DOE-STD-1082-94, Preparation, Review, and Approval of Implementation Plans for Nuclear Safety Requirements
Functional areas: Implementation Plans, Nuclear Safety, Review
This standard describes an acceptable method to prepare, review, and approve implementation plans for DOE nuclear safety requirements. DOE requirements are identified in DOE Rules, Orders, Notices, Immediate Action Directives, and Manuals (hereinafter referred to as DOE requirements documents).
Unknown Block text
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
TS
NOT MEASUREMENT
SENSITIVE
DOE-STD-1082-94
October 1994
DOE STANDARD
PREPARATION, REVIEW, AND APPROVAL
OF IMPLEMENTATION PLANS FOR
NUCLEAR SAFETY REQUIREMENTS
U.S. Department of Energy AREA SAFT
Washington D.C. 20585
DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.
WELCOME
This Portable Document Format (PDF) file contains bookmarks, thumbnails, and hyperlinks to help you navigate through the document. All items listed on the contents page are linked to the corresponding sections. In addition, if you click on a section heading while you are reading the text, you will return to the contents page. Click on the DOE seal below to move to the contents page.
This document has been reproduced directly from the best available copy.
Available to DOE and DOE contractors from the Office of Scientific and
Technical Information, P.O. Box 62, Oak Ridge, TN 37831; (615)576-8401.
Available to the public from the U.S. Department of Commerce, Technology
Administration, National Technical Information Service, Springfield, VA 22161;
(703) 487-4650.
Order No. DE95001461
DOE-STD-1082-94
iii
FOREWORD
1. This Department of Energy (DOE) technical standard has been prepared
by the Office of Environment, Safety and Health with the assistance of Steve
Hosford of Phoenix Consultants and Hank George of Synergy Consultants. In
addition, representatives of DOE program offices and field and operations offices,
as well as DOE Management and Operating contractors, contributed substantially
to the development of this standard.
2. Lessons learned in using this technical standard should be reflected in
future revisions. Therefore, beneficial comments (recommendations, additions,
and deletions) and any pertinent data that may improve this document should be
sent for consideration to the Office of Nuclear Safety Policy and Standards (EH-
60), U.S. Department of Energy, Washington, D.C. 20585, by letter or by using the
self-addressed Standardization Document Improvement proposal (DOE F 1300.X)
in Attachment 1.
3. Many DOE nuclear safety requirements documents (Rules, Orders,
Notices, Immediate Action Directives, and Manuals) require the preparation of
implementation plans for submittal to DOE for review and approval. The
implementation plans detail the planned activities to meet DOE nuclear safety
requirements. Upon approval by DOE, the implementation plans, together with
any other plans or programs required by the DOE requirements documents
become the basis for complying with the nuclear safety requirements. This
standard provides an acceptable method for preparing, reviewing, and approving
implementation plans for nuclear safety requirements. Nothing in this standard is
intended to supersede any statement in a DOE requirements document.
4. This is a general standard for the preparation, review, and approval of
implementation plans and contains only expectations common to all
implementation plans. Consequently, supplementary standards may be provided
which give more detailed expectations for implementation plans for specific
requirements, such as the specific expectations for the preparation of
DOE-STD-1082-94
iv
implementation plans to meet the requirements of DOE Order 5480.23 (Safety
Analysis Reports). If conflicts arise, the organization responsible for implementing
the DOE requirements document (hereinafter called the "implementing
Section 2
organization") shall contact the DOE Operations Office point-of-contact to facilitate
resolution. In any case, adherence to the criteria in DOE requirements documents
takes precedence over meeting technical standards.
5. DOE technical standards, such as this technical standard, do not
establish requirements. However, all or part of the provisions in a technical
standard can become requirements under the following circumstances:
(1) they are explicitly stated to be requirements in a DOE requirements
document; or
(2) the organization makes a commitment to meet a standard in a contract or in
a plan required by a DOE requirements document (such as in an
implementation plan).
Throughout this standard, the words "should" and "shall" are used to clarify which
actions need to be done to meet this standard. The word "shall" is used to denote
actions which must be performed if this standard is to be met. The word "should"
is used to indicate recommended practice. If the provisions in this technical
standard are made requirements through one of the two ways discussed above,
then the "shall" statements would become requirements, but the should
statements would not.
6. The term "Operations Office" is used throughout this document. Where it is
used, the term "Field Office" shall be substituted where appropriate.
7. In addition to the guidance provided in this technical standard, preparers
of implementation plans shall also review the specific nuclear safety requirement
documents for individual content and administrative requirements. If their are
any conflicts between this technical standard and the DOE requirements
DOE-STD-1082-94
v
documents, the provisions in the DOE requirements documents apply. Where the
provisions are complementary, the plans shall meet both the DOE requirements
document and this technical standard.
DOE-STD-1082-94
vii
TABLE OF CONTENTS
SECTION PAGE
1. SCOPE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.1 Scope . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.2 Applicability . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
2. REFERENCES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
3. PREPARATION OF IMPLEMENTATION PLANS . . . . . . . . . . . . . . . . . . . . . 2
3.1 Implementation Plan Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
3.2 General Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
3.3 Applicability of Nuclear Safety Requirements . . . . . . . . . . . . . . . . . . . 3
3.4 Safety and Implementation Guides and Technical Standards . . . . . . 4
3.5 Baseline . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
3.6 Additional Activities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
3.7 Graded Approach . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
3.8 Resource Assessment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
3.9 Prioritization . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
3.10 Milestones and Schedules . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
Section 3
3.11 Exemptions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
3.12 Compensatory Actions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
3.13 Tracking . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
4. SUBMITTAL OF IMPLEMENTATION PLANS . . . . . . . . . . . . . . . . . . . . . . . 12
5. REVIEW AND APPROVAL OF IMPLEMENTATION PLANS . . . . . . . . . . . . 13
5.1 Review and Approval Protocol . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
5.1.1 Identification of Responsible Review Staff . . . . . . . . . . . . . 15
5.1.2 Review Planning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
5.1.3 Meetings, Conference Calls, and Status Reports . . . . . . . . 17
5.1.4 Submittal and Distribution of Implementation Plans . . . . . . 18
5.1.5 Review . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
5.1.6 Approval . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19
DOE-STD-1082-94
viii
5.2 Distribution of Copies of the Final Implementation Plan . . . . . . . . . . 22
5.3 Review Responsibilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
5.4 Approval Responsibilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
5.5 Resolution of Issues . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
6. REVISIONS TO IMPLEMENTATION PLANS . . . . . . . . . . . . . . . . . . . . . . . . 24
7. EXTENSIONS TO THE SUBMITTAL SCHEDULE FOR
IMPLEMENTATION PLANS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
8. IMPLEMENTATION TRACKING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
9. COMPLETION OF IMPLEMENTATION PLANS . . . . . . . . . . . . . . . . . . . . . 26
10. INCORPORATION BY REFERENCE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26
11. SUBJECT TERM (KEY WORD) LISTING . . . . . . . . . . . . . . . . . . . . . . . . . . 27
DOE-STD-1082-94
1
1. SCOPE
1.1 Scope. This standard describes an acceptable method to prepare,
review, and approve implementation plans for DOE nuclear safety requirements.
DOE requirements are identified in DOE Rules, Orders, Notices, Immediate Action
Directives, and Manuals (hereinafter referred to as DOE requirements
documents).
1.2 Applicability. This standard is intended for use by all DOE
organizations and their contractors when preparing, reviewing or approving
implementation plans for DOE nuclear safety requirements.
Implementation plans are called by a variety of names in the DOE nuclear safety
requirements documents. For example, in 10 CFR Part 835, they are met by the
Radiation Protection Programs (RPPs); and in the proposed 10 CFR Part 834
they are met by Environmental Radiation Protection Programs (ERPPs). All of
these plans and programs, as well as a number of other plans and programs
identified in other DOE nuclear safety requirements documents, are considered to
be implementation plans for DOE nuclear safety requirements. Consequently, the
provisions of this technical standard apply to the preparation, review, and
approval of those plans. The Operations Office point-of-contact should be
contacted if clarification is needed on the applicability of this standard to specific
plans and programs.
2. REFERENCES
Section 4
DOE ORDER 5480.23, NUCLEAR SAFETY ANALYSIS REPORTS
10 CODE OF FEDERAL REGULATIONS (CFR) PART 820, PROCEDURAL
RULES FOR DOE NUCLEAR ACTIVITIES.
10 CFR PART 830, NUCLEAR SAFETY MANAGEMENT
10 CFR PART 834, RADIATION PROTECTION OF THE PUBLIC AND THE
ENVIRONMENT
10 CFR PART 835, OCCUPATIONAL RADIATION PROTECTION
DOE-STD-1082-94
2
3. PREPARATION OF IMPLEMENTATION PLANS
The implementation plans detail how the site, facility, or activity has met or will
meet the nuclear safety requirements.
The format for the implementation plan is not specified. This flexibility will
permit the implementing organizations to take advantage of pre-existing
documents. For example, when making the transition from nuclear safety
Orders to nuclear safety Rules, the Department expects the implementing
organizations to use the implementation plans developed and approved for the
Orders as a basis for the Rule implementation plans. Typically, these plans
should be revised or supplemented only as necessary to reflect any new
requirements in the Rules or additional information requested in this standard or
other DOE implementation guidance. The level of detail provided in
implementation plans should be the same for Rules or Orders.
The following sections describe the minimum content expected in
implementation plans. The headings in these sections may also be used to
define the format for the plans.
3.1 Implementation Plan Summary. Each implementation plan shall
contain a summary section in the front to allow DOE management and
reviewers to quickly assess the more significant information contained in the
plan. The summary shall identify the following minimum information:
(1) any requests for exemptions contained in the plan;
(2) the total additional funding required to meet the requirements of
the plan and the expected sources of funding by fiscal year;
(3) any significant new programs or activities needed to meet the
requirements;
(4) any significant impacts to other programs or activities not included
in the plan;
(5) any constraints to implementing the plan;
(6) those areas where there is currently full compliance with the
requirements.
DOE-STD-1082-94
3
3.2 General Information. The implementation plan shall include
general information which: (1) identifies the subject DOE requirements
document addressed in the plan; (2) identifies whether the plan is the initial
submittal or a revision; (3) identifies the facilities or activities, missions, and
contractors involved; and (4) briefly discusses the content and format of the
plan.
3.3 Applicability of Nuclear Safety Requirements. DOE nuclear safety
requirements documents state the types of facilities and activities to which they
are applicable. The implementation plan shall identify the specific facilities or
activities covered by the plan. Any determination by the implementing
organization that a specific requirement is not applicable to the facilities or
activities addressed in the plan shall be documented in the implementation
plan to ensure that the determination is clearly communicated. DOE approval
of the plan will constitute agreement with applicability statements contained
therein.
Applicability statements shall not be used to provide relief where the
requirements are clearly stated to be applicable in the DOE requirements
document. Relief from requirements which are clearly applicable must be
granted by an approved exemption as discussed in Section 3.11 of this
Section 5
technical standard.
The information provided in the plan shall clearly identify which of the following
three categories applies to each requirement for a given facility, site, or
activity:
(1) the requirement is applicable and the implementation plan
defines the actions and schedules for compliance;
(2) the requirement is applicable and an exemption is being
requested; or
(3) the requirement is not applicable for the reasons documented in
the implementation plan.
DOE-STD-1082-94
4
The plan shall also identify any requirements which are only partially
applicable, the limits of the applicability, and the reasons for the limitation.
Individuals shall contact the appropriate Operations Office to assist with any
needed clarification of applicability statements. The Operations Office shall
contact the Office of Primary Interest (DOE Office responsible for issuing and
maintaining the document in question) for any needed interpretations of
Orders, Notices, Immediate Action Directives, Manuals, or guidance materials
or the Office of General Counsel for interpretations of Rules.
3.4 Safety and Implementation Guides and Technical Standards. The
implementation plan shall identify the safety and implementation guides
(hereinafter referred to as guides) and technical standards which are to be
adopted as the means to meet DOE requirements documents. The use of
guides and technical standards is not required; however, it is encouraged for
the following reasons:
(1) the use of previously approved methodologies will streamline the
review and approval process; and
(2) the use of guides and technical standards will enhance the
consistent and successful implementation of requirements across
the DOE complex.
The implementing organization shall consider methods and guidance from
guides and technical standards when developing the implementation plans;
however, alternative methods that achieve comparable results are acceptable.
When an implementing organization identifies an alternate way to implement
the requirements, a reasonable opportunity will always be provided to
demonstrate compliance with the requirements using the alternate method.
Demonstration of compliance does not require the implementing organization
to address the differences between the alternate method and the method in
the guide or technical standard unless the comparison is necessary to
demonstrate acceptability.
DOE-STD-1082-94
5
When guides or technical standards are used, the implementing organization
shall indicate if they are adopted in their entirety or adopted with exceptions.
The exceptions, if any, shall be specifically noted. Methodologies and
guidance provided in guides and standards are acceptable DOE
methodologies when adopted in their entirety. Methodologies and guidance
which are adopted with exceptions will be reviewed on a case-by-case basis.
The adopted guides and technical standards shall be listed either by
(1) including a list of applicable guides and technical standards in the
implementation plan, or (2) incorporating a list of guides and technical
standards by reference.
Commitments in implementation plans to meet all or parts of guides and
technical standards are enforceable as part of the implementation plan.
Section 6
3.5 Baseline. The implementing organization shall determine the
extent to which the requirements are already met. This effort is generally
referred to as establishing the baseline. The implementation plan shall identify
the requirements which are already met and the actions taken to meet them.
These actions are the baseline activities. Because the baseline activities are
part of the activities which define how the requirements are met, the baseline
activities or programs are to be documented in the implementation plan and
are subject to the same assessments and enforcement as other commitments
in the implementation plan when the plan is approved by DOE.
Implementing organizations are encouraged to use existing documentation
and information wherever possible and reliable for establishing the baseline.
3.6 Additional Activities. Following the baseline effort, the
implementing organization shall identify what additional activities are
necessary to meet the requirements. The combination of the baseline
activities and the additional activities shall identify all actions necessary to
achieve full compliance with the requirements. In general, the level of detail
of the activities listed in the implementation plan should define the
commitments for implementation and should not include the day-to-day
DOE-STD-1082-94
6
activities reflected in facility-specific procedures. However, the information
provided shall be specific enough to allow clear interpretations of the intent of
the commitment. Examples of the appropriate level of detail for additional
activities are 1) "development and implementation of a recordkeeping
program," and 2) "development and implementation of a revised lockout and
tagout program."
The additional activities identified in the plan shall include not only the
development of programs to meet the requirements, but also the actions
necessary to implement those programs, such as procedure development and
training. During the development of the additional activities list, the
implementing organization is expected to consider adopting alternate
implementation activities which may be more cost-efficient ways to meet the
requirements.
3.7 Graded Approach. The complete set of activities necessary to
meet the nuclear safety requirements, as well as the level of depth, rigor, and
thoroughness in applying them to a given facility, are determined by applying
a graded approach. The graded approach is defined in 10 CFR Part 830.3 as
"a process by which the level of analysis, documentation, and actions
necessary to comply with a requirement ... are commensurate with the
following: (1) the relative importance to safety, safeguards, and security [risk];
(2) the magnitude of any hazard involved; (3) the life cycle stage of a facility;
(4) the programmatic mission of a facility; (5) the particular characteristics of a
facility; and, (6) any other relevant factor." The graded approach will permit
the implementing organization to tailor the implementing activities for each
facility or activity to appropriately address these considerations.
Consideration of the risks and hazards of the facility [items (1) and (2) in the
definition] will allow the implementing organization to focus resources on
those activities most likely to reduce the associated risks and hazards by
tailoring the implementing actions to the specific risks and hazards at the
individual facilities and activities.
DOE-STD-1082-94
7
Section 7
The consideration of the life cycle stage of a facility [item (3) above],
will permit the implementing organization to assess the best application
for the current life cycle stage of the facility (e.g., a facility in the
decommissioning phase would not require extensive documentation on the
original design basis for the safety analysis report, but rather would need to
focus on assessing information required for current and future
decommissioning activities).
The programmatic mission of a facility [item (4) above] may suggest a need
for more rigorous implementation of a requirement than would be necessary
for safety considerations alone. DOE as the owner of the facilities has the
responsibility to protect capital equipment and missions at its facilities. These
programmatic responsibilities may result in stricter requirements than would
be justified by safety risks or hazards alone. For example, a component such
as a circulating pump may have a minimal safety function but could be critical
to the continued operation of a facility. Consequently, both DOE and the
implementing organization may agree that a more rigorous maintenance
program should be applied than what would be required by the safety
significance alone. Programmatic considerations cannot be used to reduce
the rigor of implementation.
The particular characteristics of a facility [item (5) from the definition] will also
influence how nuclear safety requirements are applied. This consideration
overlaps the four considerations discussed above. For example, the training
activities developed to meet nuclear safety requirements would be
substantially different in a laboratory versus a production facility. The
differences would be influenced by (1) the specific risks, (2) the specific
hazards, (3) the life cycle stage of the facilities, and (4) the enhancements
required to support the mission. In addition, the training activities would need
to be tailored to the particular hardware and operations of the facilities.
There is no cookbook procedure for application of the graded approach to
all of the nuclear safety requirements. When a DOE requirements document
is developed, the Office of Primary Interest may include information in the
DOE-STD-1082-94
8
safety or implementation guide to help the implementing organization in
grading. In general, however, the implementing organization is empowered,
because of its detailed knowledge of the specific features and operation of
their facilities and activities, to use its best judgement in the determination of
the appropriate activities for full implementation of a requirement. The
implementing organization shall propose the method for applying a graded
approach to the particular facilities or activities in the proposed programs or
plans submitted to DOE. When approved, those activities become the basis
for assessment and enforcement.
Following the identification of the appropriate activities to meet the
requirements, the implementing organization may determine that on the
basis of limited resources or other considerations that it is not in DOE's best
interest to implement the requirement. In such cases, the implementing
organization shall request an exemption (see Section 3.11 of this technical
standard). It is important to not confuse the graded approach with the
exemption process. The graded approach is to be used to determine the
appropriate manner to comply with a requirement; it is not to be used to
Section 8
provide relief from meeting the requirement. Exemptions are used to provide
relief.
The implementation plan shall document the basis for selecting the action
pursuant to the graded approach whenever a graded approach is used.
3.8 Resource Assessment. The implementation plan shall provide an
estimate of the additional life cycle costs to implement the nuclear safety
requirements. The goals of this element of the implementation plan are as
follows: (1) to communicate the expected new costs of implementation to DOE
management for the purposes of budget planning and prioritization; (2) to
identify the need to explore more cost effective means of achieving
compliance; and (3) to identify cases where exemptions should be requested
on the basis of insufficient benefit versus the expected implementation costs.
Identification of required resources should also serve to open a dialogue
between DOE and the implementing organization on adjusting costs and
activities to the available resources.
DOE-STD-1082-94
9
When performing the assessments, the estimator shall consider monetary
costs, as well as non-monetary resource considerations such as the limited
availability of special job capabilities (e.g., pipe fitters, welders, health
physicists). The assessment shall (1) be guided by available quantitative and
qualitative information; (2) reflect the current status of plant conditions,
configurations, and processes; (3) consider the availability of materials and
resources; and (4) consider any other information that is relevant to the
nuclear safety requirements.
Organizations shall seek to achieve the broadest consistency in the methods
used to evaluate the resource requirements so that the assumptions,
evaluations, and results of the assessment can be objectively compared with
the equivalent parameters of other resource assessments. This will assist
DOE and contractor management to determine priorities for the use of
funding. All assumptions and estimates shall be made using the best
available knowledge and information.
The implementing organization shall identify the expected sources of funding
for the proposed new activities.
After evaluating the resource impacts, the implementing organization shall
consider if a more cost-effective means of achieving the intent of the
requirement is available. As a minimum, the use of more cost-effective
methods of compliance, or exemptions (see section 3.11 of this standard),
shall be considered whenever the resource expenditures necessary to meet a
requirement are not commensurate with the expected safety improvements.
The implementing organization shall limit the effort used to develop the
resource assessments to only that level of detail necessary to achieve the
goals of the assessment as stated above.
3.9 Prioritization. The implementation plan shall include a discussion
of the prioritization process used to integrate the proposed activities into a
facility or site schedule of activities. The prioritization process is to be
DOE-STD-1082-94
10
used to develop the proposed schedules and shall be sufficiently flexible to
accommodate changes at later dates.
The prioritization process shall consider available information from safety
analyses and other sources and give primary attention to controlling and
reducing risks to the public, the environment, and the workers to an
acceptable level. It should also consider other factors such as mission needs,
outage schedules, and external regulations.
Section 9
The prioritization process should be selected in consultation with the
applicable DOE Operations Office and Program Offices to ensure that the
prioritization of efforts meets DOE expectations. In order to tie budgets to
schedules, priorities should be determined in accordance with the DOE
Environment, Safety, and Health (ES&H) Management Plan wherever
budgets are determined on the basis of that plan. For other facilities, the use
of the ES&H Management Plan process or a compatible process is
encouraged in determining the priorities.
3.10 Milestones and Schedules. The implementation plan shall identify
proposed milestones with achievable schedules developed in accordance with
the additional activities and the prioritization process identified in the plan
(see Sections 3.6 and 3.9 above). In developing the schedules, the
implementing organization shall consider the resources available to support
the work, as well as any major work reductions or schedule changes in other
areas that will be required in order to meet the proposed schedules. The
implementation plan shall identify major impacts to activities or commitments
outside the scope of the plan which will be caused by the proposed additional
activities.
Schedules shall be developed using the best information available with any
assumptions on availability of resources (monetary or non-monetary) clearly
stated. The milestones and schedules will be enforceable commitments upon
approval of the plan. Schedule commitments must be firm commitments and
consequently, shall not be listed as contingent on funding. Thus, it is
essential that line program representatives participate in the review and
DOE-STD-1082-94
11
approval of implementation plans which involve additional funding needs.
Following approval of the implementation plans, DOE has a responsibility to
provide appropriate funding to support approved activities and schedules. If
funding is subsequently unavailable when needed to support the implementation
plan schedules, the implementation plans should be revised to reflect the new
schedules supported by funding (provided any schedules specifically prescribed
in the DOE requirements documents are met or schedule exemptions are
approved). Such revisions shall be submitted to DOE for review and approval.
Alternatively, implementing organizations may consider requesting an exemption
for unfunded activities, if the criteria for granting an exemption are met (see
Section 3.11 of this technical standard).
3.11 Exemptions. Exemptions are to be requested whenever relief is
sought from an applicable DOE requirement. The implementation plan shall
clearly identify any exemptions that have been approved or are being requested
from the subject requirements. Implementing organizations may submit
requests for exemptions as part of the implementation plan provided that they
relate to the same requirements. Requests for exemption that are submitted as
part of the implementation plan shall be identified in the implementation plan
summary for early recognition. Early identification of exemption requests is
important because they may need to follow a separate review and approval
process.
The provisions for requesting and granting exemptions to rules are stated in 10
CFR Part 820, Subpart E, "Exemption-Relief." All exemptions to rules must be
approved by the Secretarial Officer designated in 10 CFR Part 820,
Subpart E notwithstanding the level of approval delegated for the
implementation plan. The provisions for granting exemptions to Orders,
Notices, Immediate Action Directives and Manuals are specified in the
directives documents.
Section 10
3.12 Compensatory Actions. The implementation plan shall include a
description of any compensatory actions that will be adopted prior to full
implementation of the requirements. Compensatory actions are temporary
DOE-STD-1082-94
12
actions taken to provide adequate protection of individuals and the
environment prior to full implementation of the actions necessary to meet the
requirements.
3.13 Tracking. The implementation plan documents the implementing
organization's commitments with regard to meeting the nuclear safety
requirements. The plan will be used to measure progress in achieving
compliance with the requirements, as well as maintaining continuing
compliance. Therefore, the implementing organization shall have a
commitment tracking program to ensure that both the baseline and additional
activities described in the implementation plan are met on schedule and
continue to be met following the initial implementation. The implementation
plan shall contain a brief description of the implementing organization's
commitment tracking program.
4. SUBMITTAL OF IMPLEMENTATION PLANS
The implementing organization shall submit implementation plans to the
designated DOE Operations Office point-of-contact within the schedule
specified in the DOE requirements document. The Operations Office point-of-
contact shall time and date stamp the receipt of the implementation plan.
The implementing organization shall contact the Operations Office point-of-
contact in advance of the submittal date to determine the number of copies to
be submitted. Documents which are incorporated by reference shall be
submitted with the implementation plan unless other arrangements are made
with the Operations Office point-of-contact. In addition, if the implementation
plan is not a stand-alone document (able to be reviewed independent of other
documents), the implementing organization shall contact the Operations Office
point-of-contact prior to submittal of the implementation plan to discuss which
supporting documents are to be transmitted with the implementation plan or
made available for onsite review.
Also see section 5.2 below for software submittal requirements for final
plans.
DOE-STD-1082-94
13
5. REVIEW AND APPROVAL OF IMPLEMENTATION PLANS
5.1 Review and Approval Protocol. The Department's protocol for
review and approval of implementation plans is described below. The protocol
defines the roles, interfaces, and responsibilities of Department organizations
with respect to review and approval of implementation plans for nuclear safety
requirements. This protocol is consistent with the "Conceptual Framework for
Implementation Plan Review Teams" endorsed by the Office of Energy
Research, the Office of Nuclear Energy, the Office of Defense Programs, the
Office of Environmental Management, and the Office of Associate Deputy
Secretary for Field Management in a memorandum dated September 9, 1994.
This protocol is consistent with and supersedes the Draft Review and Approval
Protocol composed by the Rule Implementation Steering Group and
referenced in Step 6 of the September 9 Conceptual Framework.
Implementing organizations who will prepare the implementation plans and the
DOE organizations responsible for review and approval of the plans must have
a shared vision of what should be in the completed plans before submission of
the plan to DOE. In order to ensure this shared vision and the development of
successful implementation plans, early and continual dialogue between the
Section 11
implementing organization and the Review Team is essential. This dialogue
should begin well before the implementation plan is submitted to DOE. The
process described below was built on the lessons learned in similar efforts and
was designed to facilitate that dialogue.
Because review and approval of the plans will often involve multiple
Departmental organizations, the review and approval process must provide for
coordination, consistency of review, and resolution of issues among those
offices. In addition, the review and approval process must address both the
technical adequacy of the proposed implementation plans and the
programmatic responsibilities (i.e., funding and mission). These
responsibilities will require additional coordination within the Department as
they may reside in different organizations.
DOE-STD-1082-94
14
The review and approval process must be sufficiently flexible to accommodate
a wide variety of subjects addressed by the DOE requirements documents and
yet be adequately structured to permit efficient completion of the review and
approval within the schedule specified in the DOE requirements document
(typically 90 or 180 days).
In the review and approval process, the Operations Office is responsible for
coordination between the implementing organization and the Department's
Headquarters staff. This focused interface will ensure consistency in the
information provided to the implementing organization and allow the
implementing organization to interact with a single point-of-contact.
The Department's Rule Implementation Steering Group (RISG) will provide
oversight for the process and ensure consistency in the review and approval
efforts across all nuclear safety rule requirements. The RISG will resolve
issues which are generic to the rule implementation plan process.
For each DOE requirements document (or group of DOE requirements
documents, if appropriate) an Implementation Working Group will be formed to
provide oversight and coordination of implementation plan reviews for the
specific DOE requirements document to ensure consistency across the
Department. The Working Group may also recommend to the CSOs that
approval authority be delegated to the Operations Offices for specific
implementation plans or groups of implementation plans. The Working Group
memberships will include one representative from each Cognizant Secretarial
Office (CSO) and each affected Operations Office with contractors or
organizations subject to the DOE requirements document (hereinafter referred
to as affected CSOs or affected Operations Offices). The Working Groups shall
ensure that an Implementation Plan Guide (technical and program guidance) is
established to do the following: (1) ensure consistent implementation plans
across the DOE complex; (2) facilitate identification of specific reviewers and
schedule development; and (3) review implementation status through the entire
review and approval process. The Working Group will also maintain a core set
of subject matter experts to address generic questions that require consistent
DOE-STD-1082-94
15
solutions for all implementation plans. The Working Groups are responsible for
coordinating CSO approvals.
An Implementation Plan Review Team is formed for each implementation plan to
conduct the review of the plan. The Review Team members will include
Headquarters and Field Operations personnel with technical expertise and
Section 12
coordinating responsibility for program decisions (e.g., funding, schedule).
Operations Office personnel will serve as points-of-contact and Review Team
Leaders for implementation plan reviews applicable to their sites. Individual
participation in Review Team activities will vary in level of effort and time frame
based on review and approval needs.
The Operations Office point-of-contact plays a key role in coordinating all
implementation plan review and approval activities between Headquarters and
the implementing organization.
The process to be followed for the development, review, and approval of
implementation plans is discussed below. Two typical schedules for these
activities are included in Attachment 2. These schedules are for 90-day and
180-day implementation plan review requirements.
5.1.1 Identification of Responsible Review Staff.
5.1.1.1 Implementation Working Groups. The Working Groups shall
ensure consistency in the review process across the DOE complex, monitor
review progress, and resolve any issues related to the review and approval
process. The Working Group leader shall be designated by the RISG for plans
developed to meet the nuclear safety rules. For plans developed to meet other
nuclear safety requirements, the Working Group leaders shall be determined by
the CSOs or their designees. The Working Groups shall provide assistance to
the Review Team Leaders to ensure that each team has adequate
programmatic and technical capabilities. The Working Group shall also prepare
an Implementation Plan Guide as discussed in 5.1.2.1 below.
DOE-STD-1082-94
16
5.1.1.2 Points-of-Contact. Each Operations Office Manager shall identify
a point-of-contact for each DOE requirements document to the RISG. The
Operations Office point-of-contact shall be the primary interface with the
implementing organization for all activities associated with the development,
submittal, review, and approval of the implementation plans. The Operations
Office point-of-contact shall also be the Review Team Leader. Any exception to
the point-of-contact as the Review Team Leader shall be approved by the
Working Group. The Review Team Leader shall coordinate assignment of
Review Team members with the CSOs and the Operations Office through the
Working Group. The Operations Office Manager may also designate an office
coordinator for nuclear safety requirements activities.
5.1.1.3 Implementation Plan Review Teams. As discussed in the
previous paragraph, the Operations Office point-of-contact shall normally be the
Review Team Leader. The Operations Office Manager may provide additional
team members and technical assistance as necessary and agreed by the
Working Group. In addition, each affected CSO shall identify the Program Office
representatives for each Review Team to the Review Team Leaders through the
Working Group. The CSO may assign multiple reviewers to a single site or a
single reviewer.
5.1.2 Review Planning.
5.1.2.1 Implementation Plan Guide. For each requirements document or
group of DOE requirements documents, the Working Group shall prepare an
Implementation Plan Guide which defines DOE's specific technical and
programmatic expectations for the implementation plans. The guide shall
include the following types of information: (1) criteria and/or checklists of
items to be considered during the review, (2) approaches to key issues,
(3) direction on use of existing plans and approvals, (4) review and approval
Section 13
authorities, and (5) specific issues relating to Headquarters or Operations
Office review responsibilities. The guide shall be as brief as possible,
shall be user friendly, and shall not repeat general guidance available in other
guidance documents such as this technical standard. The Working Group
DOE-STD-1082-94
17
members shall provide assistance and/or training to the Review Teams on the
use of the guide.
5.1.2.2 Implementation Action Plan. For each implementation plan, the
Review Team Group shall prepare an Implementation Action Plan that defines
the Review Team activities, priorities, and schedule. A copy of the plan shall be
provided to the implementing organizations for information.
5.1.2.3 Responsibility and Interface Matrix. The Working Group shall
prepare and maintain a matrix that identifies the Review Team Leader, Review
Team members, and DOE programmatic and technical contacts for each
implementation plan.
5.1.3 Meetings, Conference Calls, and Status Reports.
5.1.3.1 Initial Site Meeting. The Review Team and a member of the
Working Group shall meet with the implementing organization at the earliest
feasible date to discuss the basic expectations for implementation of the DOE
requirements document and to discuss any issues which might impact the timely
and acceptable completion of the implementation plan. Issues to be discussed
should include: (1) how to best use existing plans or other information in
developing the implementation plan; (2) potential exemptions; (3) baseline
activity expectations; (4) plans and schedules for ongoing interactions; and (5)
funding sources for new activities identified as necessary to come into
compliance. The Operations Office point-of-contact has primary responsibility
for planning and coordinating this meeting.
5.1.3.2 Status Meetings. Periodic status meetings shall be held with the
implementing organization to fully discuss all elements of the proposed
implementation plans that could affect the acceptability of the plans.
5.1.3.3 Periodic Conference Calls. The Operations Office point-of-
contact shall coordinate regular conference calls with the implementing
organization and the Program Offices to address and resolve issues as they
arise. As necessary, site or headquarters meetings shall be held to resolve
DOE-STD-1082-94
18
difficult issues. The Operations Office point-of-contact has primary responsibility
for coordinating phone conferences, as well as necessary meetings to resolve
issues.
5.1.3.4 Implementation Status Reports. The Review Teams shall provide
brief monthly status reports to the appropriate Working Groups and to the RISG
identifying the status of the review, any significant issues or constraints, and any
planned resolutions.
5.1.4 Submittal and Distribution of Implementation Plans. As discussed
in Section 4 of this technical standard, implementing organizations shall submit
implementation plans directly to the Operation Office point-of-contact. The
Operations Office point-of-contact shall transmit a copy of the implementation
plan to the Review Team members and a copy of the transmittal memorandum
to the affected CSOs within four working days of the receipt of the plan. The
transmittal memorandum shall identify the required date for completing the
review.
5.1.5 Review.
Section 14
5.1.5.1 Implementation Plans Reviewed by Review Teams.
Implementation plans shall be reviewed by an integrated Review Team with
Program and Operations Office representatives as discussed in Section 5.1.2.1
above. Program Office team members and their contacts shall, as a minimum,
participate in the review of issues involving funding, missions, schedules,
priorities, and exemptions. The Review Team Leader shall facilitate
resolution of unique or difficult issues not addressed in the Implementation
Plan Guide.
Review Team members shall assist the implementing organization in clearly
understanding what actions or changes are necessary to result in an acceptable
implementation plan. DOE comments and feedback shall be routed through the
Review Team Leader to ensure consistent feedback. The Review Team Leader
shall also be responsible for resolving conflicts prior to communication with the
implementing organization.
DOE-STD-1082-94
19
All reviewers shall expedite their reviews to allow closure on an acceptable
implementation plan as early as possible.
5.1.5.2 Delegated Approval Authority for Implementation Plans. The
CSO may delegate the authority to approve specific implementation plans. Any
such delegation shall be provided in writing to the designee.
The Operations Office point-of-contact is responsible for identifying to the
affected CSOs any implementation plans which are based upon previously
approved implementation plans and do not involve (1) additional funding
commitments, (2) commitment schedule changes, (3) new programmatic
impacts, or (4) exemptions from the requirements. These implementation plans
will typically be new plans for nuclear safety rules which were preceded by DOE
Orders on the same subject or revisions to previously approved plans. Typically,
the review and approval authority for these plans will be delegated to the
Operations Office by the CSO.
Wherever the authority to approve an implementation plan has been delegated
to the Operations Office by all of the affected CSOs, the Operations Office may
choose to have the Review Team consist entirely of Operations Office personnel
provided any technical and programmatic requirements can be handled by the
designated team.
The authority to approve exemptions to rules cannot be delegated.
5.1.6 Approval.
5.1.6.1 Approval Recommendations by the Review Team. The Review
Team Leader is responsible for ensuring that the Operation's Office Manager
receives the Review Team's final recommendation for approval no less than five
weeks prior to the approval date specified in the DOE requirements document.
That recommendation shall either endorse acceptance of the implementation
plan as submitted (or changed through negotiations during the review process)
or, if issues cannot be resolved with the implementing organization, provide
DOE-STD-1082-94
20
recommendations regarding specific additional commitments or changes to be
incorporated in the plan.
5.1.6.2 Operations Office Review of the Review Team Recommendations.
The Operations Office Manager shall review the recommendation of the Review
Team and either endorse the recommendation or provide specific
recommendations for an acceptable plan. The Operations Office Manager is
responsible for ensuring that the Working Group receives the recommendations
of the Review Team along with any recommendations from the Operations Office
no later than three weeks before the approval date stated in the DOE
Section 15
requirements document (with information copy to the affected CSOs).
In some cases involving multiple CSOs, approval authority may be delegated by
one or more CSOs, but not all CSOs. In such cases, the Operations Office
Manager shall indicate approval of the implementation plan when it is
transmitted to the Working Group. The Working Group shall coordinate the
remaining approvals with the CSOs and return those approvals to the
Operations Office Manager.
For cases in which the approval authority has been delegated by all affected
CSOs to the Operations Office Manager, the Operations Office Manager should
skip to step 5.1.6.4 Approval Letter, below.
5.1.6.3 CSO Approval Memorandum. Each affected CSO shall indicate
approval of the implementation plan in a memorandum to the Operations Office.
The Working Group is responsible for drafting the approval memorandum,
obtaining CSO approvals, and forwarding such approvals to the Operations
Office Manager. The Working Group shall ensure that the Operations Office
Manager receives the approval memorandum no later than one week before the
approval date in the DOE requirements document.
5.1.6.4 Approval Letter. The Operations Office Manager shall transmit
the approval memorandum by letter to the implementing organization no later
than the approval date specified in the DOE requirements document.
DOE-STD-1082-94
21
5.1.6.5 Imposition of Implementation Plans. The Review Team will
endeavor to resolve any issues identified during the review process with the
implementing organization. If conflicts exist which cannot be resolved with the
implementing organization, the Department will exercise its authority to modify
proposed implementation plans to include those action and schedules that the
Department finds appropriate for achieving full compliance in a reasonable and
timely manner. In such cases, the CSO approval memorandum shall be
replaced by a memorandum imposing a revised plan. The revised plan shall be
transmitted to the implementing organization by the Operations Office Manager.
These plans may be renegotiated at a later date, but until they are replaced by
another approved plan, they will be the enforceable basis for implementation of
the DOE requirements document.
5.1.6.6 Implementation Plans which are not Approved by Final Date.
Implementation plans which are not reviewed and approved within the approval
period specified in the DOE requirements document shall be considered to be
approved unless another implementation plan is imposed by the Department.
These plans may be renegotiated at a later date, but until they are replaced by
another approved plan, they will be the enforceable basis for implementation of
the rule.
5.1.6.7 Approval of Plans Containing Exemption Requests.
Implementation plans may contain requests for exemptions. When they do, the
requests may be granted in the approval memorandum for the implementation
plan, provided that all of the requirements for processing exemptions are met.
For rules the approval shall be granted by the appropriate DOE Secretarial
Officer as stated in 10 CFR Part 820, Subpart E and the approval document
shall state how the provisions of 10 CFR Part 820, Subpart E are met.
Alternatively, exemptions may be approved separately and referenced in the
implementation plan approval letter.
Upon submittal of the plans, the Review Team Leader shall determine if any
exemption requests submitted in the plans need to be reviewed and approved
Section 16
separate from the implementation plans. Where separate review and approval
is necessary, the Review Team Leader shall alert the CSO Review Team
DOE-STD-1082-94
22
representatives to initiate a separate and expeditious review of the exemption
requests.
Typically, DOE nuclear safety requirements state that implementation plans are
considered approved 180 (or 90 days) days after submittal, unless they are
approved or rejected by DOE at an earlier date. This does not apply to
exemptions. Approval of implementation plans containing requests for
exemption are conditional pending approval of the exemption request. If the
exemption requests are subsequently disapproved, the implementing
organization shall amend the implementation plan and submit the revised plan
for approval within the time period specified in the letter transmitting the
disapproval determination. If no time period is specified, the implementing
organization shall revise and submit the implementation plan for approval within
90 days of receipt of the rejection of the exemption request.
Conditional approval of an implementation plan does not constitute or imply
approval of the exemptions contained therein.
5.2 Distribution of Copies of the Final Implementation Plan. The
Operations Office Manager is responsible for distributing approved plans to the
implementing organization (if changed from the originally submittal plan), the
Office of the Docketing Clerk (in the Office of Enforcement) in the Office of
Environment, Safety, and Health and to the affected CSOs. Copies of approved
plans transmitted to the Office of Docketing Clerk shall include both a hard cover
copy and a software copy. The software copy shall be in IBM compatible
Wordperfect version 5.1 or above or in an ASCII file. As required by 10 CFR
Part 820, the Office of the Docketing Clerk will maintain a file of enforceable
actions based upon rule violations and noncompliance with implementation
plans.
5.3 Review Responsibilities. The Review Team shall determine if the
implementation plan provides an acceptable method to meet the requirements in
accordance with the direction provided by the Working Group in the
Implementation Plan Guide. The Review Team shall also determine if the plan
adequately addresses the elements discussed in Section 3 of this technical
DOE-STD-1082-94
23
standard (Preparation of Implementation Plans). DOE has provided safety and
implementation guides which define acceptable methods for meeting the
requirements. These guides are not mandatory. The implementing organization
is encouraged to use these methodologies where they are reasonable and
economical; however, the implementing organization may elect to propose an
alternate way to meet the requirements. In cases where an alternate method is
proposed, the Review Team shall evaluate the proposed method to ensure that
it will be adequate to meet the requirements and provide a comparable level of
safety.
The Review Team shall verify that the implementation plan provides sufficient
detail to permit DOE to measure the progress towards meeting the DOE
requirements.
The Review Team shall also ensure that (1) the projected budget and schedule
information contained in the implementation plan is reasonable and consistent
with funding projections, (2) the prioritization of efforts meets DOE expectations,
(3) the proposed milestones and schedules will meet DOE needs, (4) the
Section 17
applicability of the requirements is correctly identified, and (5) the compensatory
actions are acceptable.
The Review Team should expect to see significant variations in the level of detail
and size of individual implementation plans because of the diversity of types,
sizes, and missions of DOE facilities. In order to facilitate timely reviews and
agreement on complex implementation plans, the members of the Review Team
should visit the site and/or facility and have frequent communication with the
implementing organization during both the preparation and the review of the
implementation plan.
5.4 Approval Responsibilities. DOE approval of the implementation plan
constitutes acceptance by the CSO that
(1) the proposed activities represent an acceptable
method to meet the requirements;
DOE-STD-1082-94
24
(2) the resources identified in the plan are necessary and
sufficient to ensure completion of the activities contained in
the plan and are expected to be available to support the
proposed schedules;
(3) the proposed milestones and schedules are acceptable;
(4) the applicability of the requirements is correctly identified; and
(5) the identified compensatory actions are acceptable.
5.5 Resolution of Issues. Review and approval issues related to a
specific DOE requirements document shall be brought to the Working Group for
resolution. Issues relating to the implementation plan process as a whole, shall
be brought to the RISG for resolution.
6. REVISIONS TO IMPLEMENTATION PLANS
The implementation plans are living documents which will need to be revised
and updated during the life cycle of the site, facility, or activity.
Approved implementation plans shall be revised as needed to reflect
the addition or deletion of other work at a facility or other factors that affect the
ability to meet the approved schedule, such as prospective changes in the
level of funding or assumptions regarding the availability of materials and other
resources. Several DOE nuclear safety requirements documents contain
conditions under which implementation plans may be revised without prior
approval from DOE. In such cases the implementing organization shall submit
the revised implementation plan to DOE within 30 days of the effective date of
the plan (unless another schedule is specified in the DOE requirements
document). All other changes to implementation plans shall be reviewed and
approved by DOE prior to the effective date of the change (this does not apply
to editorial changes which do not materially change the plan or revisions
required to reflect organizational changes). Revised implementation plans
shall be submitted in a timely manner for DOE approval (generally at least 180
days before the change is to be effective), along with justification for the
revision. Proposed revisions will be considered to be approved 180 days after
submittal to DOE, unless they are approved or rejected by DOE on an earlier
date or other provisions are stated in the DOE requirements document.
DOE-STD-1082-94
25
The changes to the implementation plan shall be clearly indicated (e.g.,
sidebars) to facilitate timely review. Revised plans are to be submitted to DOE
in the manner described in section 4 above and reviewed and approved in the
manner described in section 5 above.
Any changes to implementation plans which will result in a requirement not
being met require an approved exemption.
7. EXTENSIONS TO THE SUBMITTAL SCHEDULE FOR IMPLEMENTATION
PLANS
Section 18
An implementing organization may request an extension to the time allowed to
prepare and submit an implementation plan through the Operations Office
point-of-contact. The Operations Office point-of-contact will coordinate the
approval or rejection of an extension request with the appropriate CSOs.
Requests for extension shall be submitted within sufficient time for DOE to
review and approve the extension before the original due date. Extensions will
be granted only for good cause, such as the complexity of the plan or the
impact of multiple plans on an implementing organization's resources. Such
requests should be drafted as narrowly as possible to permit timely compliance
with as many nuclear safety requirements as possible.
An exemption is required to extend any schedule mandated in the DOE
requirements documents unless specific provisions for schedular relief are
provided.
8. IMPLEMENTATION TRACKING
Following approval of the plan and during the implementation process, the
DOE Operations Office shall oversee the contractor's progress in meeting the
commitments in the implementation plan (for example, schedules, milestones,
and costs) and maintain a dialogue on any problems that arise.
DOE-STD-1082-94
26
9. COMPLETION OF IMPLEMENTATION PLANS
Following completion of the commitments in the implementation plan, the
implementing organization shall retain a copy of the implementation plan, as a
record of implementation plan commitments. The implementing organization
shall also retain records which document the completed actions. The records
shall be maintained for the period of time that the facility or activity is subject to
the DOE requirements document.
The implementation plans will contain commitments to perform ongoing
activities, such as periodic surveillances to ensure ongoing compliance. By
their nature, some ongoing activities will not be terminated within the lifetime of
the facility. Consequently, the implementation plans will be considered
complete when all of the one time efforts are complete and the continuing
efforts are incorporated into plant procedures or programs which are being
implemented.
10. INCORPORATION BY REFERENCE
The implementing organization may choose to incorporate information into the
implementation plan by referencing all or selected portions of other
documents. In such cases, the portions of the referenced document which are
incorporated into the implementation plan are also subject to the provisions of
this standard.
Because referencing is an editorial tool, not all documents that are referenced
in an implementation plan will be "incorporated by reference." Consequently,
the implementing organization shall clearly indicate which documents (or
portions of documents) are part of the implementation plan commitments. The
implementing organization shall maintain a file of all documents incorporated
by reference and shall make these documents available to DOE upon their
request. See also section 4 above for submittal criteria.
DOE-STD-1082-94
27
11. SUBJECT TERM (KEY WORD) LISTING
The following list of subject terms (key words) is provided so that this
document may be found during retrieval searches.
applicability
baseline
compensatory actions
cost
exemption
funding
graded approach
guide
immediate action directive
implementation
implementation plan
milestone
manual
notice
nuclear safety requirement
order
prioritization
resource assessment
rule
Section 19
schedule
technical standard
tracking
CONCLUDING MATERIAL
Review Activities:
DOE HQ FIELD OFFICES AREA OFFICES
DP AL Amarillo
EH CH Brookhaven
EM ETEC Dayton
ER FERNALD Golden
FE ID Kansas City
HR NV
NE Oakland LABORATORIES
NN OR
PO RL ANL
PR RF BNL
RW SR INEL
Power Authorities LBL
BPA METC
WAPA PNL
LANL
LLNL
PPNL
Sandia
SSCL
SLAC
Preparing Activity:
DOE EH-62
Project Number:
SAFT 0017
DOE-STD-1082-94 Attachment 2
TYPICAL SCHEDULE FOR IMPLEMENTATION PLANS
DEVELOPMENT
Requirements document issued by DOE - 30 days
Requirements document effective (typical) 0 days
Review Team established 15 days
Review Guide issued 30 days
Initial site visit 60 days
Conference call 90 days
In process status meeting 120 days
Conference call 150 days
Submittal of plan 180 days
REVIEW AND APPROVAL
90 Day
Submittal of plan to Operations Office (Ops Office) 0 days
Ops Office sends plan to Review Team/CSOs 4 days
Review Team recommendation to Ops Office Manager 55 days
Ops Office Manager sends recommendation to Working Group 69 days
Working Group returns CSO approval to Ops Office 83 days
Ops Office Manager issues to implementing organization 90 days
180 Day
Submittal of plan to Ops Office 0 days
Ops Office sends plan to Review Team/CSOs 4 days
Review Team recommendation to Ops Office Manager 145 days
Ops Office Manager sends recommendation to Working Group 159 days
Working Group returns CSO approval to Ops Office 173 days
Ops Office Manager issues to implementing organization 180 days
FOREWORD
TABLE OF CONTENTS
1. SCOPE
1.1 Scope.
1.2 Applicability.
2. REFERENCES
3. PREPARATION OF IMPLEMENTATION PLANS
3.1 Implementation Plan Summary.
3.2 General Information.
3.3 Applicability of Nuclear Safety Requirements.
3.4 Safety and Implementation Guides and Technical Standards.
3.5 Baseline.
3.6 Additional Activities.
3.7 Graded Approach.
3.8 Resource Assessment.
3.9 Prioritization.
3.10 Milestones and Schedules.
3.11 Exemptions.
3.12 Compensatory Actions.
3.13 Tracking.
4. SUBMITTAL OF IMPLEMENTATION PLANS
5. REVIEW AND APPROVAL OF IMPLEMENTATION PLANS
5.1 Review and Approval Protocol.
5.1.1 Identification of Responsible Review Staff.
5.1.1.1 Implementation Working Groups.
5.1.1.2 Points-of-Contact.
5.1.1.3 Implementation Plan Review Teams.
5.1.2 Review Planning.
5.1.2.1 Implementation Plan Guide.
5.1.2.2 Implementation Action Plan.
5.1.2.3 Responsibility and Interface Matrix.
5.1.3 Meetings, Conference Calls, and Status Reports.
5.1.3.1 Initial Site Meeting.
5.1.3.2 Status Meetings.
5.1.3.3 Periodic Conference Calls.
5.1.3.4 Implementation Status Reports.
5.1.4 Submittal and Distribution of Implementation Plans.
5.1.5 Review.
5.1.5.1 Implementation Plans Reviewed by Review Teams.
5.1.5.2 Delegated Approval Authority for Implementation Plans.
5.1.6 Approval.
5.1.6.1 Approval Recommendations by the Review Team.
5.1.6.2 Operations Office Review of the Review Team Recommendations.
5.1.6.3 CSO Approval Memorandum.
5.1.6.4 Approval Letter.
5.1.6.5 Imposition of Implementation Plans.
5.1.6.6 Implementation Plans which are not Approved by Final Date.
5.1.6.7 Approval of Plans Containing Exemption Requests.
5.2 Distribution of Copies of the Final Implementation Plan.
5.3 Review Responsibilities.
5.4 Approval Responsibilities.
5.5 Resolution of Issues.
6. REVISIONS TO IMPLEMENTATION PLANS
7. EXTENSIONS TO THE SUBMITTAL SCHEDULE FOR IMPLEMENTATION PLANS
8. IMPLEMENTATION TRACKING
9. COMPLETION OF IMPLEMENTATION PLANS
10. INCORPORATION BY REFERENCE
11. SUBJECT TERM (KEY WORD) LISTING
CONCLUDING MATERIAL
TYPICAL SCHEDULE FOR IMPLEMENTATION PLANS