DOE-STD-1073-93 Part II, Guide for Operational Configuration Management Program
Functional areas: Operations, Configuration, Adjunct Programs, Design Reconstitution, Material Condition, Aging Management
This guidance is appropriate for high-hazard facilities expected to operate for an extended period. Since DOE facilities vary in hazard level and circumstances of operation, a graded approach to implementation should be adopted.
Unknown Block text
Version history and related documents
Superseded by
A newer version replaces this document.
- DOE-STD-1073-2003Configuration Management (Oct 01, 2003)
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
NOT MEASUREMENT
SENSITIVE
DOE-STD-1073-93-Pt.2
November 1993
DOE STANDARD
GUIDE FOR OPERATIONAL
CONFIGURATION MANAGEMENT
PROGRAM
Including the Adjunct Programs of
Design Reconstitution and
Material Condition and Aging Management
PART ll
U.S. Department of Energy AREA CMAN
Washington, D.C. 20585
DISTRIBUTION STATEMENT A: Approved for public release; distribution Is unlimited.
WELCOME
This Portable Document Format (PDF) file contains bookmarks, thumbnails, and hyperlinks to help you navigate through the document. All items listed in the Contents are linked to the corresponding sections. In addition, if you click on a section heading while you are reading the text, you will return to the Contents. Click on the DOE seal below to move to the Contents page.
This document has been reproduced directly from the best available copy.
Available to DOE and DOE contractors from the Office of Scientific and Technical
Information, P.O. Box 62, Oak Ridge, TN 37831; (615) 576-8401.
Available to the public from the National Technical Information Service, U.S.
Department of Commerce, 5285 Port Royal Rd., Springfield, VA 22161.
Order No. DE94005408
i
CONTENTS
FOREWORD . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . i
GLOSSARY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ix
ACRONYMS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . xv
BIBLIOGRAPHY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . xvii
PART I
CHAPTER 1
OPERATIONAL CONFIGURATION MANAGEMENT PROGRAM PRINCIPLES
1.1 Program Objective . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I–1
1.2 Functional Model . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I–3
1.3 Program Criteria . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I–4
1.3.1 Program Management Element . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I–4
1.3.2 Design Requirements Element . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I–7
1.3.3 Document Control Element . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I–8
1.3.4 Change Control Element . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I–9
1.3.5 Assessments Element . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I–10
1.3.6 Design Reconstitution Adjunct Program . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I–11
1.3.7 Material Condition and Aging Management Adjunct Program . . . . . . . . . . . . . I–13
1.4 Graded Approach . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I–15
1.4.1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I–15
1.4.2 General Process for Graded Approach . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I–15
1.4.3 General Application of Graded Approach . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I–24
Section 2
Appendix I–A CM Program Interfaces . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I–A–1
Appendix I–B Background Material and Conceptsfor Operational Configuration
Management . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I–B–1
PART II
CHAPTER 2
IMPLEMENTATION GUIDANCE FOR OPERATIONAL CONFIGURATION MANAGEMENT
2.1 Program Management Element . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–1
2.1.1 Program Planning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–1
2.1.2 Interfaces . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–8
2.1.3 Databases . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–9
2.1.4 Configuration Management Procedures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–11
2.1.5 Specific Application of Graded Approach: Program Management Element . . . . . . . . II–15
2.2 Design Requirements Element . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–15
2.2.1 Establishment of Design Requirements and Design Basis . . . . . . . . . . . . . . . . . . . . . II–17
2.2.2 Assignment of SSC Grades . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–24
2.2.3 Fully Developed Element . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–29
2.2.4 Specific Application of Graded Approach: Design Requirements Element . . . . . . . . . II–29
2.3 Document Control Element . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–29
2.3.1 Initial Development Activities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–29
2.3.2 Fully Developed Element . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–34
http://www.doe.gov/html/techstds/standard/std1073/s1073pt1.pdf
ii
2.3.3 Specific Application of Graded Approach: Document Control Element . . . . . . . . . . . . II–38
2.4 Change Control Element . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–39
2.4.1 Initial Development Activities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–39
2.4.2 Fully Developed Element . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–43
2.4.3 Specific Application of Graded Approach: Change Control Element . . . . . . . . . . . . . II–48
2.5 Assessments Element . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–48
2.5.1 Initial Assessments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–48
2.5.2 Post-Implementation Assessments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–54
2.5.3 Ongoing Assessments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–55
2.5.4 Specific Application of Graded Approach: Assessments Element . . . . . . . . . . . . . . . II–59
CHAPTER 3
IMPLEMENTATION GUIDANCE FOR DESIGN RECONSTITUTION
Section 3
3.1 Program Plans and Procedures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–61
3.1.1 Design Reconstitution Program Plan . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–61
3.1.2 Design Reconstitution Action Plan . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–65
3.1.3 Design Reconstitution Program Governing and Implementing Procedures . . . . . . . . II–65
3.2 Identification and Retrieval of Design Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–66
3.2.1 Identification and Retrieval of Source Documents . . . . . . . . . . . . . . . . . . . . . . . . . . . II–67
3.2.2 Extraction of Design Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–70
3.3 Evaluation, Verification, and Validation of Design Information . . . . . . . . . . . . . . . . . . . . . . . . II–70
3.3.1 Verification of Design Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–71
3.3.2 Technical Validation of Design Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–71
3.3.3 Release of Verified and Validated Design Information . . . . . . . . . . . . . . . . . . . . . . . . II–71
3.3.4 Correlation of Design Basis to Design Requirements . . . . . . . . . . . . . . . . . . . . . . . . . II–73
3.3.5 Technical Management Review of Design Information . . . . . . . . . . . . . . . . . . . . . . . . II–73
3.4 Resolution of Discrepancies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–74
3.5 Regeneration of Missing Critical Design Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–76
3.5.1 Regeneration of Design Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–76
3.5.2 Regeneration of Design Basis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–78
3.6 Preparation and Issuance of Design Information Summaries . . . . . . . . . . . . . . . . . . . . . . . . II–78
3.6.1 Pilot Design Information Summary Program . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–78
3.6.2 Design Information Summary Format and Content Guide . . . . . . . . . . . . . . . . . . . . . II–78
3.6.3 Design Information Summary Layout Guide . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–79
3.6.4 Design Information Summary Users' Guide . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–80
3.6.5 Final Verification of Design Information Summaries . . . . . . . . . . . . . . . . . . . . . . . . . . II–80
3.6.6 Issuance of Design Information Summaries . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–80
3.6.7 Field Validation of Design Information Summaries . . . . . . . . . . . . . . . . . . . . . . . . . . . II–80
3.6.8 Maintenance and Control of Design Information Summaries . . . . . . . . . . . . . . . . . . . II–81
3.7 Specific Application of Graded Approach: Design Reconstitution . . . . . . . . . . . . . . . . . . . . . II–82
CHAPTER 4
IMPLEMENTATION GUIDANCE FORMATERIAL CONDITION AND AGING MANAGEMENT
Section 4
4.1 Preliminary MCA Phase . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–85
4.1.1 Component Screening . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–85
4.1.2 Aging Degradation Mechanism Evaluations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–87
4.1.3 Estimation of Facility Remaining Lifetime . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–87
4.1.4 Feasibility of Continued Operations and Extended Operations . . . . . . . . . . . . . . . . . . II–87
4.1.5 MCA Program Plan . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–88
4.2 Detailed MCA Phase . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–88
iii
4.2.1 MCA Action Plan and Procedures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–88
4.2.2 Final Identification of Life-Limiting Components . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–89
4.2.3 Detailed Aging Degradation Evaluations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–91
4.2.4 Determination of Facility Remaining Lifetime . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–95
4.2.5 Feasibility of Continued Operations and Extended Operations . . . . . . . . . . . . . . . . . . II–98
4.3 Life Extension Techniques . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–99
4.4 Ongoing MCA Phase . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–99
4.4.1 Degradation Trending . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–100
4.4.2 Application of Life Extension Techniques . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–101
4.5 Specific Application of Graded Approach: MCA Adjunct Program . . . . . . . . . . . . . . . . . . . . II–101
Appendix lI–A Design Control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–A–1
Appendix II–B Examples of Design Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–B–1
Appendix II–C Conduct of Walkdowns . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–C–1
Appendix II–D Content of Design Information Summaries . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–D–1
v
FIGURES
CHAPTER 1
Figure 1–1 Operational Configuration Management:
Basic Relationships . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I–2
Figure 1–2 Operational Configuration Management Program:
Elements and Functions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I–5
Figure 1–3 Operational Configuration Management: Implementation
Considerations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I–17
Figure I–A–1 Relationship of a DOE CM Program to the Life of a Facility . . . . . . . . . . . . . . . . . . I–A–5
Figure I–B–1 Design Process . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I–B–4
Figure I–B–2 Assessments Element . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I–B–14
Figure I–B–3 Remaining Lifetime and Desired Lifetime . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I–B–18
Section 5
CHAPTER 2
Figure 2–1 Program Management Element:
Overall CM Program Development andImplementation . . . . . . . . . . . . . . . . . . . . . II–2
Figure 2–2 Program Management Element:
Management Actions for Program Planning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–3
Figure 2–3 Program Management Element:
Directives, Plans, and Procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–13
Figure 2–4 Design Requirements Element:
Top-Level Development Flowchart . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–16
Figure 2–5 Establishment of Design Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–18
Figure 2–6 Design Requirements Element:
CM Equipment Database . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–23
Figure 2–7 Design Requirements Element:
Assignment of System-Level Grades . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–25
Figure 2–8 Design Requirements Program:
Assignment of Component-Level Grades . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–27
Figure 2–9 Interfaces with the Fully Developed Design
Requirements Element . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–30
Figure 2–10 Document Control Element:
Top-Level Development Flowchart . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–31
Figure 2–11 Document Control Program:
Document Control Functions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–33
Figure 2–12 Document Control Program:
Document Control and Tracking . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–36
Figure 2–13 Change Control Program:
Top-Level Development Flowchart . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–40
Figure 2–14 Change Control Program:
Change Control Functions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–41
Figure 2–15 Change Control Program:
Design Envelope Review Process . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–44
Figure 2–16 Assessments Program:
Vertical Slice Methodology . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–49
Figure 2–17 Assessments Program:
Horizontal Slice Methodology . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–51
Figure 2–18 Comparative Procedures Review . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–53
http://www.doe.gov/html/techstds/standard/std1023/s1023pt1.pdf
vi
CHAPTER 3
Figure 3–1 Design Reconstitution Program:
Implementation Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–62
Figure 3–2 Design Reconstitution Program:
Sample Schedule . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–64
Figure 3–3 Design Reconstitution Program:
Design Information Identif ication and Retrieval . . . . . . . . . . . . . . . . . . . . . . . . . II–68
Figure 3–4 Design Reconstitution Program:
Evaluation of Extracted Design lnformation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–72
Figure 3–5 Design Reconstitution Program:
Discrepancy Resolution Process . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–75
CHAPTER 4
Section 6
Figure 4–1 MCA Implementation Process . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–86
Figure 4–2 Final Identification of Life-Limiting Components . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–90
Figure 4–3 Detailed Aging Degradation Evaluations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II–93
Figure 4–4 Identification of Aging Degradation Mechanisms . . . . . . . . . . . . . . . . . . . . . . . . . . . II–94
Figure 4–5 Identification of Material Condition Measurements . . . . . . . . . . . . . . . . . . . . . . . . . . II–96
Figure 4–6 Final Determination of Facility Remaining Lifetime . . . . . . . . . . . . . . . . . . . . . . . . . . II–97
DOE–STD–1073–93
II-1
CHAPTER 2
IMPLEMENTATION GUIDANCE FOR
OPERATIONAL CONFIGURATION MANAGEMENT
This guidance is appropriate for high-hazard facilities expected to operate for an extended period.
Since DOE facilities vary in hazard level and circumstances of operation, a graded approach to
implementation should be adopted.
2.1 PROGRAM MANAGEMENT ELEMENT
The program management element of a configuration management (CM) program coordinates program
development and implementation and ensures overall program effectiveness. This element leads the
development of the other CM program elements. Development of an effective CM program should be
initiated promptly, where needed, to address known issues, to improve compliance with various DOE
Orders, and to produce the benefits of improved safety, reduced errors, and increased efficiency.
Configuration management program definition and development necessitates the establishment of local
CM policy, philosophy, requirements, and strategies for development and implementation.
Configuration management program development activities should be performed in a phased manner
and should include milestones. Initially, development activities should focus on preparation of CM
program directives and plans. The CM program criteria indicate that the CM program plan should be
provided to DOE for review within 18 months of initiation of planning. Development of the CM program
elements begins after CM program plan concurrence and should be completed within 2 to 3 years (for a
large, complex facility). Program implementation should be initiated as each element is developed, with
full implementation of the five CM program elements, including satisfactory post-implementation
assessment, within 5 years. Adjunct programs such as design reconstitution could extend beyond 5
years. Once fully implemented, the CM program functions should be maintained throughout the life of
the facility. Figure 2–1 provides an overview of the schedule for CM program development and
implementation.
In the following sections, program management is described by function in the general order of its
Chronological development. The concepts and terminology, and equipment scope criteria functions are
discussed under program planning.
2.1.1 PROGRAM PLANNING
The CM program planning phase is of critical importance because it sets the direction and tone for future
development and implementation activities. Configuration management policy development is a top-
down activity, beginning with a general set of CM program criteria established at the site/division level.
The CM directives should be issued initially at the highest level of management (site/division) and flow
downward to the facility management level. In contrast with policy development, technical program
planning starts at the facility level and flows up to the site/division level. The site/division CM program
plan should be a consolidation of the facility CM program plans and should provide for implementation
variations for different facilities based on hazard levels, operational constraints, and other variables.
Figure 2–2 reflects the basic steps necessary for CM program planning.
Section 7
Through review and concurrence with the CM program plan, DOE acknowledges that the plan defines
the appropriate level of implementation, based upon the CM program criteria and the graded approach.
Once reviewed, the plan serves as the basis for future assessments of program effectiveness and
II–2
D
O
E
–S
T
D
–1073–93
II–3
D
O
E
–S
T
D
–1073–93
DOE–STD–1073–93
II-4
external audits. The program plan should be treated as a living document; it should be revised only as
necessary to reflect changes In program implementation. Proposed revisions to the CM program plan
should also be provided to DOE.
2.1.1.1 CM Policy Directives
Effective program management begins with a clear understanding and statement of management's
expectations. These expectations should be documented In a top-level management, site/division policy
directive specific to the subject. Configuration management directives provide the structure and
foundation for program development. These directives lead detailed program planning and program
element development., Per program criterion 1.3.1.1.a, the site/division CM policy directive should
accomplish the following objectives: convey top management support, define key roles and
responsibilities, provide the equipment scope criteria for the CM program, and establish key concepts and
terminology.
The principles of operational configuration management need to be understood and accepted by facility
personnel and integrated into their daily activities in order for the program to be effective. Management
has to clearly show support for the CM program and communicate its commitment to every level of the
organization for the effort to be successful. The CM policy directive should reflect top management's
decision, commitment, and support for the development and implementation of the CM program at each
facility.
The CM policy directive should also define key roles and responsibilities for developing the CM
program, Including the CM program plans. For example, it should formally empower a manager and
organization to coordinate development of the CM program and clearly define their roles and
responsibilities. If a central CM program organization is established, it should be involved in any
changes to existing programs that could affect configuration management. The directive could also
define the roles, responsibilities, and interfaces of other organizations and programs for development of
the CM program plan.
The CM policy directive should provide criteria for the scope of equipment to be included in the CM
program. The scope criteria provide the foundation for identifying the specific structures, systems, and
components (SSCs) and associated documents to be included in the program. This effort has a direct
impact on program effectiveness, costs, and schedules. Therefore, establishing the technical scope of
the program is crucial. As indicated by program criterion 1.3.1.2, SSCs with safety, environmental, and
mission design requirements should be included in the CM program. Other SSCs should be included
as an option; however, program cost and manageability should be considered.
Section 8
Establishing the scope of equipment involves defining both the general categories of equipment and the
specific criteria for its categorization. Input as to the existing categorization and recommended
revisions, if needed, should be obtained from the design authority. Sites/divisions should also establish
criteria and guidance specific to each category of design requirements. In fact, most sites/divisions
have existing mission criteria that might be useful to this end. As an example, the mission criteria might
be defined as including equipment whose failure could create a forced shutdown for 180 days or more.
Also, facilities may have existing safety criteria, such as thresholds based on DOE 6430.1A, General
Design Criteria (Section 1300-3.2). Sites/divisions should re-review existing criteria; provide any
additional criteria, guidance, or clarifications; and formally establish the criteria within the CM program
for design requirement categorization.
Finally, the CM policy directive should establish CM program concepts, terminology, and definitions to
ensure consistent usage and understanding, both within the program and among the various interfacing
programs and organizations. Many of the concepts and terms currently used regarding configuration
DOE–STD–1073–93
II-5
management derive from different programs and have various meanings depending on the context in
which they are used. CM concepts, standard terminology, and standard definitions should be
established in accordance with the definitions provided in the glossary provided in this Standard. These
key concepts and terminology, supported by a functional model of the site/division CM program, ensure
a consistent approach to facility CM program development. The site/division CM directive) should
formally adopt the CM program objective, functional model, and the functions to be used by the
facilities within the site/division.
Directives are also useful for establishing other upper-level CM policy and immediate actions relative to
program management functions such as database control and procedure development.
Figure 2–2 shows the process of establishing an interim CM development team dedicated and
committed to CM program development. This is the recommended approach because of the work and
interface efforts involved. To ensure an understanding of the needs and capabilities of the organization
as a whole, the team should be balanced with experienced personnel from different work areas.
Where several facilities are under the jurisdiction of a single management and operations (M&O)
contractor, the CM developmental team should have a mix of representatives from various facilities and
groups within the organization.
The CM development team should have a charter stipulating the activities consistent with its role in
coordinating overall CM program development. Such activities could include developing a formal
site/division CM directive for management approval early in the development process, working closely
with each site/division manager to develop directives, and providing support to each facility during the
development of the facility-level CM program plans. The details of program implementation should be
a line management function, but a small core group is usually maintained to provide the program
management functions necessary to ensure the proper implementation of the overall CM program.
2.1.1.2 Planning for Initial Assessments
Section 9
Site/division managers should take the lead in planning and coordinating initial assessments. These
assessments identify programmatic strengths and weaknesses for use as a basis for CM program
planning and for immediate corrective actions. As a first step, facilities should be grouped according to
mission, design, complexity, size, and other appropriate criteria. This action would allow for greater
efficiency in the assessment process. For similar facilities with similar CM practices, an assessment of
such practices for one site would be representative of them all. As a further example, several facilities
might use a central or common approach to document control; single assessment in this programmatic
area could be representative for several facilities.
Second, the specific representative facilities, systems, programs, and topical areas should be selected
for the initial assessments. Site/division managers should coordinate assessment activities such as the
selection of assessment teams, training, and funding. Sites/divisions could elect to go beyond the
minimum requirements in the initial assessments; the subjects of the other assessments would be
based on a judgment of needs. The initial assessments are conducted in accordance with the criteria
and guidance associated with the assessments element. When the representative assessments are
complete and the results are available, this information should be shared with other facilities in the
group (i.e., those found to be similar enough not to need separate initial assessments). Each facility in
the group should factor these assessment results into its facility CM program planning.
DOE may specify certain approaches to implementing a CM program on the basis of facility importance
or budget considerations. For example, it may elect to use certain lead facilities as pilots and to have
the others follow in a phased manner. Thus, lessons learned in the initial assessments, program
planning, and program development for pilot facilities can be applied to the remaining facilities for
DOE–STD–1073–93
II-6
greater cost-effectiveness. Wherever the pilot approach is pursued, priority attention to timely
assessment of the change control functions is warranted.
2.1.1.3 Initiation of Immediate Corrective Actions and Interim Upgrade Actions
The initial assessments should be conducted as planned and directed from the site/division level. If the
initial assessments of programs and procedures reveal major weaknesses that warrant corrective
action prior to the complete development and Implementation of the CM program, management should
initiate immediate corrective actions to mitigate these weaknesses. These immediate measures may
be replaced by Improved processes as the CM program matures.
Priority attention should be given to identifying and stopping uncontrolled and unauthorized changes to
the facility. If the initial assessments determine that uncontrolled changes are occurring, ft facility
should initiate immediate corrective actions, such as implementing an Interim change control program.
An effective approach to interim change control is lo require that nondesign organizations send all
potential changes to the design engineering organization for evaluation. This action may have to
remain in place until the change control element is fully implemented and design reconstitution efforts
are complete.
Section 10
An Interim upgrade of existing document control processes may also be necessary to ensure a proper
interface with the change control program and to improve document accuracy or retrievability. Other
areas that should receive priority attention, where major weaknesses are identified, are facility
walkdowns to establish the physical facility configuration and a formal review of summary design
information to establish an initial set of design requirements.
Interim measures are vital to prevent the continuing loss of facility configuration, thereby invalidating
other CM activities such as drawing and procedural updates. To the extent practical, interim measures
should be taken within existing program and organizational structures. In some cases, it may be
necessary to halt existing programs or processes temporarily until upgrade actions are completed.
Interim measures should be replaced by improved programs and processes, implemented within
normal line management structures, as the CM program matures.
2.1.1.4 Facility Program Plans
After the site/division directive is issued, facilities should apply the directive and develop facility CM
program plans. Configuration management program criterion 1.3.1.1.c identifies the topics that should
be addressed by CM program plans. The facility should adopt equipment scope criteria consistent with
the site/division policy directive. The facility should also review the site/division CM policy directive to
determine whether the equipment scope criteria for SSC inclusion can be applied as is or need
modification or clarification at the facility level. The CM program plan should identify the specific criteria
for each design requirement type. The specific list of SSCs is not necessary at this stage of program
development.
Much of the CM program plan will focus on the objectives and description of the CM program activities
needed to develop and implement each program element and function. A CM program plan format
organized by program elements and functions is likely to facilitate efficient application and review. The
development and implementation of each CM program element and function should be consistent with
the program criteria and the CM directive from site/division management. As an example, under the
program management element, the CM program plan should include descriptions of plans for
establishing appropriate interfaces, including vendor control; plans for developing CM governing and
implementing procedures, including associated training; and plans and criteria for CM equipment and
document databases.
DOE–STD–1073–93
II-7
The bases for the technical content of the CM program plan are (1) the findings of the initial
assessments and (2) the application of the graded approach. For example, the preliminary estimate of
a facility's remaining lifetime should be provided during the program planning phase and addressed in
the program plan. Initial assessment results and immediate corrective actions in response to the initial
assessments should be described in the facility CM program plan.
Section 11
Completed activities should be described to demonstrate CM program functions that are implemented.
For example, the CM program plan should describe the CM equipment scope criteria, the concepts and
terminology adopted, and any initial CM training. To evaluate existing functions, the contractor should
identity and analyze the existing program elements and functions, discuss the technical content of
those procedures Implementing the CM functions using functional flowcharts, describe the assignments
of responsibilities and authorities for configuration management, and define organizational and
functional interfaces by which the CM program is integrated into a cohesive program. Then, the
contractor should correlate the existing CM program elements and functions with the program criteria,
describe how the existing program and procedural requirements satisfy these criteria, and describe how
the existing program satisfies the CM objective. This analysis should build on the findings from the
initial assessments, which use applicable horizontal assessment techniques. The results of this
analysis should be documented in the CM program plan and should identify areas in which additional
work is needed to rectify any discrepancies between the existing program and the CM program criteria
discussed in Chapter 1. If DOE concurs that the combination of the existing CM program and identified
improvements is adequate, this would constitute a program that meets the program criteria.
The CM program plan should identify the organization that will have overall responsibility for developing
and implementing the CM program. It should include current staffing and a summary of key personnel.
It should also include estimates of staffing necessary to complete CM program development, along
with a staffing plan to meet these needs. Finally, the program plan should identify key organizational
interfaces and provide flowcharts, as appropriate, to show programmatic and organizational
relationships and responsibilities.
Once upgrade actions are identified, these should be prioritized both in relation to each other and in
relation to other planned facilities activities. Schedules should be developed in accordance with these
priorities. The CM program plan should provide schedules for implementation activities with defined
deliverables for each milestone. Cost estimates should be identified for each activity or deliverable. The
plan should also discuss the responsibilities and methods related to the management function of
monitoring progress in the development and implementation of the CM program. Questions such as the
following should be addressed:
• How will this monitoring be accomplished?
• What parameters will be used to gauge progress?
• How will problems be identified?
• What levels of facility management will receive periodic progress and problem reports?
• How will decisions to make midcourse adjustments to the program be made?
• Who in the contractors organization will be responsible and accountable for the progress
achieved?
2.1.1.5 Site/Division CM Program Plans
Facility plans should be consolidated into a site/division CM program plan. This upper-tier program
plan is intended to present both the individual facility CM program plans and additional summary
information such as summary schedules and costs for the site/division. During compilation activities,
the upper-level organization could ensure that the facility program plans are consistent with
expectations. In some cases, individual facility program plans might not be needed where the facility
Section 12
DOE–STD–1073–93
II-8
CM program can be fully described by an upper-tier program plan. The upper-tier program plan could
be developed as the general program plan with additional descriptions and clarifications as to how it is
applied to the individual facilities. In some cases, certain program elements or functions serve multiple
facilities. For example, document control could be established centrally for multiple facilities. In such a
case, the central document control measures would not have to be described in each facility's program
plan; they could be described once in the upper-tier program plan.
2.1.2 INTERFACES
Interface Control. Starting during development of the CM directives and continuing through program
planning and development, the CM program should identify and define the key programmatic and
organizational interfaces. Defining effective and efficient interfaces, both internal and external, Is critical
to the workability of a CM program.
Program interfaces are those relationships established to ensure that identification and integration of the
key facility programs are such as to effectively support and maintain consistency among the design
requirements, documents, and hardware. Program interfaces include those internal to the CM program,
such as the interface between document control and change control, as well as those between the CM
program and programs such as design control, project control (DOE 4700.1), surveillance testing,
maintenance, and any program or mechanism involved in defining, evaluating, and documenting
changes. As the fundamental approach to implementing the CM program is to identify, upgrade, and
integrate these existing programs, the program management element should clearly identify these
programmatic interfaces. Roles, responsibilities, and relationships among the program elements and
functions should be defined and documented. Relationships to other programs that interface with the
CM program should also be clearly defined and documented.
The CM program involves numerous interfaces among organizations. Organizational interfaces are
those relationships established to ensure that key functional organizations (such as design engineering,
operations, and maintenance) are aware of the roles, responsibilities, and interactions necessary for
adherence to the CM program. Organizational interfaces can be internal interfaces within the facility,
she, or corporate organization, as well as external interfaces with organizations outside the contractors
corporate structure. The program management element should entail identifying, formalizing, and
monitoring the organizational interfaces that can affect CM functions. Organizations and key personnel
involved in developing, implementing, and managing CM program activities should be identified.
Management expectations regarding the roles, responsibilities, and authorities of the organizations and
key personnel should be clearly defined and documented. Contractors might find it worthwhile to
designate CM program coordinators in each major organizational unit to ensure adequate interfaces.
External interfaces might need to be implemented by contractor interface agreements or formal
contracts, as appropriate.
Section 13
Often, the weakest parts of CM program implementation are the interfaces between the program
elements and the organizations implementing these elements. The accuracy and completeness of
configuration information transferred within and across organizational and functional boundaries is the
focus of the CM program, in that the transferred information establishes and maintains the CM program
basic relationships. Since information needs to flow among interfacing programs and interfacing
organizations (e.g., change control functions should provide current information to support document
control functions), flowcharts are the recommended tool for defining and analyzing program and
organizational interfaces. Flowcharts are particularly effective in identifying program interface points and
thus in exposing weaknesses in program integration. Having learned this lesson, some organizations
now use flowcharts as part of the development of every procedure. Procedure flowcharts should be
functional, not administrative (i.e., showing only the handling of forms and documents, not necessarily
the functions being performed along the way).
DOE–STD–1073–93
II-9
Vendor Control. Most DOE facilities use vendors or outside contractors for the performance of selected
technical work such as design change package development, safety evaluations, specialized analyses,
and construction. The greater the use of vendors, the greater the need for formal control. Vendors also
supply facility equipment and materials. Technical vendor control is the process used to ensure that
Important vendor activities and information support the facility's CM program.
The program management element should provide policy and procedures to ensure that important
vendor activities and information are consistent with the CM program. The CM program should provide
for the review and approval of vendor procedures prior to the commencement of work or impose the use
of facility procedures in all work performed at the facility. In addition, acceptance criteria should be
established by the facility to define when vendor work has been completed satisfactorily and is ready for
turnover to the facility. After turnover, vendor information used by facility personnel should be
incorporated directly into the facility document control program and kept current. The facility should
have sufficient resources and talent to judge the quality of work and ensure adequate control over
vendor activities. Vendor control measures might need to be implemented by contractor interface
agreements and formal contracts, as appropriate.
Special problems can arise regarding the control and use of vendor technical information such as
vendor manuals and notices. To simplify document turnover and control, facility management could
choose to review vendor technical information and excerpt relevant portions for direct inclusion into
facility procedures before that information is used by facility personnel. After turnover, vendor
Information used by facility personnel should be incorporated directly into the facility document control
program and kept current.
2.1.3 DATABASES
Section 14
The extent and interrelationships of CM-related information necessitate the effective development of
information systems such as databases, logs, indexes and cross-reference tracking systems, and
change status tracking systems. Objectives in the design of such systems include minimizing the
potential for conflicting versions of the same information in more than one system, maximizing the
flexibility and speed of information searches, establishing clear accountabilities for generating
information to be tracked and for tracking the information, ensuring that the information is, accessible to
those who need it, preventing unauthorized changes to the information, establishing a single authority for
any given information, and minimizing duplicated and otherwise redundant labor.
Well coordinated and controlled databases become primary focal points of effective CM programs.
There are two general types of CM databases that need to be established and controlled: equipment
databases and document databases. Equipment databases contain and correlate information about the
SSCs within the CM program, while document databases convey information about the documents,
including their status. Both databases provide information useful for the evaluation of changes. Properly
designed and well-managed equipment and document databases are essential (configuration
management tools; they support many functions important to safe facility operation. Such databases
are included in the scope of the CM program because they contain and correlate vital configuration
management information.
Because of the importance of these databases to the CM program, the program management element
should define policies and procedures for establishing and controlling them. A site/division CM directive
could be used to define general policy and criteria for CM equipment and document databases. The
CM program plans should discuss the steps necessary for developing (or validating) and controlling
these databases.
DOE–STD–1073–93
II-10
The program management element should identify the general contents of the two types of databases.
Their format, content, and capabilities should be adapted based on the identified needs and intended
uses. They should also be sized considering future needs by allowing for significant expansion of the
number of data fields and types of information. The program management element should also identify
controls for database development, implementation, and revision, especially those necessary to
establish and maintain the quality of information.
The steps to develop effective CM databases should include the identification of those databases that
contain CM-related information, the consolidation of related information into a few key databases, and
the establishment of control mechanisms to ensure data quality and accuracy. An initial study should be
conducted to identify existing equipment and document databases, their contents and uses, responsible
organizations, and locations. The initial study should reflect the results of, and may be performed in
conjunction with, other initial assessments.
Section 15
On the basis of the initial study, an action plan should be developed to consolidate or eliminate as many
of these databases as possible. A typical facility has many separate databases containing similar
information, with minimal interfacing or administrative controls. As a result, these databases develop
errors and inconsistencies, which contribute to configuration problems. A desirable approach is to have
all facility information computerized, residing in a master database, and accessible from most locations
within the facility. However, the time and investment for a new consolidated database should be
weighed against the need to establish a few well controlled existing databases. In some cases,
especially where databases are well coordinated and controlled, few changes are expected. In other
cases, where many databases are in use, some containing offering data because they have not been
coordinated or updated, more changes are appropriate. Key conclusions, milestones, and schedules
from the database study and action plan should be reflected in the facility CM program plans.
Procedures should be developed for control of the quality of information within these databases (for
example, procedures governing approvals, validation and verification of information, access and
security, and revisions), and there should be methods for retrieval of that information consistent with the
needs of the users. Special controls should be Instituted to ensure that any database used for
Configuration management purposes will be protected to prevent inadvertent or unauthorized changes
of the data. To be effective, the data collection function would have to be integrated into each CM -
related process and specified in written procedures. Collection of the necessary data should be
facilitated and standardized, and should be consistent with the normal flow of information. Data
collection should be supported by forms that are designed to prompt the owner or user for the
necessary information in a format that enables ready identification of the specific fields as well as
verification that the necessary information is present, coordinated, and approved.
Equipment databases should specify equipment classifications, contain or reference equipment design
requirements, and cross-reference supporting CM information. These databases should provide current
information on facility SSCs and associated documents within the CM program, with emphasis on design
documents. An approach that has proven successful elsewhere is the development of a computerized
CM master equipment database that includes every facility component. Each component is assigned a
unique identifier based on system, component type, and component function before it is included in the
database. This database can serve as the primary source of descriptive, testing, and operational data
on hardware and instrumentation. Equipment databases are discussed further in the implementation
guidance for the design requirements program element.
Document databases provide basic information about the documents in the CM program. Both
document and equipment databases include some relational information that links SSCs to documents.
Document databases provide more extensive document-specific information than equipment databases,
including information on change status and related documents (such as change notices and physical
DOE–STD–1073–93
II-11
Section 16
changes in progress) and pending changes. They also provide the capability to relate documents based
on types of documents, specific SSCs, groups of SSCs, technical topics, and other useful cross-
referencing topics. Document databases are discussed further in the implementation guidance for the
document control element.
2.1.4 CONFIGURATION MANAGEMENT PROCEDURES
This section discusses those vehicles or mechanisms that support CM program plans and directives by
communicating increasing levels of detail on program direction and guidance. The program planning
function provides top-level direction through CM policy directives and the CM program plan. The
procedures function provides CM program direction through CM action plans, CM governing procedures
and implementing procedures, and associated training.
2.1.4.1 Action Plans
Program management involves careful planning and effective controls to ensure that the effort is
credible, timely, and cost-effective. Starting from the program plan, facilities should prepare action
plans to provide further detail, as needed, on those program plan topics related to program
development and implementation. These plans should serve as an important vehicle to get the various
organizations and personnel at the facility to understand, accept, and support CM development efforts.
They are the primary management tool for coordinating development and implementation activities;
they should integrate and focus these activities to ensure that they can be implemented successfully,
managed effectively, and monitored for progress. Configuration management action plans should be
established promptly following DOE review of the CM program plan and before program development
commences.
Action plans should provide detailed direction in the areas of task descriptions, methods, assignments,
schedules, and budgets. They do not need to expound on the basis of the program. Action plans
should be consistent with the program plan but expand on implementation particulars. Regarding
assignments, for example, the program plan might identify divisions or departments responsible for
development activities, while the action plan would identify specific responsible individuals. Regarding
tasks and methods, where the program plan might, for example, state that the owners of each change
control process will be identified and that they will evaluate and upgrade their processes, the action
plan would identify more specific methods for process evaluation and upgrade, such as establishment
of process improvement teams, interviews with process users, preparation of flowcharts, interactive
sessions with trained facilitators, pilot implementation, and review by an executive sponsor and process
improvement specialist. With regard to schedules and budgets, the program plan might, for example,
establish a 2-year milestone for development and upgrade of the equipment database, while the action
plan might divide the activity into 15 identifiable tasks, each with a task description, deliverables,
milestones, a budget, and assigned personnel. Depending on program size and complexity, action
plans might be prepared for each CM program element, or even for the more complex individual
functions, such as databases or walkdowns.
Section 17
Action plans should provide more detail than program plans on process and quality controls, interface
control, communication methods, and progress-monitoring methods. They should identify how CM
development activities and results will be communicated throughout the organization, such as through
training, seminars, newsletters, and interdisciplinary teams. Action plans should also establish methods
for measuring and controlling progress, including objective parameters against which progress can be
measured, management accountabilities, regular internal status reports, and periodic management
reviews to monitor progress and resolve problems in a timely manner. While the program plan is
viewed as a commitment document and is revised only as needed, action plans should be revised
periodically until implementation is complete to keep them useful and authoritative.
DOE–STD–1073–93
II-12
2.1.4.2 Governing Procedures
Configuration management governing procedures should be developed after the CM program plan has
been reviewed by DOE and should support the action plan. Governing procedures should be
developed for each CM program element and adjunct program and should address each program
element function and its relationships. The CM program plan should identify the CM governing
procedures that will be developed.
The CM governing procedures provide the framework for integrating the implementation of the CM
program elements and functions. They should indicate how the CM functions are carried out in the
various implementing procedures, and thus, how those functions conform with the CM program plan.
The governing procedures describe how and when the CM program element is invoked and generally
how its functions are executed with reference to the detailed implementing procedures. Once the CM
governing procedures are in place, the CM program should be able to accomplish its objectives and
functions by adhering to these procedures and maintaining and updating them as needed.
The primary goal of the governing procedures is to provide overall coordination and integration of the
various implementing procedures and implementing organizations. As an example, a governing
procedure on document control would reference, describe, and show interfaces among the
implementing procedures for matters such as the drawing change process, the field change notice, the
design change notice, record retention, document distribution, the identification of key words, and
document tracking. Similarly, the change control governing procedure would identify implementing
procedures for approved change mechanisms and for such activities as the conduct of technical
reviews and the approval, implementation, and documentation of changes.
The CM governing procedures may also provide information useful for ensuring consistency in
implementation, such as the following: statements of purpose and applicability, definitions, top-level CM
program requirements (consistent with the CM program plan), key organizational interfaces, top-level
roles and responsibilities, key programmatic interfaces, and functional flowcharts showing relationships
among implementing procedures and among organizations.
Section 18
The governing procedure for the program management element should ensure that the overall CM
program is complete, coordinated, and integrated. It should identify the implementing procedures for
the program element functions and invoke the other CM program governing procedures. It could also
address the overall program model and functions, program scope, program interfaces, and
organizational interfaces and responsibilities. Much of this information will have been established by
the CM directives and plans; the overall governing procedure provides the top-level procedure for
ongoing implementation of the fully-established CM program.
Governing procedures are, in effect, an umbrella document for the implementation process. They can
be graphical in nature and take the form of functional flowcharts. Governing procedures in the form of
functional flowcharts are also helpful in identifying gaps in procedural links and conflicts between
specific implementing procedures. They can also identify decision points and places where quality or
management reviews are appropriate. These procedures can also be helpful for configuration
management orientation and training.
Figure 2–3 shows the development of the governing procedures in relation to the development of CM
policy, plans, and implementing procedures. The governing procedures provide the link between the
CM action plan and the implementing procedures.
DOE–STD–1073–93
II-13
DOE–STD–1073–93
II-14
2.1.4.3 Implementing Procedures
The program management element should also ensure that appropriate implementing procedures are
prepared for each CM program function. In contrast with governing procedures, the implementing
procedures provide the detailed instructions for carrying out CM program functions. Implementing
procedures are developed for individual program elements as needed. The size of the operating
organization influences the need to proceduralize CM activities; the larger the organization and the
more numerous the interfaces, the greater the need for procedural controls.
During the initial assessments and program planning, the organization's many existing procedures
implementing CM functions will be reviewed to determine If upgrades and enhancement!; are
necessary to satisfy the CM program criteria described in Chapter 1. Enhancement and integration of
existing implementing procedures within their established organizational structure Is the preferred
approach to CM program development and Implementation. It may be necessary or desirable,
however, to temporarily consolidate control of implementing procedures in a central CM development
organization for purposes of upgrade and integration. During this consolidation phase, it may even be
desirable to use the governing procedures to define implementation methods, and later move the
implementation methods and requirements to the implementing procedures. On completion of
implementing procedure upgrades, the revised implementing procedures would be redistributed to the
appropriate implementing organization for ongoing implementation.
2.1.4.4 Configuration Management Training
Section 19
As policy, plans, and procedures are established, associated training should be provided to
communicate expectations and to ensure effective implementation. In addition to standardizing
terminology and establishing an integrated system of procedures regarding CM activities, a formal
training program in configuration management can be very Important in property orienting facility
personnel. The program management element should establish and oversee CM program training
activities, including (1) initial awareness or orientation training, (2) follow-up training on development
and implementation of the CM program elements and functions, and (3) subsequent refresher training
as needed. As defined in the program criteria, training should be provided on CM concepts,
terminology, definitions, and procedures.
Training should be started early in the development of a CM program to acquaint users with the new
concepts, to ensure a common understanding of the objectives, and to communicate responsibilities for
implementing the program (i.e., CM-awareness training). Organizational culture change regarding
configuration management is a fundamental part of successful CM program implementation. For
example, facility personnel should be able to identify appropriate change mechanisms and always use
them. Training, supplemented by clear and documented expectations, and followed up with feedback
and coaching, is an effective tool for promoting the culture changes that are needed.
An effective approach to CM training is to provide 1 or 2 days of initial awareness training and then
follow-up training as CM procedures are developed and implemented. The initial training should be
conducted as early in the CM program development process as practicable, preferably after the
site/division CM directive is issued. This training should (1) provide an overview comprising a
description of the need, purpose, and management commitment and a definition of the CM program
and Its program elements, (2) explain the site/division strategy for developing and implementing the CM
program, and (3) identify any interim measures to be adopted until CM program development is
complete.
Follow-up training should be conducted as the governing and implementing procedures are written,
approved, and issued. The objectives would be to discuss and clarify individual roles, responsibilities,
DOE–STD–1073–93
II-15
interfaces, and key activities necessary to fully implement the CM program. The organizational and
functional CM flowcharts used in the CM program plan should be retained and used in the training
process. Training based on these charts may be started as soon as the concepts have been agreed on
and approved by facility management.
Refresher training would be provided periodically (e.g., once a year) for approximately 4 to 8 hours to
reinforce the principles of configuration management, to review implemented CM methods, and to
advise personnel on any changes In CM tools or practices.
2.1.5 SPECIFIC APPLICATION OF GRADED APPROACH: PROGRAM MANAGEMENT ELEMENT
The size and complexity of the facility indirectly affects the number of SSCs included in the CM
program. For example, at a small facility, such as a nuclear hot cell facility, there are not many SSCs.
Accordingly, the number of SSCs that can be included in the CM program will be small.
Section 20
The scope of the SSCs included in the CM program will affect the level of effort involved in every CM
program element and function. Facility management could (1) include all facility SSCs within the CM
program, (2) limit the scope to some minimum SSCs, or (3) choose a scope between these extremes.
At some facilities, it might be appropriate to limit the SSCs to those that provide personnel safety
protection. At others, such as nuclear waste tank farms, it might be appropriate to include those SSCs
that protect the environment. At other facilities, such as weapons facilities or alternate-energy
development facilities, it might be important to include the mission SSCs.
Because the magnitude of the CM program is so strongly influenced by the SSCs included in it,
contractor management might find it worthwhile to reevaluate the current classifications of systems
within the facilities. Some SSCs that have traditionally been classified as safety-related might not be
essential for safety. For example, many nuclear facilities have diesel generators that can provide
backup electric power in the event of a loss of normal power. Often, these generators are considered
safety-related because they have traditionally been classified that way. In some cases, safety is
assured regardless of the performance of the diesel generator. If the accident analysis can
demonstrate that an interruption of AC power for a significant period does not lead to unacceptable
safety consequences, and normal electric power is likely to be restored within that period, the diesel
generator is most likely not essential for safety. In such cases, classification of the diesel generator,
could be downgraded.
2.2 DESIGN REQUIREMENTS ELEMENT
As with other CM program elements, much more effort is necessary for initial establishment of this
program element than for its maintenance. For many facilities, establishing a complete and accurate set
of design requirements can involve more time and resources than any other CM program element.
However, this program element is essential because the design requirements are the foundation from
which the CM program basic relationships are maintained.
The top-level development flowchart for the design requirements program element is presented in
Figure 2–4. Existing design requirements are reviewed to establish the Best Available Design
Requirements. As new or revised design requirements are established, this information is fed into the
Best Available Design Requirements. Design requirements are correlated with SSCs through the CM
equipment database. With the design requirements established, system and component grading can be
accomplished. The two key inputs are the equipment scope criteria (from the program management
element) and the list of known SSCs. System grading establishes the scope of systems within the CM
program and assigns system grades according to the significance of the associated design
DOE–STD–1073–93
II-16
DOE–STD–1073–93
II-17
requirements. Component grading continues this SSC grading process at the component level. The
component-level grading activity also establish the system boundaries and refines the assignment of
components to systems. The SSC grades are fed into the CM equipment database.
2.2.1 ESTABLISHMENT OF DESIGN REQUIREMENTS AND DESIGN BASIS
The top-level flowchart for establishment of the design requirements is presented in Figure 2–5. This
process involves the review of existing design requirements, as well as the addition of new and revised
design requirements through design reconstitution and the ongoing design process.
Section 21
Configuration management program criterion 1.3.2.1 states that the design requirements and design
basis should be formally established, documents, and maintained. The CM program should identify the
various processes and procedures used to establish the design requirements and design basis. For new
facilities and physical changes to existing facilities, the program should ensure that procedures are in
place that adequately establish the associated design requirements and their design basis, and that
document them in a form suitable for use in the CM program. Documentation of the design
requirements includes their correlation with associated SSCs and their categorization by type (i.e.,
safety, environmental, mission, and other). Documentation of the design basis involves its correlation
with associated design requirements. Once the design requirements and design basis are established
and documented, the CM program should ensure that processes and procedures are in place to
maintain them so that they are complete and accurate.
2.2.1.1 Interim Measures for Design Requirements Element
During the development of the CM program plan, the effectiveness of existing programs and
procedures is assessed. These initial assessments may Identify cases in which the design
requirements and basis were not fully documented, not accurate, or not complete. The following are
examples of interim measures that may be needed until development of the design requirements
program element is complete:
• Additional controls to ensure that newly generated design requirements and design basis are
maintained and available
• Additional procedural guidance on sources of design requirements to ensure that an
adequate design envelope review is performed for potential facility changes
•� Additional procedural guidance to ensure that designers thoroughly research the existing
design basis before issuing new designs
• Additional procedural guidance to ensure that the design process produces a complete set of
design requirements and design basis for each new design or design change (See Appendix
lI–A for more information on various design controls.)
• Actions to prevent the destruction or disposal of source documents containing design
requirements and design basis information
• Actions and controls to ensure that the knowledge of experienced engineering and operations
personnel regarding facility design requirements and design basis is not lost when they
transfer or retire; this includes actions to collect and record design information from personnel
who recently transferred, retired, or are near retirement
Yes
DOE–STD–1073–93
II-18
DOE–STD–1073–93
II-19
2.2.1.2 Design and Construction Turnover
The operational CM program should establish formal criteria for the design and construction turnover of
new facilities or new modifications. When an effective interface can be established early in the design
process, it is more likely that the needed design products will be provided and turnover can be
successful. To ensure effective turnover, the operational CM program should (1) specify the format and
content of design basis and design output documents at design inception to ensure that they will be
compatible with the CM program needs, (2) periodically monitor the preparation of design basis and
design output documents, and (3) provide review and approval of the format and content of final design
basis and final design output documents and accept responsibility for their configuration management at
turnover.
Section 22
To ensure a format suitable for use in the operational CM program, the design requirements and design
basis should be differentiated, the design requirements should be correlated with the associated SSCs,
the design basis should be correlated with the design requirements, the design requirements should be
categorized (i.e., safety, environmental, mission, or other), and accurate as-built drawings should be
provided. Timely recognition of these interfaces and appropriate coordination will save time and avoid
additional costs after turnover.
Although it is highly desirable, it is not always possible for the operational CM program to be involved
with the designer/constructor during the design and construction phases. For example, a major new
facility might be ordered and designed before final assignment of the M&O contractor. In such a case,
the designer should be responsible for ensuring that the operational CM program has the necessary
turnover information in a usable form. If the operational CM program is not involved in the
design/construction process or if it fails to provide an effective interface, the operational CM program
should identify and implement any necessary steps to recover missing information.
As an example, the output of the DOE 4700.1 process, which controls the design for new acquisitions
and major physical changes, becomes the input to the operational CM program. If the output is in a
form compatible with the needs of the operational CM program, the turnover is acceptable and the
operational CM program can maintain the design requirements and their design basis.
2.2.1.3 Technical Management Review of Existing Design Information
With regard to the completeness and accuracy of existing design requirements and design basis, there
are many possible cases:
1. Facility design requirements and design basis are fully established, documented in an
integrated manner, and maintained so that they are complete and accurate throughout the
facility lifetime.
2. Facility design requirements and design basis are established and documented in various and
diverse design documents, and they are believed to be generally complete and accurate.
3. Facility design requirements and design basis are established and documented in various and
diverse design documents, but their completeness and accuracy cannot be demonstrated.
Case 1 is the desired objective of the CM program. Variations such as the above cases are expected
throughout the DOE complex because of such factors as the time frame of initial facility design and
construction, the CM practices during initial design and construction, the CM practices during the facility
operating life-cycle, and any design reconstitution efforts completed or in process.
DOE–STD–1073–93
II-20
As discussed in program criterion 1.3.2.1.b, a technical management review should be performed to
determine the adequacy of the facility design requirements and design basis. Judgments of adequacy
should be based on completeness, accuracy, and full documentation. The conclusions and the basis
for the conclusions regarding the adequacy of the facility design requirements and design basis should
be documented in the facility CM program plan. If the conclusion is that the design requirements and
their design basis are not fully documented, not complete, or not accurate, then they should be
reconstituted to the extent called for by the design reconstitution adjunct program.
Section 23
This technical management review should identify the actions necessary to evaluate the current status of
facility design requirements and design basis. It should consider the results of applicable assessments,
especially the initial CM assessments. The completeness and accuracy of the facility design
requirements and basis is one of the most significant areas to be evaluated during the initial
assessments. By correlating the design basis with the design requirements and the design requirements
with the physical configuration and facility documentation, the vertical slice assessment can provide
unique insights into the completeness and accuracy of existing design requirements and basis, as well
as into the effectiveness of past and present CM practices.
If the initial assessments support a definitive conclusion regarding the adequacy of the facility design
requirement and design basis, no further activities may be necessary other than a review of the
assessment results by technical management. However, if the initial assessments do not support a
definitive conclusion, the management review should identify additional actions to supplement the
findings of the initial assessments. The technical management review should include technical
managers having broad design backgrounds and experience and representing the various design
disciplines. Several different approaches to this review are possible. Whichever approach or
combination of approaches is chosen, it should focus on whether any design information is missing.
The technical management review process may include the following methods of assessing
completeness:
• Comparisons with industry codes and standards that identify expected design information
• Comparisons of like design requirements for comparable components
• Comparisons of like design basis for comparable design requirements
• Review of design information to identify SSCs with missing or incomplete information
• Review of open items and discrepancies that have not been resolved
• Review by independent, external, technical experts
In conjunction with the approaches listed above, a template approach may be used. A generic template
is prepared to identify the types of design requirements and design basis typical for a given SSC type.
The template is comprehensive and includes both the expected and possible design requirements and
design basis. The design requirements and design basis would be compared with the template to
identify missing requirements and design basis. For example, a template for piping might check for
design requirements such as basic flow diagrams, layout and arrangement diagrams, isometric
diagrams, support detail, material specification, testing requirements, and many other items. For the
design basis, the template for piping might check for pipe sizing/flow analysis, minimum wall thickness
evaluations, corrosion/erosion allowances, American Society of Mechanical Engineers (ASME) code
conformance, DOE commitments, system interface input requirements, design procedure
documentation, and many other items. Other examples of design requirement and design basis
information that could be appropriate for the templates are presented in Appendix II–B.
DOE–STD–1073–93
II-21
Inaccurate design requirements and design basis can be identified by discovering conflicting
documentation, a conflicting physical configuration, or errors (in calculation, for example) in the design
basis. To assess accuracy, the management review could employ some combination of the following
methods:
Section 24
• Checks of reasonableness by competent design personnel
• Checks to determine whether the design requirements apply to current physical configuration
• Reperformance of critical calculations and analysis independently or with different methods
The facility design requirements should be documented in a retrievable, user-friendly manner. The
relevant design information should be identified by system and an index of design documents should be
provided. To determine whether the design is fully documented, the management review should
consider whether: the design information is clearly identified; the design requirements are differentiated
from the design basis; safety, environmental, and mission design requirements are differentiated from
other types of design requirements; and the design documentation is indexed, integrated, and usable.
Objectives for the documentation of design information are provided in Chapter 3.
If design reconstitution is warranted, the management review should develop recommendations as to the
extent of design reconstitution needed and the associated priority.
2.2.1.4 System Design Descriptions
The CM program and engineering management may decide to prepare system design descriptions
(SDDs) to collect and summarize existing design requirements for each system and topical area. The
SDDs would help facility personnel understand system functions and requirements. They would include
system drawings and a system description, as well as descriptions of functional process requirements,
system and component design requirements, system interfaces and interlocks, setpoints, and design
requirements related to operations, maintenance, and testing. The SDDs could be predecessors of the
design information summaries (DISs) prepared by the DR adjunct program. They should be prepared in
a format convenient for adoption into the DISs that will be developed later. DOE Standard NE F 1-2T,
Preparation of Plant and System Design Description Documents, provides information on documenting
design requirements.
2.2.1.5 Configuration Management Equipment Database
The CM equipment database should be established to cross-reference the CM program SSCs with their
design requirements, design basis, and associated documents. This database is the primary information
source for design requirements. It should use the Best Available Design Information to fill the database
fields. This Best Available Design Information comes from three basic sources: (1) existing design
information, (2) new or revised design information, and (3) reconstituted design information.
Computer databases can effectively and efficiently support the design requirements element, serve many
users, and advance configuration management. Computer database development should maintain focus
on achieving the associated CM program elements and functions. The program management element
provides general direction, including general contents, for CM databases. Given the extent of the
contents, relational databases will likely be most effective, as they can relate records in one file to records
in many other files. For example, the equipment database should be able to identify the SSCs involved in
the fire protection program.
DOE–STD–1073–93
II-22
The CM equipment database should contain and correlate the following information:
Section 25
• System designators
• Component designators
• Component descriptive information such as type, manufacturer, model, and size
• Design requirement types applicable
• SSC grade (based on the most Important design requirement applicable)
• Design requirements or, at a minimum, references to them
• Design basis references
• Design topical area references (e.g., seismic, environmental qualification, fire protection)
• Facility document references (e.g., drawings, procedures, Safety Analysis Report (SAR) and
Technical Safety Requirement (TSR) sections)
• Other desired system and component information
A simplified sample format for a basic CM equipment database is provided as Figure 2–6. The actual
format, contents, and capabilities of an organization's CM equipment database will depend greatly on the
identified needs and intended uses.
As part of the establishment of design requirements, each SSC within the CM program should be
assigned a unique identifier, if one has not already been assigned. Unique identifiers that incorporate
system designators, component type, and numbers (e.g., SW-MOV-91) are more useful than strictly
numeric identifiers (e.g., 1357111317). The component identifiers should correspond to the labeling of
equipment for physical configuration. Unique identifiers and equipment labels are important for helping
maintain the CM program basic relationships and for supporting equipment operations. Operational
aspects of equipment designation and labeling are discussed in DOE 5480.19, Conduct of Operations
Requirements for DOE Facilities.
A database owner should be assigned, with roles and responsibilities established. As most of the
information is design information, the design authority is a likely choice. As such, the design authority
would be the focal point for resolving discrepancies and updating the database. Other organizations
should use the CM equipment database as their primary source for SSC design information.
Information necessary to complete certain facility document reference fields will likely come from
personnel coordinating implementation of the document control program element. The purpose of
these facility document references is to support identification of the affected documents when design
changes are made. The design authority can be expected to complete the document references that
relate to design information -- either design requirements or design basis. However, other organizations
will be assigned ownership of other documents important to configuration management (e.g., as-built
drawings; operations, maintenance, and testing procedures; SARs and TSRS). A central document
control organization may support completion of the affected database fields by coordinating database
input for nondesign documents and ensuring the ongoing integrity of that information.
2.2.1.6 Design Reconstitution Interface
The DR adjunct program, if pursued, contributes to the Best Available Design Information. The verified
and validated results of these efforts should be entered into the CM equipment database. Further, these
results should be reviewed for their impact on system and component grading while they are being
entered into the database. If design reconstitution is necessary, certain DR program actions, such as the
formal review of on-hand design documents, should be considered for prompt initiation to support
development of the design requirements element. For major design changes, it may also be desirable
to accelerate design reconstitution on selected systems and components. Implementation guidance for
design reconstitution is provided in Chapter 3.
Section 26
D
O
E
-S
T
D
-1073-93
II-23
SSC SSC Descriptive Safety Environmental Mission Other SSC Design Design Seismic EQ Fire
System Component Information Design Design Design Design Grade Rqmts. Basis Program Program Protection
Rqmts. Rqmts. Rqmts. Rqmts. References References Program
System 1 Comp. 1 • • • • 7 7 7 7 S Ref1, Ref2, •,•,• Ref1, Ref2, •,•,• 7 7 7
System 1 Comp. 2 • • • • 7 7 E Ref1, Ref2, •,•,• Ref1, Ref2, •,•,• 7
System 1 Comp. 3 • • • • 7 7 M Ref1, Ref2, •,•,• Ref1, Ref2, •,•,• 7
• • • • • • 7 S Ref1, Ref2, •,•,• Ref1, Ref2, •,•,• 7 7
• • • • • • 7 E Ref1, Ref2, •,•,• Ref1, Ref2, •,•,•
• • • • • • 7 7 M Ref1, Ref2, •,•,• Ref1, Ref2, •,•,•
System 1 Comp. M • • • • 7 O Ref1, Ref2, •,•,• Ref1, Ref2, •,•,•
System 2 Comp. 1 • • • • 7 7 E Ref1, Ref2, •,•,• Ref1, Ref2, •,•,• 7 7 7
System 2 Comp. 2 • • • • 7 7 7 S Ref1, Ref2, •,•,• Ref1, Ref2, •,•,• 7 7 7
System 2 Comp. 3 • • • • 7 O Ref1, Ref2, •,•,• Ref1, Ref2, •,•,• 7 7 7
• • • • • • 7 E Ref1, Ref2, •,•,• Ref1, Ref2, •,•,•
• • • • • • 7 7 M Ref1, Ref2, •,•,• Ref1, Ref2, •,•,•
• • • • • • 7 S Ref1, Ref2, •,•,• Ref1, Ref2, •,•,• 7
System 2 Comp. M • • • • 7 7 S Ref1, Ref2, •,•,• Ref1, Ref2, •,•,• 7
• • • • • • • • • • • • • • • •
• • • • • • • • • • • • • • • •
• • • • • • • • • • • • • • • •
• • • • • • • • • • • • • • • •
• • • • • • • • • • • • • • • •
• • • • • • • • • • • • • • • •
• • • • • • • • • • • • • • • •
• • • • • • • • • • • • • • • •
• • • • • • • • • • • • • • • •
Figure 2–6. Design Requirements Element: CM Equipment Database
DOE–STD–1073–93
II-24
2.2.2 ASSIGNMENT OF SSC GRADES
The grading of SSCs can be performed efficiently by separating system and component grading. The
systems are graded first the components to systems and graded next. This approach to grading calls
for increasing levels of design requirements knowledge as the grading proceeds to the component level.
For example, it might be obvious that a given system is related to safety, but less obvious that a given
component within that system has a safety function.
2.2.2.1 System-Level Grading
Facility structures may be categorized as either systems or components, whichever makes the most
sense for the facility. The facility may choose to address structures collectively as a single overall
system and address individual structures as components. Alternatively, individual structures may be
associated with the systems they house and support. Similarly, computers and software important to
facility operation should be evaluated as either systems or components, as appropriate.
A flowchart showing the basic steps for system-level grading is presented as Figure 2–7. The initial step
of system grading is to identify the facility systems. System designations already exist at most facilities.
If such designations do not exist, the components that accomplish the same basic facility functions and
processes should be grouped into systems.
The second step is to identify the types of design requirements that apply to each system according to
the best information on the design requirements available. (The specific criteria for each requirement
type will have been established during program planning.) For the Initial system grading, experienced
personnel with key design documents on hand are capable of applying their design knowledge to make
this determination quickly and accurately. Such summary design references include the facility SAR, the
TSR, SDDs, fire protection analyses, criticality evaluations, and any other readily available general and
summary design documents deemed appropriate by experienced personnel. Later, as design
requirements are formally reconstituted, the Best Available Design Information might indicate a need to
refine these determinations.
Section 27
The next step is to assign a system grade according to the types of design requirements that apply to
each system. The grade is based on the most important category of design requirements that applies.
For example, if a system has safety design requirements, it is a safety system. If it has mission design
requirements and neither safety nor environmental requirements, it is a mission system. For example, a
facility life-limiting component, as identified by the material condition and aging (MCA) adjunct program,
would be graded as mission if no higher grade applied.
2.2.2.2 SSC Inclusion In Configuration Management Program
Finally, the facility CM program equipment scope criteria are applied to determine which systems will be
included in the CM program. (These criteria should have been established by the program
management element equipment scope criteria function and documented in policy directives and the
CM program plan.) For example, the equipment scope criteria may be such that only safety,
environmental, and mission SSCs are within scope, in which case the optional systems are out of scope
and no further action is necessary for these systems. A facility may elect to include none, some, or all of
the optional systems. As another example, if only the safety SSCs were within the scope, the other
systems would not be included in the CM program.
New information relevant to system grading will be identified periodically in ongoing CM program
development and implementation as well as normal design and operations activities. This includes the
preparation of new designs. For example, the facility might add a new system that needs grading.
DOE–STD–1073–93
II-25
DOE–STD–1073–93
II-26
Further, the DR adjunct program might uncover facility design requirements that affect system grading.
The impact on system grading should be considered for any newly found information. While system
grading is generally a one-time activity, it is reviewed and revised, as necessary, when new information
becomes available.
2.2.2.3 Component-Level Grading
The scope of component grading is much greater than that of system grading because of the much
greater number of components. However, the grading process is analogous. In addition to assigning
grades, this activity also formally establishes the detailed system boundaries and refines the assignment
of components to systems.
Component grading should not be attempted until there is a fairly complete set of design requirements
and thus the necessary level of detail. Initial component-related activities should focus on establishing
system boundaries and assigning components to systems. Initial or default component grades
equivalent to the associated system grade may be assigned until the design requirements information is
complete. If design reconstitution is necessary, the formal review of on-hand design information
documents should be completed fairly early to facilitate component grading. A flowchart for component-
level grading is presented as Figure 2–8.
Section 28
List of SSCs. A complete list of facility components is essential if all possible SSCs are to be considered
for inclusion within the CM program. Existing configuration information in the form of a Master
Equipment List (MEL), required by DOE 4330.4A, Maintenance Management Program, or the equivalent
may be an adequate starting point for component evaluation. The initial CM program assessments will
examine the need for facility walkdowns to establish accurate facility drawings and equipment lists. The
CM program plan will reflect the results of these initial assessments. If comprehensive walkdowns are
not necessary and the component lists are essentially complete, system boundary evaluation and
component grading can proceed. However, if walkdowns or other activities are needed to define a
complete list of facility components, they will have to be coordinated with component grading. The
validated MEL should be combined with CM equipment data to form a single, complete equipment list
for the facility, contained in the CM equipment database, that will satisfy all data owners and users.
The first several steps shown in Figure 2–8 identify the scope of components that need grading. Known
components should be sorted into systems with other components that have the same basic functions
and processes or are located or connected together. Only systems that meet the CM program
equipment scope criteria need to be considered during the component-level grading activity. The next
step refines the system boundaries. Components are already assigned to systems at most facilities.
Following the refinement of system boundaries, it may be necessary to adjust the assignment of
components to systems.
System Boundaries. Facilities should carefully evaluate and define system boundaries. Systems should
contain those components that are necessary to fulfill the system's design requirements (e.g., the
functional and performance requirements). Design codes and standards often identify reasonable and
natural system boundaries. The following system interface considerations may apply to system
boundary evaluation:
• Location of piping class breaks
• Location of isolation valves
• Location of seismic class breaks
• Location of test features
• Supporting features and functions
DOE–STD–1073–93
II-27
DOE–STD–1073–93
II-28
In establishing boundaries between facility systems and essential supporting systems, arbitrary but
reasonable boundaries may be defined. Essential support services include electric and control power,
instrument air, lubricating oil, and ventilation.
There are two primary approaches, one recommended and one alternate, for establishing system
boundaries for essential support systems. The recommended approach is to extend the safety system
boundaries to include essential support items out to an appropriate interface, such as an isolation valve.
The alternate approach Is to deem the essential support systems to have safety portions. According to
the recommended approach for air-operated equipment, the air controller, solenoid switches, and air
isolation valves would be considered part of the basic safety system, while equipment upstream of the
valve would be considered part of the instrument air system. According to the same approach for
electrically operated equipment, the electrical components, including limit switches, out to and including
the first breaker, would be considered part of the basic safety system, and the components upstream of
the breaker would be considered part of the electric power system.
Section 29
Assignment of Component Grades. Component grades should be assigned in a manner analogous to
system grading. Best Available Design Information should be used to identify the design requirements
associated with each component and determine the design requirement types associated with each
component. In some cases, the design requirements might indicate that a component is not essential to
the system's top-level function. For example, a safety cooling-water system might have a chemical
release monitor with an environmental design function, but no safety design function. Component
grades should be assigned on the basis of the applicable types of design requirements. The component
grade should be based on the most important type of applicable design requirements.
As previously stated, the default component grade is the same as the system grade. In many cases, the
component is graded consistently with its system. The net result of component grading may be the
downgrading of certain components that are not essential to the top-level category of design
requirements for the system. For example, local instrumentation to support maintenance might not be
needed to fulfill either safety, environmental or mission requirements. If there is any doubt with regard to
downgrading a component, the component should retain the system grade until associated design
requirements are fully reconstituted. If a component appears to have design requirements of a higher
grade than its system, the system might be incorrectly graded or the component might be in the wrong
system.
With the exception of components whose design requirements have been established and found to be
adequate and outside the equipment scope criteria, all components within a CM system should be
included in the CM program, even those without a safety, environmental, or mission function. Once the
design requirements are fully established and adequate, the CM equipment scope criteria may be used
to consider component exclusions. However, the inclusion of components other than safety,
environment, and mission ones is generally advisable for CM systems to enhance overall configuration
control.
As with system grading activities, other ongoing activities will periodically identify new information
relevant to component grading. New design activity, for example, might add new systems as well as
new components to existing systems. The DR adjunct program might uncover facility design
requirements that affect component grading. Moreover, system walkdowns or operational activities
might identify previously overlooked components. The impact of new information on component grading
should be taken into consideration. While component grading is generally a one-time activity, its results
are subject to review and revision as necessary when new information becomes available.
DOE–STD–1073–93
II-29
2.2.3 FULLY DEVELOPED ELEMENT
A schematic for the fully developed design requirements element and its program interfaces is
presented as Figure 2–9. The design process can be initiated through change control processes that
involve requests for a wide range of engineering design support - from major permanent facility physical
changes to engineering evaluations for adjusting operations setpoints or revising maintenance and
testing requirements. Requests for engineering design typically include a description of the problem and
sometimes include a requested or proposed facility change. This information contributes to the design
inputs for the design process.
Section 30
After the design process establishes new or revised design requirements and their basis, the approved
design requirements are processed through the change control processes necessary to authorize,
implement, test, and document physical changes in the facility or changes in facility documentation.
When a design change affects neither the physical configuration of the facility nor facility
documentation, the approved design output documents may go directly to the document control
program element for a records update and distribution as appropriate. An example of this type of
design change would be a design reanalysis that discloses the need for a reduction in heat exchange
capacity from 88 to 80 percent. Design basis documentation may also be forwarded to document
control for storage and future retrieval. Revisions to the design requirements that affect the
assessments element should provide appropriate review and for execution of the various assessments
element functions. For example, a design change might specify in-service testing or post-modification
testing requirements. Additionally, design requirements might specify periodic monitoring criteria and
methods.
2.2.4 SPECIFIC APPLICATION OF GRADED APPROACH: DESIGN REQUIREMENTS ELEMENT
With respect to the establishment of the design requirements and design basis, a distinction is made
between new work and reconstitution. Design requirements and design basis should be developed for
new design work. For the reconstitution process of retrieving and regenerating existing design
requirements and design basis, these functions should be adjusted according to a graded approach, as
described in Chapter 3.
2.3 DOCUMENT CONTROL ELEMENT
Development of the document control element is discussed below in two stages: the initial
development activities and the fully developed program element. The initial development activities
include those actions necessary to identify and evaluate the existing population of documents and
document processes. The fully developed program element comprises the activities involved in
ongoing, steady-state document control.
2.3.1 INITIAL DEVELOPMENT ACTIVITIES
Initial development of the document control element is depicted in Figure 2–10.
2.3.1.1 Identification of Documents To Be Included In CM Program
Early in CM program development, a determination should be made as to which documents will be
included. The steps necessary to accomplish this are as follows:
FOR
DOE–STD–1073–93
II-30
Yes
Yes
Yes
DOE–STD–1073–93
II-31
DOE–STD–1073–93
II-32
• Identify document types used at the facility.
• Determine which document types should be in the CM program.
• Determine which specific documents should be in the CM program.
First, a complete survey of document types in use should be conducted with support of the various
organizations at the facility. Each organization should identify the document types it prepares and the
important document types it uses. Document types identified during the initial assessments should
also be addressed.
Section 31
After document types are identified, a document owner should be assigned to each document type.
The natural document owner is the person or organization responsible for developing and revising the
technical content of documents within the assigned document type. The owners should review the
document types for which they are responsible to identify those important for supporting the CM
program objective and criteria. They should then perform an importance evaluation In light of their
experience with, and knowledge of, the document types. Document scope criteria may vary according
to the importance of the SSCs involved. These criteria should be defined to include only those
document types that support the design or operation of facility SSCs included In the CM program.
Document types that reflect the facility's design requirements and those that are necessary for day-to-
day operation should receive the highest priority for inclusion in the CM program.
Finally, the document owners, with the assistance of those persons responsible for the document
retrieval function, should identify the individual documents within each document type and determine
which of these documents should be included in the CM program. To accomplish this, a determination
should be made as to whether that document supports an SSC that is included in the CM program.
The CM program equipment scope criteria and the specific list of SSCs within the CM program, if
available, should be provided to the document owners for support in their evaluation. For example, if
Quality Receipt Inspections were a document type to be included in the CM program, it would not be
necessary to include inspections that pertain to equipment not included in the program. The intent is to
include only those documents necessary to support configuration management. Documents specifying
requirements for day-to-day operations (e.g., procedures, drawings, vendor-supplied documents) and
those necessary for modifying the facility (e.g., design requirements, design calculations, accident
analyses) should be Included. If there is any doubt, the document should be included in the CM
program. It may be advantageous to coordinate this activity with the design reconstitution document
searches described in Section 3.2.
After identification of the specific documents for inclusion in the CM program, the following information
on each document should be recorded in the document databases to facilitate tracking and control:
document type, unique document number, and document uses and priority. This information should be
retained. Selected document information (e.g., SSC-specific drawings, procedures, and vendor
information) should also be entered into the CM equipment database to establish a cross-reference or
link between SSCs within the CM program and the associated documents.
2.3.1.2 Review and Upgrade of Existing Document Control Processes
For each document type to be included in the CM program, the adequacy of the existing document
control process should be evaluated against each of the basic document control functions. A survey of
existing document control processes should be conducted to identify the process that either identifies,
stores, controls, tracks, or retrieves the included document types. After the document control element
is developed, documents within the CM program should be processed in a manner consistent with the
model shown in Figure 2–11, as discussed in more detail in Section 2.3.2.
Section 32
DOE–STD–1073–93
II-33
DOE–STD–1073–93
II-34
Each identified document control process should be reviewed against the expectations for the fully
developed program. Deficient document control processes should be upgraded as necessary. For
example, if piping and instrument drawings (P&IDs) are to be included in the CM document control
element and it is determined that little formal control exists, the existing P&ID document control process
should be enhanced consistent with the requirements established by the CM document control element.
Various document control processes may also need to be consolidated to provide a consistent, reliable
approach. A centralized document control process is often the most efficient and effective, particularly
for the storage, tracking, and retrieval functions. A centralized approach should include satellite
document distribution stations if needed for user support.
The establishment of an effective document database should begin during the initial development stage.
As discussed in connection with the program management element, this involves a review of existing
databases, consolidation and upgrades as necessary, and the addition of any missing document data.
The document database is integral to the control and tracking function and the retrieval function of this
program element.
2.3.2 FULLY DEVELOPED ELEMENT
The following discussion presents recommended methods for and features of the basic document
control functions reflected in Figure 2–11.
2.3.2.1 Identification of Documents
The process for evaluating newly identified documents is similar to that outlined in Section 2.3.1. As new
documents are generated, they should be reviewed for inclusion into the CM program. To accomplish
this, the document owner determines if the new document supports an SSC within the CM program or
satisfies other scope criteria established for inclusion.
Once included, the document owner should categorize the new documents according to document type
and identify their uses and establish importance to users. Either the document owner or document
control organization should uniquely number each document and prioritize that document consistent
with its importance. The appropriate data on the document should be entered into the document
database with the appropriate data fields completed.
New types of documents may also emerge and have to be identified for inclusion in the CM program.
The identification of new document types for inclusion into the CM program should be considered
whenever new document types are established.
2.3.2.2 Storage of Documents
The objective of temporary and long-term storage facilities is to preclude damage or loss from
deterioration, larceny, or vandalism. Methods of storage should be based on the particular
characteristics of the document. Special consideration should be given to light-, pressure-, or
temperature-sensitive documents (e.g., radiographs, photographs, film) consistent with applicable
industry standards. Responsibilities should be assigned to ensure that records (active and inactive) and
other documents are protected, preserved, and stored such that they can be retrieved within defined
retrieval times. For example, a central document control organization may be assigned storage
responsibilities.
Storage and retention of documents should be in accordance with DOE Orders, specific commitments
to DOE, national standards, and the needs of the document owners and users. Many of these storage
Section 33
DOE–STD–1073–93
II-35
and retention requirements are already established and in place. The document owners may specify
retention times longer - but not shorter - than the minimums specified by DOE 1324.2A, Records
Disposition.
2.3.2.3 Control and Tracking
Figure 2–12 supplements Figure 2–11 by providing more detail on the process used to control and
track documents. Control features aim primarily at ensuring that only the currently-approved revisions
of documents are in use. Tracking features support this aim through the maintenance of information on
the current status of documents and the provision of information on pending changes. The major
features for the effective control and tracking of documents within the CM program are discussed
below.
Control Procedures. Procedures specifying the document identification, control, storage, and retrieval
requirements should be developed and implemented to ensure consistency in, and to facilitate
management of, the document control program. These procedures should establish responsibilities
and, methods for each document control function. Document change notices (DCNs) should be used
for the notification of document changes.
Secure File. A secure master file of the original documents or master copies should be established
and maintained. The master copies should not be released from that file; only reproductions should be
provided, either on a regular distribution schedule or in response to specific requests. Strict controls
should be established for the viewing of master copies. Access and security precautions should be
established to ensure that the document master file is controlled and kept current.
Controlled Document Distribution List. A controlled document distribution list should be established
and maintained. That list should Identify both the documents that are to be controlled and the holders
of copies of those documents. Users of documents should identify their document needs to the
document owners, who should determine the users to be included on the controlled document list. The
distribution list should include any satellite document distribution centers.
Identification of Proposed Changes. The document control organization should be notified of any need
to change a document as soon as that need is identified and approved. A DCN may be used for this
purpose. The document control organization, in turn, should provide a receipt acknowledgement of
such a notice to the originator. The document control organization should update the document status
in the document database.
Notification of Pending Changes. Pending changes are those changes for which conceptual design
has been approved and the design change is in process, those changes that have been approved for
implementation, or those approved unincorporated changes that have been implemented in the field,
but for which the document revision has not been completed. The document control organization
should provide notice of pending changes to the persons on the controlled distribution list for the
document involved. A notice of the pending change should also be attached to, or appropriately
referenced on, the affected master document, in order to alert anyone requesting a copy of the
document.
Section 34
Timely Incorporation of Changes. After the actual document changes are defined and are approved by
the document owner, the changes should be incorporated onto the document master copy in a timely
manner. The backlog of unincorporated changes should be controlled. Consideration should be given
to incorporating small changes in batches. On the other hand, a large backlog of unincorporated
changes adversely affects the value and usability of the documents. The number of unincorporated
changes should be limited by establishing a threshold to trigger the incorporation of the outstanding
DOE–STD–1073–93
II-36
DOE–STD–1073–93
II-37
changes for that document. The threshold level should depend upon the type of document, document
priority, complexity of the changes, and the degree of overlap of those changes. For example, using
such a threshold approach, the number of unincorporated drawing changes could be allowed to reach
two to five changes per drawing before the changes were actually incorporated on the document. The
document owners should also periodically monitor the incorporation of changes to ensure that the
threshold levels are effective.
Distribution of Documents. When a controlled document is issued or revised, copies should be
automatically sent to those on the distribution list associated with the document, along with a request for
written receipt acknowledgment. A receipt acknowledgement form may be used. Timeliness
guidelines for distribution of documents should also be established. In some cases, prior to the formal
document distribution, the most important documents, such as control room drawings are posted within
24 hours. Less important ones are posted within 72 hours. The least important ones are posted within
7 days. The recipients should update their copy of the document (for example, by inserting changed
pages), and discard any obsolete pages or copies of documents. The recipient should then return
written receipt acknowledgment to the document control organization. The controlled copies in use
should be periodically reviewed to ensure their accuracy and their consistency with the master copies.
Control of Superseded or Cancelled Documents. The document control process should include
measures to ensure that superseded or canceled documents are replaced. ff a copy of a superseded
or canceled document is requested, that copy should be clearly and distinctively marked as such.
Document Database. A database should be provided for use in tracking document status and pending
changes. This database should contain basic information about the document, including the document
number, the functional group or document owner, the document type, the current revision number, the
current document status (e.g., in revision, recently revised, needs to be revised), information regarding
pending changes, outstanding document change notices, and any other information necessary for
control and tracking. As discussed below, the document database also supports the document retrieval
function with associated information such as retention times, storage location, retrievability guidelines,
and key words. The document database should be controlled in accordance with policy established by
the program management element.
2.3.2.4 Retrieval of Documents
Section 35
Fundamentally, the document retrieval function ensures that documents are retrieved in a timely
manner upon request, and that when a copy of a document is issued, it is the most recent version. The
status of the controlled documents should be available to the affected organizations. Additionally, the
retrieval function ensures that information regarding pending changes, including references to detailed
information, is supplied to anyone requesting the latest copy of the document. For example, if a
drawing is requested, the document control organization should also provide the requester with a list or
copies of existing change information (e.g., outstanding document change notices, pending changes,
and related physical changes in progress). This will alert the requester to upcoming changes that could
affect the retrieved document.
The document database needs to provide the capability to support identification of relevant documents.
Numerous document identification systems possessing unique advantages and disadvantages
regarding time and resources are available. Document identification systems range from the simple,
manual control of hard copies to elaborate computer-based, keyword-searchable, full-text databases
linked to the document images. Variables that affect the type and degree of sophistication are the size
of the facility, the volume of documents included in the CM program, available resources, existing
programs, and the retrieval requirements of the users of these documents.
DOE–STD–1073–93
II-38
As defined in the program criteria, the document database should have the capability to identify
documents within the CM program on the basis of their relationship to particular SSCs (such as a
particular pump), types of SSCs (such as motor-operated valves), technical topics (such as fire
protection), and other relational data (such as the specific vendor) necessary for the adequate
identification of documents. This information should be integrated with the types of information
discussed above (e.g., information regarding pending changes) for document control and tracking.
Consideration should be given to assigning key words or using fully searchable text files for the most
important documents.
Availability and retrieval times should be based on the needs of document owners and users. If the
documents are necessary for the day-to-day operation of the facility, they should be available on a real-
time or short-turnaround basis (e.g., controlled copies of procedures and P&IDs should be located in a
central area such as the control room). Conversely, if the documents are not routinely needed and, if
time permits, a retrieval time of 24 hours or more may be acceptable; this is typical, for example, of
design basis information used by the design engineering organization for physical change preparation.
Many documents included in the CM program fall into the latter category; immediate access is not
needed. The selection of appropriate retrieval times calls for formally soliciting and considering input
from the document owners and the ultimate users of the documents. This should be followed by
periodic monitoring to ensure that document retrieval requirements continue to be adequate. Many
facilities employ satellite document distribution centers to encourage the use of controlled copies and to
facilitate timely retrieval from diverse work locations.
Section 36
In addition to DOE 5700.6C, ANSI/ASME NQA-1, Quality Assurance Program Requirements for
Nuclear Facilities, NQA-1 Supplement 6S-1, Supplementary Requirements for Document Control, and
Supplement 17S-1, Supplementary Requirements for Quality Assurance Records, also provide useful
guidance on document control.
2.3.3 SPECIFIC APPLICATION OF GRADED APPROACH: DOCUMENT CONTROL ELEMENT
The document control element is a process, and as such, the graded approach should not be used to
eliminate any steps or functions. The identification of types and specific documents to be controlled by
the CM program is a function that can be adjusted based on SSC grade. For any facility SSC, there is
a fairly standard list of types of documents that could be included in the CM program: lists of materials,
flow diagrams, electrical diagrams, isometric drawings, instrumentation logic and schematic diagrams,
and calculations and analysis. In many cases, especially for the less important SSCs, many of these
types of documents are not applicable or have never existed. Therefore, the inputs limit the scope.
Additionally, for each SSC, a conscious decision should be made regarding how much documentation
needs to be controlled to maintain configuration. For the most important SSCs, such as those with
safety design requirements, it might be appropriate to control every document type and specific
document that is available or can be retrieved. For low-importance SSCs, it might be appropriate to
control only basic documents, such as the design requirements, flow diagrams, and test requirements.
Documents that are not selected for inclusion within the special controls of the CM program would
remain available in the normal document control system.
Furthermore, management options may limit the degree of rigor and detail in the performance of the
CM document control functions based on document importance, which in turn is based on the
importance of the associated SSC and the priorities assigned by the document owners.
DOE–STD–1073–93
II-39
2.4 CHANGE CONTROL ELEMENT
The development of the change control element is discussed below in two stages: the initial
development activities and the fully developed program element. The initial development activities
include those actions necessary to identify and evaluate existing change mechanisms. The fully
developed program element entails the activities involved in ongoing, steady-state change control.
2.4.1 INITIAL DEVELOPMENT ACTIVITIES
Major change mechanisms and immediate actions to improve change control will have been identified
by the initial program assessments and described in the CM program plan. This serves as the starting
point for a complete review of existing change mechanisms or processes. During this evaluation,
corrective actions should be Initiated promptly where necessary to prevent unauthorized, unreviewed,
improperly controlled, and poorly documented changes. An overview of the initial development
activities is presented as Figure 2–13, and these activities are discussed in more detail below.
2.4.1.1 Change Process Identification
Section 37
A survey should be conducted to identify each change source (such as operations, maintenance,
procurement, procedures, and software) for each major change type (physical changes, document
changes, or design changes resulting in either). Facilities should focus on each change type (physical,
document, or design) individually to determine which sources initiate these changes and which
mechanisms are used to identify, evaluate, and control these changes. Input from each facility
organization should be solicited to identify the change sources and the control processes currently in
use. All change sources, mechanisms, organizations, and control processes that can possibly affect
configuration management should be identified. The identification of change processes is often the
most critical step to achieve effective change control. Change mechanisms that are not identified
cannot be controlled.
Facility personnel should strive to identify subtle change sources that do not conveniently fall in one of
the previously identified sources. Some change mechanisms exist independent of formal procedures
or processes. For example, if the system engineer approves minor changes such as different gaskets,
this should be identified and reviewed as a change source. Mechanisms for temporary physical
changes and temporary document changes should be identified for formal change control.
2.4.1.2 Change Process Evaluation
After the various sources of change have been identified, a determination should be made regarding
which of those processes after the configuration and therefore need formal controls. Formal control
measures should be provided for any change process that affects either (1) the physical configuration,
as defined by the SSCs included in the CM program or (2) the facility documents included in the CM
program. An example of a change mechanism that might be out of scope is the control of scaffolding
that cannot affect an SSC within the CM program (i.e., no system interaction through failing, etc.) or its
associated documentation.
The adequacy of the existing controls should be evaluated against each of the basic change control
functions, depicted in Figure 2–14 and described in Section 2.4.2. Checklists may be used to ensure
that the evaluations are complete and documented. Any weaknesses or deficiencies should be
identified. For example, if operations or maintenance personnel make undocumented changes to the
facility, existing controls are not adequate and do not meet the objectives of the CM program. Similarly,
if operations or maintenance personnel make changes without considering and documenting whether
ALL
Yes
DOE–STD–1073–93
II-40
DOE–STD–1073–93
II-41
DOE–STD–1073–93
II-42
these changes are supported by the design requirements, the associated change mechanisms need
attention. Corrective actions should be initiated promptly where necessary to prevent unauthorized,
unreviewed, improperly controlled, or poorly documented changes.
The conditions that initiate the change mechanism and the organizations that use the change
mechanism should also be documented. This information will support the evaluation of potential
consolidation of existing change mechanisms. It will also be useful as a starting point for a listing of
change mechanisms that should be Included in the governing change control procedure.
2.4.1.3 Change Process Elimination, Consolidation, and Upgrade
Section 38
For each change mechanism, a determination should be made as to whether it will be retained,
improved, or terminated. When deciding which change mechanisms to retain, consideration should be
given to (1) the extent and impact of improvement actions necessary to eliminate deficiencies and
weaknesses and (2) potential consolidation with other similar change processes. The ability to
effectively manage many change processes should be considered. Consolidation of a deficient change
process with a similar, acceptable change process is often preferred to upgrading the deficient process.
A typical facility may have a number of different organizations making changes to the facility using
many different control mechanisms. As a result, unnecessary management and control problems can
arise. To minimize these problems, consideration should be given to consolidating as many types of
changes as practical into a few well managed control processes for use by all facility personnel. For
example, various temporary physical change mechanisms, regardless of which organization (e.g.,
Engineering, Operations, Maintenance) is making the change, can be consolidated into a single
process.
For each change mechanism retained, upgrade actions should be defined to bring the process into
alignment with accepted methods and requirements established by the change control program
element. For example, the temporary change control process might be upgraded to include the
following needed features: technical reviews of proposed temporary changes prior to implementation;
preparation and distribution of interim, marked-up drawings and procedures for use by operators and
other facility personnel; and periodic assessment (e.g., at least every 6 months) of the continued need
of the temporary change until removal.
Change processes should be streamlined and efficient to ensure that they are used. Also, they should
be enhanced to accommodate change faster and easier. Change processing should be defined by
procedure for each approved change mechanism. Streamlining of internal program forms and
documents is important to improve comprehensibility and ease-of-use. This applies throughout the CM
program, but is particularly applicable to change control, which directly interfaces with the most
organizations and personnel. Effective internal forms and documentation associated with change
control have the following attributes: they facilitate complete and timely change identification and
control, they are user-friendly and encourage participants to use them, and they provide for
management tracking and reporting.
Upgrade and consolidation of change mechanisms typically include revised procedures, revised forms,
and associated training. Active involvement of the process owners in answering questions and
providing clarifications can be critical to a smooth transition to new or different processes. An
effectiveness review of the upgraded or consolidated processes after 6 to 12 months can be very useful
in defining further improvements and efficiencies.
The initial development of the change control element is complete after the change control processes
have been identified, reviewed, consolidated, upgraded, and determined to be acceptable.
DOE–STD–1073–93
II-43
2.4.2 FULLY DEVELOPED ELEMENT
Under fully developed change control, changes may only be identified, reviewed, approved,
implemented, and documented through change processes that have been determined to be adequate.
The following discussion presents recommended features of, and methods for, accomplishing each of
the basic change control functions, presented in Figure 2–14.
Section 39
2.4.2.1 Identification of Specific Changes
Specific changes should be identified only within established change processes. The need for a
potential change may be identified by anyone within the facility and should be documented by the
requester to support the processing of the change request. As defined by the CM program criteria,
each proposed change should be described adequately to support technical and management reviews
prior to approval. Change initiation should include the name of the requester, a description of the
proposed change, the affected SSCs and associated SSC grade, the reason for the change, alternative
solutions, due date, and constraints. It should also include any other information needed for review,
tracking, approval and further processing.
2.4.2.2 Technical Review of Changes
Effective change control involves formal, multidisciplined, technical reviews for each change. Some of
these are necessary to maintain configuration and others are defined as good management practices.
The technical reviews defined by the CM program criteria to maintain configuration can be grouped into
these areas: design envelope review; identification of affected hardware and documents; identification
of post-implementation acceptance criteria; and, safety, environment, and mission reviews.
Design Envelope Review. Design envelopes are pre-approved limits or constraints within which
changes may be made within the bounds of the design requirements. For example, suppose the
design authority has approved three different lubricants as acceptable for a given valve and specifies
that they may not be mixed. If the maintenance organization desires to switch from one approved
lubricant to another, the change needs to be recorded and documented; however it is not a design
change. As another example, suppose the design authority has specified a pump actuation setpoint as
55-65 psig and the operating organization has requested the actual setpoint of 62.5 psig to be reduced
to 57.5 psig to reduce spurious actuations. Again, the change is a physical configuration change, which
needs to be documented, but it is not a design change. As a third example, if the design authority has
determined, by evaluation, that the maximum number of plugged tubes for a specific heat exchanger
cannot exceed 15 percent, this value becomes the design envelope for future maintenance work. Up
to this limit, the maintenance organization does not have to check with the design authority each time it
needs to plug tubes because the number is within the design envelope. However, if the maintenance
organization needs to exceed this limit, evaluation and approval by the design authority needs to be
obtained, and a new design envelope may be established. The same approach may also be used for
setpoint changes, torque values, machining tolerances, vibration limits, or other routine activities where
design envelopes can be established.
Changes that are shown to be within existing design requirements or defined design envelopes do not
need evaluation by the design authority. Any personnel or organization, such as operations,
maintenance, technical support (i.e., system engineers), or others, may perform the design envelope
review, provided they are competent to make such an evaluation and have access to the appropriate
design requirements, or specific design envelopes. The CM equipment database provides access to
design requirements and design envelopes. Figure 2–15 shows the general approach for performing
design envelope reviews, described further below.
Section 40
Yes
Yes
Yes
Yes
Yes
DOE–STD–1073–93
II-44
DOE–STD–1073–93
II-45
First, a determination should be made regarding the desirability of design engineering support. Design
support may be desired for many reasons. If the organization performing the design envelope review
determines that design engineering support is desired for the design envelope review (e.g., based on
known changes to the design requirements or technical complexity), a request for design engineering
assistance should be made. Requests for design assistance may be made through the systems
engineer, the facility technical support organization (or other interfacing entity) or directly to the design
authority.
If the reviewing organization does not desire design support, the reviewer should determine if the
necessary design requirements or design envelopes are available for the review to proceed. If not,
assistance from the design authority is needed and should be requested. If requested, the design
authority could search the applicable information sources (such as the CM equipment database,
calculations of record, and design basis information) and provide this information to the requesting
organization to allow them to proceed with the design envelope review. If the design requirements are
not available, the design authority may need to develop new information, which will be included in the
CM equipment database. The design authority may also define design envelopes for future use.
If the design requirements are available, the proposed change should be compared to the design
requirements to determine if it is within the existing design envelope. The proposed change is ready for
additional technical reviews upon determination and documentation that the change is within the
bounds of the applicable design requirements. Organizations outside the design authority should be
conservative in their review of design requirements. The design engineering organization should be
consulted when there is any doubt as to whether the proposed change is within the design envelope.
If the proposed change is not within the design envelope, it involves a design change and design
engineering assistance is necessary to proceed. In some cases, the revised design requirement is
within the current design basis and, therefore, could be approved with relative ease. If the proposed
change is beyond the current design basis, the development of a new or revised design basis is
necessary to support the change. The new or revised design basis generally involves significant efforts
by the design authority and potentially includes external evaluations and approvals. In such a case, the
facility management would weigh the development time and investment against the benefits of the
proposed change. An adjusted, more cost-effective change might be possible that could accomplish
the objectives of the original change within the current design basis. Administrative review and approval
to develop the proposed design change should be obtained. The design authority can recommend
three general courses of action: (1) change the design requirements after reviewing applicable design
basis information; (2) suggest that the change request be canceled; or (3) suggest that the proposed
change be revised, if possible, to stay within the limits of the existing design requirements. The
requesting organization should select the option. For physical changes that are to be implemented, the
design authority should prepare a design change package consistent with the design process and
controls. The design change package may accomplish the additional technical reviews and should
facilitate outstanding technical reviews, management review, and implementation (i.e., with no further
action by the requesting organization).
Section 41
Identification of Affected Hardware and Documents. Once it is determined that a change can be made
within the defined design envelope or within new or revised design requirements, each affected SSC or
document within the CM program needs to be identified. This includes the documents that are directly
affected by the change, such as drawings. It also includes those that are indirectly affected by the
change, such as the SAR or a procedure containing a system drawing that will no longer be accurate.
By complete and thorough review, each affected item may be identified, thereby maintaining the basic
CM relationships during implementation of the change process. Examples of affected items that are
sometimes overlooked are design basis information, safety analysis reports, CM databases, operating
and maintenance procedures, and training lesson plans. The CM equipment database and the
DOE–STD–1073–93
II-46
document database should be used as primary tools to identify affected documents. Cross-disciplinary
and cross-organizational review may also be necessary if the databases do not provide adequate
information to complete this review.
Identification of Post-Implementation Acceptance Criteria. Methods and acceptance criteria should be
defined for post-implementation testing (e.g., post-modification testing for physical changes) prior to
change implementation. Post-modification testing ensures that the SSC performs as intended and
operates within the design requirements after the change is installed and before turnover to operations.
These tests serve as a final and independent adequacy check of the design and technical reviews for
the proposed change.
Safety, Environment, and Mission Reviews. Each change needs to be reviewed to ensure that the
safety, environment, and mission objectives are preserved.
Other Reviews. The following examples illustrate other reviews likely to be associated with change
development and approval, but not necessary to maintain configuration. Reviews performed as a
matter of good practice might include a review to determine the costs and benefits associated with a
change in order to facilitate management reviews and decision making. Facility walkdowns may be
necessary because there is a lack of confidence that the physical configuration is accurately reflected
in the as-built drawings. As another example, once the change is fully defined, the impact on the
operations schedule for implementation would generally be reviewed. Some technical reviews of
changes are imposed by external requirements. For example, DOE 5480.21, Unreviewed Safety
Questions, requires review of each proposed change to determine whether prior DOE approval is
required. In addition, DOE may have established additional reviews and review criteria consistent with
its management and oversight of the DOE-owned facilities. Additional reviews for determining quality
assurance actions may also be necessary.
Some DOE facilities use Change Control Boards (CCBs) for all or part of the technical evaluation of
changes. For CCBs to be effective, they need to perform the technical review functions discussed
above or ensure that they are performed for each change.
2.4.2.3 Management Review of Changes
As defined by the CM program criteria, management should review the proposed change to verify that
the technical reviews have been performed adequately, the change package is complete and ready for
implementation, any necessary external approvals have been obtained, and that the change is
authorized for implementation.
Section 42
Management reviews may also consider whether the need for the change exists, whether the benefits
of the change warrant the cost and schedule impacts, whether adequate resources are available for
implementation, or whether management approval should be based on other criteria. Some aspects of
these management reviews may take place prior to finalization of the change package; others,
subsequently. For example, management review and approval of proposed major design changes
would be expected prior to significant expenditure of resources.
Management review and approval requirements may vary based on the magnitude, cost, or the
importance of the change (grade of SSCs involved). For instance, changes related to safety SSCs
might call for senior management approval, while changes related to low importance SSCs might call
for only the approval of first-line management.
DOE–STD–1073–93
II-47
The management review process should be streamlined to the extent practicable. Management
reviews by many different levels and organizations can dilute accountability for a substantive review and
increase the review cycle duration without adding value.
2.4.2.4 Implementation of Changes
The change package should be reviewed prior to actual implementation of physical changes to ensure
that it is complete and constructible, that there are no unidentifiable physical interferences, and that the
change is likely to meet defined post-implementation acceptance criteria. This constructability review
should be performed independent of the original design organization. A modification or construction
package may be used to define implementation instructions.
Any deviations from the defined change package during implementation/construction should be
identified, reviewed, and approved by the design authority. Provisions for this process, often called field
change requests, should be defined by procedures. Following engineering evaluation and approval,
field change notices should be issued.
As-built documentation should be prepared at the completion of implementation of physical changes.
Post-modification testing should be performed in accordance with methods and acceptance criteria
defined during the change development. If an SSC fails to meet the post-modification acceptance
criteria, it should not be turned over for normal operations until either a technical review and any
necessary follow-up actions have been completed, or the SSC is returned to its original condition and
tested satisfactorily.
Special attention should be given to the partial implementation of changes. Two types of partial
implementation can occur: (1) staged implementation, where availability of time, money, or equipment
dictates that the modification has to be planned and implemented in a staged manner or (2) interrupted
implementation, where the implementation could not be completed as planned for any of a variety of
reasons. Failure to identify this condition and take the proper precautions can lead to the premature
closure of the modification package resulting in an unanalyzed condition, as well as facility
documentation that does not reflect the as-built configuration. Partially implemented changes should
be reviewed and approved by the design authority prior to operation. This design engineering review
should ensure that the original technical reviews are still valid or that new technical reviews are
performed, as necessary.
2.4.2.5 Documentation of Changes
Section 43
Change documentation is produced at each step of the change process (i.e., identification, review,
approval, and implementation). This is necessary to indicate what is accomplished, to ensure that the
details of the proposed change are established and understood, and to record as-built information.
The change documentation function is established as a unique and separate function within the change
control element to emphasize that change closeout ensures that the change documentation is
complete and all affected documents are identified and updated.
Because essentially every change directly or indirectly affects associated documentation, a major
interface exists between the change control and document control elements. Directly affected facility
documents, such as drawings, are confirmed to be as-built following implementation. Indirectly
affected documents are identified as part of the technical review of changes. The affected documents
should be updated in a timely manner. Critical facility documents, such as drawings and procedures
needed for operation, should be updated prior to placing the SSC in operation.
DOE–STD–1073–93
II-48
Change packages should be used to capture the change request, the various technical reviews and
evaluations, the management review, and the implementation results. Related information (such as the
change request, design package, installation package and, post-modification testing) should be
combined into a single file or change package. This information should be kept in one location until
installation is complete. Furthermore, consideration should be given to assigning an individual the
responsibility for tracking physical change status and ensuring that the change package is complete at
all times up to and including turnover to the document control organization after installation. Many
facilities have successfully used system engineers to perform this function.
2.4.3 SPECIFIC APPLICATION OF GRADED APPROACH: CHANGE CONTROL ELEMENT
Like document control, change control is a process. Once a design requirement is established for an
included SSC or a change is proposed, that information should be controlled by the change control
element. The level of effort is influenced primarily by the number of specific SSCs included in the CM
program and the number of changes that are proposed. However, management may exercise options
to limit the degree or rigor and detail when reviewing and approving changes based upon the
importance of the SSCs involved. For example, adjusting the degree of technical reviews and
management sign-offs to be commensurate with the SSC grade is appropriate.
2.5 ASSESSMENTS ELEMENT
The assessments element may be considered fully developed on completion of the following
• Initial CM programmatic and physical configuration assessments
• Detailed action plans and procedures for conducting post-implementation assessments
• Ongoing assessment programs established by procedure and effectively implemented
Senior management should retain overall responsibility for management assessments (i.e., all initial
and post-implementation assessments and the periodic program effectiveness assessments). Direct
participation of senior management during these assessments is essential. This process should also
involve other levels of management, as appropriate. Management assessment results should be
documented. Senior management should take prompt action and document resulting decisions in
response to recommendations resulting from the management assessment process. Follow-up should
include an evaluation of the effectiveness of management's actions.
Section 44
2.5.1 INITIAL ASSESSMENTS
2.5.1.1 Vertical Slice Assessments
The following is a description of the vertical slice assessment process. An overview of that process is
presented as Figure 2–16.
Identify the systems to be assessed. System selection is determined using judgment and anticipated
need to obtain a representative cross-section of existing SSCs, control programs, and document types.
For large, complex facilities, two or more vertical slice assessments are usually needed to detect
patterns and major existing problems the larger the number, the more accurate the results. As defined
by the CM program criteria, at least two representative vertical slice assessments should be performed,
with one on a safety system related to the principal facility hazard.
Collect and compare system-related information. A comparison is made between the available design
basis information and design requirements to determine consistency and technical adequacy. Special
Technical
Adequacy
Review
Sum
- - - - - - - - - - - - - -
Differences
Compare
by
Walkdowns
DOE–STD–1073–93
II-49
DOE–STD–1073–93
II-50
attention should be given to consistency between the assumptions made in different design basis
calculations; the design basis documentation and design requirements documentation; and, the design
requirements against one another and as reflected in the SAR, procedures, vendor material, and other
sources of design requirement information. Another comparison should made between documents
containing the design requirements and the as-built documents (such as drawings and procedures).
Inconsistencies, technical inadequacies, and missing information should become preliminary
assessment findings to be analyzed further.
Perform walkdowns and compare the existing physical configuration to the facility documentation.
Walkdowns are an integral part of a vertical slice assessment. They are performed to establish the as-
found facility physical configuration, the results of which are compared to the associated documentation
in order to identify discrepancies. Initial walkdowns provide insight Into the accuracy of existing facility
drawings. Walkdown methods and follow-up actions are addressed in the discussion of physical
configuration assessments In Section 2.5.3.2.
Evaluate preliminary assessment findings to identify programmatic strengths and weaknesses.
Correcting each specific finding without determining the programmatic deficiencies that allowed these
findings to occur is not the objective. Final analysis of the findings should result in the determination of
the extent of weaknesses and the underlying causes. For example, a discrepancy between the existing
configuration and the as-built documentation might be due to inadequate interfaces between the
change control and document control programs, while differences between the design basis
information and design requirements might be due to inadequacies in the design engineering process.
Once programmatic strengths and weaknesses are identified, this information should be factored into
the associated CM program plans to assist in CM program development.
Section 45
Develop corrective actions. As a result of the initial assessments, corrective actions should be
developed to address the identified weaknesses. Recommendations should be made addressing
programmatic deficiencies that, if corrected, will prevent these types of problems from occurring in the
future. The CM program management will evaluate the initial assessments, including recommended
corrective actions, and determine the appropriate actions for the facility. Program management should
take immediate corrective actions to remedy the major programmatic weaknesses. Further, specific
interim upgrades may be prudent in areas such as change control, document control, design control,
and physical configuration determination.
2.5.1.2 Horizontal Slice Assessments
The horizontal slice assessment process is described in the following sections. An overview of that
process is presented as Figure 2–17.
ldentify the programs or topics to be assessed. Likely candidates for horizontal assessments are the
change control program, the document control program, the design change process, a topical program
common to many SSCs, the design requirement documentation and design reconstitution efforts (if
underway at the time). As defined by the CM program criteria, at least two initial horizontal
assessments should be performed. One is to be conducted on the change control program and
another in a topical area such as seismic, fire protection, or environmental qualification.
Develop evaluation criteria that define the requirements for the program. These evaluation criteria are
similar to the performance objectives and criteria used by DOE and the commercial nuclear power
industry for conducting performance-based assessments. Examples of upper-tier evaluation criteria in
various areas of the CM program are as follows:
DOE–STD–1073–93
II-51
DOE–STD–1073–93
II-52
• A formal CM program is in place and governed by published directives, a CM program plan,
and CM implementing procedures.
• Organizational and programmatic interfaces, including responsibilities and authorities, are
clearly defined and understood by key personnel responsible for implementing CM program
functions.
• The design requirements for SSCs included in the CM program are identified, documented,
retrievable, and maintained current for use by facility personnel.
• Change mechanisms are identified and controlled.
• Proposed changes to facility hardware and documents are technically reviewed to ensure
consistency with the design requirements.
• Changes are documented and affected documents are updated.
• Documents within the CM program are consistent with the design requirements and the
physical configuration.
Compare existing program implementation with the evaluation criteria to determine strengths and
potential weaknesses. Determine whether the existing program is comprehensive and identifies
obvious omissions.
Figure 2–18 shows the recommended method for evaluating existing procedures. Starting at the top
left corner, the facility CM program criteria are identified by applying the graded approach to the
general CM program criteria. The existing programs and procedures providing configuration
management functions are then identified and analyzed. The program objectives, methods, and
procedures are considered. Functional flowcharts are developed for the existing procedures. This
evaluation of existing procedures can provide a basis for determining whether they are
programmatically adequate for accomplishing the CM program criteria.
Section 46
Based on functional flowcharts, judgments can be made regarding the strengths and weaknesses of
the processes prescribed by the procedures. An assessment can be made of how well the procedures
achieve their objectives and whether the procedural links and other interface considerations are
adequate. Using the functional flowcharts, an assessment also can be made regarding how well the
functions actually provided by the existing procedures match the functional criteria of the facility CM
program. The comparison of the functional capabilities of the existing programs may show that no
additional work is necessary to accomplish the CM program functions, or it will indicate where
improvements are needed. The functional flowcharts for existing procedures may indicate strengths
and weaknesses not related to the CM program; other improvements may be appropriate. Assessment
of procedures without the aid of functional flowcharts can result in misleading conclusions. The time
and effort involved in developing functional flowcharts is well invested.
Perform an effectiveness review in the field. This review is an assessment of how well the program is
implemented. During this step, information is gathered through interviews with knowledgeable facility
personnel, additional document reviews, and observation of work in progress to determine the
program's effectiveness at accomplishing the objectives. Therefore, emphasis during the effectiveness
review should be placed on problems. This performance-based approach is essential to identifying the
underlying causes of these problems and effectively upgrading a weak or poorly implemented
program. This is not a compliance review.
DOE–STD–1073–93
II-53
DOE–STD–1073–93
II-54
ldentify relevant programmatic strengths and weaknesses and make recommendations for
improvements. Compare the potential weaknesses identified during the document review step with the
problems identified during the effectiveness review step. Recommendations should be made to correct
programmatic weaknesses and prevent these types of problems from occurring in the future. Strengths
should be identified and acknowledged to ensure that resources are properly allocated for sustaining
program strengths. This information should be factored into the associated CM program plans to assist
in CM program development. The CM program management will evaluate the initial assessments,
including recommended corrective actions, and determine the appropriate actions.
2.5.2 POST-IMPLEMENTATION ASSESSMENTS
Post-implementation assessments to determine the adequacy and effectiveness of a program are
conducted shortly after program implementation and prior to final turnover to facility personnel for
ongoing use. These assessments are not compliance audits. Like initial assessments, these post-
implementation assessments employ vertical and horizontal slice methods. Post-implementation
assessments include CM program effectiveness assessments, DIS field validations, and MCA program
effectiveness assessments.
2.5.2.1 CM Program Effectiveness Assessment
Horizontal slice assessments should be performed shortly after each element of the CM program is
implemented (i.e., within 12 months of program element implementation). The main objective of the CM
program effectiveness assessments is to examine newly implemented CM programs and processes
(such as change control, the design requirements process, and document control) to identify and correct
weaknesses prior to authorization for use. These post-implementation CM program assessments also
serve as a model for ongoing, periodic program effectiveness assessments.
Section 47
The horizontal slice assessment techniques used for the post-implementation CM program
effectiveness assessments are identical to those employed in the initial horizontal slice assessments.
The recommendations for improvement resulting from the initial assessments should be used as a
starting point for the CM program effectiveness assessments. This will ensure that the previously
identified problems have been adequately addressed and resolved. The post-implementation program
effectiveness assessments should go beyond the initial assessment findings to ensure that the newly
developed and upgraded programs are effective. Assessment findings and corrective actions should be
documented.
2.5.2.2 Design Information Summaries Field Validations
As each DIS is issued by the design reconstitution adjunct program, a field validation should be
provided to ensure that the design requirements are accurately reflected in both the physical
configuration and the associated facility documents. Each DIS may receive varying degrees of
technical validation, ranging from a review of specific critical design basis information to detailed vertical
slice assessments of the entire system. Within each DIS, the system engineer or other technically
qualified person should check the critical design requirements information for consistence, with the
hardware and documents on a case-by-case basis.
Full vertical slice assessments should be performed on a sample basis to provide a broader
assessment of the design reconstitution process. The sample should be large enough to, provide
assurance that design basis information and design requirements established by design reconstitution
are accurately reflected in the physical configuration and associated documentation. A representative
sample of at least 5 percent per facility would be prudent. In selecting the sample systems for these
detailed DIS validations, the following criteria should be considered: status of original design and
DOE–STD–1073–93
II-55
construction documents, system importance to safety and mission, change history, and number of
outstanding open items identified during design reconstitution. Systems that support accident
prevention and mitigation and design documents for which the accuracy of the original calculations and
analysis were suspect, receive highest priority. If the representative sample indicates substantive
weaknesses, immediate corrective actions and assessment of an expanded sample should be initiated.
2.5.2.3 MCA Adjunct Program Effectiveness Assessment
An MCA adjunct program effectiveness assessment should be performed after the MCA program is
fully implemented but prior to final turnover to facility personnel for continued use. The main objective
of the MCA adjunct program effectiveness assessment is to provide a technical quality review of the
MCA methods used, input assumptions, and final products. This review should be performed by
persons other than those who did the work and should provide assurance that the MCA information was
property developed and is technically appropriate and accurate for its intended use. Therefore, the
MCA adjunct program effectiveness assessment should include, but not be limited to, an accuracy and
appropriateness check of the following:
• Final identification of the life-limiting components
• Detailed MCA analysis (evaluation of aging mechanisms and conduct of baseline
Section 48
measurements)
• Final determination of remaining facility lifetime
• Trend analysis and monitoring
• Life extension techniques (development and application)
2.5.3 ONGOING ASSESSMENTS
2.5.3.1 Periodic Program Effectiveness Assessments
These assessments periodically examine existing functions and processes related to the CM program
to ensure their continued effectiveness and to identify improvements and enhancements, if needed.
Similar to the initial assessments, periodic program effectiveness assessments use a combination of
vertical slice and horizontal slice assessment methods. Objective measures and criteria to assess
effectiveness should be defined and used. These periodic assessments should be used as the
technical basis for adjusting the CM program by increasing or decreasing the controls. Periodic
program assessments should be performed at sufficient intervals (such as every 3 years for full vertical
slice or horizontal slice assessments) after implementation to provide management with the assurance
that these CM control programs are functioning as intended.
2.5.3.2 Physical Configuration Assessments
Physical configuration assessments test whether the physical configuration is accurately reflected in the
facility as-built documentation. Physical configuration assessments, or walkdowns, are an integral part
of any vertical slice assessment, and therefore, they are included in initial assessments, post-
implementation assessments (related to DIS field validation), as well as ongoing assessments.
While the processes of walkdowns, as-builting, and vertical slices have significant overlaps, the
distinctions among them need to be understood. One distinction is based on the products of these
processes. Walkdowns produce a set of marked-up documents that reflect the actual physical
configuration and identify discrepancies with the currently-approved facility documentation. The as--
builting process produces as-built documents that have been field-verified and design-verified. Vertical
slice products include an evaluation of the extent, significance, and root cause of discrepancies
DOE–STD–1073–93
II-56
identified in walkdowns. Vertical slice assessments are primarily diagnostic and would not generally
produce discrepancy resolutions or as-built documents.
Walkdowns. During walkdowns, the as-found configuration is identified by comparing the existing
physical configuration with the facility documentation to identify any discrepancies, typically by marking
up the documents. Appendix 11–C provides detailed guidance for conducting walkdowns. Walkdowns
are sometimes conducted to record manufacturers' nameplate data from equipment, to identify missing
or incorrect equipment labeling, to determine the present material condition of equipment, and to
identify potential physical interactions between equipment (such as non-seismically qualified equipment
mounted In such a position as to impact seismically qualified equipment during an earthquake).
Physical configuration assessments may be performed on a sample basis, with the sample providing a
representative cross-section of component types within the system being assessed. The sample should
be large enough to ensure that a statistically significant portion of the system and its components are
chosen. For instance, the sample should Include major and minor components, large and small bore
piping, and instruments and controls. Minimum thresholds for determining an acceptable number of
discrepancies should be established prior to walkdowns based on proven statistical techniques (e.g.,
similar to those used in quality programs for the selection of samples and the determination of
acceptability).
Section 49
If the initial physical assessments confirm that the facility documents accurately reflect the physical
configuration, further physical configuration assessments should be included on a sample basis with
periodic program effectiveness assessments. However, if the initial physical assessments indicate that
substantive discrepancies exist (either in number or type) between the physical configuration and its
documentation, appropriate immediate corrective actions should be identified to establish agreement
between the physical configuration and the facility documentation.
The corrective actions for substantive discrepancies include additional walkdowns to characterize and
determine the extent of the problem. Sometimes the discrepancies can be isolated to certain systems,
certain modification vintages, or certain change mechanisms (modification processes). If the extent of
the problem can be limited, appropriate corrective actions can be directed at the root cause. Where
control of the physical configuration has been lost, walkdowns of every important system may be
necessary. In this case, a justification for continued operations may be necessary if continued
operations are desired.
As-Builting Process. As-builting is a process that involves determining the actual physical configuration
that exists at a point in time, identifying any discrepancies with the facility documentation, and
technically resolving those discrepancies. In some cases, discrepancies arise simply because the
facility documentation is incomplete or inaccurate in some details. In other cases, discrepancies arise
because inadequately controlled hardware changes caused the physical configuration to become
different from the facility documentation. The level of detail of a particular facility document type
establishes the threshold of the corrections that need to be made. If a facility document provides, or is
intended to provide, a level of detail that includes information that does not agree with the actual
physical configuration, those discrepancies should be identified and resolved. Leaving incorrect or
unverified information on a document is likely to mislead users of the document. Further, any
information that is left on as-found documents and has not been verified should be clearly identified.
The resolution of the as-found discrepancies needs a technical review to determine if the physical
configuration is correct (in accordance with the currently-approved design requirements) or if the facility
documentation is correct (the physical configuration is not correct). In some cases, the resolution of a
discrepancy might be to establish the acceptability of the existing physical configuration and change the
design requirements. Technical approval from the design authority (i.e., design verification) should be
DOE–STD–1073–93
II-57
obtained on discrepancy resolutions to ensure that the final configuration is consistent with the design
requirements. The end product of the process is as-built documentation that has been both field-
verified and design-verified.
2.5.3.3 Periodic Equipment Performance Monitoring
This ongoing assessment function verifies that selected SSCs continue to be able to perform their
intended functions (i.e., meet their design requirements). Equipment performance monitoring is
included in the CM program because it is important to maintaining the bonds between the physical
configuration and the design requirements. The results of this monitoring function should be used to
correct any equipment deficiencies that cause the equipment to deviate from the design requirements
and to identify any root causes of performance degradation.
Section 50
The fully developed program should include (1) implementing procedures established to specify and
control periodic equipment performance monitoring, (2) acceptance criteria defined consistent with the
design requirements, and (3) testing procedures established for frequently performed tests.
Performance monitoring programs should be implemented to routinely monitor, collect (using
calibrated instrumentation), trend, and analyze performance data (including thermal, hydraulic,
electrical, and mechanical data) for SSCs within the CM program. The methods of implementation
should include procedures, checklists, or other guidance documents necessary to conduct these
activities. Specific facility personnel, such as system engineers, should be assigned to each SSC and
held responsible for the performance monitoring activities on assigned SSCs. This responsibility should
include the establishment of performance goals and acceptance criteria consistent with the associated
SSC design requirements. Examples of major tests that should be included in the performance
monitoring program are as follows:
• Heat exchanger performance tests (e.g., fouling and heat transfer rate)
• Pump performance tests (e.g., head versus flow tests)
• Valve performance tests (including stroke times)
• Vibration monitoring for major rotating equipment
• Battery capacity and performance tests
• Other major equipment tests, as applicable (e.g., diesel generators and inverters)
The frequencies for each test should be specified in procedures and periodically reviewed to ensure
adequacy. Reviewing trend graphs of collected equipment data at specified intervals is a proven,
effective approach. For example, if the trend graph indicates that the equipment likely will not meet the
acceptance criteria at or before the next scheduled test, an adjustment in the test schedule and other
maintenance actions would be necessary.
For cost-effective implementation of this function, the timely recognition of interfaces with existing
program requirements is necessary. The equipment monitoring function interfaces with operations,
maintenance, and systems engineering programs. In some cases, adjustments to existing programs
may be sufficient to satisfy the need for ongoing CM assessments. Existing programs should be
reviewed to determine whether they are adequately oriented to maintain configuration and support the
objectives of the CM program and are adequately integrated with other important CM functions. They
should also be reviewed to determine whether their scope is sufficient to address the full breadth of
SSCs within the CM program.
Surveillance testing is typically performed to satisfy regulatory, code, or other requirements to ensure
operability of the equipment within established limits. For SSCs included in the CM program the results
of surveillance testing should be used to detect and correct any deficiencies that cause the equipment
DOE–STD–1073–93
II-58
to deviate from the design requirements. Surveillance testing techniques are similar in many ways to
those used In SSC performance monitoring. A comprehensive surveillance testing program ensures
that the identified testing is scheduled and performed, the results are reviewed and trended, and
necessary corrective actions are taken to return equipment performance to within the design
requirements.
Section 51
The periodic equipment performance monitoring function should take credit for periodic surveillance
testing, where appropriate. Full integration of the surveillance test program with other periodic
equipment monitoring can provide efficiencies in manpower and scheduling. Periodic testing, beyond
that in the TSR surveillance requirements, may be adjusted both In frequency and degree of technical
content based on the importance of the SSC or the particular SSC function. The origin of various
testing requirements should be documented and maintained.
DOE 4330.4A, Maintenance Management Program, establishes preventive and predictive maintenance
activities, such as tests, inspections, diagnostics, and trending. It further requires that a documented
basis for planned preventive and predictive maintenance activities should be provided. Existing
program to satisfy these Order requirements should provide a good interface with the CM program.
Existing programs should be reviewed to determine whether they are adequately oriented toward
maintaining configuration and achieving the associated CM program objectives.
Aging degradation monitoring is an important subset of equipment performance monitoring. It is
directed at detecting the impact of known and anticipated aging degradation mechanisms. The MCA
adjunct program will establish the technical basis for inspection and testing activities to trend important
characteristics, anticipate the time of failure, and detect component degradation, which can result in
systems and components operating outside their design requirements. The results of the MCA
program will be reviewed by the design authority to determine which should be implemented within the
periodic monitoring function (i.e., new design requirements). The assessments element supports the
MCA adjunct program by coordinating implementation of identified monitoring actions performed
throughout the life of the facility (i.e., during ongoing MCA implementation, after development).
2.5.3.4 Post-Modification Tests
Post-modification tests are performed each time an important SSC is installed or modified. These tests
ensure that the SSC meets the design requirements and is verified to be operable prior to being placed
into service initially or returned to service. This function prevents unintended changes from being
introduced through errors during design or construction. For physical changes, these tests serve as a
final and independent adequacy check of the design and technical reviews for the change. If a
changed SSC fails to meet its acceptance criteria, ft may not be turned over for normal operations until
either a technical review has been completed and any follow-up actions completed or the SSC is
returned to its original condition and tested satisfactorily.
The fully developed program should include (1) implementing procedures established to specify and
control post-modification testing and (2) acceptance criteria defined consistent with the design
requirements. A recommended approach is to develop a generic procedure for identifying the post-
modification tests to be performed and to invoke this procedure each time a facility change is made.
For the post-modification tests to be effective, test conditions should be consistent with normal and
emergency operating conditions and acceptance criteria should demonstrate that the applicable design
requirements are met. The dominant factor affecting the level of effort for post-modification testing is
the complexity of the design change involved.
Section 52
DOE–STD–1073–93
II-59
2.5.4 SPECIFIC APPLICATION OF GRADED APPROACH: ASSESSMENTS ELEMENT
The initial assessments are important in identifying the strengths and weaknesses of existing programs
and procedures. Accordingly, the more thorough these assessments are, the more representative and
accurate the findings will be. Initial assessments may be adjusted based on facility grade. As defined
in the program criteria, at least two vertical slices (one on a principal safety system) and at least two
horizontal slices (one on change control and one on a topical area) should be conducted. However, for
some small facilities that have limited hazards and are not complex, the number of vertical slices and
horizontal slices may be adjusted. The following table presents different levels of implementation for
the initial assessments, based on the facility grade.
ASSESSMENT
TYPE
FACILITY GRADE
High Medium Low Minimal
Vertical Slice Necessary Necessary Necessary Recommended
Principal Safety System
Horizontal Slice Necessary Necessary Recommended Optional
Change Control
Second Vertical Slice Necessary Recommended Recommended Optional
Horizontal Slice Necessary Recommended Optional Optional
Topical Area
This matrix applies to the case in which the facility grade is being applied directly to the CM program
general criteria. In other words, no other graded approach considerations (such as facility remaining
lifetime, etc.) have been applied. With application of other graded-approach considerations, the
implementation level may be adjusted further and this matrix would serve as an example of relative
priorities.
DOE–STD–1073–93
II-61
CHAPTER 3
IMPLEMENTATION GUIDANCE FOR
DESIGN RECONSTITUTION
This guidance is appropriate for high-hazard facilities expected to operate for an extended period.
Since DOE facilities vary in hazard level and circumstances of operation, a graded approach to
implementation should be adopted.
The implementation guidance is presented in the general sequence in which the design reconstitution
(DR) adjunct program is expected to be developed and implemented. Figure 3–1 presents the top-
level flowchart for the DR adjunct program.
3.1 PROGRAM PLANS AND PROCEDURES
3.1.1 DESIGN RECONSTITUTION PROGRAM PLAN
The DR program plan should address the topics defined in program criterion 1.3.1.1.c. It should be
prepared in accordance with direction set forth by the program management element of the CM
program. Although part of the CM program plan, the DR program plan may be provided to DOE
separately and should be developed as a stand-alone document.
The DR program plan should identify the scope of the Design Information Summaries (DISs), for both
the systems and for design topics, to be prepared. The DR program should prepare DISs for the
systems within the CM program scope. To reduce redundancy and ensure consistent application of the
topical information, the plan should identify design topics for which a separate topical DIS will be
prepared. Potential design topics include seismic qualification, fire protection, environmental protection,
electrical separation, single failure, and nuclear criticality.
The DR program plan should provide the method for prioritizing DISs. The priorities of DISs may be
based on safety significance, Technical Safety Requirements (TSRs) significance, probabilistic risk
assessments, facility modification schedules, impact on other DISs, and the specific needs of the
operating and design organizations. Highest priority should be given to those systems addressed by the
facility accident analyses or TSRs. The priorities are used to establish the order of DIS preparation.
Section 53
As part of the description of each DR program activity, the DR program plan should reflect the chosen
technical approach and methods for each DR program activity. Descriptions of program activities
should demonstrate how the program functions will be accomplished. Within each activity, there are a
number of management options that can only be evaluated and selected facility by facility. Examples of
these management options are:
• Selection of DIS topical areas
• Detailed methodology for comprehensive search
• Approach to management review to identify the missing basis
• Prioritization methods for regeneration activities
• Scope of regeneration activities
• Approach to the selection of regeneration methods
To clarify the DR program envisioned, program plans should describe selected options. The availability
and reliability of existing design information are key in DR program planning. The need for the DR
Prepare
Program Plan,
Action Plan,
and Procedures
Identify and Retrieve
Design
Information
Evaluate, Verify,
and Validate Design
Information
Prepare Rev. 0
Design Information
Summaries
Regenerate
Missing
Critical Design
Requirements
Resolve
Open Issues
Discrepancies
Regenerate
Missing
Critical
Design Basis
Prepare Rev. 1
Design Information
Summaries
Perform
Field
Validation
Issue Rev. 1 DISs
Issue Rev. 0 DISs
- Formal Review
- Smart Search
- Comprehensive Search
Figure 3-1. Design Reconstitution Program: Implementation Overview
DOE–STD–1073–93
II-62
DOE–STD–1073–93
II-63
program is based on the completeness, accuracy, and full documentation of existing design
information. The DR program plan should present the results and recommendations of the technical
management review performed under the design requirements element of the CM program. It should
reflect the graded approach and provide the basis for its application. The DR program plan should also
reflect the relevant findings of the initial assessments, including:
• Location of design documents
• Availability of design documents
• Control of design documents
• Consistency of information among design documents
• Immediate actions taken and planned
Four examples of different situations regarding the availability and reliability of existing design
information are:
• Almost no information readily available
• Moderate amount of information available; some essential information not readily available
• Moderate amount of information available; reliability of information questionable
• Vast amount of information available that is highly trustworthy
The DR program plan should identify key interfaces with other programs. For example, the Safety
Analysis Report (SAR) upgrade program is an important interface to establish. To this end, the DR
program would need to include early coordination with the SAR upgrade program to prevent duplication
and to ensure the effectiveness of both programs. The program plan should define interfaces with the
design requirements program element of the CM program and other CM program elements.
Phased Implementation. The DR program is performed in a phased manner with defined milestones
and associated deliverables. A phased approach to design reconstitution provides for an initial set of
design information, with further design information added as it is reconstituted. Each activity should be
scoped, prioritized, staffed, and funded as appropriate to ensure attainment of the defined milestones.
Section 54
The program criteria call for the DR program plan to be provided to DOE for review within 6 months
after the CM program plan is provided. Thus, the DR program plan may be provided to DOE up to 24
months following the initiation of CM program planning. Design reconstitution program activities should
not be implemented before an adequate CM change control element is available. Sample milestones
in design reconstitution beginning from the time DOE reviews the DR program plan (see Figure 3–2)
are as follows:
• DR action plan (0-6 months)
• Formal review (6-12 months)
• Smart search (1-2 years)
• Comprehensive search (2-4 years)
• regeneration of design requirements (2-5 years)
• Pilot DIS program (2-5 years)
• DIS Revision 0 completion (4-6 years)
• Regeneration of design basis (4-6 years)
• Field validation of DISs (5-7 years)
• DIS Revision 1 completion (5-7 years)
The issuance of completed DISs is also phased by system and topic; as individual DISs are completed,
they are issued. The phased preparation and issuance of DISs should be consistent with priorities
established by the DR program plan.
II-64
D
O
E
-S
T
D
-1073-93
II-64
DOE–STD–1073–93
II-65
Graded-approach considerations such as facility size and complexity can affect implementation
schedules; small, low-complexity facilities could possibly complete a DR program much sooner than the
sample milestones shown in Figure 3–2. Facilities that have already completed substantial design
reconstitution could also finish sooner than those that have done little or nothing.
3.1.2 DESIGN RECONSTITUTION ACTION PLAN
As described in Section 2.1.4.1, action plans provide additional detail to support program
implementation. The DR action plan should identify the program manager and project organization. A
clear management mandate and consistent management support are essential to success. Direct
involvement by the primary contractor for the facility is also necessary to ensure ownership; knowledge
retention; achievement of purpose; and continuing, effective DIS usage. Proper selection of the project
team is vital.
The DR action plan should also do the following:
• Identify DIS content and format. Facilities may have somewhat different uses that the DISs will
satisfy. A determination of the intended uses of the DISs provides the basis for the format and
content of the DISs. Examples of potential DIS applications are provided in Appendix II–D.
• Identify end users, as well as the review and approval process for project deliverables. Early
input and feedback from end users is crucial to the usefulness and use of DISs.
• Describe the DR governing and implementing procedures to be prepared. Such procedures
establish management control over the processes for developing, reviewing, and approving
DISs, and define and communicate the appropriate standards.
• Address programmatic controls and procedures for implementation of applicable portions of
the site/facility quality assurance (QA) plan.
• Identify periodic assessments of DR program activities. Throughout program implementation, it
is important to maintain a broad perspective and a questioning attitude regarding assumptions
and the use of information from reference documents, as well as the relationships and use of
information from resource documents. Periodic assessments can supplement training and
supervision in ensuring that a questioning attitude is maintained.
Section 55
The DR action plan should be revised and updated as the program proceeds. Initially, the plan should
provide the greatest detail on the earlier activities -- the design information retrieval activities.
3.1.3 DESIGN RECONSTITUTION PROGRAM GOVERNING AND IMPLEMENTING PROCEDURES
As an outgrowth of the DR action plan, an overall DR program governing procedure should be prepared
to provide coordination and integration of the various implementation procedures and implementing
organizations. The governing procedure should indicate how the DR program functions are carried out
in the various implementing procedures and, thus, how they conform with the DR program plan.
Governing procedures in the form of functional flowcharts are helpful in identifying procedural gaps and
conflicts between specific implementing procedures.
In contrast with governing procedures, the DR implementing procedures provide detailed instructions for
carrying out DR program functions. Development of DR implementing procedures to control technical
methods and interfaces should be completed before each activity begins. These procedures should
DOE–STD–1073–93
II-66
ensure a consistent approach from source document identification through DIS issuance. They should
address and control responsibilities associated with document preparation, review and approval
processes, and the long-term maintenance and control of completed documents. They should address
the activities necessary to implement the DR program, including the following:
• Personnel selection, orientation, and training
• Project interfaces (organizational and programmatic)
• Project control (schedule and milestones control)
• Identification of potential source documents
• Technical review of source documents
• Verification and technical validation
• Discrepancy resolution and open-item management
• DIS development (including format and content guide, and layout guide)
• DIS review and approval
• DIS field validation
• DIS maintenance and revision
3.2 IDENTIFICATION AND RETRIEVAL OF DESIGN INFORMATION
Identification and retrieval of design information are divisible into two distinct subfunctions: (1)
identification and retrieval of the source document that might contain design information and (2)
extraction of the design information contained in the identified source documents Each of these
subfunctions calls for unique experience and expertise. Identification and retrieval of source documents
involves identifying the document types and specific documents that contain design information, locating
the documents, and retrieving and cataloging the documents. Extraction of design information
presupposes technical expertise in recognizing and classifying various types of such information.
Identification and retrieval of design information is accomplished through three phased activities: formal
review, smart search, and comprehensive search. These phases correlate with increasing design detail:
the formal review concentrates on summary-level design documents; the smart search, the outputs of
the design process; and the comprehensive search, the remaining relevant source documents,
particularly those establishing the design basis for the design requirements. These phases differ
primarily in scope. During each phase, after the source documents are identified and retrieved, the
source documents are reviewed to extract the relevant design information, both design requirements
and design basis. The approach to design information extraction should be essentially the same,
regardless of the source document. The cumulative result of these activities at any stage constitutes the
Best Available Design Information.
Section 56
Facilities should identify pilot DR activities to gain experience and to solidify methods. For example, a
selected file room could be reviewed initially to identify and retrieve source documents. Then, this effort
could be critiqued to improve the methods used before going on and applying the approach to other
document locations. Similarly, pilot extraction efforts on selected documents could be useful in refining
extraction methods and procedures. Appropriate implementation procedures could be prepared and
then tested by pilots to control each activity. Further, where adequate design information is not
available, individual facilities may also identify supplementary activities for design reconstitution. For
example, facility walkdowns to gather nameplate data could be undertaken, if necessary and beneficial.
Concurrent with DR efforts, the normal design process continues to generate new and revised design
requirements and the design basis. These normal design activities also contribute to the Best Available
Design Information. Controls should be in place to ensure that ongoing design process efforts and DR
DOE–STD–1073–93
II-67
efforts are coordinated. For major design changes, it might prove necessary to accelerate the design
reconstitution of associated systems and components.
3.2.1 IDENTIFICATION AND RETRIEVAL OF SOURCE DOCUMENTS
Throughout these searches, the document control organization should provide support in locating and
retrieving the subject documents. If possible, these search activities should be coordinated with
document control activities that identify that organization's design and configuration documents.
Documents identified during the searches should be reviewed for inclusion into document control
processes and systems, such as the CM document database. A comprehensive index of design
documents is a very useful tool until design reconstitution is completed. Figure 3–3 shows the key steps
of source document identification and retrieval.
3.2.1.1 Formal Review
The formal review of on-hand, summary-level design documents is the first stage of identification and
retrieval of existing design information. The scope for this review should be limited to readily available,
top-level design documents such as SARs, Technical Safety Requirements, and System Design
Descriptions (SDDs), if available, and other top-level synthesis and summary-type design documents.
Through document identification and information extraction, the formal review establishes the
preliminary set of design requirements and the design basis. For facilities with inadequate design
requirements (as determined by the CM program initial assessments or otherwise), the formal review
may be needed to support initial development of certain portions of the DR program element (i.e.,
establishment of the CM equipment database, initial system categorization, and initial system grading)
and may be pursued as a priority action within CM program implementation.
3.2.1.2 Smart Search
The smart search identifies and retrieves those types of documents most likely to contain design
requirements. It culminates in the identification of most of the retrievable design requirements as well
as the design basis information contained in the associated source documents. The smart search
provides an expedited input to the CM equipment database for use by design and other facility
personnel. The documents that are most likely to contain design requirements are the design output
documents. These documents include drawings, specifications, load lists, valve lists, operational
setpoints, maintenance and test requirements, and construction and installation instructions. Further
examples of design output documents are provided in Appendix II–B.
Section 57
Experienced personnel can provide insight into the most likely document types and their locations.
Experienced facility personnel might know of facility-specific documents that are not design output
documents but are likely to contain design requirements; the smart search should target these
documents. While certain design analyses and calculations might contain design requirements, such
documents should generally be reviewed during the comprehensive search, which focuses on source
documents containing primarily design basis information.
To capture the facility design requirements, the smart search scope may have to include facility
documentation that reflects the as-built design. Original design documents are preferred over
reconstituted as-built documents but are not always available. Sometimes these reconstituted as-built
documents use nameplate rating as the design requirement, lacking better information. This approach
presumes that the design is competent and the nameplate rating meets or exceeds the requirements
determined by the original design. In most cases, the structures, systems, and components (SSCs)
can continue to meet their nameplate ratings and detailed analysis of the original design requirement is
DOE–STD–1073–93
II-68
DOE–STD–1073–93
II-69
not necessary. If, however, a test indicated a component (e.g., a pump) could no longer meet its
nameplate rating, the design engineering organization would reevaluate the design requirement.
Document types may be identified before they are located, as indicated in Figure 3–3. They may also
be uncovered by surveying files at storage locations known to contain design documents. The
locations can range from vendor files and warehouse storage to individual design engineer files. Many
original design documents may be stored in warehouses or other files and not be easy to retrieve.
To facilitate document review, it is useful to (1) assign each document a unique identifier to facilitate
control and tracking and (2) perform an initial or receipt inspection to ensure that the documents are
readable and complete. If the documents are not already indexed as to technical content, facilities
should consider indexing them. A document review matrix may be helpful in determining, (I) which
document types do not need to be reviewed for design information, (2) which document types should
be reviewed, and (3) which document types are expected to contain such information. Each potential
source document should be screened to determine if it contains design information and if technical
review is necessary to extract that information. Documents related to past missions and past
configurations that are no longer valid should be excluded at this point, as should documents related to
SSCs that are not included in the CM program. Other specific documents that do not actually provide
design information should also be excluded. A second-party review should be conducted to verify that
the exclusion of specific documents or document types from further review was warranted.
The collected source documents that contain design information should be organized or sorted by
system or topical area such that they are readily retrievable for future review needs. Documents thus
sorted can be easily directed to the best technical reviewer for the extraction of design information.
Sorting may be difficult, as some documents involve many systems and topics.
3.2.1.3 Comprehensive Search
Section 58
The comprehensive search aims at identifying and retrieving the remaining documents that might
contain design information, including design analyses and calculations, DOE correspondence, and
vendor correspondence. This search identifies mostly design-basis information, but it may serve to
capture additional design requirements.
Care should be taken not to limit the extent of the comprehensive search, for its success depends
primarily on the identification and location of all source documents containing design information. The
comprehensive search team should interview and interact with experienced engineering and operations
personnel to locate and collect information, including information stored in desks and personal files.
Moreover, they should investigate referenced design documents for potential design basis information.
A design output document identified and reviewed in the smart search might contain references to
various documents used as the basis for the design requirements it defines; these are good targets for
the comprehensive search.
Source document types likely to contain design basis information include DOE correspondence, design
agency correspondence, vendor correspondence, internal correspondence, meeting minutes,
engineering procedures, engineering calculations and analyses, engineering studies and reports, code
conformance