DOE-STD-1071-94, Guideline to Good Practices for Material Receipt, Inspection, Handling, Storage, Retrieval, and Issuance at DOE Nuclear Facilities
Functional areas: Good Practices, Material Receipt, Inspection, Handling, Storage
This guide is intended to assist facility maintenance organizations in the review of existing methods and in the development of new methods for establishing a material receipt, inspection, handling, storage, retrieval, and issuance process/system which ensures timely delivery of the proper parts and materials, in the condition required for effective
maintenance activities, and periodic services which provide unique and/or supplemental maintenance support.
Unknown Block text
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
TS
NOT MEASUREMENT
SENSITIVE
DOE-STD-1071-94
June 1994
DOE STANDARD
GUIDELINE TO GOOD PRACTICES FOR
MATERIAL RECEIPT, INSPECTION,
HANDLING, STORAGE, RETRIEVAL, AND
ISSUANCE AT DOE NUCLEAR FACILITIES
U.S. Department of Energy AREA MNTY
Washington, D.C. 20585
DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.
WELCOME
This Portable Document Format (PDF) file contains bookmarks, thumbnails, and hyperlinks to help you navigate through the document. All items listed in the Contents are linked to the corresponding sections. In addition, if you click on a section heading while you are reading the text, you will return to the Contents. Click on the DOE seal below to move to the Contents page.
This document has been reproduced directly from the best available copy.
Available to DOE and DOE contractors from the Office of Scientific and
Technical Information, P.O. Box 62, Oak Ridge, TN 37831; (615) 576-8401.
Available to the public from the U.S. Department of Commerce, Technology
Administration, National Technical Information Service, Springfield, VA 22161;
(703) 487-4650.
Order No. DE94014949
DOE-STD-1071-94
FOREWORD
The Guideline to Good Practices for Material Receipt, Inspection, Handling, Storage,
Retrieval, and Issuance at DOE Nuclear Facilities provides contractor maintenance
organizations with information which may be used for the development and implementation
of a rigorously controlled material receipt inspection process for maintenance organizations
at DOE (Department of Energy) nuclear facilities. This document is intended to be an
example guideline for the implementation of DOE Order 4330.4A, Maintenance Management
Program Chapter 11, Element 11, Material Receipt, Inspection, Handling, Storage, Retrieval,
and Issuance. DOE contractors should not feel obligated to adopt all parts of this guide.
Rather, they should use the information contained herein as a guide for establishing a
material receipt, inspection, handling, storage, retrieval, and issuance process applicable to
their facility.
iii
DOE-STD-1071-94
CONTENTS
FOREWORD . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . iii
1. INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.1 Purpose . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.2 Background . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.3 Application . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
2. DEFINITIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
2.1 Acronyms . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
2.2 Acceptance Tag . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
2.3 Item . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
2.4 Purchase Documents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
2.5 Q-List . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
2.6 Shelf Life . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
2.7 Storage Controls . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
2.8 Storeroom . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
2.9 Tickler File . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
Section 2
3. MATERIAL RECEIPT, INSPECTION, HANDLING, STORAGE
RETRIEVAL, AND ISSUANCE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
3.1 Discussion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
3.2 Scope . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
3.3 Responsibilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
3.3.1 Maintenance Manager . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
3.4 Guidelines . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
3.4.1 Receipt Inspection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
3.4.2 Handling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
3.4.3 Storage of Material and Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
3.4.4 Retrieval and Issuance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
APPENDIX A EXAMPLE ACCEPTANCE TAG . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A - 1
APPENDIX B EXAMPLE INSPECTION CHECKLIST . . . . . . . . . . . . . . . . . . . . . . . . . . B - 1
APPENDIX C EXAMPLE TICKLER FILE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . C - 1
APPENDIX D SAMPLE LESSON PLAN . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . D - 1
v
DOE-STD-1071-94
1. INTRODUCTION
1.1 Purpose
This guide is intended to assist facility maintenance organizations in the review of
existing methods and in the development of new methods for establishing a material
receipt, inspection, handling, storage, retrieval, and issuance process/system which ensures
timely delivery of the proper parts and materials, in the condition required for effective
maintenance activities, and periodic services which provide unique and/or supplemental
maintenance support. It is expected that each DOE facility may use approaches or
methods different from those defined in this guide. The specific guidelines that follow
reflect generally accepted industry practices. Therefore, deviation from any particular
guideline would not, in itself, indicate a problem. If substantive differences exist between
the intent of this guideline and actual practice, management should evaluate current
practice to determine the need to include/exclude proposed features. A change in
maintenance practice would be appropriate if a performance weakness were determined
to exist. The development, documentation, and implementation of other features that
further enhance these guidelines for specific applications are encouraged.
Additional information pertinent to the implementation of this guideline may be
found in DOE-STD-1070-93, "Guideline to Good Practices for Procurement of Parts,
Materials, and Services at DOE Nuclear Facilities."
Appendix D (Sample Lesson Plan) is provided for use by facility trainers who provide
training regarding this element of DOE Order 4330.4A, "Maintenance Management
Program."
1.2 Background
Section 3
The information in this guide was developed from commercial and DOE sources.
Each facility should select any details applicable, add any additional knowledge or
experience that is applicable, and then develop and implement facility-specific methods
for establishing a material receipt, inspection, handling, storage, retrieval, and issuance
process. Facilities which use existing documented methods should review this guide to
identify any details which may enhance their existing process.
1
DOE-STD-1071-94
1.3 Application
The content of this guide is generally applicable to all DOE nuclear facilities.
Portions of the methods outlined may not be applicable to all facilities, because
maintenance organizations, disciplines, titles, and responsibilities may vary among DOE
nuclear facilities. Facility maintenance personnel should (1) verify the adequacy of or (2)
improve existing methods by adapting this guide to their specific facility and individual
maintenance disciplines.
2
DOE-STD-1071-94
2. DEFINITIONS
2.1 Acr onyms
DOE: Department of Energy
MSDS: Material Safety Data Sheets
RECID: Record Identification
2.2 Acceptance Tag. The final receipt inspection identifier affixed to an item prior to
placing the item in storage. It indicates all purchase requirements have been met.
2.3 Item. Any spare part, consumable, equipment or material. May include entire
component, valve, motor, instrument, gasket, adhesive, sea], etc.
2.4 Purchase Documents. Documents that describe the item(s) to be purchased.
These include requisitions and purchase orders with equipment specifications and
requirements.
2.5 Q-List. An engineered approved listing of safety class structures, systems, or
components (SSC).
2.6 Shelf Life. A specific period or interval of time after which a stored item may not
meet its original design specifications, quality, or manufacture requirements.
2.7 Storage Controls. Controls applied during purchasing, receiving, packaging, and
storing of items to ensure that they are maintained properly.
2.8 Storeroom. Any facility designed or used for receiving, storing, and issuing items.
2.9 Tickler File. A file that serves as a reminder and is arranged to bring matters to
timely attention.
3
DOE-STD-1071-94
3. MATERIAL RECEIPT, INSPECTION, HANDLING, STORAGE
RETRIEVAL, AND ISSUANCE
3.1 Discussion
The fundamental objective of an effective material receipt, inspection, handling, storage,
retrieval, and issuance process should be to ensure the integrity of parts, equipment, and
material is maintained and verifiable from the time the item is received until it is placed into
service by the owner/operator. This objective requires that appropriate controls be
established to ensure that the quality of parts and material is not degraded during
purchasing, receipt, storage, and handling. This guideline should not be limited to new
purchases of materials and equipment, but should include all materials and equipment stored
at the plant.
The plant process should clearly define responsibilities, accountabilities, and interfaces
for each functional organization supporting each step in the process. Specific controls
should be tailored to be consistent with the type, importance, and intended service of
individual items.
A material control process should include the following elements:
• Appropriate requirements should be included in purchase documents on the basis of
vendor information, material specifications, standards, experience, and plant environment.
Section 4
• Ensure that cleaning fluids, solvents, and other chemicals are compatible with plant
systems and equipment, and that special chemical requirements such as temperature,
shelf life, hazard communications, and physical segregation are properly addressed.
• Ensure that storage controls are defined prior to purchase, that quality documentation is
required for Q-list items, and that the receipt inspection process requirements are clearly
addressed.
• Establish and maintain a file system (e.g., tickler file) to ensure that specific storage
instructions are accomplished, preventive maintenance tasks are completed, and
perishable items are replaced before their shelf life expires.
• Program effectiveness should be monitored periodically by supervisory inspection, and
there should be appropriate tracking to correct deficiencies.
3.2 Scope
This guideline applies to material receipt, inspection, handling, storage, retrieval, and
issuance activities involving maintenance organizations throughout.
4
DOE-STD-1071-94
3.3 Responsibilities
3.3.1 Maintenance Manager, accountable for maintenance of the facility, is responsible for
evaluating status, determine and implement enhancements/improvements of material
receipt, inspection, handling, storage, retrieval, and issuance activities.
3.4 Guidelines
3.4.1 Receipt Inspection
3.4.1.1 During receipt inspection, the designated organization should ensure that
special storage instructions have been addressed. Prior to final acceptance
of an item, the designated organization should ensure that the necessary
purchase order instructions and requirements are completed such as the
following:
• The tickler file has been updated as described in Section 3.4.3.20.
• Appropriate items have been added to the preventive maintenance
program.
• Appropriate inspection instructions are clearly defined.
3.4.1.2 Inspection and test activities should be selectively and judiciously applied to
new, repaired, and replacement items, on the basis of risk to safety and/or
importance to reliable capacity, to ensure items will perform as expected.
3.4.1.3 Plant Engineering should develop a process for providing data sheets which
form the basis for procurement of Safety Class Items and other major
purchases (i.e., equipment and construction projects). These data sheets
should provide:
• Procurement information
• Establish critical parameters and their acceptance criteria
• Specify unique or special testing requirements/methods
• Reorder instructions
• Suspect/counterfeit parts information
5
DOE-STD-1071-94
3.4.1.4 Items or parameter values which do not satisfy established acceptance
criteria should be rejected or involve Plant Engineering approval for other
disposition.
Non-conforming items should be:
• Clearly identified
• Segregated from normal items to prevent inadvertent use
• Documented on a Nonconformance Report and/or a Defective or
Substandard Material Report
• Tracked and dispositioned as soon as practical by the applicable
authority
3 4.1.5 Routine inspections performed by appropriate personnel should include:
• Ensuring that packaging is proper (as designated on the purchase
order when specified), packaging is undamaged and/or not
deteriorated
• Color, count, shape, size, part number, model number,
manufacturer/vendor name, etc. are as specified on the purchase
order
• Shelf-life and other time-environment requirements have not been
violated - date and time of receipt are logged for regular follow-up
review during the storage period
Section 5
• Specified vendor documentation, in the quantities required by the
purchase order exist
3.4.1.6 Special inspections should be performed on Safety Class Items and other
items when designated by the requisitioner.
3.4.1.7 Special inspections should be performed by the organization specified on
the requisition.
3.4.1.8 Special inspection requirements for items not involving Engineering data
sheets should be defined by the requisitioner.
6
DOE-STD-1071-94
3.4.1.9 Special inspections normally require:
• Formal quality records of all measured data
• Date inspection performed
• The identification of the individual and the organization performing
the inspection
• Accept/reject status identification
• The signature of the applicable authority to approve the status
3.4.1.10 Items receiving special inspection (especially Safety Class Items) should be
appropriately identified and segregated from normal stock to indicate status
and ensure proper application.
3.4.1.11 Materials and equipment which have been repaired and/or stored in the
plant should require the same inspection defined for the original purchase
and/or appropriate for its intended application as specified by engineering
before becoming available for use or restock.
3.4.1.12 Stored items which are affected by time-environment should be regularly
checked by designated personnel, expired or otherwise jeopardized items
should be removed from normal storage until dispositioned by the proper
authority.
3.4.1.13 An "Acceptance Tag" should be placed on the item after satisfactory
receipt inspection. The tag should be legibly marked to indicate whether
an item has any type of special storage requirements (see Appendix A for
an example). This provides the user, requester, or storeroom personnel
with an easy method to ensure special storage control requirements are
satisfied. The tag may cross-reference a particular entry in a file system
(tickler file) for further instructions.
3.4.2 Handling
3.4.2.1 Lifting equipment labels should be current and the maximum load
capability, as marked on the equipment, should not be violated when
handling or moving items.
3.4.2.2 Lifting equipment should be regularly tested, inspected, and acceptance
tagged to ensure integrity.
7
DOE-STD-1071-94
3.4.2.3 Individuals required to operate cranes, forklifts, and other lifting
equipment should be performance-based trained, and appropriately
licensed to verify their qualification.
3.4.2.4 Unusual, unique, or deceptive weight, balance, lift points, and other critical
information regarding items to be lifted or otherwise handled should
require that clearly defined instructions or job plans be communicated to
the handler.
3.4.2.5 Items which require special handling such as vibration isolation, protection
from the environment, specific orientation, etc. to ensure integrity should
require that clearly defined instructions or job plans be communicated to
the handler.
3.4.2.6 Calibrated/certified items should be handled in a manner that ensures their
integrity is not jeopardized.
3.4.3 Storage of Material and Equipment
3 4.3.1 A system should be established which ensures the proper storage,
segregation, and control of hazardous materials such as;
• Chemicals
• Radioactive/reactive organics
• Reagents
• Explosives
• Flammables/combustibles
• Corrosives
• Pesticide/herbicide
3.4.3.2 A system should be established which ensures the proper storage,
segregation, and control of specialty equipment and tools.
Section 6
3.4.3.3 A system should be established which ensures the proper storage,
segregation, and control of general materials, equipment, and tools.
8
DOE-STD-1071-94
3.4.3.4 Material and equipment subject to restricted use and distribution such as
Safety Class Items, critical spare parts, Bill-of-Material items, certain
sealants and compounds, precious metals, etc. should have clearly defined
instructions, which provide for:
• Segregation from normal stock
• Access control
• Unique identification
• Issue only to those on authorized signature lists
• Stock records maintenance
• Purchase order tracking and ready traceability from design drawing
through purchasing, storage, and handling, to installation
3.4.3.5 The quality of stored items should be maintained through the selective and
judicious application of clearly defined protection and availability controls.
3.4.3.6 A system for the periodic general inspection of storage areas should exist.
Typical storage control observations should verify the following:
• Corrosive chemicals segregated from sensitive equipment and metal
items
• Flammables in proper containers and marked
• Radioactive substances properly shielded and marked
• Stainless steel and other "pedigree" metals segregated from other
metals (particularly carbon steel)
• Motors, pumps, relief valves, and other items are stored on their
bases
• Stacking of items, crates, boxes, barrels, etc. do not exceed stacking
recommendations
• Packaging and seals have not been violated leaving contents exposed
to degradation caused by the intrusion of foreign materials or
environmental conditions
9
DOE-STD-1071-94
• Machined surfaces are left adequately protected
• Applicable insect and rodent controls are in effect
• Applicable shelf-life conditions are in effect
• Carcinogens segregated from other materials and equipment
• Re-order/restocking is clearly indicated
3.4.3.7 A system should exist which ensures that Material Safety Data Sheets record
identification (MSDS RECID) are readily accessible to the user.
3.4.3.8 The process where regulatory requirements regarding storage and disposal of
materials should be regularly verified to ensure compliance status.
3.4.3.9 When established, automatic reorder/restock criteria should be implemented.
3.4.3.10 Reorder/restock quantities should be reviewed and adjusted on the basis of;
• Lead-time
• Usage (historical and projected)
• Value-added or other established criteria
3.4.3.11 A shelf-life program should be developed which applies to items stored in
warehouses and plants prior to end use. Shelf-life requirements should be
specified for (but not limited to) the following types of items:
• rubber components
• silicon sealants
• certain paints
• photosensitive chart paper
• photographic material
• certain pre-lubed bearings
10
DOE-STD-1071-94
• capacitors
• resins
• complete assemblies containing items listed above
• chemicals, reagents, and organics
3.4.3.12 Certain items, such as electric motors with heaters, may be required to be
energized continuously or periodically when stored in an uncontrolled
environment.
3.4.3.13 Heavy equipment such as motors, gearboxes, and other prime-movers
should be rotated periodically to maintain a proper coating of lubrication
and to prevent bearing or gear-face denting at point of contact.
3.4.3.14 In addition to the controls of the general storage areas, temperature and
humidity controls should be considered for individual item groups. It may
also be necessary to change or monitor desiccants or to provide heaters.
Section 7
3.4.3.15 Certain items such as gearboxes may be required to be filled with fluid.
3.4.3.16 It may be necessary to seal or cap components to the extent possible to
prevent entry of foreign material, dust, or contaminants. Reinforced
packing or barriers between items may be required to prevent damage or
prevent mixing of chemicals due to leakage or breakage.
3.4.3.17 Periodic inspections should be made to ensure that the general condition of
the storage area is acceptable. Examples include cleanliness, vermin
control, lighting, preservation, labeling, flooding, fire protection, safety, and
segregation of material, including segregation of reactive chemicals.
3.4.3.18 Items stored in the plant should be placed under the same type of controls
used for the storeroom.
3.4.3.19 A monthly inspection of storage facilities and items should be performed.
The inspection should be performed and documented utilizing a checklist
that includes criteria appropriate to the inspection. Observed deficiencies
should be noted and corrective action addressed prior to resolution of the
checklist. (See Appendix B for an example of inspection checklist format.)
11
DOE-STD-1071-94
3.4.3.20 A tickler file system is one method which may be used to ensure that
specific storage control instructions are followed.
• The system may be either manual (similar to a card file) or
computerized.
• The tickler file should be organized by months of the year.
• Specific storage control instructions for individual items should be
entered into the tickler file system by designated personnel. These
instructions should be entered separately (either as a separate card
or computer entry) and put in the appropriate month that the
activity is to take place. As a minimum, additional information, such
as part number, P.O. number, item description, and RECID should
be included. (See Appendix C for examples.)
• Designated personnel should ensure that the particular storage
control activities for the month are completed. (This may require
assistance from other departments for activities such as rotating
motors and functional tests.)
• Designated personnel should review the tickler file entries on a
monthly basis for upcoming activities, e.g., 60-90 days. This review
is in addition to the review and completion of storage control
instructions for the particular month. This review is to ensure
proper planning for certain activities and advance notification for
assistance from other departments.
3.4.4 Retrieval and Issuance
3.4.4.1 A system should exist to ensure that items are identified and stored to
facilitate ready retrieval upon approved request.
3.4.4.2 Items should be selectively and judiciously controlled, on the basis of their
risk to safety and/or importance to reliable operations, during the interval
between stores issue and installation to ensure intended traceability and/or
integrity is not violated prior to installation.
3.4.4.3 Safety Class Items and other controlled items to be issued ONLY to
individuals on authorized requester lists should be clearly defined in
applicable documents.
12
DOE-STD-1071-94
3.4.4.4 Issuance documentation should be handled as quality records.
3.4.4.5 A system should exist which provides for current storage inventory status
information to be maintained, to be made available to and usable by
authorized individuals upon request.
3.4.4.6 Information on storage inventory lists which may enhance usability should
include:
• Stores catalog number
Section 8
• Noun name
• Manufacturer/vendor part number
• Application and contact for controlled item disposition
• Reorder criteria, when applicable
• Quantity on-hand
• RECID
• Consideration for configuration managed items
13
DOE-STD-1071-94
APPENDIX A
EXAMPLE ACCEPTANCE TAG
A - 1
DOE-STD-1071-94
APPENDIX A
EXAMPLE ACCEPTANCE TAG
If storage controls are necessary,
the “acceptance” tag may restamped “S”
with a transparent colored stamp.
A - 2
DOE-STD-1071-94
APPENDIX B
EXAMPLE INSPECTION CHECKLIST
B - 1
DOE-STD-1071-94
APPENDIX B
EXAMPLE INSPECTION CHECKLIST
OUTSIDE WAREHOUSE
INSPECTOR
INITIALS/DATE
INSPECTION
CRITERIA
COMMENTS &
DEFICIENCIES
CORRECTIVE ACTION
COMPLETED INITIAL/DATE
JB 3/9/82 1. FLOODING Ensure water has not
entered storage areas and caused
damage.
OK
JB 3/9/82 2. FIRE SPRINKLERS Ensure
storage of items does not reduce the
effectiveness of the fire sprinklers.
OK
JB 3/9/82 3. DISTORTION OF ITEMS Ensure
that items are not damaged or
distorted because of crowding or
excessive weight.
Insulated damaged
because of new desks.
Moved Desks
JB 3/15/82
Note: Additional criteria to consider are as follows:
Cleanliness Protective covers
Safety Hazards Tags in place
Fire extinguishers Corrosion
Vermin control Adequate Room
Leaking roofs Colored wire protected from sunlight
Climate controls Lifting equipment in proper operation
Locks in place Dust and dirt
Temperature controls Tickler file complete
B - 2
DOE-STD-1071-94
APPENDIX C
EXAMPLE TICKLER FILE
C - 1
DOE-STD-1071-94
APPENDIX C
EXAMPLES OF TICKLER FILE INFORMATION
COMPUTERIZED METHOD
MONTH/TASK #
FOR MONTH P.O. # PART # DESCRIPTION TASK
06-20 Q 207 EZ 12 F. D. Cylinder Check gas pressure
greater than 1000 psi
every six months
06-27 Q 312 OH 17 R. H. Motor Rotate Shaft XX
degrees every six
months
09-13 Q12 Z-30 F. T. Gasket Shelf life expires
September 1989
12-2 Q 312 OH 17 R. H. Motor Rotate Shaft XX
degrees every six
months
NOTE: Computer printout may be used as a check-off and filed
with records with comments.
CARD FILE should be organized by month. Appropriate personnel should check for tasks that
are due for the particular month and in the next several months.
C - 2
DOE-STD-1071-94
APPENDIX D
MATERIAL RECEIPT, INSPECTION, HANDLING,
STORAGE, RETRIEVAL, AND ISSUANCE
SAMPLE LESSON PLAN
D - 1
DOE-STD-1071-94
APPENDIX D
MATERIAL RECEIPT, INSPECTION, HANDLING,
STORAGE, RETRIEVAL, AND ISSUANCE
SAMPLE LESSON PLAN
LESSON PLAN
1. The instructor should be familiar with the following background information:
The proper care of parts, materials, and equipment is required from the time an
item is received until it is installed. Numerous site personnel and organizations are
involved in this process. A program should be in place for the correct processing
of material so that it is easily retrievable and usable when issued.
2. To teach this lesson, the following training housekeeping items are required:
a. Location for the training,
b. Approximately 30 minute time period for the training,
c. Notification of selected employees, and
d. A copy of the site's applicable program for material receipt and issuance.
3. This lesson has the following trainee enabling objective:
Explain the key elements of material receipt, inspection, handling, issuance, and
storage.
4. Important aspects of receipt, inspection, handling, storage, retrieval, and issuance
include the following:
Section 9
a. When material is received at the facility it should be inspected and verified
to meet the specifications of the original purchase documentation. Critical
material should be segregated from non-critical, and any nonconforming
material should be tagged and set aside to prevent inadvertent use.
Additionally, a method should be developed to accept site repaired
material.
b. Special handling procedures should be established for relocating materials
and equipment. Personnel required to operate cranes, fork-lifts, and other
lifting equipment should be properly trained and qualified.
D - 2
DOE-STD-1071-94
c. Material should be stored to maximize protection and availability.
Additionally, periodic changes of desiccant, rotation of pump shafts, oil
changes, and other preventive maintenance requirements specified by the
vendor should be performed.
d. Periodic inspections of store rooms should be performed to ensure the
following:
• corrosive chemicals are segregated and not located near equipment
and metal stock,
• flammable materials are properly stored,
• radioactive materials are properly controlled,
• relief valves, motors, and other equipment are stored on their bases,
• machined surfaces are properly protected, and
• equipment internals are protected from intrusion of foreign
materials.
e. A catalog for parts, materials, and equipment should be developed to allow
plant personnel to determine what is available for issue. This catalog
should provide a cross-references listing that provides information such as
the manufacturer part number, facility part number, noun name, and
component or system for which the part is used.
5. Discuss with the trainees the site's material receipt and issuance program.
D - 3
DOE-STD-1071-94
CONCLUDING MATERIAL
Review Activity: Preparing Activity:
DOE Field Offices DOE-EH-63
FM AL
DP CH Project Number:
EH ID
EM NV MNTY-0011
ER OR
NE RL
NS SR
RW OAK
RF
Area Offices
Amarillo
Brookhaven
Fernald
Kansas City
Kirtlant
Princeton
Facilities
ANL
KC AlliedSignal
NBL
LBL
LANL
LLNL
ORAU
PANTEX M&H
PNL
PPPL
RF-EG&G
SNL
NV REECo.
NV EG&G
OR OSTI
WHC
ID-EG&G
RF
SLAC
WSRC
FOREWORD
CONTENTS
1. INTRODUCTION
1.1 Purpose
1.2 Background
1.3 Application
2. DEFINITIONS
2.1 Acronyms
2.2 Acceptance Tag
2.3 Item
2.4 Purchase Documents.
2.5 Q-List.
2.6 Shelf Life.
2.7 Storage Controls.
2.8 Storeroom.
2.9 Tickler File.
3. MATERIAL RECEIPT, INSPECTION, HANDLING, STORAGE RETRIEVAL, AND ISSUANCE
3.1 Discussion
3.2 Scope
3.3 Responsibilities
3.3.1 Maintenance Manager
3.4 Guidelines
3.4.1 Receipt Inspection
3.4.2 Handling
3.4.3 Storage of Material and Equipment
3.4.4 Retrieval and Issuance
APPENDIX A EXAMPLE ACCEPTANCE TAG
APPENDIX B EXAMPLE INSPECTION CHECKLIST
APPENDIX C EXAMPLE TICKLER FILE
APPENDIX D SAMPLE LESSON PLAN