3006-2010).
4. Compensatory measures are defined and implemented with provisions for phase-out
as confidence is gained (DOE O 425.1D, DOE-STD-3006-2008).
5. Required documentation is identified to demonstrate effective implementation of the
program (DOE O 425.1D, DOE-STD-3006-2008).
APPROACH
Document Review:
• TEF Contractor Operational Readiness Review (CORR) final report discussion of the
adequacy and implementation of the SUP
• DOE O 425.1D, Startup and Restart of Nuclear Facilities
• DOE-STD-3006-2010, Planning and Conduct of Operational Readiness Reviews
(ORR)
• Site Contractor Startup Plan for TEF startup
• Implementing processes and documentation for SUP, such as guidance for
Section 88
compensatory measures, records of oversight and monitoring, planning sequence
documentation, and training records
Interviews:
DOE-STD-3006-2010
3-14
• TEF Facility Manager
• TEF Operations Supervisors
• Identified participants in TEF SUP
• TEF Facility Representative
Observations:
Observe implementation of elements of SUP during operational demonstrations,
including performance of management oversight and verification of specified
compensatory measures
DOE-STD-3006-2010
3-15
FIELD ELEMENT (FIELD ELEMENT)
OBJECTIVE
FIELD ELEMENT.1: Field Element programs that provide oversight for the Facility,
such as Project Management, Facility Representatives (FRs), Authorization Basis (AB),
Safety System Oversight (SSO), Safety Subject Matter Experts (SMEs), Occurrence
Reporting, Contractor Assessment (CA), Issues Management, and Quality Assurance
(QA) are adequate (Core Requirement 17).
CRITERIA
1. Required Field Element management, oversight, and assessment programs important
to nuclear safety activities specific to Facility operations such as facility readiness and
authorization, program management, nuclear safety, fire protection, emergency
management, radiological protection, occupational safety and industrial hygiene,
quality assurance, occurrence reporting, contractor assessment, and issues
management are adequately defined, effectively integrated into existing Field
Element programs and are satisfactorily implemented (DOE O 231.1A Chg 1, DOE O
226.1A, DOE O 420.1B, DOE O 413.3A, DOE O 433.1A, DOE Order 5480.20A, 10
CFR 830, Field Element Functions, Responsibilities, and Authorities Manual
(FRAM)).
2. Field Element oversight processes include evaluation of the adequacy of
implementation of the various Safety Management Programs defined in the Facility
Basis for Interim Operation (BIO), Technical Safety Requirements (TSRs), and
Facility requirements management (DOE P 450. 4; DOE O 226.1A).
3. Field Element validation of readiness, including the validation of finding closure
actions and readiness to oversee Facility operations, is adequate and is reflected in the
Field Element endorsement to the contractor Readiness to Proceed Memorandum
(DOE O 425.1D).
APPROACH
Requirements:
• DOE P 411.1, Safety Management Functions, Responsibilities, and Authorities Policy
• DOE O 231.1A Chg 1, Environment, Safety and Health Reporting
• DOE O 226.1A, Implementation of Department of Energy Oversight Policy
• DOE O 420.1B, Facility Safety
• DOE O 413.3A, Program and Project Management for the Acquisition of Capital
Assets
• DOE O 433.1A, Maintenance Management Program for DOE Nuclear Facilities
• DOE Order 5480.20A, Chg 1, Personnel Selection, Qualification, and Training
Requirements for DOE Nuclear Facilities
• 10 CFR 830, Nuclear Safety Management
• DOE P 450.4, Safety Management System Policy
DOE-STD-3006-2010
3-16
• DOE 425.1D, Startup and Restart of Nuclear Facilities
• DOE O 360.1B, Federal Employee Training
Record Review:
• Field Element process procedures and management documents that define the Field
Element oversight program and facility authorization requirements for Facility
operations
• Recently completed program self-assessments for the Facility Representative
Program and other Facility oversight programs
• Field Element’s validation of the Project Execution Plan and project deliverables
• Senior Technical Safety Managers, FRs, Authorization Basis, SSO, safety SMEs, and
Section 89
occurrence reporting training and qualification program documentation and records
• Field Element assessment reports and surveillance oversight plans for Facility
contractor assessments
• Field Element organization chart
• Field Element Safety Evaluation Report approving the Facility BIO and TSRs
• Field Element Facility readiness validation reports and documentation
• Field Element line oversight and analysis evaluation reports
• Field Element fire protection oversight assessments of fire protection programs in
support of Facility
• Field Element emergency management procedures that include Facility
• Field Element operational awareness documentation associated with formality of
operations
• Field Element oversight records associated with requirements management for
Facility
Interviews:
• Field Element FRs assigned to Facility and associated support facilities
• Field Element Safety System Oversight engineer assigned to Facility safety system
oversight
• Field Element Program Managers assigned to Facility as a GPP
• Authorization Basis review personnel who prepared the SER for the facility
• Personnel who oversee the Occurrence Reporting, issues management/operational
awareness programs for Facility Operations
• Field Element Technical Qualification Program Manager
• Field Element SMEs with Facility responsibilities (e.g. Radiological Protection
Program, Quality Assurance Operations and Startup, Fire Protection, Criticality
Safety, Occupational and Industrial Safety and Hygiene)
Observations:
• Facility Representative, SSO engineer, and subject matter expert field activities at
Facility, including a facility walkdown and a facility surveillance or assessment, as
scheduled
• Determine Field Element personnel’s understanding of Facility operations,
specifically, operations layout, radiologically controlled areas, process and safety
DOE-STD-3006-2010
3-17
system operations, normal operator routines, abnormal conditions response,
emergency and life safety equipment, and backshift activities
DOE-STD-3006-2010
3-18
FIELD ELEMENT.2
OBJECTIVE
FIELD ELEMENT.2: The technical and managerial qualifications and competence of
those personnel at the DOE field organization and at DOE Headquarters assigned
responsibilities for providing direction and guidance to the contractor and those assigned
oversight responsibilities within the scope of the RR, including the Facility
Representatives, are commensurate with the assigned responsibilities (Core
Requirement 16).
CRITERIA
1. Qualification of Field Element personnel with oversight responsibilities specific to
Facility operations, such as the Field Element Senior Technical Safety Managers,
Facility Representatives, Authorization Basis Specialists, Safety System Oversight
Engineers, and safety Subject Matter Experts are documented by formal training and
qualification requirements, are complete, and are adequate to address the hazards
identified with Facility operations and the required safety controls (DOE O 360.1B,
DOE-STD-1063-2000, 10 CFR 830).
2. The demonstrated level of understanding of the systems, hazards, and controls by
Field Element personnel with responsibilities specific for verifying readiness and
authorizing Facility operations, such as Field Element Senior Technical Safety
Managers, Facility Representatives, Authorization Basis Specialists, Safety System
Oversight Engineers, and safety Subject Matter Experts is adequate (DOE-STD-1063-
2000, DOE O 226.1A, DOE O 420.1B, DOE O 425.1D, 10 CFR 830).
Section 90
APPROACH
Requirements:
• DOE P 411.1, Safety Management Functions, Responsibilities, and Authorities Policy
• DOE O 420.1B, Facility Safety
• 10 CFR 830, Nuclear Safety Management
• DOE P 450.4; Safety Management System Policy
• DOE O 360.1B, Federal Employee Training
Record Review:
• Field Element process procedures and management documents that define the Field
Element oversight program and facility authorization requirements for Facility
operations
• Recently completed program self-assessments for the Facility Representative
Program and other Facility oversight programs
• Senior Technical Safety Managers, Facility Representative, Authorization Basis,
Safety System Oversight, safety Subject Matter Experts, and occurrence reporting
training and qualification program documentation and records
DOE-STD-3006-2010
3-19
• Field Element assessment reports and surveillance oversight plans for Facility
contractor assessments
Interviews:
• Field Element personnel assigned to oversee Facility operations to determine their
understanding of operations, safety envelope, past incidents and occurrences, conduct
of operations principles, and stop work authority relating to Facility operations.
Personnel include:
• Field Element Facility Representative(s) assigned to Facility and associated support
facilities.
• Field Element Safety System Oversight engineer assigned to Facility safety system
oversight.
• Authorization Basis review personnel who prepared the SER for the Facility.
• Personnel who oversee the Occurrence Reporting, issues management/operational
awareness programs for Facility Operations.
• Field Element Technical Qualification Program Manager
• Field Element safety Subject Matter Experts with Facility responsibilities (e. g.
Radiological Protection Program, Quality Assurance Operations/Startup, Fire
Protection, Criticality Safety, Occupational and Industrial Safety and Hygiene
(OISH), etc. )
Observations:
• Facility Representative, Safety System Oversight engineer, and subject matter expert
field activities at Facility, including a facility walkdown and a facility surveillance or
assessment, as scheduled
• Determine Field Element personnel’s understanding of Facility operations,
specifically, operations layout, radiologically controlled areas, process and safety
system operations, normal operator routines, abnormal conditions response,
emergency and life safety equipment, and backshift activities
DOE-STD-3006-2010
3-20
SAFETY BASIS (SB)
OBJECTIVE
SB.1: Facility safety documentation (normally Documented Safety Analyses (DSAs) and
Technical Safety Requirements (TSRs)) is in place that describes the safety envelope of
the facility. The safety documentation should characterize the hazards/risks associated
with the facility and should identify preventive and mitigating measures (systems,
procedures, administrative controls) that protect workers and the public from those
hazards/risks. Facility safety documentation is approved and has been implemented.
Implementation of facility safety documentation has been verified and is current. Safety
structures, systems, and components (SSCs) and any SACs are defined. A system to
maintain control over facility design with emphasis on Vital Safety Systems (VSSs) is
established. Procedures for maintaining the safety documentation provide for required
updates. A DOE-approved Unreviewed Safety Question (USQ) procedure has been
effectively implemented. Required environmental permits have been approved and
implemented (Core Requirement 6).
Section 91
CRITERIA
1. A DSA and TSRs have been developed by the Site Contractor, approved by the Field
Element, and implemented to reflect the Facilities and Operations (10 CFR 830.200).
2. The safety documentation (DSA, TSRs, and Safety Evaluation Report (SER))
consistently and properly addresses appropriate hazards and risks, necessary controls,
and safety systems associated with Facility Operations necessary to protect the public,
workers, and the environment from the safety and health hazards posed by the facility
(10 CFR 830.200, Site Contractor Manual).
3. The DSA and TSRs are consistent with the physical facility configuration, including
all modifications. The equipment and systems are present as described and credited,
and the requirements can be accomplished (10 CFR 830.202; Site Contractor
Manual).
4. Requirements, assumptions, commitments, and controls in the DSA and TSRs
addenda have been implemented into Facility processes and procedures and verified.
The relevant portions of the Site and Facility DSA and TSRs that apply are clear and
are implemented into Facility procedures and processes. (10 CFR 830.201, DSA,
TSRs, Site Contractor Manual).
5. The Facility has been included within the DOE-approved USQ procedure with
adequate numbers of qualified personnel to ensure that the authorization basis
remains accurate. The USQ program is effectively implemented. Field Element and
Site Contractor procedures and processes for DSA annual updates are effective (10
CFR 830.203, Site Contractor Manual).
DOE-STD-3006-2010
3-21
6. Environmental permits required for Facility operations have been obtained and
implemented, and processes are in place to maintain them current (Environmental
regulations such as Resource Conservation and Recovery Act (RCRA), Toxic
Substances Control Act (TSCA), Clean Air Act, and Clean Water Act).
APPROACH
Note: Some of the specific aspects of this review approach may be integrated with
Operations and observed by the Operations team members. In those cases, the
conclusions will be noted in the assessment form for this CRAD with the specific details
in the Assessment Form of the team member who actually conducted the review.
Note: A vertical slice of at least two safety-related functions should be subject to
comprehensive evaluation, from the identified hazard through implementation of the
selected control. In addition, in conjunction with the Maintenance functional area, at
least two SSCs will be subject to a vertical slice, from determination of the safety
function, required surveillances and calibrations, development of the TSRs and
subsequent procedures, and the records of accomplishment determining that the SSCs
were operable. If the selected safety functions involve SACs, those also should be subject
to the vertical slice approach to ensure they are appropriate and adequately
implemented.
Record Review:
• Contractor Operational Readiness Review final report sections associated with the
safety basis
• Facility DSAs, TSRs, permits, and other safety basis documents to assess whether the
safety basis adequately includes appropriate hazards and risks associated with
operations and associated activities
• Related permits, including implementation flowdown and permit maintenance
processes
• Facility SER, including any Conditions of Approval
• DSA and TSR implementation flowdown database to confirm implementation of all
commitments, assumptions, requirements, and controls.
• Sample of implementing mechanisms for accuracy and completeness of
Section 92
implementations
• Process and procedures to confirm the DSA and TSRs are subjected to the annual
review and revision process
• USQ program documentation for adequacy
• Completed USQ screens and evaluations for adequacy and accuracy
• Training and qualification of designated USQ screeners and evaluators
• Criticality safety analysis
Interviews:
• Nuclear safety and engineering personnel associated with development and
maintenance of the safety basis documentation
• Facility Managers
• USQ Determination evaluators
DOE-STD-3006-2010
3-22
• Criticality Safety Manager
• Facility Representatives
• Safety Basis Managers
Observations:
• During operations, observe evidence of implementation of the controls and
requirements from the DSA and TSRs and required environmental permits
• Observe selected scheduled surveillances
DOE-STD-3006-2010
3-23
CRAD References
DOE-STD-1027-92 Guidance on Preliminary Hazard Classification
and Accident Analysis Techniques for Compliance
with DOE Order 5480.23, Safety Analysis Reports
DOE-STD-1063-2006 Facility Representatives
DOE-STD-1073-2003 Operational Configuration Management Program
DOE-STD-1186-2004 Specific Administrative Controls
DOE O 151.1C Comprehensive Emergency Management System
DOE O 226.1A Implementation of Department of Energy Oversight
Policy
DOE O 231.1A Environment, Safety and Health Reporting
DOE O 420.1B Facility Safety
DOE O 425.1D Startup and Restart of Nuclear Facilities
DOE O 430.1B Real Property Asset Management
DOE O 433.1A Maintenance Management Program for DOE
Nuclear Facilities
DOE O 440.1B Worker Protection Management for DOE
(including the National Nuclear Security
Administration) Federal Employees
DOE O 442.1A Department of Energy Employee Concerns
Program
DOE P 450.4 Safety Management System Policy
DOE Order 5480.19 Conduct of Operations Requirements for DOE
Facilities
DOE Order 5480.20A Personnel Selection, Qualification, and Training
Requirements for DOE Nuclear Facilities
10 CFR Part 830 Subpart A Quality Assurance Requirements
10 CFR Part 830 Subpart B Safety Basis Requirements
10 CFR Part 835 Occupational Radiation Protection
10 CFR Part 851 Worker Safety and Health Program
Team Member Qualifications Documentation
DOE O 425.1D specifies the areas of qualification which is required for each RR team
member. The record of the RR must include evidence of each team member’s
qualification. In addition, the Team Leader is responsible for selecting the team based on
the technical and assessment qualifications of each prospective member. The specific
requirements described in sections 7.5 and 7.6 include:
• Technical knowledge of the assigned functional area,
• Knowledge of evaluation processes and methods,
• Facility-specific information, and
DOE-STD-3006-2010
3-24
• Independence.
The attached form has been developed both to assist the Team Leader in his selection
process as well as to provide a consistent, consolidated record of the team qualifications
for inclusion in the RR record. While the use of the form is optional, the information it
requires should be available in the RR record and should be sufficiently persuasive that
the individual team member satisfies each of the four requirements noted above for
participating in the RR.
Section 93
The form is intended to summarize the relevant factors that qualify the individual to
assess the Core Requirement(s) (CR) assigned, not provide the individual’s complete
resume. It is appropriate that the team member’s resume be attached. In addition, it is
recommended that a required reading program be utilized to ensure team member
familiarity with site and facility documentation such as procedures and the documents
that comprise the facility safety basis. The completed required reading record sheets are
attached to the form to fulfill the facility familiarization qualification requirement. In
addition, more detailed information, such as site visits, specialized site-specific training,
and presentations, is recorded on the summary form.
DOE O 425.1D requires that each CR be assessed by a qualified team member. It is
therefore necessary that the compilation of team member qualification summaries include
each CR within the scope of the RR described in the approved POA.
The Basis for Acceptable Independence section is to include information demonstrating
that the chosen team member meets the criteria for independence specified in DOE O
425.1D and this Standard. In essence, the requirement is that the individual cannot have
been responsible for the work he or she is to review, either as a worker or supervisor, and
that he or she cannot be a member of the direct line management for the facility.
DOE-STD-3006-2010
3-25
TEAM MEMBER QUALIFICATION SUMMARY (Form)
Name:
Objectives Assigned:
Employer/Normal Work Assignment:
Summary of Technical Qualifications: (Bullet format please, no narrative)
Summary of Assessment/RR/Inspection Qualifications: (Bullet format please, no
narrative)
Basis for Acceptable Independence:
Summary of Facility Familiarization:
Required Reading
Date/
Initials
• DSA, XYZ Sections in Chap X ...........................................................................
• DOE Plan of Action .............................................................................................
• DOE Implementation Plan ...................................................................................
• Readiness Standard: Writer’s Guide (Appendix 3) .............................................
• TSRs for XYZ Operations ...................................................................................
• Training Study Guide for facility/activity ............................................................
Training
• Familiarization briefing .......................................................................................
• Rad Worker I Training/Qualification ...................................................................
• Facility/Activity Access Training ........................................................................
• General Employee Training .................................................................................
• Tour, XYZ Facility and Operating Areas ...........................................................
Qualified
Team Leader Signature:
DOE-STD-3006-2010
3-26
Assessment Form (FORM 1)
Form 1s are used to document the methods and actions taken by a team member in the
criteria evaluation process. Each Form 1 covers a specific objective and lists the means
the team member used to measure the site’s performance relative to the objective
provided in the CRAD. The Form should be complete enough to allow the reader to
follow the inspection logic and means utilized to verify the facility’s performance with
respect to the criteria and to thereby validate the completeness and adequacy of the RR.
The approach used should be what the CRAD called for. If for some reason the approach
used does not exactly match the approach described in the CRAD, the reason should be
documented.
Section 94
Functional Area: The functional area to which the CRAD is assigned.
CRAD Identifier/Title: Identifies the CRAD or portion of the CRAD that the
Appraisal Form supports.
Date: Indicates the date on which the Form is completed and ultimately signed.
Personnel Contacted/Positions: The individuals who are interviewed should be listed
by title.
Records and Other Documents Reviewed: The documents should be listed in bullet
format.
Observations/Evolutions: List evolutions/observations with location (e.g., building)
and specific facilities visited in bullet form.
Discussion of results: Provide a discussion of the performance against the criteria.
Each criterion should be discussed separately so that it is clear why the criterion was
or was not met.
Conclusion: Provide a conclusion as to whether the objective has been met, and if not
met, reference applicable Form 2s. It is possible for individual criteria to be not met
and findings developed while still considering the overall objective met. Similarly, it
is appropriate to conclude that a criterion was met even if findings are identified that
relate to the criterion. The professional judgment of the team member, Team Leader,
and Senior Advisor will come into play to determine whether criteria and objectives
are met. This section of the Form 1 provides the basis for the RR final report and
conclusions as to whether the facility has achieved readiness to start nuclear
operations. This section should be a standalone statement that describes in detail
whether or not the objective was met and why. It is anticipated that the wording in
this section can be transcribed directly into the report within the functional area
summary.
Inspected by: The team member who conducted the evaluation signs where indicated.
DOE-STD-3006-2010
3-27
Approved by: The Team Leader signs the form after all changes have been
incorporated. His or her signature indicates that the Form is final.
Deficiency Form (FORM 2)
The Form 2 is used to document the findings identified during the evaluation process. A
separate Form 2 should be generated for each finding related to a particular CR. For
instance, in reviewing a CRAD or portion of a CRAD, a team member generates a single
Form 1 that describes the methods utilized in the investigation. If, for example, three
findings are discovered, the inspector would then generate three Form 2s to detail each
deficiency. A single Form 2 may be used to identify a generic problem for which a
number of individual examples are listed. Clear communication is the objective and the
specific number of Form 2s necessary to detail findings is at the discretion of the team
member and Team Leader.
Proper completion of Form 2s takes a significant amount of time. During the RR, time
should be set aside daily to complete the discussion section of the Form 2s. Experience
has shown that it is easier to produce a quality write-up the day of the inspection rather
than trying to reconstruct events at a later date. There are daily meetings between the
team members and Team Leader to discuss progress and results. Team members should
provide the Team Leader with essentially complete, draft Form 2 write-ups from
inspections conducted that day or at the beginning of the following day. This allows the
Team Leader to present to site management a daily briefing of emerging issues. Draft
Form 2s should be left with the site points of contact to facilitate the validation (i.e.,
factual accuracy) process. Findings should be documented on a Form 2 as soon as there
is reasonable evidence to substantiate a finding. The process for development of a
corrective action plan including an evaluation of the basic cause and extent of conditions,
is required even if the facility management has resolved the immediate symptoms that led
to the finding. The following is some detailed guidance for writing Form 2s that are
based on lessons learned from previous RRs.
Section 95
The extent to which the final report reflects actual readiness conditions at the facility
fundamentally depends upon the quality of the Form 2s completed by the individual team
members.
Functional Area: The functional area to which the CRAD has been assigned.
CRAD Identifier/Title: Identifies the CRAD or portion of the CRAD that the
Appraisal Form supports.
Date: Indicates the date on which the Form is completed and ultimately signed.
ID #: The team member uses a unique identifying number to correlate the finding
(Form 2) and disposition document (Form 3). Once assigned, this number should
appear on all revisions and updates.
DOE-STD-3006-2010
3-28
Requirement: The applicable portion of the CRAD should be quoted to clearly state
the standard of performance that was judged to be deficient. The requirement may
also include specific quotes from a contract requirement or an implementing
mechanism to which the facility shall comply.
References: All applicable references, such as DOE Orders, CFRs, and site
implementing documents should be listed. The reference should be specific down to
the section to allow for easy referral.
Issue: A title for the finding that can be used to identify the finding verbally, much as
the ID # is used to identify the finding numerically. The appropriate block should be
marked to indicate whether the issue is a finding (deficiency) or an observation,
which, if implemented, will lead to excellence of performance.
Discussion: The key to preparing quality Form 2s is staying focused on the CR and
criteria. Avoid speculation and stick to specifics when describing observed strengths
and weaknesses. Sweeping generalities based on a small sample should be avoided.
However, drawing conclusions that assert programmatic deficiencies based upon
multiple observed inadequacies or weaknesses are valid. Team members should avoid
superlatives of the type: “…is the worst,” or … is the best.” Again, the key is to stay
focused on whether the CR is being met as measured by the criteria. Following are a
few sample Form 2 Discussion sections demonstrating some desirable and some
undesirable traits.
1. Review of training and qualification issue; Required Reading Program
(a) Desirable: specific, objective, measured traits
Implementation of the Required Reading Program was examined.
Twenty-five items in the program were tracked to determine if the 16
qualified Stationary Operating Engineers (SOEs) have signed off as
having read the required documents. Over half the required reading items
checked were found to be deficient; that is, over half of the 400 (16 x 25)
items checked were not documented as complete. In addition, some
significant items from the required reading items were provided to RR
team members to sample SOE retention of the material covered in the
readings. The retention of the key points in these required reading items
was poor. Of eight SOEs interviewed on three items, over half produced
unsatisfactory responses.
(b) Not desirable: extreme, speculative, too general, inappropriate
The Required Reading Program was examined. It was determined to be
one of the worst programs this reviewer has encountered. Many of the
operators had not done the reading and their attitude was unacceptable.
Management said they had a procedure for the program, but I couldn’t
locate it. The RR interviewers asked some of the SOEs about items in
DOE-STD-3006-2010
3-29
their required reading. Their responses were unsatisfactory. This area
needs work.
Section 96
2. Review of DSA/TSR implementation; maintenance of pressure differential in
glove boxes for personnel protection
(a) Desirable: objective, analytical, supported by background detail
Chapter XXX of the DSA requires “….absolute pressure in a glove box in
operation with radioactive material in it shall be maintained below the
pressure of the surrounding area such that any air flow shall be from the
surrounding area into the glove box. This is to prevent the escape of
airborne or potentially airborne radionuclides from the glove box to the
surrounding area.” This requirement has been implemented through
Technical Safety Requirement (TSR) xxxx that requires a differential
pressure (DP) of xx inches of water to be maintained between a glove box
and its surrounding area.
The gauges installed to monitor this DP are not calibrated on a regular
basis and have not been calibrated since installation 5 years ago. These
gauges are the principal means of surveillance to ensure that the TSR is
complied with. The DP gauges are not considered safety-related
equipment by the contractor and are, therefore, not part of the calibration
program. The contractor’s position is that the gauges are informational
only and not safety-related equipment. The RR team disagrees with this
interpretation and asserts that the DP gauges are safety-related equipment
in that they provide the means to monitor a TSR and need to be reliable
and, therefore, should be part of the M&TE Calibration Program.
(b) Undesirable: confusing, argumentative, lacking in detail and background,
requirement not established.
The DP gauges installed on the glove boxes are out of calibration. I
looked at 13 of them and all were out of calibration. The contractor
maintains that they do not have to calibrate them per the DSA. We
disagree.
Finding Designation: This section defines whether the finding is a prestart
or post-start finding. The RR Team Leader, in consultation with the team
member responsible for the finding and Senior Advisor, if applicable, will
make this determination using the criteria specified in the POA.
Finding Resolution Form (FORM 3)
The Finding Resolution Form is used by site management to document the plans and
actions taken to correct findings identified during the RR and, when completed, forms the
closure certificate described in section of this Standard. A separate Form 3 should be
DOE-STD-3006-2010
3-30
generated for each finding related to a particular objective. For instance, if three findings
are discovered while reviewing a CRAD, the team member would then generate three
Form 2s to detail the deficiencies, thereby requiring that site management generate three
Form 3s to document the resolution of the findings.
Functional Area: The functional area to which the CRAD has been assigned.
CRAD Identifier/Title: Identifies the CRAD or portion of the CRAD that the
Appraisal Form supports.
ID #: This number correlates the finding (Form 2) and resolution (Form 3) documents
and should be the same number listed on the applicable Form 2.
Issue: The finding issue statement from the corresponding Form 2 is placed here.
Finding Designation: This section indicates whether the finding is a prestart or post-
start finding.
Responsible Individual: The individual who is assigned responsibility for correcting
the finding is identified in this block. The name and phone number of the person
should be provided.
Section 97
Action Plan: A description of the plan to resolve the finding, along with proposed
dates of completion, is presented in this section. A compilation of these plans taken
from all the Form 3s generated during the RR forms the basis for the Action Plan that
is submitted to the startup authorization authority for approval. Modifications to the
Action Plan made by the startup authorization need to be incorporated in the Form 3.
Due to the comprehensive expectation for the Action Plan, it may be an attachment to
the Form. The Action Plan may reflect the standard issues management process
deliverable if it meets the requirements for an Action Plan specified in DOE O
425.1D.
Resolution: A description of the actual actions taken, the reasons for concluding that
closure has been achieved, and how referenced documents support closure is provided,
along with dates of completion. This formally documents the corrective measures
used to resolve the finding. As with the Action Plan, the resolution closure package
may be an attachment to the Form. The closure package may be in accordance with
site procedures for issues management resolution if that process meets the minimum
requirements specified in DOE O 425.1D.
Certified: This block is used by management to certify that the actions specified in the
Action Plan and detailed in the resolution block have been completed. The designated
manager signs this block when he or she is satisfied that all corrective actions are
completed.
DOE-STD-3006-2010
3-31
Verified: This signature block is used by the official designated by the appointing
authority to verify management’s successful fulfillment of the corrective actions. This
signature may not be required in all cases.
DOE-STD-3006-2010
3-32
ASSESSMENT FORM
(FORM 1)
FUNCTIONAL AREA: OBJECTIVE, REV.
DATE:
OBJECTIVE MET
YES NO
OBJECTIVE: as stated in the CRAD
Criteria: as stated in the CRAD
Approach: as stated in the CRAD
Record Review: as stated in the CRAD
Interviews: as stated in the CRAD
Observations: as stated in the CRAD
Records Reviewed:
•
•
Interviews Conducted:
•
•
Observations Performed:
•
•
Discussion of Results:
Restate each criterion in the order given in the CRAD.
The discussion should include the relevant conclusion from the interviews, record
reviews, and shift performance that led to the conclusion as to whether the criterion was
met. Discussions include deficiencies and noncompliance’s and may include or refer to
findings. Whenever a deficiency supports a finding, the finding number should be
included in parentheses at the end of the sentence that summarizes the finding. At the
end of the discussion for each criterion, state whether or not the criterion was met.
Conclusion:
The Objective has/has not been met. You make a statement on each Form 1 whether or
not the Objective has (or has not) been met. Add a discussion that supports the
conclusion.
Issue(s):
Team Member:________________________
Team Leader:
DOE-STD-3006-2010
3-33
DOE-STD-3006-2010
3-34
DEFICIENCY FORM
(FORM 2)
Functional Area:
Objective No.:
Finding: Prestart:
Post-Start:
Issue No.:
Date:
ISSUE:
(The identified finding or observation) This section reads exactly (word for word) the issue
documented on the Form 1. For every issue on a Form 1, you write a Form 2.
REQUIREMENT:
REFERENCES:
DISCUSSION:
Submitted:
Team Member
Approved:
Team Leader
Date:
DOE-STD-3006-2010
3-35
FINDING RESOLUTION FORM
(Form 3)
Functional Area:
Section 98
CRAD Number/Title: ID #:
Issue:
Finding Designation:
Prestart
Post-start
Date Received:
Responsible Individual:
Phone #:
Action Plan:
a. Evaluation of root cause or systemic failure that results in the finding.
b. Specific corrective action, including completion dates and responsibilities.
c. Compensatory measures (post-start findings).
d. DOE approval (for DOE RRs only)
Resolution:
Actual actions taken and justification for difference from approved Action Plan.
Corrective Action Completion
Certified by: Date:
Verified by
Date:
DOE-STD-3006-2010
3-36
EXAMPLE FORMS 1 AND 2
The following pages contain example Forms 1 and 2 from recent RRs. In some cases, the
Forms were paraphrased. The purpose for the examples is to show the format and types
of information that is normally included. An important lesson learned is that the Team
Leader should provide example Forms 1 and 2 to the team at the beginning of the RR to
remind the team of the expected format and content, reducing rework and confusion.
Also, the Team Leader or the administrative assistant should provide draft Forms 1 to
each team member. The draft Forms should contain all of the information from the
CRAD so that the team member may immediately start to enter data into the forms
without having to format the Form or copy the information from the CRAD.
DOE-STD-3006-2010
3-37
ORR ASSESSMENT FORM 1
(NOTE THAT THIS IS A PARTIAL COPY OF THE ACTUAL FORM 1)
Functional Area:
Operations
Objective: OP.2
Date: November 2, 2006
OBJECTIVE MET
YES
NO X
OBJECTIVE
OP. 2: Adequate and correct procedures and safety limits are in place for operating the
process systems and utility systems that include revisions for modifications that have
been made to the facility. A process is in place to maintain configuration control to
ensure only the most current document is in use (CORE REQUIREMENTS 1, 4, 10, 13
and 15).
CRITERIA
1. There are adequate and correct procedures, processes, and other work control
documents in place to implement the applicable elements of DOE Order 5480.19
(DOE Order 5480.19, Chapter XVI, DOE O 433.1A CRD, 10 CFR 830.120).
2. WSRC procedure development processes require that procedures that direct or
guide TEF operations and operations support are developed and verified to be
accurate prior to use. Adequate training is required prior to use to ensure
personnel understand and can follow the procedures (DOE Order 5480.19, DOE
O 433.1A).
3. A structured assessment program of implementation of COO is planned and
accomplished, documented, corrective actions established and tracked to
completion. (Evaluation in conjunction with OP.1) (DOE Order 5480.19, DOE P
450.4, DOE O 226.1A).
4. WSRC processes require that procedures be updated and verified whenever
facilities or requirements to which the procedure applies changes (DOE O
433.1A, 10 CFR 830.120, DOE O 5480.19).
5. A process is in place to maintain configuration control to ensure only the most
current document is in use (DOE Order 5480.19, DOE O 433.1A, 10 CFR
830.120).
6. Workers follow procedures, work control documents and other implementing
methods. When procedures cannot be followed, work is stopped until they are
corrected (DOE Order 5480.19; WSRC 2S Manual).
DOE-STD-3006-2010
3-38
Records Reviewed: (IN THIS EXAMPLE, MANY RECORDS WERE NOT SHOWN)
• WSRC Memo, Bickley to Bauer, August 11, 2006, “TEF Pre-Tritium Introduction
Section 99
Glovebox Ion Chamber Operational Status”
• Standing Order TFSO-06-006-A, October 16, 2006
• Maintenance History for GB-2000 Glovebox Ion Chambers
• WSRC Contractor Operational Readiness Review Report for TEF, September 26,
2006
• WSRC Manual 2S, Conduct of Operations Manual
• WSRC 12Q, Assessment Manual
• TEF System Engineer Qualification List, September 20, 2006
• SOP 264-H-5510, PR-Evac Operations (U), Revision 1
• SOP 264-H-5510, Unloading Legal Weight Truck Cask in the Remote Handling Area
(U), Revision 3
• SOP 264-H-5503, Transfer of PES Storage/Transfer Tank Contents to 233-H,
Revision 0, SMPK.01
Interviews Conducted:
• TEF Control Room Operators (4)
• TEF Auxiliary Operators (3)
• TEF Maintenance personnel (2)
• TEF Maintenance supervisor
Observations:
• UPS-2 Monthly Battery Check
• Walk around of 264-H, Room 111
• Z-Bed Recovery manual valve lineup
• Z-Bed Recovery Train 2 operations (simulator)
• Oxygen Monitor Monthly Functional Check
• Switching Blowers on High Activity Glovebox Stripper
• Switching Blowers on Low Activity Glovebox Stripper
• Furnace Extraction (limited control room observations)
• General control room observations
DISCUSSION OF RESULTS:
1. There are adequate and correct procedures, processes, and other work control
documents in place to implement the applicable elements of DOE Order 5480.19
(DOE Order 5480.19, Chapter XVI, DOE O 433.1A CRD, 10 CFR 830.120).
Overview: A sample of the operations procedures, maintenance procedures, work
packages, and other work control documents was evaluated against applicable
requirements, and, with a few exceptions, the reviewed procedures and work control
documents could be executed as written and met applicable conduct of operations
requirements.
No significant errors in work instructions were identified in the reviewed, non-
electronic operations or maintenance procedures that prevented the procedure from
DOE-STD-3006-2010
3-39
being executed as written. During the Contractor Operational Readiness Review
(CORR), only a few such errors were noted (CORR finding 22-16/02). These errors
were corrected prior to the NNSA ORR. From a performance-based perspective, the
various mechanisms employed by TEF personnel to develop, review, validate, and
approve work control documents were effective. Among the noteworthy practices
was the use of Procedure Improvement Teams (PITs). The use of integrated teams,
including procedure writers, engineers, operators, and other subject matter experts,
provided both an efficient and (based on the quality of reviewed procedures) effective
mechanism to ensure the accuracy and quality of procedures subjected to this process.
A TEF memorandum (March 29, 2006, Bauer/Miller to Distribution) noted that this
process “delivered sufficient return-on-investment that TEF management has
requested that PIT reviews continue.” Other NNSA sites and contractors should
consider evaluating this approach for application to their procedure development
processes.
Electronic Procedures: A relatively unique aspect to TEF work control documents is
the extensive use of electronic procedures to conduct plant operations. The
procedures are run via a distributed control system and generally executed in a semi-
automatic mode. In this mode, the operator initiates the execution of each step, but
underlying control software automatically executes the step (opening valves,
changing set points, etc). The operator is then expected to verify (via examination of
available graphic indications) that the procedure step was correctly executed. TEF
administrative procedures provide a crosswalk between the execution of procedures
electronically and the conduct of operations requirements written for manual
execution of paper procedures. In general, the intended use of electronic procedures
is consistent with the intent of conduct of operations requirements in DOE Order
5480.19 or the WSRC 2S Manual.
Section 100
However, a problem with the underlying software that executes the TEF electronic
procedures led to inadvertent failure to meet the WSRC 2S Manual requirements for
procedures (OP.2-1). While executing the procedure for Z-Bed Recovery (SOP-264-
H-5303) on a simulator platform, the electronic system automatically executed three
steps in a row without providing feedback to the operator that two of the three steps
had been executed. The operator did not notice that the visual indications he had for
procedure execution indicated that the steps in question were not executed. The
software quality assurance aspects of this issue are discussed in the assessment forms
for software quality assurance (Form 1 SQA.1). From a conduct of operations
perspective, this was a deviation from the expectation of deliberate, controlled
operations.
The fact that the software may execute steps without direction from the operator is a
violation of requirements in DOE O 5480.19 and the WSRC 2S Manual for
deliberate, controlled operations (WSRC 2S Manual, Procedure 1.3, A.2). The
importance of being aware of equipment indications and treating those as real unless
proven otherwise are in Chapter II (Discussion and Guideline C.6) to DOE O 5480.19
and in Procedures 4.4 (A. 1) and 5.3 (C.1) of the WSRC 2S Manual. The
DOE-STD-3006-2010
3-40
requirement for executing procedures in the intended manner (and with a single
action per step) is in Chapter XVI of DOE O 5480.19 and Procedure 1.3 (A2, B.2) of
the WSRC 2S Manual.
A subsequent review of a furnace extraction procedure being executed in the control
room (SOP-264-H-5015) also identified cases where the electronic procedure system
was not providing visual indication (via graying out of listed steps) that procedure
steps were being executed by the underlying software, and, again, this was not
noticed by TEF control room operators. The required time stamp identifying
completion of procedure steps is not visible to the TEF operators (and thus there can
be no expectation they notice its absence), but the graying/marking of procedure steps
as complete by the interface software is noticeable to the operators. WSRC 2S
Manual, Procedure 5.3, C1 requires operators to be alert and attentive to control panel
indications and to take prompt action to determine the cause of any abnormalities.
PORTION OF WRITEUP REMOVED FOR BREVITY
The criterion was not met.
2. WSRC procedure development processes require that procedures that direct or
guide TEF operations and operations support are developed and verified to be
accurate prior to use. Adequate training is required prior to use to ensure
personnel understand and can follow the procedures (DOE Order 5480.19; DOE
O 433.1A).
The WSRC 2S Manual, chapter 1.1, provides direction and requirements for the
development and verification of WSRC procedures prior to use. Additional guidance
for TEF procedures is contained in procedures such as ADM-TRIT 6308 and ADM-
TRIT 6310. The lack of significant errors in work procedures (with the exception of
the electronic procedures issue) provides evidence of the effectiveness of WSRC
programs to develop and verify work control documents prior to use.
The criterion was met.
3. A structured assessment program of implementation of COO is planned and
accomplished, documented, corrective actions established and tracked to
completion (evaluation in conjunction with OP.1) (DOE Order 5480.19, DOE P
450.4, DOE O 226.1A).
Section 101
The assessment program for TEF is driven by the WSRC 12Q Manual and Tritium
Facilities plans for self-assessment. In addition, TEF will be subjected to assessments
by the WSRC Facility Evaluation Board. These programs and activities represent a
structured assessment program. The quality of the procedures observed and the
minimal number of problems with their execution provides a performance-based data
point on the effectiveness of the assessment programs.
The criterion was met.
DOE-STD-3006-2010
3-41
4. WSRC processes require that procedures be updated and verified whenever
facilities or requirements to which the procedure applies changes (DOE O
433.1A, 10 CFR 830.120, DOE Order 5480.19).
The WSRC Engineering Manual (E7) provides requirements for design personnel to
ensure that proposed design changes are reviewed for potential impact to various
documents, including facility and operations procedures. From a performance-based
perspective, only minor instances (such as references to out-of-date requirements
documents) were noted where a change to TEF facilities or requirements was not
reflected in TEF procedures.
The criterion was met.
5. A process is in place to maintain configuration control to ensure only the most
current document is in use (DOE Order 5480.19, DOE O 433.1A, 10 CFR
830.120).
The WSRC 2S Manual provides requirements for ensuring the most current version
of work control documents is used. There were no noted failures to execute these
requirements, and no procedures were used that were not verified as being the current
version.
The criterion was met.
6. Workers follow procedures, work control documents and other implementing
methods. When procedures cannot be followed, work is stopped until they are
corrected (DOE Order 5480.19, WSRC 2S Manual).
WSRC employees are required to follow procedures as written. WSRC work
processes require that work is stopped whenever procedures cannot be followed. In
general, operators and maintenance personnel followed this requirement.
REMAINDER OF WRITEUP ELIMINATED FOR BREVITY
The criterion was met.
CONCLUSION:
The Objective was not met.
A performance-based evaluation of the implementation of WSRC processes governing
the development and execution of procedures, processes and other work control
documents was conducted by sampling a limited set of documents and observing their
execution. Startup actions, including the use of dedicated procedure improvement teams,
were effective in producing procedures that were accurate and could be followed as
DOE-STD-3006-2010
3-42
written. No significant errors in work instructions were identified in any of the reviewed
non-electronic operations or maintenance procedures that prevented the procedure from
being executed as written. This is remarkable.
There were, however, concerns identified with adherence to appropriate conduct of
operations requirements in executing electronic procedures. A problem with the
underlying software led to abnormal execution of the operator interface to the electronic
procedures and a deviation from the expectation of deliberate, controlled operations.
Issues:
Pre-start:
OP.2-1: A problem with the underlying software that executes the TEF electronic
procedures led to inadvertent failure to meet the WSRC 2S Manual requirements for
procedures.
Section 102
Post Start:
OP.2-2: An issue raised by the Contractor Operational Readiness Review (CORR)
related to the development and implementation of activity-level work controls (finding
10-04/01) has not been resolved, and the specific corrective actions identified in the
CORR report will not address the issue completely.
Inspector: ___________________________
Team Leader: ________________________
DOE-STD-3006-2010
3-43
ORR Deficiency Form 2
Functional Area:
Operations
Objective: OP.2
Criterion 1
Pre-Start: X
Post Start
Issue No.: OP.2-1
Date: November 2, 2006
ISSUE: TEF operators did not always execute electronic procedures in a manner
consistent with the WSRC 2S Manual.
REQUIREMENT
• WSRC 2S Manual Procedure 1.3 (A.2, B.2), Procedure 4.4 (A.2), Procedure 5.3 (C.1)
REFERENCES
• DOE Order 5480.19, Conduct of Operations Requirements for DOE Facilities
• WSRC 2S Manual, Conduct of Operations Manual
• TEF Memo M&O-DPT-2006-00417, TEF Digital Electronic Procedures / Digital
Control Program Clarification, October 5, 2006
• SOP-264-H-5303, Z-bed Recovery Train 2 Operations, Revision 2
• SOP-264-H-5015, Extraction Furnace FE-100 Operations (U), Revision 5
DISCUSSION
While executing the Z-Bed Recovery procedure (SOP-264-H-5303) on a simulator
platform, the electronic system automatically executed three steps in a row (5.2.3.7,
5.2.3.8, and 5.2.3.9) without providing feedback to the operator that two of the three steps
had been executed. The operator did not notice that the visual indications he had for
procedure execution indicated that the steps in question were not executed. The software
quality assurance aspects of this issue are discussed in the Assessment Form 1 for SQA.
From a conduct of operations perspective, this was a deviation from the expectation of
deliberate, controlled operations.
The fact that the software may execute steps without direction from the operator is a
violation of requirements in DOE Order 5480.19 and the WSRC 2S Manual for
deliberate, controlled operations (WSRC 2S Manual, Procedure 1.3, A.2). The
importance of being aware of equipment indications and treating those as real unless
proven otherwise are in Chapter II (Discussion and Guideline C.6) to DOE Order
5480.19 and in Procedures 4.4 (A.1) and 5.3 (C.1) of the WSRC 2S Manual. The
requirement for executing procedures in the intended manner (and with a single action
per step) is in Chapter XVI of DOE Order 5480.19 and Procedure 1.3 (A2, B.2) of the
WSRC 2S Manual.
A subsequent review of a furnace extraction procedure being executed in the control
room (SOP-264-H-5015) also identified cases where the electronic procedure system was
not providing visual indication (via graying out of listed steps) that procedure steps were
being executed by the underlying software, and, again, this was not noticed by TEF
control room operators. The required time stamp identifying completion of procedure
DOE-STD-3006-2010
3-44
steps is not visible to the TEF operators (and thus there can be no expectation they notice
its absence), but the graying/marking of procedure steps as complete by the interface
software is noticeable to the operators. WSRC 2S Manual, Procedure 5.3, C1 requires
operators to be alert and attentive to control panel indications and to take prompt action
to determine the cause of any abnormalities.
CONCLUSION
Section 103
Notwithstanding the identified error in the software for electronic procedures, TEF
should continue its planned implementation of electronic procedures. Assuming the error
is identified and corrected (and actions are already in progress to accomplish this), there
is no reason to believe that the execution of electronic procedures is any more prone to
error than the manual execution of paper procedures. However, during the initial
implementation phase, it is important that TEF pay careful attention to the conduct of
operations implications of electronic procedure execution.
In particular, as part of its closure of the issue noted above, WSRC may wish to consider
whether additional process requirements or training are necessary to reinforce to
operators the importance of attention to detail in observing the various visual indications
provided by the electronic procedures (particularly those indications provided by the
PROCVIEW windows). In addition, it is important to screen identified software
concerns as they arise for potential implications such as their impact on the ability to
conduct deliberate, controlled operations.
Inspector: __________________________
Team Leader: ________________________
DOE-STD-3006-2010
3-45
Note this is an example of format. Many of the listed review items and much of the
write-up has been eliminated for brevity
ORR ASSESSMENT FORM 1
Functional Area:
Savannah River Site Office
Objective: SRSO.1
Date: November 3, 2006
OBJECTIVE MET
YES X NO
OBJECTIVE:
SRSO.1: Savannah River Site Office (SRSO) Programs, such as Senior Technical Safety
Manager (STSM), Facility Representative (FR), Authorization Basis, (AB), Safety
System Oversight (SSO), safety Subject Matter Experts (SMEs), Occurrence Reporting,
Contractor Assessment (CA), Issues Management, and Quality Assurance (QA) are
adequate. The technical and managerial qualifications of those personnel at SRSO who
have been assigned responsibilities for providing nuclear safety technical direction and
guidance to the M&O contractor are adequate (CRs 16 and 18).
CRITERIA:
1. Qualification of SRSO personnel with responsibilities specific to TEF operations,
such as the SRSO Senior Technical Safety Managers, Facility Representatives,
Authorization Basis Specialist, Safety System Oversight Engineer, and safety Subject
Matter Experts are documented by formal training and qualification requirements, are
complete, and are adequate to address the hazards identified with TEF operations and
the required safety controls (DOE O 360.1; DOE-STD-1063-2000, 10 CFR 830).
2. The demonstrated level of understanding of the systems, hazards, and controls by
SRSO personnel with responsibilities specific for verifying readiness and authorizing
TEF operations, such as SRSO Senior Technical Safety Managers, Facility
Representatives, Authorization Basis Specialist, Safety System Oversight Engineers,
and safety Subject Matter Experts is adequate (DOE-STD-1063-2000, DOE O 226.1,
DOE O 420.1, DOE O 425.1, 10 CFR 830).
3. Required SRSO management, oversight, and assessment programs important to
nuclear safety activities specific to TEF operations such as facility readiness and
authorization, nuclear safety, fire protection, emergency management, radiological
assistance, occurrence reporting, contractor assessment, and issues management are
adequately defined, effectively integrated into existing SRSO programs and are
satisfactorily implemented (DOE-STD-1063-2000, DOE O 231.1, DOE O 226.1,
DOE O 420.1, 10 CFR 830, FRAM).
Section 104
DOE-STD-3006-2010
3-46
APPROACH
Records Reviewed:
• SRSO Annual Workforce Analysis and Staffing Plan Report, December 21, 2005
• Report of NNSA CDNS Biennial Review and associated corrective action plans and
issues management documentation
• SRSO Safety Evaluation Report, Revision 0, approving “WSRC-SA-1-2VOL-1 & -
VOL-2, Revision 7, WSRX-SA-1-2-VOL-4, Revision 0”, and “S-TSR-H-00005,
Revision 0”
• SV-MAN-002, SRSO Safety Management FRAM, Rev. 3, Jan. 9, 2006
• SV-PRO-008, Vital Safety System Assessments, Rev. 2, Jan. 3, 2006
Interviews Conducted:
• SRSO Facility Representatives (4)
• SRSO Manager
Shift Performance Observed:
• Facility Representative Walkthroughs (4)
• SRSO Weekly Authorization Basis meeting with WSRC Authorization Basis
Manager(s), 10/23/06
• Tritium Operational Review Committee meeting, 10/25/06
• Z-Bed Recovery Manual Valve Lineup, 10/25/06
• SRSO Daily Operations Brief, 10/24/06
• TEF Shift Turnover, 10/24/06
• TEF Startup Meeting, 10/24/06
• TEF Pre-Drill Briefing, 10/25/06
DISCUSSION OF RESULTS: (For brevity, the write-ups as well as the lists above
have been truncated. This is an example of format, not necessarily content)
1. Qualification of SRSO personnel with responsibilities specific to TEF operations,
such as the SRSO Senior Technical Safety Managers, Facility Representatives,
Authorization Basis Specialist, Safety System Oversight Engineer, and safety
Subject Matter Experts are documented by formal training and qualification
requirements, are complete, and are adequate to address the hazards identified
with TEF operations and the required safety controls. (DOE O 360.1; DOE-
STD-1063-2000, 10 CFR 830)
SRSO Technical Qualification Program (TQP) records for the Senior Technical
Safety Manager (STSM), Facility Representative (FR), Nuclear Safety Specialist
DOE-STD-3006-2010
3-47
(NSS), Safety System Oversight (SSO), and Quality Assurance (QA) functional areas
were assessed. Each TQP functional area qualification is supported with a TQP
standard and qualification card. The formal training and qualification requirements
for SRSO personnel are stated in these documents. The completed qualification card
provides objective evidence documenting the accomplishment of each qualification
requirement.
Qualification records were reviewed to determine whether Tritium Extraction Facility
(TEF) related hazards, systems, and safety controls had been included. The FR
qualification records include requirements specific to the TEF. Specifically, the
requirements to describe the operation, purpose and/or function of major
components, interlocks, operational requirements, and system interrelationships were
included for TEF safety and process systems (e.g., worker protection, stack monitors,
fire suppression, breathing air, electrical distribution, distributive controls, cranes,
cooling water, remote handling and storage, target rod preparation, and furnace
extraction). The TEF-related requirements included in the SSO qualification records
are a subset of those required of the FR but are appropriately scoped to include safety
systems and the analyzed hazards for TEF. Specifically, this includes fire
suppression, glove box oxygen monitoring, tritium room air monitors, area radiation
monitors, worker protection, furnace interlock, uninterruptible power supply, glove
box stripper, and ventilation systems.
The criterion was met.
2. The demonstrated level of understanding of the systems, hazards, and controls
Section 105
by SRSO personnel with responsibilities specific for verifying readiness and
authorizing TEF operations, such as SRSO Senior Technical Safety Managers,
Facility Representatives, Authorization Basis Specialist, Safety System Oversight
Engineers, and safety Subject Matter Experts is adequate (DOE-STD-1063-2000,
DOE O 226.1, DOE O 420.1, DOE O 425.1, 10 CFR 830).
Interviews were conducted with SRSO technical safety managers, FRs, SSO, NSS,
and other subject matter experts involved in the oversight of the TEF. These
interviews consisted of a sampling of questions related to the technical oversight of
the TEF. The questions included topics such as the hazards associated with TEF
(common to tritium operations and unique to the TEF), required safety controls,
systems and programs, and their processes to oversee the contractor operations. No
knowledge deficiencies were identified.
Facility walkthroughs were conducted with each of the assigned FRs. It was evident
that the FRs are familiar with the facility layout and the current status of facility
conditions. The FRs explained field conditions, articulated pertinent details of
tritium, and remote handling processes and identified required safety systems and
their functional requirements. Their field observations demonstrated adequate
technical inquisitiveness that supports effective oversight of the TEF.
DOE-STD-3006-2010
3-48
Interviews, walkthroughs, and observations demonstrated an adequate level of
understanding of the systems, hazards, and controls by SRSO personnel with specific
responsibilities for verifying readiness and authorizing TEF operations.
The criterion was met.
3. Required SRSO management, oversight, and assessment programs important to
nuclear safety activities specific to TEF operations such as facility readiness and
authorization, nuclear safety, fire protection, emergency management,
radiological assistance, occurrence reporting, contractor assessment, and issues
management are adequately defined, effectively integrated into existing SRSO
programs and are satisfactorily implemented (DOE-STD-1063-2000, DOE O
231.1, DOE O 226.1, DOE O 420.1, 10 CFR 830, FRAM).
The current SRSO Staffing Analysis indicates staffing needs for four FRs, two SSOs,
one NSS, four STSM, two QA SMEs (one specific to Safety Software QA), and one
SME for construction management. Presently, SRSO is at these staffing levels with
the exception that there is only one SSO assigned. SRSO management indicated that
following the qualification of the NSS, the NSS will serve as an SSO and be
employed as a backup to the currently assigned SSO. Sufficient documentation exists
to demonstrate the personnel requirements to effectively oversee TEF have been
sufficiently incorporated into the SRSO’s staffing profile.
As noted by a combination of observations of SRSO management meetings and in-
field performance of assessments as well as review of completed documentation from
required Field Element assessments and reporting procedures, sufficient
documentation exists to demonstrate that the TEF has been effectively included in the
SRSO management, oversight, and assessment programs important to nuclear safety
activities.
The criterion was met.
Conclusion:
The Objective was met.
Section 106
The stated requirements of the SRSO technical qualification program, the number of
qualified SRSO TQP personnel and the level of prior experience and progress of the
remaining qualifying personnel, indicate SRSO TQP qualifications are substantially
complete, are documented by formal training and qualification requirements, and are
adequate to address the identified hazards and required safety controls related to TEF
operations. Interviews, walkthroughs, and observations of SRSO TQP personnel,
confirm an adequate level of understanding of the systems, hazards, and controls specific
for verifying readiness and authorizing TEF operations. In addition, the SRSO
demonstrated sufficient awareness of current TEF conditions, activities and planned work
to provide effective and informed technical safety oversight through the startup of the
DOE-STD-3006-2010
3-49
TEF. Observations of SRSO personnel during management meetings, in-field
performance of assessments, and a review of completed documentation from required
field Element technical and RA and reporting procedures, provide sufficient
documentation to demonstrate the TEF has been effectively included in the SRSO
management, oversight, and technical assessment processes.
Issue(s): None.
Inspector: ___________________________
Team Leader: ________________________
DOE-STD-3006-2010
3-50
FACILITY ORR ASSESSMENT FORM
(FORM 1)
FUNCTIONAL AREA:
Training and Qualification
OBJECTIVE: TQ.1
DATE: August 2, 2007
OBJECTIVE MET
YES NO
OBJECTIVE
TQ.1: The selection, training, and qualification programs for operations, operations
management, technical, and operations support personnel have been established,
documented, and implemented for the range of duties required to be performed to operate
and support Facility activities. For the training and qualification program, sufficient
numbers of qualified personnel as well as adequate facilities and equipment are available
to support Facility operations (CRs 1, 3, 4, 5, 6, and 7).
CRITERIA
1. The Site implementation processes for the T&Q Safety Management Program (SMP)
associated with Facility comply with contract requirements.
2. A training implementation matrix (TIM) has been submitted and approved by the
Field Element that includes Facility and meets the commitments within the approved
Facility BIO and TSR, including training and qualification for forklift operators (TSR
5.8).
3. Site Contractor has conducted periodic systematic evaluations of the Facility T&Q
program and found it to be effective and compliant with contract requirements (DOE
Order 5480.20A, DOE-STD-1070-94).
4. Field Element has conducted periodic systematic evaluations of the Facility T&Q
program and found it to be effective and compliant with contract requirements (DOE
Order 5480.20A, DOE-STD-1070-94).
5. Facility T&Q records including lesson plans and completed qualification records are
complete, auditable and meet the requirements of the TIM and the Contractor T&Q
program (DOE Order 5480.20A).
6. Modifications to the facility, as well as procedural and work control document
requirements have been reviewed for potential impacts on training and qualifications.
Required changes to training and qualification program documents have been
completed and implemented (DOE Order 5480.20A, DOE O 433.1A).
7. Level of knowledge of managers, operations, and operations support personnel is
adequate based on reviews of examinations, examination results, and any pertinent
qualification program documentation (DOE Order 5480.20A).
Section 107
DOE-STD-3006-2010
3-51
Records Reviewed:
• Facility Contractor Operational Readiness Review Final Report, June 28, 2007
• QS-FACILITY-001, R. 1, Facility Shift Operations Supervisor Qualification Standard
• QS-FACILITY-002, R. 1, Facility Shift Operations Manager Qualification Standard
Interviews:
• Senior Training Specialist
• Deputy Group Leader Central Training – Deployed Training Services
• Computer Information Specialist
• Engineering Manager
• Cognizant System Engineers (2)
• ESH&Q Manager, Environmental Programs
• Division Leader, Central Training Division
• Training Manager
DISCUSSION OF RESULTS
1. The Site implementation processes for the T&Q Safety Management Program
(SMP) associated with Facility comply with contract requirements.
Write-up has been eliminated for brevity
The criterion was met.
2. A training implementation matrix (TIM) has been submitted and approved by
the Field Element that includes Facility and meets the commitments within the
approved Facility BIO and TSR, including training and qualification for forklift
operators. (TSR 5.8)
Prior to the current initiative to upgrade Facility from a Category 3 to a Category 2
nuclear facility, Facility was included in the Facility Training Program. This program
was reviewed by both NNSA and the Field Element in 2004. Several issues were
identified by both reviews. Credit is given to ISD 781-1 for closing many of these
findings.
A Facility TIM was submitted to the Field Element prior to the Facility Contractor
Operational Readiness Review (CORR). The TIM has been reviewed by Field
Element, but final approval has not been granted. The Management Self-Assessment
(MSA) Pre-Start Finding MSA TQ-PRE-1.1.2 was not closed prior to completion of
the DOE ORR. (Pre-Start Finding TQ.1-1) DOE Order 425.1C allows for a
manageable list of pre-start findings to exist at the initiation of the DOE ORR.
However, the items on the manageable list must have a well defined schedule for
closure to allow the DOE ORR team to review the results of the closure process.
DOE-STD-3006-2010
3-52
The criterion was not met.
3. The Site Contractor has conducted periodic systematic evaluations of the
Facility T&Q program and found it to be effective and compliant with contract
requirements (DOE Order 5480.20A, DOE-STD-1070-94).
The Field Element performed a review of DOE Order 5480.20A compliance in 2003
and a Laboratory Readiness Review (LRR) for resumption of work activities in 2004.
The LRR consisted of one training related objective with six related criteria. The
LRR did not fully address the eight objectives and 36 corresponding criteria in DOE-
STD-1070-94. No additional evidence was provided regarding any Site Contractor
T&Q evaluations prior to the Facility Management Self-Assessment (MSA) and
CORR.
DOE Order 5480.20A, section 6.b, states that “Evaluations of training and
qualification programs shall be conducted using DOE-STD-1070-94.” DOE-STD-
1070-94, Guidelines for Evaluation of Nuclear Facility Training Programs, Section
5.4, states that “Training program evaluations should be conducted every three years
to determine the effectiveness and efficiency of the training system in providing a
knowledgeable and skilled workforce to support safe and efficient facility operations.
”
The Site Contractor has not conducted periodic evaluations of Facility T&Q program
per DOE Order 5480.20A (Post-Start Finding TQ.1-2).
The criterion was not met.
Section 108
4. The Field Element has conducted periodic systematic evaluations of the Site
Contractor T&Q program and found it to be effective and compliant with
contract requirements (DOE Order 5480.20A, DOE-STD-1070-94).
The Field Element conducted an extensive DOE-STD-1070-94 review of the Site
Contractor T&Q program in April 2005. The review included Facility as a Category
3 nuclear facility. A formal corrective action plan was submitted to the Acting
Administrator for Defense Programs. In January 2007, the Conduct of Training
Manual was issued; this document completes many of the findings applicable to
Facility.
The next Field Element DOE-STD-1070-94 review of the Site Contractor T&Q
program is scheduled to be performed in April 2008. The proposed timing for this
review meets the requirements in DOE Order 5480.20A and DOE-STD-1070-94.
The criterion was met.
DOE-STD-3006-2010
3-53
5. Site Contractor Facility T&Q records, including lesson plans and completed
qualification records, are complete, auditable, and meet the requirements of the
TIM and the LANL T&Q program (DOE Order 5480.20A).
Write-up removed for brevity
WQAS contains electronic records of personnel authorized to perform work and
associated requirements for developing supplementary documentation. This aspect of
records is discussed in greater detail under Criterion 7 of this CRAD.
The criterion was met.
6. Modifications to the facility, as well as procedural and work control document
requirements have been reviewed for potential impacts on training and
qualifications. Required changes to training and qualification program
documents have been completed and implemented (DOE Order 5480.20A, DOE
O 433.1A).
EP-DIR-SOP-4001, Document Control Procedure, was recently revised to require
that a training requirements determination be added to all Procedure Change Request
(PCR) and Document Action Request (DAR) forms to catch changes that were
significant enough to warrant inclusion in training plans. Recent changes were
reviewed, and the form was in accordance with the procedure.
EP-DIR-SOP-2011, Personnel Training and Qualification, defines a grading scheme
for the training that needs to be performed. Training can take the form of required
reading, a briefing, or an actual training class. Training for changes to training and
qualification program documentation is formally developed and assigned an EDS
number so it can be tracked in Data Warehouse.
Design Change Package DCP-07-TA-50-0069-035, Exhaust Fan Control Upgrades,
requires training to be administered to personnel involved in this work activity.
Course number 41712, Technical Safety Requirements, was determined to be one of
the four courses that captured information for Site Contractor workers performing this
work. Information on class attendance was obtained from Data Warehouse. One
Inventory Controller, one Radiological Control Technician, two Waste Management
Coordinators, one Industrial Hygienist, and two Cognizant System Engineers have
not taken this course. It was not clearly defined who needed to attend the training;
however, several of the listed positions are clearly required to have the most up-to-
date information regarding the TSRs. All workers have not completed the training
associated with changes to the Facility and operations (Pre-Start Finding TQ.1-3).
Supplementary training is typically not added to the workers’ qualification standards
because most of the information will be captured in future updates to the standard
training classes, so it will not apply to future trainees. There is no process in place to
ensure that all pertinent workers have received supplemental training associated with
facility modifications and with procedural and work control changes (Post-Start
Finding TQ.1-4).
Section 109
DOE-STD-3006-2010
3-54
The criterion was not met.
DOE-STD-3006-2010
3-55
7. Level of knowledge of managers, operations, and operations support personnel
is adequate based on reviews of examinations, examination results, and any
pertinent qualification program documentation (DOE Order 5480.20A).
The Field Element training and qualification program is defined in ISD 781-1,
Conduct of Training Manual. Additional implementing guidance for the
Environmental Programs Directorate is contained in EP-DIR-SOP-2011, Personnel
Training and Qualification. The Site Contractor has defined several positions that
require employees to be qualified and authorized by a Responsible Line Manager
(RLM) to perform work.
Write-up removed for brevity
The criterion was not met.
CONCLUSION
The Objective was not met.
A performance-based evaluation of the implementation of the training and qualification
processes used associated with the Site Contractor was conducted by sampling a limited
set of documents and their execution. The changes that have been made to the
Laboratory training and qualification program over the last year are significant and are
clearly improving the level of rigor applied to this area. The selection, training, and
qualification programs for Site Contractor personnel have been established and
documented for the range of duties required to be performed to operate and support Site
Contractor activities. The implementation of the training and qualification program at
Site Contractor by Laboratory line managers still requires improvement to meet the
requirements of the recently revised Laboratory Training and Qualification Program.
Sufficient numbers of Site Contractor personnel have not completed the training and
qualification program.
Issues:
Pre-Start:
TQ.1-1: The CORR Pre-Start Finding CORR TQ-PRE-1.1.2 was not closed prior to
completion of the DOE ORR.
TQ.1-3: All workers have not completed the training associated with changes to the
Facility and operations.
TQ.1-5: The conditional authorizations captured in WQAS were not properly
documented by the RLM.
DOE-STD-3006-2010
3-56
TQ.1-6: Key individuals have not completed their qualifications and are not authorized
to perform their functions, including meeting TSR minimum staffing requirements.
Post-Start:
TQ.1-2: The Site Contractor has not conducted periodic evaluations of the Site
Contractor T&Q program per DOE Order 5480.20A.
TQ.1-4: There is no process in place to ensure that all pertinent workers have received
supplemental training associated with facility modifications and with procedural and
work control changes.
Submitted:
Team Member
Approved:
Team Leader
DOE-STD-3006-2010
Table I – STARTUP AND RESTART REQUIREMENTS SUMMARY (DOE O 425.1D)
Hazard Category
of facility being
started
Initial Startup
of Newly
Constructed
Facility
Initial Startup
of New
Activity or
Operation
Initial Startup
after
Conversion to
a New Nuclear
Mission
Restart for
upgrade in
Hazard
Categorization
Restart after
Shutdown
directed by DOE
Management
Official for safety
reasons
Restart after
shutdown
following
Violation of
Safety Limit
Restart after
Extended
Shutdown*
Restart after
Substantial
process,
system or
Facility
modifications
Deemed
appropriate by
DOE Official
Hazard Category
1
Authorization
Authority
S-1 or designee DSA Approval
Authority or
official of
commensurate
level
S-1 or designee S-1 or designee Official of level
commensurate or
higher than
official ordering
shutdown
Section 110
Official of level
commensurate
with Safety Basis
Approval
Authority for
Safety Limit or
designee
* >6 months
Cognizant Sec
Officer
Cognizant Sec
Officer or
designee
Official of level
commensurate
with official
directing review
be conducted
Review Type ORRa
CRD 2.a.(2)(a)
RAb
CRD 2.(a)(3),
CRD 2.b.(1)
ORRa
CRD 2.a.(2)(b)
ORR
CRD 2.a.(2)(c)
ORR
CRD 2.a.(2)(d)
ORR
CRD 2.a.(2)(e)
RAb
CRD 2.a.(3)
RAb
CRD 2.a.(3)
ORR/RA
CRD 2.a.(2)(f),
CRD 2.b(3)
Hazard Category
2
Authorization
Authority
S-1 or designee DSA Approval
Authority or
official of
commensurate
level
S-1 or designee S-1 or designee Official of level
commensurate or
higher than
official ordering
shutdown
Official of level
commensurate
with Safety Basis
Approval
Authority for
Safety Limit or
designee
*>12 months
Cognizant Sec
Officer or
designee
Cognizant Sec
Officer or
designee
Official of level
commensurate
with official
directing review
be conducted
Review Type ORRa
CRD 2.a.(2)(a)
RAb
CRD 2.(a)(3)
CRD 2.b.(1)
ORRa
CRD 2.a.(2)(b)
ORR
CRD 2.a.(2)(c)
ORR
CRD 2.a.(2)(d)
ORR
CRD 2.a.(2)(e)
RAb
CRD 2.a.(3)
RAb
CRD 2.a.(3)
ORR/RA
CRD 2.a.(2)(f),
CRD 2.b.(3)
Hazard Category
3
Authorization
Authority
Cognizant Sec
Officer or
designee
DSA Approval
Authority or
official of
commensurate
level
Cognizant Sec
Officer or
designeea
Cognizant Sec
Officer or
designee
Official of level
commensurate or
higher than
official ordering
shutdown
N/Ac As defined in
local
procedures
As defined in
local
procedures
Official of level
commensurate
with official
directing review
be conducted
Review Type ORRa
CRD 2.a.(2)(a)
RA
CRD 2.a.(3),
CRD 2.b.(1)
ORRa
CRD 2.a.(2)(b)
ORR
CRD 2.a.(2)(c)
ORR
CRD 2.a.(2)(d)
N/A RA
CRD 2.a.(3)
RA
CRD 2.a.(3)
ORR/RA
CRD 2.a.(2)(f),
CRD 2.b.(3)
Notes:
a - Note if other DOE orders require a higher level of startup authorization, the official described in this order will recommend startup to the higher-level official
b- DOE RA required
c - Assumes Hazard Category 3 facilities do not have safety limits