DOE-STD-1050-93, Guideline to Good Practices for Planning, Scheduling, and Coordination of Maintenance at DOE Nuclear Facilities
Functional areas: Good Practices, Planning, Scheduling, Maintenance
This guide is intended to assist facility maintenance operations in the review of existing and in developing new programs to ensure maintenance work package planning, scheduling, and coordination identifies all technical and administrative requirements for a work activity and provides the materials, tools, and support activities needed to perform the work.
Unknown Block text
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
NOT MEASUREMENT
SENSITIVE
DOE-STD-1050-93
March 1993
DOE STANDARD
GUIDELINE TO GOOD PRACTICES FOR
PLANNING, SCHEDULING, AND
COORDINATION OF MAINTENANCE AT
DOE NUCLEAR FACILITIES
U.S. Department of Energy AREA MNTY
Washington, D.C. 20585
DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.
WELCOME
This Portable Document Format (PDF) file contains bookmarks, thumbnails, and hyperlinks to help you navigate through the document. All items listed in the Contents are linked to the corresponding sections. In addition, if you click on a section heading while you are reading the text, you will return to the Contents. Click on the DOE seal below to move to the Contents page.
This document has been reproduced directly from the best available copy.
Available to DOE and DOE contractors from the Office of Scientific and
Technical Information, P.O. Box 62 Oak Ridge, TN 37831.
Available to the public from the National Technical Information Service, U.S.
Department of Commerce, 5285 Port Royal Rd., Springfield, VA 22161.
Order No. DE93014266
DOE-STD-1050-93
FOREWORD
The purpose of the Guideline to Good Practices for Planning, Scheduling, and
Coordination of Maintenance at DOE Nuclear Facilities is to provide contractor maintenance
organizations with information that may be used for the development and implementation of
a rigorously controlled maintenance program directed at planning, scheduling, and coordinating
work packages for maintenance tasks at DOE nuclear facilities. This document is intended
to be an example guideline for the implementation of DOE Order 4330.4A, Maintenance
Management Program, Chapter II, Element 6. DOE contractors should not feel obligated to
adopt all parts of this guide. Rather, they should use the information contained herein as a
guide for developing maintenance programs that are applicable to their facility.
iii
DOE-STD-1050-93
CONTENTS
FOREWORD . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . iii
1. INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.1 Purpose . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.2 Background . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
1.3 Application . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
2. Definitions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
2.1 Acronyms Used in This Standard. . . . . . . . . . . . . . . . . . . 3
2.2 ALARA . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
2.3 Corrective Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . 3
2.4 Deficiency . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
2.5 Deficiency Tag/Sticker . . . . . . . . . . . . . . . . . . . . . . . . . . 4
2.6 Facility . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
2.7 Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
2.8 Maintenance Importance Generator (MIG) . . . . . . . . . . . . . 4
2.9 Maintenance Job Request (MJR) . . . . . . . . . . . . . . . . . . . . 4
2.10 Maintenance Management . . . . . . . . . . . . . . . . . . . . . . . . 4
2.11 Maintenance Procedure . . . . . . . . . . . . . . . . . . . . . . . . . . 4
2.12 Maintenance Work Instructions . . . . . . . . . . . . . . . . . . . . 5
2.13 Maintenance Work Package . . . . . . . . . . . . . . . . . . . . . . . 5
2.14 Minor Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
2.15 Outage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
2.16 Performance Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
2.17 Performance Monitoring . . . . . . . . . . . . . . . . . . . . . . . . . 6
2.18 Periodic Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
2.19 Planned Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
2.20 Postmaintenance Test . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
2.21 Predictive Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . 6
2.22 Preventive Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . 7
2.23 Root Cause . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
2.24 Structures, Systems and Components (SSC).. . . . . . . . . . . 7
2.25 Technical Support. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
2.26 Work Control Document . . . . . . . . . . . . . . . . . . . . . . . . . 7
Section 2
3. PLANNING, SCHEDULING, AND
COORDINATION OF MAINTENANCE ACTIVITIES . . . . . . . . . 8
3.1 Discussion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
3.1.1 Planning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
3.1.2 Scheduling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
3.1.3 Coordination . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
v
DOE-STD-1050-93
3.2 Scope . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
3.3 Responsibilities. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
3.4 Planning Guidelines . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
3.4.1 Maintenance Job Request (MJR) Processing . . . . . 17
3.4.2 Maintenance Job Request (MJR) Planning . . . . . . . 19
3.5 Scheduling Guidelines . . . . . . . . . . . . . . . . . . . . . . . . . . 23
3.5.1 Schedule Requirements . . . . . . . . . . . . . . . . . . . . 23
3.5.2 Schedule Methods. . . . . . . . . . . . . . . . . . . . . . . . 24
3.5.3 Schedule Detail . . . . . . . . . . . . . . . . . . . . . . . . . 24
3.5.4 Daily Schedules . . . . . . . . . . . . . . . . . . . . . . . . . 25
3.5.5 Schedule Preparation . . . . . . . . . . . . . . . . . . . . . . 26
3.5.6 Schedule Integration . . . . . . . . . . . . . . . . . . . . . . 27
3.5.7 Schedule Review . . . . . . . . . . . . . . . . . . . . . . . . 27
3.5.8 Format, Progress Reporting,
Updating, and Distribution . . . . . . . . . . . . . . . . . . 27
3.6 Coordination Guidelines . . . . . . . . . . . . . . . . . . . . . . . . 29
3.6.1 Organization and Supervision . . . . . . . . . . . . . . . . 29
3.6.2 Prejob Coordination . . . . . . . . . . . . . . . . . . . . . . 29
3.6.3 Material Staging and Availability. . . . . . . . . . . . . 30
3.6.4 Daily Meetings . . . . . . . . . . . . . . . . . . . . . . . . . . 31
3.6.5 Performance Monitoring . . . . . . . . . . . . . . . . . . . 32
APPENDIX A MAINTENANCE OPERATIONS MODEL . . . . . . . . . A-1
APPENDIX B FACILITY MANAGEMENT . . . . . . . . . . . . . . . . . . . B-1
APPENDIX C EXAMPLES OF MINOR MAINTENANCE . . . . . . . . C-1
APPENDIX D EXAMPLE MAINTENANCE JOB REQUEST . . . . . . D-1
APPENDIX E EXAMPLE WALKDOWN CHECKLIST . . . . . . . . . . E-1
APPENDIX F EXAMPLE TROUBLESHOOTING GUIDE . . . . . . . . F-1
APPENDIX G EXAMPLE PLANNING CHECKSHEET . . . . . . . . . . G-1
APPENDIX H PLANNING, SCHEDULING, AND
COORDINATION OF MAINTENANCE
SAMPLE LESSON PLAN . . . . . . . . . . . . . . . . . . . . . H-1
vi
DOE-STD-1050-93
1. INTRODUCTION
1.1 Purpose
This guide is intended to assist facility maintenance operations in the review of existing
and in developing new programs to ensure maintenance work package planning, scheduling,
and coordination identifies all technical and administrative requirements for a work activity
and provides the materials, tools, and support activities needed to perform the work. It is
expected that each DOE facility may use different approaches or methods than those defined
in this guide. The specific guidelines that follow reflect generally accepted industry practices.
Therefore, deviation from any particular guideline would not, in itself, indicate a problem.
If substantive differences exist between the intent of the Guideline and actual practice,
management should evaluate current practice to determine the need to include/exclude
proposed features. A change to maintenance practice would be appropriate if a performance
weakness was determined to exist. Development, documentation, and implementation of other
features which further enhance these guidelines for specific applications, is encouraged.
Additional information pertinent to the implementation of this guideline is found in the
following DOE Guidelines:
Section 3
1) DOE-NE-STD-1003-91 "Guidelines to Good Practice for Training and Qualif ication of
Maintenance Personnel"
2) "W riter's Guide for Technical Procedures"
3) "Guidelines to Good Practices for Postmaintenance Testing at DOE Nuclear Facilities"
4) "Guidelines to Good Practices for Control and Calibration of Measuring and Test
Equipment (M&TE) at DOE Nuclear Facilities"
5) "Guidelines to Good Practices for Maintenance History at DOE Nuclear Facilities"
6) "Guidelines to Good Practice for Modif ication W ork at DOE Nuclear Facilities"
7) "Guidelines to Good Practice for Procurement of Parts, Materials, and Services at DOE
Nuclear Facilities"
8) "Guidelines to Good Practice for Material Receipt, Inspection, Handling, Storage,
Retrieval, and Issuance at DOE Nuclear Facilities"
9) "DOE Guideline DOE-NE-STD-1004-92 Root Cause A nalysis Guidance Document"
10) "Guidelines to Good Practices for Management Involvement at DOE Nuclear Facilities"
Appendix H is provided for use by facility trainers who intend to provide training
1
DOE-STD-1050-93
regarding this element.
1.2 Background
The information in this guide was developed from commercial and DOE sources. Each
facility should select those details that are applicable, add any unlisted knowledge or
experience that are applicable, and develop and implement facility-specific maintenance
programs. Facilities that have existing documented maintenance programs should review this
guide to identify details that may enhance their existing programs.
1.3 Application
The content of this guide is generally applicable to all DOE nuclear facilities. Portions
of the programs outlined may not be applicable to all facilities because maintenance
organizations, disciplines, titles, and responsibilities may vary among DOE nuclear facilities.
Facility maintenance personnel should verify the adequacy or improve existing maintenance
programs by adapting this guide to their specific facility and individual maintenance
disciplines.
2
DOE-STD-1050-93
2. DEFINITIONS
2.1 Acronyms Used in This Standard. The acronyms used in this standard are defined as
follows:
a. ALARA - As Low As Reasonably Achievable
b. ASME - American Society of Mechanical Engineers
c. DOE - Department of Energy
d. EQ - Environmental Qualification
e. MIG - Maintenance Importance Generator
f. MJR - Maintenance Job Request
g. PM - Preventive Maintenance
h. PMT - Postmaintenance Test
i. RWP - Radiation Work Permit
j. SSC - Structures, Systems, and Components
k. SWP - Safe Work Permit
2.2 ALARA (As Low As Reasonably Achievable). A radiation protection philosophy
requiring that personnel exposure to radiation and radioactive material be kept not only
within regulatory limits, but be maintained as low as reasonably achievable in light of
current technology with appropriate consideration for economic and social factors, and
benefits derived.
2.3 Corrective Maintenance. Repair and restoration of SSC that have failed or are
malfunctioning and are not performing their intended function. As a rule of thumb, if
the specific component (such as packing or bearing) requiring maintenance has failed,
the action required to repair it should be classified as corrective maintenance.
2.4 Deficiency. Any condition that deviates from the design of a structure, system, or
component (SSC) and results in a degraded ability to accomplish its intended function.
3
DOE-STD-1050-93
Section 4
2.5 Deficiency Tag/Sticker. A small tag or adhesive-backed sticker that is used to identify
a plant material deficiency. The form may be marked with a serialized number for
administrative control, work order identification, and deficiency location by maintenance
personnel.
2.6 Facility. Any equipment, structure, system, process, or activity that fulfills a specific
purpose. Examples include storage areas, fusion research devices, nuclear reactors,
production or processing plants, waste management disposal systems and burial grounds,
testing laboratories, research laboratories, transportation activities, weapons development
and production, standards and calibrations labs, and accommodations for analytical
examinations of irradiated and un-irradiated components.
2.7 Maintenance. Day-to-day work that is required to maintain and preserve plant and
capital equipment in a condition suitable for its designated purpose and includes
preventive, predictive, and corrective (repair) maintenance.
2.8 Maintenance Importance Generator (MIG). A computerized system using predetermined
rules to compare data on an MJR and to establish relative-importance ranking for each
maintenance job.
2.9 Maintenance Job Request (MJR) (Appendix D). Means of obtaining maintenance
services available on both paper and electronic mediums and initiated by maintenance
customers. Issued to Maintenance Planners and Estimators and used to define, plan, and
execute maintenance activities. Documentation of a deficient equipment condition,
requires detailed documentation of work performed, spare parts, procedures, or testing
to verify maintenance was performed correctly. The MJR may also serve as
documentation for completion of minor maintenance activities such as lubrication, light
bulb replacement, etc.
2.10 Maintenance Management. The administration of a program utilizing such concepts as
organization, plans, procedures, schedules, cost control, periodic evaluation, and
feedback for the effective performance and control of maintenance with adequate
provisions for interface with other concerned disciplines such as health, safety,
environmental compliance, quality control, and security. All work done in conjunction
with existing property is either maintenance (preserving), repair (restoring), service
(cleaning and making usable), or improvements (modification). The work to be
considered under the DOE maintenance management program is only that for
maintenance, repair, and modification.
2.11 Maintenance Procedure. A document providing direction to implement policy, comply
with external directives, or meet operational objectives in a consistent manner. A
procedure provides necessary delineation of roles, responsibilities, action steps, and
requirements.
4
DOE-STD-1050-93
2.12 Maintenance Work Instructions. Written instructions provided to the craftsperson to
assist in performance of a task. The level of detail of these instructions is based on the
complexity of the task, special engineering considerations/specifications, and skill levels
of the workers performing the task (skill-of-the-craft).
2.13 Maintenance Work Package. A consolidated document that identifies to the craftsperson
all the necessary requirements to safely and accurately perform a maintenance task with
minimum delays.
2.14 Minor Maintenance. Maintenance actions for deficiencies on plant electrical,
mechanical, or instrument components or parts where all the following conditions are
met:
Section 5
a) The component is nonsafety-related or, if the component is safety-related, the
portion or part being worked does not perform or affect a safety-related function.
b) The component or part does not perform an environmental qualification (EQ)
function.
c) Integrity of the component will not be violated.
d) Material substitution will not be involved.
e) Disassembly of the component or part will not be required.
f) Welding will not be performed on a component or part that is safety-related,
treated as safety-related, or seismically mounted.
g) Welding will not be performed on a pressure vessel.
h) Welding will not be performed on system piping.
i) A tagout will not be required.
j) The work performed is of such a minor nature that a written procedure is not
required. However, if a procedure exists, it may be used.
k) "Documented" postmaintenance testing will not be required.
l) The work is of such a simple nature that a detailed job planning package is not
required.
5
DOE-STD-1050-93
(Examples of activities that may qualify as "minor maintenance" and those that do not
qualify are given in Appendix C. These are examples only and do not constitute a
definitive list.)
2.15 Outage. Condition existing whenever normal operations has stopped, due to planned
or unplanned occurrences.
2.16 Performance Test. A test of SSC to verify that required performance characteristics
may be achieved, to detect any abnormal performance characteristics, and to
determine the effect of maintenance and operating activities on equipment
performance.
2.17 Performance Monitoring. Systematic monitoring and trending of the performance of
selected plant SSC to measure and assess the impact of any performance changes on
overall plant efficiency, reliability, and availability.
2.18 Periodic Maintenance. Preventive maintenance activities accomplished on a routine
basis (typically based on operating hours or calendar time) and may include any
combination of external inspections, alignments or calibrations, internal inspections,
overhauls, and SSC replacements.
2.19 Planned Maintenance. Preventive maintenance activities performed prior to SSC failure
and may be initiated by predictive or periodic maintenance results, by vendor
recommendations, or by experience/lessons learned. These include items such as
scheduled valve repacking, replacement of bearings as indicated from vibration analysis,
major or minor overhauls based on experience factors or vendor recommendations and
replacement of known life-span components. For example, repacking a valve due to
packing leakage would be corrective maintenance, but scheduled repacking prior to
leakage would be planned maintenance.
2.20 Postmaintenance Test. Any appropriate testing performed following maintenance to
verify that a particular piece of equipment or system performs its intended function
based on its design criteria and that the original deficiency has been corrected and no
new deficiencies created.
2.21 Predictive Maintenance. Predictive maintenance activities involve continuous or
periodic monitoring and diagnosis in order to forecast component degradation so that
"as-needed" planned maintenance may be performed prior to SSC failure. Not all SSC
conditions and failure modes may be monitored; therefore, predictive maintenance
should be selectively applied. Reliable predictive maintenance is normally preferable
to periodic internal inspection or equipment overhauls.
6
DOE-STD-1050-93
Section 6
2.22 Preventive Maintenance. Preventive maintenance includes periodic and planned
maintenance actions taken to maintain SSC within their design operating conditions,
extend its life, and is performed to prevent SSC failure. This includes technical safety
requirements surveillances, in-service inspections, and other regulatory forms of
preventive maintenance.
2.23 Root Cause. A determination based on analytical techniques that determines the
fundamental cause of failure.
2.24 Structures, Systems and Components (SSC). Physical items designed, built, or installed
to support the operation of the plant.
2.25 Technical Support. The engineering, design, specialized inspections, planning, or other
such support of capital asset maintenance and repair.
2.26 Work Control Document. Proceduralized document used by facility personnel to
perform inspections, testing or work.
7
DOE-STD-1050-93
3. PLANNING, SCHEDULING, AND COORDINATION
OF MAINTENANCE ACTIVITIES
3.1 Discussion
3.1.1 Planning
3.1.1.1 To correctly and efficiently perform the planning function, management
should provide adequate guidance on the level of control necessary to ensure
consistent quality maintenance of plant equipment. The requirements to
provide procedures for safety-related equipment and equipment important to
plant safety are well defined in DOE Order 4330.4A, Maintenance
Management Program, DOE Order 5480.19, Conduct of Operations
Requirements for DOE Facilities, and technical safety requirements.
However, large disparities exist throughout the industry in the level of
instruction provided to craftspersons for performing work on plant
equipment. Many plants rely heavily on "skill-of-the-craft" but have not
assessed the actual skill levels possessed by their personnel. For example,
it is commonly accepted that an electrician possesses the necessary skills to
install wiring lugs; however, the industry continues to have problems with
loose wiring.
3.1.1.2 "Skill-of-the-craft" skills should be given careful consideration when
preparing planned packages, job request, and work instructions to ensure that
additional training, worker qualifications, or job oversight/quality control are
included, if required. For example, work instructions for non-facility
contractors may need to include more detail, inspections, or supervisory
guidance. To reduce problems caused by inadequate instructions being
provided to the craftspersons, managers should establish minimum levels of
craft proficiency and implement training programs to ensure that the
expected craft skill levels are developed and maintained (see DOE-NE-STD-
1003-91 "Guide to Good Practice for Training and Qualif ication of
Maintenance Personnel"). Deficiencies identified through daily activities,
industry experience, or root cause analysis may result in the identification of
additional training needs to maintain this skill level. For work beyond
expected skills, detailed work instructions should be provided to the
craftspersons. "Skills-of-the-craft," are work skills that should be common
knowledge to the individual performing the work. Plant employees should
be formally trained, by means of an accredited on the-job training (OJT)
program, and qualified to perform these skills or they should be assigned to
work under the supervision of a qualified individual.
8
DOE-STD-1050-93
Some examples of these skills include the following:
• tightening or replacing fittings
• replacing gaskets, bolting, valve packing, stationary seals
Section 7
• valve lapping
• standard testing, such as insulation resistance, voltage, etc.
• replacing fuses and lamps
• lubricating equipment
• removing corrosion from surfaces
• trimming refrigerant charge
• removing oil from refrigeration plants
• cleaning threads by mechanical means
• cutting fasteners to length
• wire wrapping (except on printed circuit boards)
• soldering (except on printed circuit boards)
• crimping of lugs and splices
• tubing installation
• tubing fitting makeup
9
DOE-STD-1050-93
a) "Skill-of-the-craft" skills are considered to be standard industry
practices and do not usually require job steps, instructions, or an
approved procedure in hand. However, if a job requires a work-
authorizing document such as a maintenance job request (Appendix D),
the inclusion of "skill-of-the-craft" does not alter this requirement. The
use of "skill-of-the-craft" in the performance of a job is not considered
to be a change of work scope, providing it is confined to the job
covered by the maintenance job request and that all other work
performed is in accordance with approved plant procedures. In all
cases, however, all work should be documented on the maintenance job
request:.
3.1.1.3 The primary objective of work planning is to identify all technical and
administrative requirements for a work activity and to provide the materials,
tools, and support activities needed to perform the work. These items should
be provided to craftspersons in an easy-to-use, complete work package.
Effective planning should help ensure that consistent, quality maintenance
activities are conducted safely and correctly. Also, when coupled with an
effective scheduling and coordination methodology, many delays in
performing plant maintenance should be eliminated. Work planning is an
evolutionary process that should be periodically assessed through field
observation of work being performed and direct feedback from the
craftspersons to the planners. An effective planning program should contain
the following key elements:
• management commitment, overview, and support to ensure success of
the program
• management direction to ensure appropriate level of detailed work
instructions is developed and provided
• consistency in planning between disciplines to avoid confusion and
frustration of work groups
• thorough reviews by experienced individuals of products produced by
the planning group to minimize and eliminate errors
• feedback from craftspersons and supervisors to facilitate future
planning activities
10
DOE-STD-1050-93
• use of job history for establishing standard job durations, parts, and
consumables for repetitive jobs
3.1.2 Scheduling
Scheduling of corrective and preventive maintenance and of planned and forced outage
work is necessary to ensure that maintenance is conducted efficiently and within
prescribed time limits. Scheduling daily activities based on accurate planning estimates
should improve the use of time on the job and help reduce hazardous exposure.
Scheduling of planned outages is important to support the return of the facility to
service on schedule (and within the approved budget) and results in improved
availability and capacity factors. A contingency schedule should be maintained so that
if a forced outage occurs, the forced outage time is minimized and effectively used and
so that all needed maintenance is performed prior to restart.
Section 8
An effective schedule should assist management in controlling and directing
maintenance activities and should enhance the ability to assess progress. The schedule
should reflect the long-range plan and day-to-day activities. Effective scheduling should
enhance the efficient use of resources significantly by decreasing duplication of support
work, decreasing craftspersons idle time and ensuring completion of planned tasks. The
schedule should be the road map for reaching plant maintenance goals.
Scheduling is an integral part of the overall preparation for maintenance activities and
should be performed concurrently with the planning activities covered in this guideline.
The integrated schedule should be based upon such details as work scope, importance
to plant goals, prerequisites and interrelations, resources, and constraints, developed
during the planning process.
A properly prepared and updated integrated schedule should be a tool to assist in
managing maintenance activities. Performance deteriorates if a schedule is not available
to identify and properly sequence maintenance tasks. Sufficient detail should be
included to coordinate activities and track progress. By grouping individual work items
and integrating major tasks, more efficient use of support resources should be achieved.
The integrated schedule should form the basis for progress reporting. The schedule
should remain useful if it is updated frequently based on the progress reports.
11
DOE-STD-1050-93
Effective daily schedules are needed to implement the maintenance activity plans
represented by the integrated schedule. Management should track and periodically
assess performance to the daily schedule. Effectiveness of the daily scheduling process
during normal operation should be a good indicator of how effective the daily schedule
may be during outages.
The integrated schedule should be reviewed by those responsible for implementation.
It should be accepted and widely used by personnel involved in maintenance activities.
Preparation of schedules for contingencies should decrease the time necessary to
respond to problems if they occur and increase the information available for decision
making.
A maintenance job request priority coding system should be established to aide in
scheduling maintenance activities. An example of such a coding system is as follows:
a. Critical (C): Equipment or systems that shall operate greater than 90 percent of the
time. Being out of service for one working day may result in imminent and
significant environmental damage; potential to expose personnel to serious health
and safety damage, including injury or death; breach of security; or interruption
of production or experiment.
b. Urgent (U): Equipment, systems, or experiments important to plant goals and
which when out of service may result in a significant interruption of production
or experiment. Importance is great enough to justify diverting personnel from
other assignments and to work overtime, based on real-time circumstances.
Required uptime is greater than 80 percent.
c. Priority (P): Equipment, systems, or experiments important to plant goals but
which have backup or redundant hardware. Required uptime is greater than 70
percent.
d. Routine (R): Equipment, systems, or experiments not meeting one of above
categories which may be worked in most economical manner.
3.1.3 Coordination
Section 9
Plant maintenance activities may be complex projects involving large numbers of
personnel. Resources to support the activities should be coordinated in a timely,
controlled manner to ensure that they are ready to support the schedule. The types of
resources to be considered include personnel, material, expendable supplies, special
tools, and services.
12
DOE-STD-1050-93
Since the quality of maintenance activities performed directly impacts the plant's
reliability, management of the work force to achieve quality workmanship while
maximizing productivity requires close control by maintenance managers and
supervisors.
Material availability is an important element to a successful maintenance program.
Many items, particularly material needed for modifications and repair parts for older
equipment, may be long lead-time items. They should be identified and ordered well
in advance and tracked to delivery to ensure that they will be available at the job-site
when needed.
Daily meetings, with affected individuals, should be conducted to focus on the progress
of key jobs and to provide short-range coordination of scheduled activities. Meetings
should be managed to efficiently use the time of the managers and supervisors, to
minimize redirection of work in progress, and to prevent delays to oncoming work
shifts. Care should be taken to ensure that meetings focus on problems and their
solutions and do not become a forum for exchange of status only.
Performance measures of the rate of activity completion, schedule adherence,
productivity, and progress toward meeting plant maintenance goals, should be developed
(see DOE "Guidelines to Good Practices for Management Involvement at DOE Nuclear
Facilities.") These measures should be periodically checked for validity and should be
used by maintenance management to monitor performance.
3.2 Scope
3.2.1 This document addresses the elements considered essential for maintenance managers
and direct line supervisors to assign responsibilities and outline methods that may be
used in the overall planning, scheduling, and coordination functions to accomplish the
following:
a) Identify and screen plant deficiencies.
b) Control minor maintenance work activities within the plant work control system.
c) Determine the level of detail necessary to accomplish maintenance tasks and
troubleshooting.
d) Use maintenance history in planning corrective maintenance and repetitive job
tasks (see DOE "Guidelines to Good Practices for Maintenance History at DOE
Nuclear Facilities.")
13
DOE-STD-1050-93
e) Identify needed support to perform maintenance.
f) Prepare and assemble a maintenance work package.
Activities that are not covered in this guideline, but are closely related to the planning,
scheduling, and coordinating process, include the following:
a) procedures and work package approval
b) work package closeout and maintenance history update
3.2.2 A system of planning, scheduling, and coordinating maintenance work activities should
be clearly defined based upon the Maintenance Operations Model (Appendix A), which
consists of five interrelated processes applicable to each maintenance job. The
processes are as follows:
• Plan Maintenance Job. Identify the scope of a needed maintenance job. Produce
a maintenance job plan. Determine maintenance job planning category, priority,
and safety concerns. Identify and procure materials, and identify other
maintenance task resources. Prepare the maintenance job package.
Section 10
• Schedule Maintenance Job. Calculate estimated start date and project resources
for the maintenance job. Schedule and commit required resources and special
tools/equipment items to allow performance of all maintenance tasks within the
maintenance job.
• Execute Maintenance Job. Initiate and perform a maintenance job and collect job
information as defined in the maintenance job package.
• Execute Postmaintenance Test. Verify facilities and equipment items fulfill their
design functions when returned to service after execution of a maintenance job.
• Complete Maintenance Job. Perform maintenance job closeout to include
completion of all documentation contained in the maintenance job package to
ensure historical information is captured.
14
DOE-STD-1050-93
3.2.3 Appendix B (Facility Management) illustrates a comprehensive "Work Control Program"
based on the requirements of DOE Order 4330.4A, Maintenance Management Program.
The implementation of this program should ensure that the maintenance activities in
nuclear facilities are conducted in a manner that preserves and restores the availability
and operability of the SSC important to safe and reliable plant operation.
3.3 Responsibilities
3.3.1 The maintenance manager should have overall responsibility for the establishment,
implementation, and performance of the planning, scheduling, and coordination program
as described below:
a. maintaining equipment in accordance with applicable manufacturer's
recommendations for facility application and the requirements of this guideline;
b. specifying maintenance methods, procedures, and controls to ensure the quality of
materials, parts, and workmanship;
c. ensuring maintenance personnel are appropriately qualified;
d. ensuring an adequate supply of suitable spare parts, materials, and supplies to
service equipment covered by the maintenance program;
e. maintaining maintenance history files, and analyzing root causes of off-normal
operation (see "DOE Guideline DOE-NE-STD-1004-92 Root Cause A nalysis
Guidance Document");
f. coordinating maintenance with the owner/operator to establish proper plant
conditions, obtaining authorizations to conduct maintenance activities, and
obtaining acceptance prior to return to service;
g. coordinating activities/work crews to minimize interferences
h. maintaining critical path work on schedule or initiating appropriate alternatives as
needed
i. inspecting areas periodically to ensure safety, ALARA, and housekeeping
requirements are maintained
j. keeping plant management appraised, in a timely manner, of the overall status of
work and potential problems
15
DOE-STD-1050-93
k. maintaining a record of significant events and problems for use in planning future
maintenance activities
l. monitoring the overall effectiveness of the maintenance program and incorporating
program changes based on lessons learned from plant history, performance, worker
observations, and industry experience;
m. approving revisions to the program.
3.3.2 The operations manager should be responsible for:
a. ensuring that maintenance tasks are properly authorized;
b. setting and reviewing priorities for maintenance activities;
c. identifying postmaintenance test requirements and acceptance criteria;
d. providing schedule and technical assistance to maintenance;
e. restoring systems and components to correct operating alignment or standby modes
upon completion of maintenance tasks;
Section 11
f. making the final equipment operability/acceptance determination, if applicable,
prior to returning the equipment to service.
3.3.3 The technical support manager should be responsible for assisting, as required, in the
development and implementation of the planning, scheduling, and coordination program
as noted below:
a. maintaining an engineering staff which develops a close working relationship with
maintenance planners;
b. assist in the development of special procedures and work instructions for
equipment;
c. analyzing data for trends to prevent and resolve repetitive equipment failure
problems (see "DOE Guideline DOE-NE-STD-1004-92 Root Cause A nalysis
Guidance Document");
d. reviewing and approving modifications to systems (see DOE "Guidelines to Good
Practice for Modif ication W ork at DOE Nuclear Facilities";
e. assisting in troubleshooting of plant equipment problems;
16
DOE-STD-1050-93
f. providing recommendations to maintenance managers to upgrade equipment
performance (including processing design changes) or to make necessary
maintenance program adjustments.
3.3.4 The Planner should be responsible for the following:
a. ensuring that Job Packages and Work Instructions are developed which satisfy the
detail essential to effective job\task completion.
b. ensuring that incoming MJRs are screened and determined to contain all applicable
information.
c. ensuring adequate work definition and initiating requests for support crafts.
d. serving as initial customer contact and reflecting a positive customer-service
attitude by providing assistance in obtaining needed support or service.
e. planning jobs and ensuring that applicable requirements of interfacing policies,
procedures, and programs are incorporated into the Work Instructions.
3.4 Planning Guidelines
3.4.1 Maintenance Job Request (MJR) Processing
NOTE: Deficiency identification and control of work vary widely from plant to
plant. This section provides the basic elements needed in the work control
system to provide the planner with adequate information to perform the
planning function.
3.4.1.1 A maintenance job request (MJR) should be initiated and a maintenance
deficiency tag/sticker attached as soon as practical after discovery of a plant
equipment deficiency. (See Appendix D, Maintenance Job Request.)
3.4.1.2 All MJRs for plant equipment should be delivered to the owner/operator
designated representative for review and appropriate action to minimize
further equipment damage. The owner/operator review should include the
following:
a) Verify the MJR is not a duplicate of an existing MJR.
b) Equipment noun name, identification number, and location are properly
entered.
17
DOE-STD-1050-93
c) Originator information is included on the form and is legible.
d) Deficiency tag number and location are documented, if applicable.
e) Failure/problem description is accurate and clearly stated.
f) Identification of special conditions necessary to remove equipment
from service such as a limiting condition for operation, a system
outage, or a major plant outage.
g) Priority is assigned, technical safety requirements are identified, and
time limits for action are specified, if applicable.
3.4.1.3 Reviewed MJRs should be initialed by the owner/operator representative and
forwarded to the maintenance planning department.
3.4.1.4 The planning supervisor, or designated individual should review the MJR
and perform the following:
Section 12
a) Determine if the work on the Maintenance Job Request should be
performed as a minor maintenance task.
b) Assign the MJR to the responsible craft planner.
3.4.1.5 The craft planner should review the MJR and perform the following:
a) Verify the MJR is not a duplicate of an existing MJR.
b) Walkdown of the identified deficiency. Use the walkdown checklist
(Appendix E) as necessary to assist with job planning.
c) Verify the identified deficiency accurately describes the equipment
problem. For example, "waste disposal pump leaks," does not provide
enough information to assess the urgency of needed repairs or to
provide accurate direction in performing repairs on the pump. A more
accurate and quantitative problem description would be, 'The casing
flange on the waste disposal pump leaks 10 drops per minute during
pump operation at full load."
18
DOE-STD-1050-93
d) Identify special equipment/conditions to be considered in planning the
work such as scaffolding requirements, special tools, interference
removal, special radiological considerations, etc.
e) If the activity should be performed as minor maintenance, forward the
MJR to the appropriate craft supervisor or scheduler for
accomplishment.
3.4.2 Maintenance Job Request (MJR) Planning
NOTE: The planner should perform the following steps using Appendix E
(Walkdown Checklist).
3.4.2.1 Identify any other pending and/or appropriate maintenance tasks, such as
preventive maintenance, surveillance tests, or related corrective maintenance,
that may be performed concurrently with the work being planned.
Discussion with operations, scheduling, and engineering may be necessary
to coordinate all associated work.
3.4.2.2 Identify and initiate appropriate requests as necessary for additional task
and/or support needs such as scaffolding erection, electrical disconnection,
piping removal, etc.
3.4.2.3 Review component history to determine when and what actions were
previously taken for similar repairs. Consider repairs to similar equipment
in other locations. Repetitive maintenance trends for problem equipment,
components, and structures should be brought to the attention of engineering
for resolution.
3.4.2.4 Obtain applicable detailed drawings of the component(s) and associated
system(s) to be repaired or affected by the repair.
3.4.2.5 Review vendor information for special requirements for component repair
and parts that may be needed to perform repairs.
3.4.2.6 Provide a listing of required special tools and parts for the job in the job
package. If like-for-like replacement parts are not available, contact
engineering for resolution.
3.4.2.7 Check for parts availability. Order/reserve parts as necessary to perform
repair.
19
DOE-STD-1050-93
3.4.2.8 Determine procedure requirements based on equipment classification,
ALARA (as low as reasonably achievable) considerations, and/or extent of
repair needed to restore the equipment to operating condition (see DOE
"Writer's Guide for Technical Procedures"). Typically, the following types
of repairs should have an approved procedure or work instructions prior to
work:
• work on safety-related equipment
• work on environmentally qualified (EQ) equipment
• welding
• code repairs
• repairs that involve quality control verification
• configuration managed equipment
Where pre-approved procedures are available, work should be performed
using these procedures.
Section 13
3.4.2.9 If an approved procedure is not required as determined in Step 3.4.2.8,
provide work instructions to the craftsperson in sufficient detail to correct the
equipment deficiency. Vendor recommendations, engineering requirements,
craft training/skills (skill-of-the-craft), special tool needs, and hazards
involved in performing the task should be considered when preparing these
instructions. Engineering review of new work instructions should be
performed to ensure adequacy. Work instructions to control troubleshooting
should be developed as outlined in Appendix F.
Note: Consideration should be given to maintaining a library of routine,
recurring maintenance instructions to minimize planning time.
Previous job histories should be reviewed to establish standard job
durations, typical parts and consumables needed, and other job
requirements listed in Appendix G (Planning Checksheet).
3.4.2.10 Working with craft supervision and reviewing maintenance history records
to determine time and coordination requirements to accomplish the task.
20
DOE-STD-1050-93
3.4.2.11 Initiate special permits necessary to perform the maintenance task. Flame
permits, confined space permits, tagging requests, radiation work permit
requests, etc., should be included in the work package if available.
3.4.2.12 When ALARA work planning is performed, special consideration should be
given to providing adequate detail to assist the craftsperson in performing the
task and reducing radiation exposure. Examples of items that should be
considered include the following:
• reviewing previous work packages for lessons learned and effective
methods of performing the task
• reviewing area photographs, if available, to identify problems that may
delay work
• providing detailed tool lists
• providing rigging and handling sketches
• performing mockups or practice runs in non-radiation areas
• using portable shielding to reduce radiation levels
• dividing work into distinct tasks to be performed by different
individuals
• holding an in-depth prejob briefing to ensure craftspersons have a
clear understanding of the task to be performed
• improving access to the work through portable scaffolding or work
platforms
• flagging work areas to control access
• including ALARA personnel in the planning process
• designing special tools that may reduce time to complete repair
21
DOE-STD-1050-93
3.4.2.13 Work with the operations manager and engineers to determine the following:
a) operational impacts such as alarms, possible actuation, special system
alignment, or operator actions
b) postmaintenance test requirements that should be performed to check
the maintenance performed and to return the component to operation,
"Guidelines to Good Practices for Postmaintenance Testing at DOE
Nuclear Facilities" addresses postmaintenance testing.
3.4.2.14 Assemble the work package. Include items listed in Appendix G (Planning
Checksheet), as required. Plant document control procedures should be
followed to ensure the most recent revision of a procedure is used by the
craftsperson in performing the maintenance.
3.4.2.15 Place work package in the appropriate file or forward to scheduling for
accomplishment. Files should include the following:
a) Ready to Work - All requirements are met; parts are available; support
needs, such as scaffolding, are identified.
b) Hold for Parts - Repair parts are on order but have not been received
or are not available.
Section 14
c) Hold for Plant Conditions - All requirements have been met; however,
special plant conditions, such as a component outage/limiting
condition for operation, are needed to perform the work.
d) Outage Item - Plant outage or major system outage is needed to
perform task.
22
DOE-STD-1050-93
3.5 Scheduling Guidelines
3.5.1 Schedule Requirements
The schedule should be a management tool (specifically including first line supervision)
to control and direct maintenance activities. It should be used by management to
determine the critical path and explore alternatives when needed. The schedule should
be a concise method for tracking completion of maintenance tasks, particularly critical
path activities. The following are some of the attributes that should be included in the
schedule:
• The schedule should be useful. The individuals expected to follow the schedule
need to understand that it should make their tasks and the tasks of others easier.
They also should understand the importance of their tasks in relation to the
schedule as a whole.
• The schedule report format should be appropriate for the user. The level of detail
needed by the plant manager is different from the level of detail needed by a craft
supervisor.
• The schedule should be proactive in that it should predict and lead activities and
not only be an historical document.
• The schedule should be credible. It should be based on the best information
available and reviewed and accepted by those actually responsible for doing the
work.
• The schedule should be up to date. The schedule should be updated to reflect
changing situations to maintain credibility. An out-of-date schedule often may be
worse than no schedule.
• The schedule should be flexible, within the overall goals of the plant, in order to
produce optimum results in dealing with unanticipated events.
• There should be one overall schedule. The overall schedule should be developed
such that a hierarchy of schedules of varying detail may be obtained from a
common data base. It has generally proven difficult to keep two or more
schedules consistent, even when significantly different in level of detail
shown.
23
DOE-STD-1050-93
3.5.2 Schedule Methods
To be responsive to the needs of management, a computerized scheduling system should
be used.
Computerized scheduling offers the following advantages:
• rapid update capability
• ease in exploring alternatives
• resource determination and leveling
• identification of work-site congestion
• reports tailored to user
The success of a computerized planning and scheduling program is very dependent on
the knowledge and experience of planning personnel and on the management support,
training, and emphasis placed on its use. All supervisory personnel should have a basic
understanding of the schedule program appropriate to their needs and uses of the
schedule. Training sessions may be used to enhance this understanding and explain the
reporting, updating, and adherence policies.
3.5.3 Schedule Detail
The detail included in the overall schedule should be that required to ensure
coordination of work and permit assessment of progress. It is particularly important to
include details of tasks that have interfaces among the various crafts and support
personnel. The following are some examples of the coordination required:
• Operations Manager should be able to anticipate tagout needs.
• Radiological protection personnel should be able to determine in advance the
needs for radiation work permits and technician support.
Section 15
• Quality Control personnel and other inspection groups should be able to anticipate
the need for their presence at the job site.
• Critical resource needs, such as overhead cranes, should be provided in sufficient
detail to avoid interference, conflicts, and work delays.
24
DOE-STD-1050-93
• Major radiological protection actions, such as installation of temporary shielding,
should be scheduled events.
• Major support activities, such as scaffolding erection, should be adequately defined
in the schedule.
For minor jobs, some plants have been successful in identifying support requirements,
such as tagging and radiation work permit (RWP) requirements, within the coding
structure for activities in the schedule. When this is done, it is very important that
sufficient training and familiarization be given to enable personnel to interpret the
coding easily. It has generally been found necessary to explicitly schedule the support
needed for major tasks rather than use only activity coding. A sufficient number of
activities should be scheduled to ensure the short-term visibility needed for work
coordination and progress tracking. Milestones should be defined for the completion
of logical collections of tasks. Use of these intermediate milestones may provide an
overall measure of the progress of maintenance activities and identify tasks
significantly behind schedule. Management may then take appropriate corrective
action.
Associating detailed work lists to a single activity in the schedule, rather than explicitly
scheduling start dates for each job, has proven useful. This provides visibility of details
but permits the individual tasks to be managed by the responsible departments and/or
first-line supervisors. This is only successful, however, when a particular sequence of
completing the work is not required, the support and interface requirements are minor,
and a strong daily schedule and good communications exist. Note that the completion
of the individual jobs should be closely monitored and progress tracked or there is a risk
that delays in completion of one or more of the jobs may result in major schedule
delays.
3.5.4 Daily Schedules
Daily schedules are important to ensure that work is properly coordinated even when
there may be last-minute schedule changes. A daily schedule is generally used as the
basis for discussions at daily meetings. The daily schedule may be generated by the
computerized scheduling program itself or developed separately from information
contained in the scheduling program data base.
A three-day look-ahead schedule issued daily has proven useful at many plants. This
schedule provides the detail necessary to control the present day's work and provides
an opportunity for craft planning for the next few days without an
unreasonable amount of data. Extending the look-ahead period longer than about five
days and not issuing the schedule on a daily basis increases the risk that data may not
be current when needed.
25
DOE-STD-1050-93
A detailed review of the daily schedule should be an integral part of shift turnover
activities to ensure that the on-coming shift is familiar with any short-term adjustments
made to the schedule. This is particularly important for operator turnovers to ensure
that operators know the status of the plant and are familiar with upcoming maintenance
activities including tagging needs.
3.5.5 Schedule Preparation
The following items should be considered during the schedule preparation process:
Section 16
• The schedule should be success oriented (i.e., contingency plans should not be
included). If a contingency plan needs to be implemented, the schedule then
should be revised to fit the particular situation.
• The schedule should be challenging but achievable. It should be consistent with
the goals set by management.
• Work items should be coded to identify their discrete locations in the plant. They
then may be reviewed together to assess the degree of area congestion and to
minimize duplication of support work such as scaffolding and insulation removal.
• The schedule should be craft-loaded and the sequence and timing of activities
adjusted to ensure that resource requirements are consistent with resource
availability.
• Tests, inspections, or other tasks that may identify additional work should be
scheduled as early as possible to permit time for completion of the additional work
within the established envelope.
• Significant as-found, postmaintenance, and postmodification testing should be
explicitly scheduled. Time should be allotted for testing, line up, and other
activities required for returning systems to service. System interactions and
operator resources should be considered when scheduling system and plant startup.
26
DOE-STD-1050-93
3.5.6 Schedule Integration
Integration of major tasks is a key to successful schedule development. There should
be one all inclusive schedule that includes work to be done by non-facility contractors
contributing support to the schedule as well as work to be done by site personnel.
Details for specific tasks should be provided by those responsible for the task. The
planning organization should integrate these details into the overall schedule.
Manpower and support requirements should be included for maintenance activities.
Work that should be integrated includes preventive maintenance, corrective maintenance,
modifications, surveillance testing, and inservice inspections.
Non-facility contractors should be involved in early planning to ensure their work is
integrated and scheduled properly.
3.5.7 Schedule Review
Schedule users, including non-facility contractors, should be required to review and
comment on the schedule. Several reviews during the preparation process frequently
avoid last-minute problems during the final review. Comments should be resolved
before the next revision of the schedule. Support of this activity by line managers is
a key to the success of the schedule.
The rationale behind specific schedule decisions should be documented and explained
to those who are responsible for implementing the schedule. The explanation also
should include restraints on the activity and restraints the activity places on others.
Opportunities for schedule improvements should be explored during the review process.
This should include review of technical safety requirements and other regulatory
requirements to determine if changes are possible that may result in work efficiency or
schedule improvements without sacrificing safety.
The overall intent of the schedule review process, coupled with obtaining user input to
the planning process, should be to provide a sense of ownership of the schedule to those
who are expected to implement it.
3.5.8 Format, Progress Reporting, Updating, and Distribution
The schedule should be viewed as a tool by everyone involved in maintenance
activities. The information provided to individuals should be commensurate with their
responsibility and authority.
Section 17
27
DOE-STD-1050-93
The following points on schedule distribution should be considered:
• Detailed information should be limited to the needs of the recipient. For example,
a machinist overhauling a valve may need only start and finish times. The
supervisor, however, should know the work scheduled several days in advance so
availability of needed tools, materials, and required support may be ensured. The
discipline manager should require advance schedule information for all associated
work so assignments may be planned.
• Progress information should be summarized for management personnel,
emphasizing problem areas and potential problem areas. Progress associated with
the critical path or near-critical path should receive particular attention.
• The schedule information provided should be concise and understandable to the
user.
The fundamental principles of a progress reporting system should be simplicity,
accuracy, and timeliness. The individuals responsible for the work also should be
responsible for progress reporting. To be most effective, the reporting system should
be structured to be useful to those reporting and doing the work. The information
requested should be limited to the minimum required.
The individuals responsible for progress reporting should be selected, by name, in
advance of the start of the maintenance activities. Training should be held for those
selected to ensure they understand the reporting system, the information needed, and
how the information may be used. The need to report problems should be emphasized.
Reporting should be more accurate and timely if the need for the data is fully
understood. Vendors and contractors should be included in the progress reporting
system.
Progress may be reported in a number of ways, some of which depend on the particular
scheduling system used. For some systems, reporting start date, time, and remaining
duration has been effective. An effective method is marking up daily schedules used
by the work groups and returning them to the scheduling organization. Reporting
progress relative to intermediate milestones also is useful.
As mentioned in section 3.5.1 of this guideline, "Schedule Requirements," the schedule
should be current. The schedule should be updated regularly, based on the progress
reports. The interval of updating should depend on the rate of change. For major
changes and changes affecting the critical path or near-critical path, daily updates may
be necessary. The key is that the schedule is maintained credible and provides the
guidance needed to those responsible for performing the work.
28
DOE-STD-1050-93
3.6 Coordination Guidelines
3.6.1 Organization and Supervision
Extensive involvement of managers and supervisors in maintenance activities ensures
timely completion of work, quality of completed work, and safety of personnel and
equipment. Timely corrective actions should be taken when performance deficiencies
are noted.
Supervisors should routinely monitor maintenance work in progress to ensure timely
availability of support services and coordination with other activities and to ensure that
activities are performed in accordance with plant policies and procedures. Particular
emphasis should be given to the following areas in training supervisors:
• monitoring on-going work to control quality and progress
• providing accurate and timely work status reporting
• coordinating support and interface work activities
• ensuring the timely availability of tools, supplies, and parts
Section 18
• understanding schedule interpretation and use
Supervisory controls should be applied to verification of tagouts prior to opening piping,
valves, or mechanical equipment or working on electrical equipment. Additionally,
specific precautions should be taken to exclude foreign material intrusion into open
systems.
3.6.2 Prejob Coordination
Coordination of maintenance activities may involve detailed integration and timely
implementation of many interrelated activities. Planners should be responsible for
identifying and planning these interrelated activities, but the actions of managers and
supervisors determine the success of completing the scheduled work.
Specific coordination and integration activities that should be considered by the line
supervisors in preparing for work include the following:
• effective integration of plant system operation and maintenance activities to ensure
proper plant conditions, timely equipment or system tagouts, initiation and
completion of maintenance or modifications, and timely performance of
inspections
29
DOE-STD-1050-93
• ALARA actions, including shielding installation and prejob briefings on ALARA
precautions
• support of maintenance activities by health physics and decontamination personnel,
including support during the performance of tasks, identifying and posting work
areas, and timely decontamination of tools, floors, and equipment
• allocation of space and crane use
• inspection of maintenance activities by quality control personnel, including
completion of associated documents
• continuous document processing, issuing, and closeout throughout the job
The effectiveness of prejob coordination should be routinely assessed by managers and
supervisors and corrective actions taken when required to improve the efficiency of
conduct of work.
3.6.3 Material Staging and Availability
A clear definition of the responsibility for ensuring that adequate parts and material are
on site and available for the performance of scheduled work activities is necessary to
avoid problems during the performance of maintenance. Plant responsibilities regarding
procurement of material required for maintenance and modifications should be included
in the definition. Having one organization responsible for coordinating material needs
and a single point of contact for expediting material has proven successful and should
be considered. (See DOE "Guidelines to Good Practices for Procurement of Parts,
Materials, and Services at DOE Nuclear Facilities.")
Parts and material required for maintenance activities should be identified and purchased
in time to allow for receipt and inspection well before they are needed. After
processing, these parts and material should be identified for specific work packages and
segregated from other stock inventory. Standard stock items and consumables required
for planned work should be allocated to ensure their availability. (see DOE Guidelines
to Good Practices for Material Receipt, Inspection, Handling, Storage, Retrieval, and
Issuance at DOE Nuclear Facilities.")
Adequate storage and protection of parts and materials segregated for planned
maintenance activities should be provided. This is particularly important for material
staged at the job-site and not within normal storage areas.
30
DOE-STD-1050-93
Periodic reports highlighting any material or parts problems should be distributed to
appropriate management personnel. Problems with material availability should be
identified early to permit contingency planning.
Section 19
3.6.4 Daily Meetings
Well managed planning and scheduling meetings are necessary to keep facility
personnel aware of significant maintenance activities that are in progress and to make
corrections to schedules. Meetings should be effectively managed to limit the time
personnel spend in the meetings. Participation in meetings should be limited to those
personnel affected. Three types of meetings, discussed below, have been shown to be
effective in improving communications among work groups and in enhancing job
coordination.
A daily directional meeting may be held after the start of the primary work shift. This
meeting should be attended by management personnel and representatives from all
major work groups. The meeting should focus on major jobs and evolutions planned
for the next 48 hours and identify any redirection necessary due to significant problems
such as lack of materials, shortage of other support resources, delays in key support
activities, or other problems. Care should be taken to not unnecessarily perturb work
in progress. At many plants, the planning organization prepares discussion material for
this meeting including considerations for alternative paths. Results of the directional
meeting affecting activities should be factored into the schedule at the daily planning
meeting.
A planning meeting should be held each day following the directional meeting to review
the near-term (next three to five days) schedule and verify that jobs may be worked as
scheduled. Planners, and representatives of the operations manager, radiological
protection, and other support departments should attend. The participants at this
meeting should ensure that the information contained in the next updated schedule is
consistent with current plans and resource availability. The schedule then should be
updated by incorporating information from the directional meeting and the planning
meeting. Re-prioritizing or rescheduling some work may be necessary for some support
groups.
31
DOE-STD-1050-93
A shift work coordination meeting should be held shortly before the start of each shift.
This meeting should be attended by oncoming shift supervision for each of the groups
supporting the maintenance schedule, including maintenance, health physics, technical
staff engineering, area coordinators, and task coordinators, for jobs requiring significant
support. The Operations Supervisor for the oncoming shift should also attend. The
shift work coordination meeting should address all scheduled work for the upcoming
shift by exception and should modify the schedule as necessary to reflect last-minute
changes. Reissue of the daily schedule to reflect these changes should not be -
necessary. Items requiring multi-discipline support should be identified to the respective
support groups and an estimate of the quantity of resources and the time required should
be provided. Each attendee should leave the meeting with a clear under-standing of
what their work group should do on the upcoming shift. The meeting should end in
time for supervisors to return to their work groups before the shift starts.
Assignments for problem resolution should be made at meetings, but resolution should
not be attempted during the meeting. The meetings should not be used as the primary
method to determine status of maintenance activities.
3.6.5 Performance Monitoring
Section 20
Performance measures should be developed to monitor the progress toward meeting
plant maintenance goals (see DOE "Guidelines to Good Practices for Management
Involvement at DOE Nuclear Facilities") Progress toward meeting these goals should
be monitored frequently. Results of the routine monitoring should be reported to plant
management. Examples of goals that are typically monitored include:
• rate of activity completion
• percent compliance to the daily schedule
• progress against the schedule
• amount and rate of bulk work (nonscheduled or listed work) completed
• expended man-hours versus planned man-hours by each craft or work group
• number of industrial accidents
• expended man-rem versus planned man-rem
• amount of radwaste generated
32
DOE-STD-1050-93
• number of skin and clothing contaminations
The performance measures should be monitored frequently to check that they are valid
measures of plant maintenance status. Examples of areas that may be checked to ensure
that the progress reported actually reflects real status include the following:
• The rate of activity completion is checked against the projected activity
completion, the number of activities remaining, and the remaining duration on the
schedule to ensure that the current rate supports the scheduled completion date.
• Compliance to the daily schedule is maintained at a high level to ensure that
scheduled work is being completed to support the overall plant maintenance goals.
• Progress against the overall schedule is tracked to identify areas where work
completion does not support the schedule.
• Bulk work completions should be tracked against remaining resources and time
to ensure that bulk work is being completed at a rate that supports the schedule.
• Actual man-hours expended are tracked against earned value (original estimates)
of completed jobs and against remaining scheduled work, manhours, and time
remaining to ensure that sufficient resources and time exist to complete the
maintenance activities as scheduled.
• Other performance measures, such as industrial accidents, skin and clothing
contaminations, and overall exposure, should be tracked to identify areas of
concern where actual values are exceeding projections.
Deviations in the expected results identified in reviews of the performance measures, such as
those listed previously, should be analyzed to identify their root causes and should be reported
to plant management for appropriate corrective action. (see "DOE Guideline DOE-NE-STD-
1004-92 Root Cause A nalysis Guidance Document")
33
DOE-STD-1050-93
APPENDIX A
MAINTENANCE OPERATIONS MODEL
A - 1
DOE-STD-1050-93
The Maintenance Operations Model incorporates five interrelated processes
applicable to each maintenance job. These five processes are Plan Maintenance Job,
Schedule Maintenance Job, Execute Maintenance Job, Execute Postmaintenance Testing,
and Complete Maintenance Job.
The Plan Maintenance Job process is identifying the job scope; producing a job plan;
determining the planning category, priority, and safety concerns; identifying and procuring
parts, materials, and supplies; identifying other task resources required; and preparing the
work package. This process was developed based on DOE Order 4330.4A Chapter II
Section 7.3.1.
The Schedule Maintenance Job process is calculating estimated start date and project
resources required for job; scheduling and committing required resources and special
tools/equipment to allow performance of all job tasks associated with the job. This process
was developed based on DOE Order 4330.4A Chapter II Section 7.3.2.
Section 21
The Execute Maintenance Job process is initiating and performing the job; and
collecting job information as defined in the work package. This process was developed
based on DOE Order 4330.4A Chapter II Section 8.
The Execute Postmaintenance Testing process is verifying facilities SSC fulfill their
design functions prior to return to service after execution of the job. This process was
developed based on DOE Order 4330.4A Chapter II Section 9.
The Complete Maintenance Job process is performing job closeout to include
completion of all documentation contained in the work package to ensure historical
information is captured. This process was developed based on DOE Order 4330.4A Chapter
II Section 8.3.4.
A - 3
DOE-STD-1050-93
APPENDIX B
FACILITY MANAGEMENT
B - 1
DOE-STD-1050-93
APPENDIX B
B - 3
DOE-STD-1050-93
APPENDIX C
EXAMPLES OF MINOR MAINTENANCE
C - 1
DOE-STD-1050-93
APPENDIX C
EXAMPLES OF MINOR MAINTENANCE
Examples of Mechanical Minor Maintenance
A. The following are examples of work that may qualify as minor maintenance:
1. Manual Valve: Adjust packing on manual valves not subject to testing, repair or
replace handwheel, lubricate valve stem.
2. Pumps: Adjust packing; adjust cooling water flow.
3. Flanges: Tighten to stop leakage (not to exceed recommended torque values).
4. Diaphragms: Seal against in-leakage.
5. Brackets/Hangers: Replace missing bolts (except safety-related/seismically qualified or
material substitution).
6. Doors: Repair or replace knobs, hinges, bars, or closures.
7. Plumbing: Repair or replace commodes, water fountains, sinks.
8. Structures: Patch walls, roofs, etc. (except fire barrier seals).
9. Grating/Stair Treads: Repair or replace grating, clips, or treads.
B. The following are examples of work that does not qualify as minor maintenance:
1. Manual Valves: Adjust packing on valves that require testing.
2. Motor-operated Valves: Adjust or replace packing.
3. Pumps: Replace packing or seals, replace casing bolts, replace gasket.
4. Flanges: Replace gasket or fasteners; install or remove blank flange.
C - 3
DOE-STD-1050-93
APPENDIX C
EXAMPLES OF MINOR MAINTENANCE
Examples of Electrical Minor Maintenance
A. The following are examples of work that may qualify as minor maintenance:
1. Lamps or Bulbs: Replace.
2. Fuses: Replace where fuse is not required to be safety-related.
3. Junction Boxes (non-EQ): Replace covers or screws.
4. Conduit: Replace covers, screws, brackets.
5. Motors: Replace air filters, replace cover screws, replace screens.
6. Plant Paging System: Repair or replace handles, knobs, etc.
7. Portable Sump Pumps: Repair or replace motor or wiring.
8. Door Locks or Latches: Repair or replace (except fire and security doors).
9. Telephone Equipment: Install, replace, or repair.
B. The following are examples of work that does not qualify as minor maintenance:
1. Light Fixture: Repair or replace where tagout is required.
2. Fuses: Replace where fuse is safety-related.
3. Fire Alarm Panel: Repair.
4. Protection Relay Test Switches: Repair or replace.
C - 4
DOE-STD-1050-93
APPENDIX C
EXAMPLES OF MINOR MAINTENANCE
Examples of Instrument Minor Maintenance
A. The following are examples of work that may qualify as minor maintenance:
1. Lamps or Bulbs: Replace.
2. Fuses: Replace where they do not perform a safety-related function.
3. Pressure Gauges: Replace gauge or glass.
4. Instrument tubing: Tighten.
5. Air Filters: Replace.
Section 22
6. Knobs: Tighten, repair, or replace.
B. The following are examples of work that does not qualify as minor maintenance:
1. Electro-pneumatic Equipment and Positioners: Clean or adjust.
2. Pneumatic Controllers: Clean, adjust, or calibrate.
3. Fuses: Replace when the fuse performs a safety-related function.
4. Transmitters: Vent or fill.
C - 5
DOE-STD-1050-93
APPENDIX D
EXAMPLE MAINTENANCE JOB REQUEST
D - 1
DOE-STD-1050-93
APPENDIX D
EXAMPLE MAINTENANCE JOB REQUEST
D - 3
DOE-STD-1050-93
APPENDIX E
EXAMPLE WALKDOWN CHECKLIST
E - 1
DOE-STD-1050-93
E - 3
DOE-STD-1050-93
APPENDIX F
EXAMPLE TROUBLESHOOTING GUIDE
F - 1
DOE-STD-1050-93
APPENDIX F
EXAMPLE TROUBLESHOOTING GUIDE
For work that requires troubleshooting for unknown conditions on energized, pressurized, or
operating equipment, perform the following:
1. Prior to developing the troubleshooting methodology, review/consult with the following
sources of information as necessary to understand the equipment/systems interactions:
a. system engineers
b. owner/operator personnel (organization responsible for the equipment)
c. training
d. technical safety requirements
e. final safety analysis report (FSAR)
f. equipment vendor manuals
g. equipment manufacturers
h. applicable procedures
i. applicable system/circuit drawings
j. vendor drawings
2. Include the following, as applicable, in the work instructions to the craftsperson:
a. Notes, precautions, and prerequisites for the specific task (e.g., "system contains live
steam, do not vent"; "do not exceed three motor starts in any one-hour period"; "do
not remove input/output signal cable before de-energizing power supply").
b. Steps to record and observe as-found/as-left conditions of the affected equipment.
c. Steps to record any abnormalities observed during equipment operation, e.g., bearing
noise, smoke, vibration, etc.
d. Steps to prevent further damage if any abnormal conditions are observed.
e. Specific instructions for craft/technician to stop work when problems or conditions
encountered were not anticipated or are not understood. They should be directed to
consult with their supervisor or planner prior to taking action.
f. Steps to record and verify lifted/landed leads. Lifted lead forms should be included
in the work package as required.
F - 3
DOE-STD-1050-93
APPENDIX F
EXAMPLE TROUBLESHOOTING GUIDE
g. Steps to record the identification numbers and calibration due dates of measuring and
test equipment used (see DOE "Guidelines to Good Practices for Control and
Calibration of Measuring and Test Equipment (M&TE) at DOE Nuclear Facilities."
h. Steps to tag and retain all parts removed during the troubleshooting process. These
parts shall be retained as appropriate for further investigation/analysis by maintenance
or systems engineer.
3. For troubleshooting of safety-related equipment, or equipment important to safe and
reliable plant operation, a troubleshooting impact statement should be included as part of
the planned package. Include the following information on the statement:
a. scope of the troubleshooting
b. required equipment status
c. work boundaries for the activity
d. potential plant upsets that may occur
e. approval of owner/operator supervision prior to beginning troubleshooting activities
4. Any follow-up corrective maintenance deemed necessary as a result of troubleshooting
should be performed under a separate corrective maintenance work order or under an
approved revision to the work plan.
Section 23
F - 4
DOE-STD-1050-93
APPENDIX G
EXAMPLE PLANNING CHECKSHEET
G - 1
DOE-STD-1050-93
G - 3
DOE-STD-1050-93
G - 4
DOE-STD-1050-93
APPENDIX H
PLANNING, SCHEDULING, AND COORDINATION OF MAINTENANCE
SAMPLE LESSON PLAN
H - 1
DOE-STD-1050-93
APPENDIX H
PLANNING, SCHEDULING, AND COORDINATION OF MAINTENANCE
SAMPLE LESSON PLAN
LESSON PLAN
1. The instructor should be familiar with the following background information:
a. An effective system for planning, scheduling, and coordinating maintenance work
should provide benefits such as improved maintenance efficiency, reduced radiation
exposure, and increased equipment availability.
b. Planning is that function where the actions and support of a specific maintenance
activity are prearranged prior to the crew receiving the assignment work package.
Some elements of planning include the following:
• the work activity defined in scope,
• identification of required support,
• adequate task instruction or procedures,
• identification of qualified craftsperson,
• and maintenance history update.
c. Scheduling is that function where multiple work activities are arranged to conduct
overall site maintenance efficiently and within prescribed time limits. Scheduling
includes:
• accurate site-wide priority setting, and
• scheduling meetings to integrate multiple work activities in order to prevent
conflicting job tasks, and site support requirements.
d. Coordination is a sub-function of scheduling where work permits, tagouts, Quality
Control verifications, and other support activities are organized and timed to support
the overall efficiency of the maintenance task.
2. To teach this lesson, the following training housekeeping items are required:
a. Location for the training,
H - 3
DOE-STD-1050-93
b. Approximately 30 minute time period for the training,
c. Notification of selected employees, and
d. A copy of the facility's daily/weekly planning and scheduling sheet, a copy of a current
backlog report, and a listing of the job priority codes.
3. This lesson has the following trainee enabling objectives:
a. Explain the facility's planning, scheduling, and coordinating process,
b. Define the concept of backlog of corrective maintenance work, and
c. State the priority system.
4. Some important factors in ensuring that site maintenance is performed in an efficient and
timely manner are job/task planning, integrated scheduling of multiple work activities, and
coordination of tagouts, permits and materials. If these considerations are performed
effectively, then each work crew should receive a work package and accomplish the work
task without spending valuable craftspersons time chasing down parts, searching for
support documentation, or waiting on other departmental support. Components of
planning, scheduling, and coordination include the following:
a. All maintenance work orders on operational equipment should be reviewed by the
planning organization. This review should address the following:
• the deficiency identified on the work order should be verified as correct prior to
issuing the job. (This prevents mobilization of a crew for a non-maintenance
activity.
• appropriate procedures, drawing, vendor manuals, and historical information
should be selected to support the activity,
• essential tools, equipment, parts, and materials should be identified and available,
• manpower requirements should be specified,
• ALARA considerations should be included in the job scope,
Section 24
• identification of the initial system or component conditions should be performed
prior to performing maintenance,
H - 4
DOE-STD-1050-93
• instructions for equipment restoration and postmaintenance testing should be
included in the work order, and
• a post-activity review of completed work documentation and an update to the
equipment history files.
b. Corrective Maintenance Backlog should be monitored to help ensure that important
jobs are not being unnecessarily delayed, and that management control is maintained
over the amount and type of work in the backlog. Corrective maintenance backlog is
an important indicator of how responsible the maintenance organization is to their
customers. If the customer, usually operations and/or fabrication, has to work around
defective or out-of-service equipment, then the overall operability of the site may be
compromised. The greater the amount of defective equipment and the longer the
equipment is left defective, the more significant that risk becomes.
c. A work priority system is used to minimize the congestion of jobs that are important
to safe and reliable operations with those that are of less importance. An example of
a work priority system includes the following:
• Critical (C): Equipment or systems that shall operate greater than 90 percent of the
time. Being out of service for one working day may result in imminent and
significant environmental damage; potential to expose personnel to serious health
and safety damage, including injury or death; breach of security; or interruption
of production or experiment.
• Urgent (U): Equipment, systems, or experiments important to plant goals and
which when out of service may result in a significant interruption of' production
or experiment. Importance is great enough to justify diverting personnel from
other assignments and to work overtime, based on realtime circumstances.
Required uptime is greater than 80 percent.
• Priority (P): Equipment, systems, or experiments important to plant goals but
which have backup or redundant hardware. Required uptime is greater than 70
percent.
• Routine (R): Equipment, systems, or experiments not meeting one of above
categories which may be worked in most economical manner.
d. The effective coordination of maintenance activities requires plant wide adherence to
site work priorities, and timely support from other departments for items such as
permits, tagouts, and radiological protection coverage.
5. Discuss with the trainees the scheduling work sheet, a backlog report, and the work
priority system. Emphasize a clear understanding of each item.
H - 5
DOE-STD-1050-93
CONCLUDING MATERIAL
Review Activities: Preparing Activity:
DOE Field Offices DOE-NE-73
AD AL
DP CH Project Number:
EH ID
EM NV MNTY-0005
ER OR
NP RL
NS SR
RW SF
Area Offices
Amarillo
Brookhaven
Kansas City
Kirtland
Princeton
Facilities
ANL
BNL
LBL
PNL
PPPL
SNL
NV REECo.
NV EG&G
OR OSTI
WHC
EG&G
RF
SLAC
WSRC
FOREWORD
1. INTRODUCTION
1.1 Purpose
1.2 Background
1.3 Application
2. DEFINITIONS
2.1 Acronums Used in This Standard.
2.2 ALARA
2.3 Corrective Maintenance.
2.4 Deficiency.
2.5 De ficiency Tag/Sticker
2.6 Facility.
2.7 Maintenance.
2.8 Maintenance Importance Generator (MIG).
2.9 Maintenance Job Request (MJR)
2.10 Maintenance Management.
2.11 Maintenance Procedure.
2.12 Maintenance Work Instructions
2.13 Maintenance Work Package.
2.14 Minor Maintenance.
2.15 Outage.
2.16 Performance Test.
2.17 Performance Monitoring.
2.18 Periodic Maintenance.
2.19 Planned Maintenance.
2.20 Postmaintenance Test.
2.21 Predictive Maintenance.
2.22 Preventive Maintenance.
2.23 Root Cause.
2.24 Structures, Systems and Components (SSC).
2.25 Technical Support.
2.26 Work Control Document.
Section 25
3. PLANNING, SCHEDULING, AND COORDINATION OF MAINTENANCE ACTIVITIES
3.1 Discussion
3.1.1 Planning
3.1.2 Scheduling
3.1.3 Coordination
3.2 Scope
3.3 Responsibilities
3.4 Planning Guidelines
3.4.1 Maintenance Job Request (MJR) Processing
3.4.2 Maintenance Job Request (MJR) Planning
3.5 Scheduling Guidelines
3.5.1 Schedule Requirements
3.5.2 Schedule Methods
3.5.3 Schedule Detail
3.5.4 Daily Schedules
3.5.5 Schedule Preparation
3.5.6 Schedule Integration
3.5.7 Schedule Review
3.5.8 Format , Progress Reporting, Updating, and Distribution
3.6 Coordination Guidelines
3.6.1 Organization and Supervision
3.6.2 Prejob Coordination
3.6.3 Material Staging and Availability
3.6.4 Daily Meetings
3.6.5 Performance Monitoring
APPENDIX A MAINTENANCE OPERATIONS MODEL
APPENDIX B FACILITY MANAGEMENT
APPENDIX C EXAMPLES OF MINOR MAINTENANCE
APPENDIX D EXAMPLE MAINTENANCE JOB REQUEST
APPENDIX E EXAMPLE WALKDOWN CHECKLIST
APPENDIX F EXAMPLE TROUBLESHOOTING GUIDE
APPENDIX G EXAMPLE PLANNING CHECKSHEET
APPENDIX H PLANNING, SCHEDULING, AND COORDINATION OF MAINTENANCE SAMPLE LESSON PLAN