DOE-HDBK-1211-2014, Activity-Level Work Planning and Control Implementation
Functional areas: Activity Level Work, Lessons Learned, Work Performance
This Handbook describes non-mandatory approaches for implementing DOE requirements for activity-level work planning and control (WP&C) at Hazard Category 1, 2 and 3 nuclear facilities and is intended to be a resource for improvement in the performance of work at the activity-level by the DOE contractor community.
Version history and related documents
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
NOT MEASUREMENT
SENSITIVE
DOE-HDBK-1211-2014
April 2014
DOE HANDBOOK
ACTIVITY-LEVEL WORK PLANNING AND
CONTROL IMPLEMENTATION
U.S. Department of Energy AREA HDBK
Washington, DC 20585
DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.
DOE-HDBK-1211-2014
TABLE OF CONTENTS
FOREWORD .......................................................................................................................... v
1.0. PURPOSE......................................................................................................................... 1
2.0. SCOPE.............................................................................................................................. 1
3.0. APPLICABILITY ............................................................................................................... 1
4.0. REFERENCES.................................................................................................................. 2
5.0. DEFINITIONS ................................................................................................................... 2
6.0. IMPLEMENTATION OF WORK PLANNING AND CONTROL ........................................ 7
6.1. Work Planning and Control and Integrated Safety Management System (ISMS) ....... 9
6.1.1 Roles and Responsibilities ....................................................................................9
6.1.2 Training Needs and Qualifications ......................................................................14
6.1.3 Supporting ISMS Functional Elements................................................................17
6.1.4 WP&C and Crosscutting Programs .....................................................................20
6.1.5 Conduct of Operations Relationship to WP&C ....................................................23
6.1.6 Research and Development Activities’ Relationship to WP&C ...........................24
6.1.7 Supporting Facility-Level Documents..................................................................24
6.1.8 The Graded Approach and Tailoring in WP&C....................................................26
6.1.9 Measuring System Effectiveness for Activity-Level WP&C .................................27
6.2. Defining the Scope of Work ....................................................................................... 28
6.2.1 Work Identification and Request .........................................................................28
6.2.2 Work Screening, Validation, Prioritization, and Backlog Control .........................29
6.2.2.1 Emergency Work .........................................................................................31
6.2.2.2 Systematic Testing and Repairs of Failed Components ..............................32
6.2.3 Work Scope Development ...................................................................................32
6.2.4 Planning Team ....................................................................................................33
6.2.5 Acceptance Criteria .............................................................................................35
6.3. Planning the Work – Identify and Analyze Hazards .................................................. 35
Section 2
6.3.1 Hazard Identification............................................................................................35
6.3.2 Identify Safety Requirements, Standards, and Guidance....................................36
6.3.3 Hazard Analysis ..................................................................................................36
6.3.3.1 General Hazard Analysis.............................................................................39
6.3.3.2 Job Hazard Analysis ....................................................................................39
6.3.3.3 JHA Walkdowns or Roundtable Reviews ....................................................41
6.4. Planning the Work – Develop and Implement Hazard Controls ................................ 42
ii
DOE-HDBK-1211-2014
6.4.1 Safety SSCs and Technical Safety Requirements ..............................................42
6.4.2 Establish a Hierarchy of Controls ........................................................................43
6.4.3 ALWCD Development .........................................................................................44
6.4.3.1 Work Scope .................................................................................................45
6.4.3.2 ALWCD Types .............................................................................................45
6.4.3.3 ALWCD Use Categories ..............................................................................47
6.4.3.4 ALWCD Preparation ....................................................................................48
6.4.4 ALWCD Verification and Validation.....................................................................49
6.4.5 ALWCD Approval ................................................................................................50
6.4.6 ALWCD Change Process ....................................................................................51
6.5. Planning the Work – Scheduling ............................................................................... 52
6.5.1 Schedule Attributes and Detail ............................................................................52
6.5.2 Schedule Integration ...........................................................................................54
6.5.3 Schedule Approval and Changes........................................................................55
6.6. Performing Work within Controls ............................................................................... 55
6.6.1 Preparation and Release of Work .......................................................................56
6.6.2 Pre-Job Brief .......................................................................................................57
6.6.3 Performing Work .................................................................................................60
6.6.3.1 Stop/Pause Work Expectations and Responsibilities ..................................61
6.6.3.2 Monitoring Work, Status Updates, and Turnovers .......................................63
6.6.4 Post-Work Testing...............................................................................................64
6.6.4.1 Post-Work Acceptance ................................................................................65
Section 3
6.6.4.2 ALWCD Closeout ........................................................................................66
6.7. Providing Feedback on Adequacy of Controls and Continuing to Improve Safety
Management ............................................................................................................. 66
6.7.1 Post-Work Review...............................................................................................66
6.7.2 Document Lessons Learned ...............................................................................67
6.7.3 Implement Lessons Learned ...............................................................................68
6.7.4 Assessing Performance ......................................................................................68
7.0. ACRONYMS ................................................................................................................... 70
APPENDIX A. SKILL OF THE WORKER ............................................................................... A-1
APPENDIX B. WORK PLANNING AND CONTROL METRICS, ANALYSIS, AND
TRENDING ................................................................................................... B-1
APPENDIX C. COLLABORATIVE TEAM APPROACHES..................................................... C-1
APPENDIX D. ACTIVITY-LEVEL WORK CONTROL DOCUMENT WRITERS GUIDE ......... D-1
iii
DOE-HDBK-1211-2014
APPENDIX E. ACTIVITY-LEVEL WORK CONTROL DOCUMENT VERIFICATION AND
VALIDATION GUIDELINES ......................................................................... E-1
APPENDIX F. MULTI-WEEK SCHEDULING MANAGEMENT................................................F-1
APPENDIX G. FOSTERING AN ENVIRONMENT TO PROMOTE A POSITIVE SAFETY
CULTURE AND A SAFETY-CONSCIOUS WORK ENVIRONMENT .......... G-1
APPENDIX H: DOE REQUIREMENT CITATIONS FOR PERFORMANCE EXPECTATIONS
...................................................................................................................... H-1
LIST OF FIGURES
Figure 1. WP&C Flow Diagram.................................................................................................... 8
Figure 2. Core Functions and Guiding Principles of ISM ........................................................... 18
Figure 3. An Illustration of Major Interactions between Organizational Levels for the Five
ISM Core Functions ................................................................................................ 20
Figure 4. A Prioritization System ................................................................................................ 30
Figure C-1. Core Team Storefront Model ................................................................................ C-2
LIST OF TABLES
Table B-1. Survey Results ....................................................................................................... B-1
Table E-1. ALWCD Verification Checklist ................................................................................ E-1
Table E-2. ALWCD Validation Checklist .................................................................................. E-5
iv
DOE-HDBK-1211-2014
FOREWORD
Section 4
This Handbook describes non-mandatory approaches for implementing Department of Energy
(DOE) requirements for activity-level work planning and control (WP&C) at Hazard Category 1,
2 and 3 nuclear facilities and is intended to be a resource for improvement in the performance of
work at the activity-level by the DOE contractor community. DOE’s intentions for publishing this
Handbook are that lessons will be shared and learned across all phases of work performance
and that activity-level work is reinforced with a greater awareness and commitment by the DOE
and its contractors. As important, this Handbook provides a common approach in developing or
improving contractor WP&C processes.
Continuous improvement and long-term performance excellence are tenants of a strong safety
culture. This Handbook strives to improve contractor work processes and their implementation,
consistent with the DOE safety culture focus areas of leadership, employee/worker engagement
and organizational learning.
DOE requirements have been referenced in the form of Performance Expectations to provide
context for the described implementation approaches of activity-level WP&C. The Handbook
further describes attributes and good practices for effective WP&C implementation, and is
responsive to recommendations provided by the DOE Analysis of Integrated Safety
Management at the Activity-Level: Work Planning and Control, August 1, 2013. Good practices
of WP&C implementation are provided in Section 6 and Appendices. The Handbook presents a
performance-based approach to activity-level WP&C.
DOE is also developing guidance on Federal oversight of WP&C in DOE G 226.1-2, Federal
Line Management Oversight of DOE Nuclear Facilities. This Handbook complements the
oversight approach described in the DOE Guide. However, information in this Handbook is not
to be construed as requirements in any audit or appraisal for compliance with DOE rules and
directives.
The Handbook’s descriptions of performance expectations clarify the Integrated Safety
Management (ISM) requirements in DOE regulations and directives that govern activity-level
work. Appendix H also provides a full listing of requirement citations referenced in performance
expectations.
The guidance documents listed below in addition to the reference documents in Section 4.0
were valuable resources in the development of this Handbook.
• Department of Energy, URS Global Management & Operations Services, Work Planning
and Control Program Standard, Revision 1, January 31, 2013.
• Energy Facilities Contractor Group (EFCOG), Work Planning and Control Guideline
Document, May 18, 2012.
• Department of Energy, Environmental Management Work Planning and Control Guidelines,
April 7, 2010.
• National Nuclear Security Administration, Activity Level Work Planning and Control
Processes: Attributes, Best Practices, and Guidance for Effective Incorporation of Integrated
Safety Management and Quality Assurance, January 23, 2006.
v
DOE-HDBK-1211-2014
1.0. PURPOSE
This Handbook was prepared as a resource document to improve activity-level work
planning and control (WP&C) implementation for the Department of Energy (DOE)
(including the National Nuclear Security Administration (NNSA)) and contractor line
management since there is a lack of voluntary consensus standards for this topic. The
Handbook contains performance expectations that are consistent with DOE
requirements. It also contains attributes and good practices that are based on DOE
guidance and nuclear industry experience. The Handbook presents a performance-
based approach to executing activity-level WP&C while complementing existing
Departmental guidance for:
Section 5
• Federal Line Management Oversight of DOE Nuclear Facilities (DOE G 226.1-2A);
• Nuclear Facility Maintenance (DOE G 433.1-1A);
• Integrated Safety Management System (DOE G 450.4-1C);
• Human Performance Improvement (DOE-HDBK-1028-2009);
• Writer’s Guide for Technical Procedures (DOE-STD-1029-1992); and
• Configuration Management (DOE-STD-1073-2003).
2.0. SCOPE
This Handbook is intended to provide information to DOE and contractors for the
implementation of a fully effective activity-level WP&C system for Hazard Category 1, 2,
and 3 nuclear facilities (see the definitions and interpretations in DOE-STD-1027-92).
The Handbook presents performance expectations, attributes, and good practices that
can be used to develop or improve contractor WP&C processes and provide
performance-based approaches for improvement of WP&C execution.
Use of the Handbook is not mandatory.
3.0. APPLICABILITY
This Handbook is intended to support improvement and implementation of contractor
WP&C processes, including WP&C processes of subcontractors, to all activities
conducted within the lifecycle of a Hazard Category 1, 2, or 3 nuclear facility. This
includes construction, research and development (R&D), operations, maintenance, and
decontamination and decommissioning (D&D). Organizations at facilities other than
Hazard Category 1, 2, and 3 nuclear facilities (e.g., chemical processing/storage,
explosives processing/storage) also may find the information in this Handbook useful.
The terms “graded approach” and “tailoring” in this Handbook apply to different elements
of activity-level WP&C. Graded approach applies to determining the level of effort,
degree of detail, and rigor of application, to meet requirements and remain consistent
with the seven attributes listed in the definition for graded approach when planning work.
Tailoring applies to determining the types of controls that are appropriate to the analyzed
hazards for the planned work.
1
DOE-HDBK-1211-2014
4.0. REFERENCES
• 10 CFR Part 830, Nuclear Safety Management;
• 10 CFR Part 851, Worker Safety and Health Program;
• 48 CFR 970.5223-1, Integration of Environment, Safety and Health into Work
Planning and Execution;
• DOE G 226.1-2A, Federal Line Management Oversight of DOE Nuclear Facilities;
• DOE O 226.1B, Implementation of Department of Energy Oversight Policy;
• DOE G 414.1-2B, Quality Assurance Program Guide;
• DOE O 414.1D, Quality Assurance;
• DOE O 420.1C, Facility Safety;
• DOE O 422.1, Conduct of Operations;
• DOE G 423.1-1A, Implementation Guide for Use in Developing Technical Safety
Requirements;
• DOE O 426.2, Personnel Selection, Training, Qualification, and Certification
Requirements for DOE Nuclear Facilities;
• DOE G 433.1-1A, Nuclear Facility Maintenance Management Program Guide for Use
with DOE O 433.1B;
• DOE O 433.1B, Maintenance Management Program for DOE Nuclear Facilities;
• DOE G 440.1-1B, Worker Safety and Health Program for DOE (Including the
National Nuclear Security Administration) Federal and Contractor Employees;
• DOE O 440.1B, Worker Protection Program for DOE (Including the National Nuclear
Security Administration) Federal Employees;
• DOE O 450.2, Integrated Safety Management;
• DOE G 450.4-1C, Integrated Safety Management Guide
• DOE P 450.4A, Integrated Safety Management System Policy;
• DOE-HDBK-1028-2009, Human Performance Improvement;
• DOE-STD-1027-92, Hazard Categorization and Accident Analysis Techniques for
Compliance with DOE Order 5480.23, Nuclear Safety Analysis Reports;
Section 6
• DOE-STD-1029-1992, Writer’s Guide for Technical Procedures;
• DOE-STD-1073-2003, Configuration Management; and
• The American Society of Mechanical Engineers (ASME) standard for nuclear quality
assurance (NQA)-1-2008, Quality Assurance Requirements for Nuclear Facility
Applications (with the NQA-1a-2009 addenda).
5.0. DEFINITIONS
Active Controls: Hazard controls that require a change of state or personnel action to
accomplish the safety function.
Activity-level work (ALW): Any job, task, or sub-task performed where hazards are present;
are introduced by the work, such as R&D, D&D, construction, operations, and maintenance; or
are introduced by the work environment (regardless of who is performing the work or the
2
DOE-HDBK-1211-2014
organization with which they are affiliated). The hazards involved could be potentially adverse to
worker health and safety, the public, the environment, or safeguards or security.
Activity-Level Work Control Document (ALWCD): A document that records, at a minimum,
the scope of an activity, the Responsible Manager (RM), location, a list of activities or tasks, and
the hazards and controls associated with the activity. This is the work document that is used in
the field to execute activity-level work. This may include technical procedures, work packages,
test plans, and work instructions for use by contractor personnel to perform activities.
ALWCD Validation: Part of the ALWCD approval process, utilizing worker input and
involvement, which demonstrates that the ALWCD can be performed as written to accomplish
the scope of work.
ALWCD Verification: Part of the ALWCD approval process that verifies the technical
adequacy of the ALWCD. Verification ensures that the ALWCD is technically accurate,
incorporating appropriate input, programmatic and regulatory requirements, and controls from
SMEs.
Critical Step: An ALWCD work instruction step or series of steps that, if performed improperly,
could cause irreversible harm to plant equipment or personnel, or could significantly affect
facility operations. An action, if performed improperly, that has an immediate negative
consequence that cannot be reversed or undone.
Documented safety analysis (DSA): A documented analysis of the extent to which a nuclear
facility can be operated safely with respect to workers, the public, and the environment;
including a description of the conditions, safe boundaries, and hazard controls that provide the
basis for ensuring safety.
Emergency work: The highest priority work in the WP&C program. An activity or activities
required to support emergency response or prevent or mitigate a situation that could cause
serious personnel injury, environmental harm, a security breach, the loss of mission-critical
systems or data, or significant property loss. Emergency work is completed without delay or
interruption until the condition is stabilized with controls established by senior management or
qualified designee instead of the normal work screening and planning processes.
General hazard analysis: The documented identification, analysis, and specification of
mitigation for those industrial safety and industrial hygiene hazards routinely encountered at a
facility, site, or area. Workers are trained to general safety and health requirements and
expected to be cognizant of the conditions and apply controls for general hazards when the
situation and tasks present themselves.
Section 7
Graded Approach: The process of ensuring that the level of analysis, documentation, and
actions used to comply with a requirement are commensurate with: (1) the relative importance
to safety, safeguards, and security; (2) the magnitude of any hazard involved; (3) the lifecycle
stage of a facility; (4) the programmatic mission of a facility; (5) the particular characteristics of a
facility; (6) the relative importance of radiological and nonradiological hazards; and (7) any other
relevant factor.
Hazard: A source of danger (i.e., material, energy source, or operation) with the potential to
cause illness, injury, or death to a person (workers or the public), or damage to a facility, or to
3
DOE-HDBK-1211-2014
the environment (without regard to the likelihood or credibility of accident scenarios or
consequence mitigation).
Human Performance Improvement (HPI): A set of concepts and principles associated with a
performance model that illustrates the organizational context of human performance. The model
contends that human performance is a system that comprises a network of elements that work
together to produce repeatable outcomes. The system encompasses organizational factors, job-
site conditions, individual behavior, and results (DOE-HDBK-1028-2009).
Independent Verification: The act of checking, by a separate qualified person, that a given
operation or component position conforms to established criteria.
Job hazards analysis (JHA): A documented analysis for specific activity-level work; identifies
activity-wide, task- or step-specific, and work environment/location safety and health hazards
and defines controls to eliminate or mitigate hazards to protect personnel and the environment.
Another common term in industry is job safety analysis.
Limiting Condition for Operation (LCO): The limits that represent the lowest functional
capability or performance level of safety structures, systems, and components (SSCs) required
for safe operations.
Passive Controls: Hazard controls that may already exist as part of facility/equipment design
and do not require change of state or personnel action to complete the safety function.
Pause Work: A request by any employee for a pause in the work activity, including clarification
or resolution on a potential problem, concern, or issue. Organizational processes define when
work release is required to resume work.
Performance Expectation: As used in this document, performance expectations reflect
existing requirements and are cited accordingly. In some cases, performance expectations are
direct quotes from requirements. Where performance expectations are paraphrased from
requirements, the citations are followed with the word “see” and referenced requirements.
Post-Work Review: A review of the post-work testing, acceptance, and work documentation
conducted at the completion of work activities, aimed at improving the effectiveness of the
activity. A post-work review often includes an interactive discussion with the group that
performed the work. Lessons learned and operating experience for continuous improvement are
derived from this review.
Pre-Job Briefing: A briefing with formalization and details consistent with the complexity and
hazards of the activity to be performed. Examples include: (1) a self-readiness check for
individual workers working alone performing routine tasks, (2) a discussion between the Work
Supervisor (WS) or Person in Charge (PIC) and the workers or support personnel, or (3) a
formal, documented briefing between the WS or PIC and the workers or support personnel that
is part of the ALWCD for initial, complex, or hazardous work.
Section 8
Risk: The quantitative or qualitative expression of the possibility of an event occurring that
considers both the probability that a hazard will cause harm and the consequences of that
event. For the purpose of this Handbook, risk is determined by the frequency and complexity of
the work activity as well as the hazards of the work and the environment.
4
DOE-HDBK-1211-2014
Roundtable: Sometimes referred as a “tabletop.” A roundtable is often done in conjunction with
a walkdown (often the second walkdown) to facilitate communication between the WS/PIC, work
planner, operations or facility personnel, system engineer (if one is assigned), subject matter
experts (SMEs), and the workers. Roundtable reviews ensure that all hazards are identified with
adequate and compatible controls.
Safety Basis: The documented safety analysis and hazard controls that provide reasonable
assurance that a DOE nuclear facility can be operated safely in a manner that adequately
protects workers, the public, and the environment.
Safety-class structures, systems, and components (SSCs): The SSCs include portions of
process systems whose preventive or mitigative function is necessary to limit radioactive
hazardous material exposure to the public, as determined from the safety analysis.
Safety-significant SSCs: The SSCs that are not designated as safety-class SSCs, but whose
preventive or mitigative function is a major contributor to defense in depth or worker safety, as
determined from safety analyses.
Significant to Safety: Scope contained in an approved ALWCD that includes work impacting
DSA-credited safety systems, equipment, or applicable Technical Safety Requirement (TSR)
controls. Steps in the ALWCD that execute necessary actions resulting in planned impact on
DSA-credited safety systems, equipment, or applicable TSR controls are referred to as steps
significant to safety.
Skill of the Worker (SOW): Encompasses Skill of the Craft (SOC). The basic discipline-
specific competencies, defined by the contractor organization, for each Worker includes the
required proficiency, experience, knowledge, skill, and ability. Competencies are obtained
through approved methods such as accepted training, qualification, certification, education, and
experience.
Step: An action that must be performed in order to complete a work instruction task (e.g.,
OPEN cooling water discharge valve, START cooling water pump).
Stop Work: The authority given any employee to immediately cease an activity that, in the view
of that person, could result in imminent danger (i.e., harm to persons or the environment if work
continues). Resumption requires mitigation of the hazard and formal authorization from
management.
SSCs: Physical items designed, built, or installed to support the operation of the facility. A
structure is an element or a collection of elements to provide support or enclosure such as a
building, freestanding tank, basin, dike, or stack. A system is a collection of components
assembled to perform a function such as piping; cable trays; conduits; or heating, ventilation,
and air conditioning. A component is an item of equipment such as a pump, valve, or relay or an
element of a larger array such as a length of pipe, elbow, or reducer.
Tailoring: The method to determine the types of controls that are appropriate for the hazards
associated with the planned work.
Section 9
Task: A step (i.e., action) or series of steps designed to contribute to a specified end result for
an activity. It has an identifiable beginning and end that is a measurable component of the
duties and responsibilities of a specific activity (e.g., INITIATE cooling water system operation).
5
DOE-HDBK-1211-2014
Technical Safety Requirements: The limits, controls, and related actions that establish the
specific parameters and requisite actions for the safe operation of a nuclear facility and include,
as appropriate for the work and the hazards in the DSA for the facility: Safety limits, operating
limits, surveillance requirements, administrative and management controls, use and application
provisions, and design features, as well as a basis appendix.
Troubleshooting: The process of locating and identifying SSC malfunctions through deductive
and inductive reasoning or testing. The process includes activities such as evaluating
components or systems by bounding (including applicable hazard identification and mitigation),
what will be evaluated, providing an expectation of outcome, and identifying repairs to be made
based on evaluation results.
Unreviewed Safety Question (USQ): A situation where (1) the probability of the occurrence or
the consequences of an accident or the malfunction of equipment important to safety previously
evaluated in the documented safety analysis could be increased; (2) the possibility of an
accident or malfunction of a different type than any evaluated previously in the documented
safety analysis could be created; (3) a margin of safety could be reduced; or (4) the
documented safety analysis may not be bounding or may be otherwise inadequate.
USQ Process: The mechanism for keeping a safety basis current by reviewing potential USQs,
reporting them to DOE, and obtaining approval from DOE prior to taking any action that involves
an unreviewed safety question.
Validation: See ALWCD Validation.
Verification: See ALWCD Verification.
Walkdown: A method to identify the tasks needed to accomplish the activity and the hazards
associated with the tasks. A walkdown also confirms that the controls selected align
appropriately with the field conditions. This should be led by the work planner or RM and may
include the Facility Manager (FM), SMEs, system engineers, workers, and the work requestor.
Work Approval: A formal process performed by line management to ensure that the ALWCD
has been reviewed and is approved as a workable document.
Work Authorization: A formal process performed by an individual in authority who is
responsible for overall facility/project activities signifying that all preparations or prerequisites
(e.g., notification, permits, approvals) and required controls have been identified and can be
implemented. Work authorization may be performed as part of the site’s scheduling process.
Worker: A worker is anyone who performs assigned activity-level work tasks. Examples of
workers include crafts, researchers, scientists, engineers, technicians, operators, and
maintenance and test personnel. Workers can be contractor or subcontractor personnel who
either normally work at the facility where the work is being performed or who normally work
elsewhere at the site or offsite and are present at the facility to perform or support ongoing work
activities.
Work Instruction: An instruction that provides the specific information, details, and actions on
performing the tasks and associated steps necessary to carry out the activities described in an
ALWCD.
Section 10
6
DOE-HDBK-1211-2014
Work Planner: A work planner is a trained and qualified individual responsible for facilitating
the activity-level work planning process in development of ALWCDs.
Work Release: A formal process performed by an individual in authority who is the designated
point of release responsible for all work and site conditions in a facility or area. The process
needs to evaluate workability for the specific activity, just prior to executing the activity, by
ensuring that:
• Work is authorized and the ALWCD is reviewed so that workers understand the scope of
work, including critical steps and associated hazards and controls;
• Concurrent work activities are compatible; and
• Work environment conditions and configuration support the specific activity.
6.0. IMPLEMENTATION OF WORK PLANNING AND CONTROL
This Handbook is intended to support improvement of contractor, including subcontractors,
WP&C process and corresponding implementation to all activities conducted within the lifecycle
of a Hazard Category 1, 2, or 3 nuclear facility. Activities include those associated with
construction, research and development (R&D), operations, maintenance, and decontamination
and decommissioning (D&D). Section 6.1 discusses the WP&C program and Integrated Safety
Management (ISM) system. Sections 6.2-6.7 discuss an iterative WP&C implementation
approach (see Figure 1). This Handbook includes Performance Expectations derived from DOE
requirements, including the ISM Guiding Principles and Core Functions.
Figure 1 illustrates an example of a WP&C process with the prime input defined as “activity-level
work.” A contractor or sub-contractor’s WP&C process and supporting resources will screen and
prioritize such activities flowing from work breakdown structures, project plans or other drivers
that document jobs, tasks, or sub-tasks that need to be performed where hazards are present or
are introduced by the work or the work environment, for example:
7
DOE-HDBK-1211-2014
8
DOE-HDBK-1211-2014
Construction: e.g., activities to erect a new facility or modify an existing facility, field
design change requests, and general condition items such as debris removal, temporary
facilities,
Operations: e.g., program operation campaigns, waste processing, component
fabrication, operator rounds (see Section 6.1.5),
Research and Development: e.g., programmatic research, laboratory directed R&D,
R&D work for others (see Section 6.1.6),
Maintenance: e.g., preventive maintenance, corrective maintenance, equipment
replacement, and
Decontamination and Decommissioning: e.g., facility decontamination, equipment
removal, facility characterization, field design change requests, and general condition
items such as debris removal, temporary facilities.
This Handbook can serve as a resource for contractors seeking to benchmark their WP&C
process for improved implementation. This Handbook identifies performance expectations and
good practices (see Sections 6.1-6.7). The goals for an effective WP&C process are:
1. Ensure protection of the worker, the public and the environment by scoping, planning,
scheduling, and preparing in a manner that result in the safe execution of work.
2. Eliminate or mitigate the hazards associated with work.
3. Identify the impact of work to the facility and work groups and plan, control, and execute the
work without incurring unanticipated issues resulting from the work.
Section 11
4. Maximize the efficiency and effectiveness of site personnel and material resources.
5. Maximize the availability and reliability of facility equipment and systems.
6. Maximize continual improvement and learning with robust feedback and improvement
processes.
Applying these principles can further improve an organization’s WP&C process and culture.
6.1. Work Planning and Control and Integrated Safety Management System (ISMS)
6.1.1 Roles and Responsibilities
Performance Expectation: Organizational structure, functional roles, responsibilities,
levels of authority, accountability, and interfaces for those managing, planning,
performing, and assessing work are clearly defined and documented (see 10 CFR
830.122.a, 48 CFR 970.5223-1(b)(1) and (b)(2), DOE O 433.1B, Attachment 2, para. 1.a
and 2.b, and DOE O 422.1, Attachment 2, Appendix A, para. 2.a).
Good Practices:
Roles and responsibilities for activity-level WP&C are defined and understood for work
planners, work supervisors, responsible line managers, workers, subcontractors, subject
matter experts, and all other personnel involved in such activity. The goal should be to
9
DOE-HDBK-1211-2014
establish a work environment that strives for excellence in work planning and
performance and that promotes productivity and safety. Open and effective
communications, constructive feedback, and due consideration of diverse opinions
should be encouraged at all organizational levels. Individual ownership, accountability,
teamwork, continuous improvement, and proactiveness to prevent or address and
correct issues before they become major are visible traits of a safety-conscious culture.
The responsibilities listed below are one possible combination of functional category
positions. These roles and responsibilities may be performed by multiple and various
positions depending on the organizational structure. Specific titles with associated roles
and responsibilities (e.g., Facility XYZ Operations Manager as one of the RMs) would be
addressed in contractor WP&C procedures. More detailed roles and responsibilities for
specific subject matter experts (e.g., Radiation Protection, Maintenance, Security) can
be found in other resources, for instance the Work Management Process Description
(AP-928) published by the Institute of Nuclear Power Operations (INPO).
Senior Management:
• Assigns WP&C program roles and responsibilities.
• Approves and releases Emergency Work prior to execution.
• Delegates Emergency Work approval and release authority to qualified designees.
• Establish criteria to define when Independent Hazard Review Teams (IHRTs) are
necessary.
• Leads IHRTs (i.e., senior management review board) of high-impact work during the
ALWCD approval process.
• Establish expectations for key performance objectives and measures related to safe
work accomplishment.
Responsible Manager (Line Management):
• Line Managers clearly understand how to safely conduct their work activities and
accomplish their performance objectives.
• Ensures a complete understanding of the work scope and work environment where
the work will be performed in order to effectively execute assigned responsibilities.
• Ensures that the timing of work activities supports safe work performance.
• Ensures that the work activity is adequately funded.
• Ensures that critical resources (equipment and trained personnel) for safe
performance of work are available before authorizing work.
• Ensures that all of the appropriate controls are in place to protect the safety and
Section 12
health of workers during the execution of work activities.
• Ensures overall safety of the workers.
• Demonstrates visible leadership at the work site and in employee work areas,
including coaching, mentoring, and reinforcing standards and positive behaviors.
• Ensures compliance with ALWCDs, including working within scope, documentation
of work, and feedback during execution.
• Supports worker decisions in taking conservative actions (e.g., pause work, stop
work) when faced with unexpected or uncertain conditions.
• Acknowledges personnel for self-identification and reporting of errors.
10
DOE-HDBK-1211-2014
• Ensures compliance with the site and facility DSAs and TSRs.
• Ensures that activities affecting systems or components that require independent
verification have been identified.
• Ensures that task-specific mitigations determined to be needed by JHAs are properly
incorporated into the ALWCDs.
• Ensures that the feedback process is effectively implemented.
• Ensures the proper release of equipment and work areas.
• Ensures that subcontractors perform work in accordance with Integrated Safety
Management System (ISMS) principles and contract requirements. At a minimum,
meets with the organization’s Subcontractor Technical Representative and the
subcontractor’s supervisor to review in detail the processes workers will follow,
identify potential hazards, and describe methods for controlling those hazards.
• Ensures that work activities are coordinated with facility management.
• Implements the contractor’s procedures that address line management’s
responsibility for safety, clearly defined roles and responsibilities, competence
commensurate with responsibility, and a clearly documented graded approach
program.
• Reviews and approves all requests for work.
• Reviews and approves ALWCDs for compliance and completeness and performs
post-work acceptance and completion activities.
• Reviews and approves changes to ALWCDs.
• Controls the activity-related schedule, including setting priorities and integrating or
interfacing with operations, project, site, and facility activities.
• Manages the schedule change control process to ensure the maximum utilization of
resources.
• Approves the activity-related schedule and any changes.
• Authorizes shutdown of machinery, equipment, and systems.
• Reviews approved ALWCDs to ensure that conditions for performing the work are
established, verifies the work is authorized, and grants work release.
• Reviews incoming requests for work for project, site, and facility impact.
• Establishes and maintains awareness of key performance measures related to safe
work accomplishment and take action on adverse trends or anomalies.
Work Requestor/Responsible Individual (RI) for Work Initiation:
• Describes the proposed scope of work to include possible deliverables, milestones,
and mission-critical needs.
• Provides accurate, detailed data and notifies the Project Manager, FM, or Shift
Operations Manager (SOM) of field-observed conditions requiring interface support,
awareness, or any followup work.
• Contacts the Project Manager, FM, or SOM for urgent or facility-impacting items
immediately.
• Initiates a request for work.
WP&C Management:
• Ensures that SMEs identified as part of the planning team concur with, and
participate in the development of the hazard analysis and the ALWCD.
11
DOE-HDBK-1211-2014
Section 13
• Ensures that the proper level of review and approval is identified and obtained for
different types of ALWCDs.
• Ensures that ALWCDs are ready to work prior to the execution week.
• Ensures that resources are available to support all work planning and control
activities.
• Ensures that ALWCDs have been properly completed and closed out.
• Screens requests against Davis-Bacon Act requirements, as applicable.
• Makes an initial determination of the type of ALWCD to be used for each work task
based upon the hazards associated with and rigor level (complexity or failure mode
consequence) of the work activity.
• Makes an initial determination if a work planner or planning team is necessary based
on the graded approach. Selects work planner or planning team members that
should comprise the appropriate personnel (e.g., work preparer/work planner,
workers, operations, principal investigator, SME).
• Screens requests for work, ensuring that work scope and associated boundaries are
clearly defined.
• Participates in scheduling and resolves obstacles to schedule execution.
• Conducts periodic assessments of the WP&C process in accordance with Contractor
Assurance System guidance.
• Serves as qualification authority for work planners.
Work Planner (Preparer):
• Leads the planning process in work site scoping walkdowns; roundtables; work
scope definition; job hazard identification, analysis, and control selection; and
ALWCD development.
• Reviews lessons learned and feedback information for entries with applicability to the
work to be performed.
• Takes Human Performance Improvement (HPI) factors into consideration.
• Develops the ALWCD, incorporating input from the planning team, the RM, and
appropriate task-related requirements.
• Coordinates the integration of controls and preparation of the required permits (e.g.,
radiological work permits (RWPs), hot-work permits, confined-space permits).
• Coordinates ALWCD comment resolution and submits the package for concurrence
by the WS and relevant SMEs and approval by the RM.
• Ensures that all documents necessary for completion of the work are included in the
ALWCD (e.g., work instructions, drawings, permits).
• Makes sure controls based on the hierarchy of control principles (e.g., hazard
elimination or reduction, engineered, administrative, or personal protective
equipment (PPE)) are clearly delineated in the ALWCDs or supporting documents.
• Incorporates SME identified inspections, acceptance criteria, and hold and witness
points into ALWCDs.
• Ensures that special task-specific training and medical screening and surveillance
requirements are specified.
• Coordinates input for feedback and lessons learned in a timely manner to capture
information for process improvement.
Subject Matter Expert (e.g., safety system engineers; functional experts in Radiological
Controls, Safety, Industrial Hygiene, Engineering):
12
DOE-HDBK-1211-2014
• Participates in the work site job or task walkdowns, roundtables, hazard
identification, JHA and control selection, and ALWCD development as part of the
planning team, consistent with the contractor’s WP&C process.
• Supports the RM and preparer/work planner in reviewing ALWCDs to ensure that the
hazard controls have been incorporated consistent with requirements.
• Contributes to the development of ALWCD instructions, ensuring that steps with DSA
or regulatory permit requirements are properly incorporated.
Section 14
• Ensures that planning decisions are consistent with programmatic requirements.
• Specifies inspections, acceptance criteria, and hold and witness points.
• Reviews SME discipline-related, subcontractor-prepared ALWCD documents for
suitability.
• Supports the RM and preparer/work planner in reviewing the applicable completed
ALWCDs to ensure that required data are properly recorded in accordance with
programmatic requirements.
• Concurs with the ALWCD as part of the approval process.
• Performs or supports the specified inspections and supports the specified
acceptance criteria, hold and witness points.
Work Supervisor:
• Ensures work group participation in the planning process.
• Supports scheduling activities.
• Ensures that the ALWCD is approved and that work is released.
• Ensures that the prerequisite activities for work have been completed.
• Ensures that hazard controls are implemented.
• Ensures that personnel executing the work have attended the pre-job briefing (or are
briefed separately) and are fit to perform work.
• Ensures that the ALWCD workability review is conducted.
• Ensures that the referenced documents are current prior to start of work.
• Ensures that workers are aware of their responsibility to stop or pause work and
notify supervision whenever changing conditions, unexpected conditions, or
unidentified hazards are encountered or if work practices have the potential to
compromise quality or safety.
• Ensures that controls based on the hierarchy of control principles (e.g., hazard
elimination or reduction, engineered or administrative controls, or PPE) are clearly
delineated in the ALWCDs or supporting documents.
• Ensures the proper turnover of work status when transferring WS responsibilities.
• Ensures that good housekeeping practices are followed during the performance of
work and that work areas are cleaned and restored after the completion of work or
the work activity cycle.
• Ensures compliance with ALWCDs, including working within scope, documentation
of work, and feedback during execution.
• Acknowledges personnel for self-identification and reporting of errors.
• Ensures the proper completion of documentation, including work history.
• Ensures that post-work reviews are conducted.
• Concurs with the ALWCD, confirming workability, as part of the approval process.
• Conducts pre-job briefings to review the scope of work, hazards, and controls with
assigned workers.
13
DOE-HDBK-1211-2014
• Ensures that workers are trained and qualified and that they meet special program
requirements (e.g., medical screening and surveillance requirements) to
independently perform work.
• Supervises work activities to meet ALWCD requirements.
• Complies with the ALWCD change control process.
• Prepares and submits feedback and lessons learned in a timely manner to capture
information for process improvement.
Worker:
• Participates in the work site job or task walkdowns, roundtables, hazard
identification, JHA and control selection, and ALWCD development consistent with
the contractor’s WP&C process.
• Participates in the ALWCD validation walkdown and workability review prior to the
start of work to ensure the adequacy of the ALWCD.
• Participates in the pre-job briefing and does not perform work until properly briefed
and the scope of work and hazard control strategies are clearly understood.
• Complies with ALWCDs, including working within scope, documenting work, and
providing feedback during execution.
Section 15
• Completes documentation properly, including work history.
• Identifies and proposes the best tools and work practices for the activity.
• Identifies any special material requirements for the work to the WS and work planner.
• Performs only work that he or she is qualified to perform.
• Performs only work that he or she is authorized to perform after work is released by
appropriate authority.
• Implements required controls specified in the ALWCD or for general hazards (as
prescribed in general safety training, management policy, or as posted for hazard
mitigation).
• Completes work activities safely in accordance with the ALWCD.
• Adheres to the requirements of supporting documents, including the RWP and other
permits and site-specific waste management instructions.
• Promptly reports unintended failures to follow ALWCD or supporting document
requirements.
• Adheres to Stop Work or Pause Work direction and notifies the WS if the work
instructions cannot be followed as written, a change of scope is identified, changing
conditions or unidentified hazards are encountered, or work practices could
compromise safety or the environment.
• Participates in the post-work review and identifies feedback and process
improvement opportunities to the WS.
6.1.2 Training Needs and Qualifications
Performance Expectations:
1. The knowledge, skills, and abilities required for performing assigned work are
established, documented, and maintained (see 10 CFR 830.122(b) and (d), 48 CFR
970.5223-1(b)(3) and (b)(5), and DOE O 433.1B, Attachment 2, para. 2.g).
2. Personnel possess the knowledge, skills, and abilities required for performing
assigned work (see 10 CFR 830.122(b), 48 CFR 970.5223-1(b)(3), DOE O 433.1B,
14
DOE-HDBK-1211-2014
Attachment 2, para. 2.g, and DOE O 422.1, Attachment 2, Appendix A, para. 2.a(5),
2.a (6)(b), and 2.b(5)(a)).
3. Continuing training is provided, including lessons learned, to maintain and improve
proficiency (see 10 CFR 830.122(b) and (d), 48 CFR 970.5223-1(b)(3), DOE O
433.1B, Attachment 2, para. 2.g).
4. Personnel are trained on the activity-level work planning and control process and
understand how their function contributes to, and integrates with; the process (see
10 CFR 830.122(b) and (d), 48 CFR 970.5223-1(b)(2) and (b)(3), DOE O 422.1,
Attachment 2, Appendix A, para. 2.a.(6)(b), DOE O 433.1B, Attachment 2, para. 2.g).
Good Practices:
Line management is responsible for defining WP&C training requirements for all
personnel involved in WP&C program activities, including managers, planners,
supervisors, SMEs, and workers. Line management is responsible for ensuring that only
qualified personnel who meet the requirements are permitted to perform work
independently. The training program and processes need to establish the required
competencies and related knowledge, skills, and abilities to support assigned work.
Workers (e.g., crafts, operators, engineers, researchers, specialists) need to possess
the skills required to perform the work and to be adequately trained prior to their
performing work. Personnel who are not fully trained and qualified for the specific activity
should be continuously supervised by qualified personnel.
Section 16
All personnel with responsibilities for WP&C program activities, including managers,
work planners, supervisors, SMEs, and workers, should receive training on the
organization’s WP&C procedures. ISMS Core Functions (CFs) and Guiding Principles
(GPs) and the WP&C program overview should be included in the training programs of
personnel with WP&C program responsibilities. Continuing training, focusing on WP&C
process changes and lessons learned, should be conducted periodically, taking the form
of briefings, issuance of lessons learned, and other forms of communication. Contractor
training systems should produce records of the training and qualification of the
aforementioned personnel.
The following topics should be included in the training and qualification programs of
personnel with WP&C program responsibilities:
All personnel:
• ISMS CFs and GPs;
• WP&C program overview;
• Hazard identification;
• Hazard analysis and control selection processes;
• Work and activity request initiation processes;
• Conduct and oversight of work activities;Hazardous energy control awareness;
• Stop Work/Pause Work policies and procedures to include recognizing and
responding to unexpected conditions; and
• Feedback and improvement processes.
Responsible Managers (Project, Site, or Facility Managers; Shift Operations
Managers; or WP&C Managers):
15
DOE-HDBK-1211-2014
• Work request approval, screening, prioritization, and categorization processes;
• ALWCD approval and change control processes;
• Work authorization and scheduling processes;
• Work release process;
• Work acceptance process;
• ALWCD closeout process; and
• WP&C program assessments and oversight.
Work Supervisor:
• Conduct and appropriate use of walkdowns;
• ALWCD compliance;
• Pre-job briefings (including minimum expectations and techniques);
• ALWCD verification and validation;
• ALWCD approval and change control processes;
• Work authorization and scheduling processes;
• Workability review;
• Work release process;
• Work turnover process;
• Work acceptance process;
• ALWCD closeout process; and
• Post-work reviews.
Worker:
• Conduct and appropriate use of walkdowns;
• ALWCD compliance;
• ALWCD validation;
• Workability review;
• Pre-job briefings;
• Work release process;
• Expectations for the conduct of work activities;
• Work acceptance process;
• ALWCD closeout process; and
• Post-work reviews.
Skill of the Worker:
SOW skills are evaluated, defined, and documented by line management based upon
accepted industry practices, training and qualification, familiarity with tools and
equipment, processes, and methods. See Appendix A for additional discussion on
SOW.
Subject Matter Expert (e.g., Radiological Controls, Safety, Industrial Hygiene,
Engineering):
16
DOE-HDBK-1211-2014
• Conduct and appropriate use of walkdowns;
• Incorporation of hazard controls into the ALWCD;
• ALWCD verification;
• Work acceptance process;
• ALWCD closeout process; and
• Post-work reviews.
Planners:
There should be a training and qualification program for planners who are qualified by
WP&C management. This program specifies the:
• Education, knowledge, and experience criteria to be included in the position
description;
• Organization-, site-, and facility-specific training and qualification requirements;
• Mentoring, disqualification, and the remedial training process; and
• Continuing training requirements.
Planner training and qualification should include the following elements:
Section 17
• Roles, responsibilities, authorities, and accountabilities of interfacing organizations;
• WP&C program procedures;
• Hazard analysis process procedures;
• Applicable WP&C systems (e.g., types of work performed, processes used, tools,
software, ALWCD content, applying lessons learned);
• Incorporation of hazard controls into the ALWCD;
• Work instruction development;
• SOW protocols;
• Conduct and appropriate use of walkdowns;
• Applying applicable requirements, standards, permits, and regulations to work
planning;
• The appropriate selection and use of SMEs;
• Facilitation of planning team meetings, walkdowns, and round tables;
• ALWCD verification and validation;
• Technical writing skills; and
• Use of feedback and improvement process outputs.
6.1.3 Supporting ISMS Functional Elements
17
DOE-HDBK-1211-2014
WP&C, as described here, is an iterative process that incorporates the ISM CFs and
GPs to accomplish work safely (see Figure 2).
Figure 2: Core Functions and Guiding Principles of ISM (courtesy CH2MWG, Idaho, LLC)
Performance Expectations:
1. A contractor’s ISMS shall be integrated with business processes for work planning,
budgeting, authorization, execution, and change control (48 CFR 970.5223-1(e)).
2. Contractors shall ensure that programmatic resources are effectively allocated to
address environment, safety, and health (ES&H), programmatic, and operational
considerations of an ISMS (48 CFR 970.5223-1(b)(4)).
3. WP&C processes are coordinated (see 48 CFR 970.5223-1(b)(2), 10 CFR
830.122(a) and (d), DOE O 422.1, Attachment 2, para. 2.a(6)(a), DOE O 433.1B,
Attachment 2, para. 1.a and 2.b).
Good Practices:
18
DOE-HDBK-1211-2014
ISM is DOE’s management framework for integrating safety programs. Activity-level
WP&C is embedded in ISM, as evidenced by the following regulations and directives
that address WP&C:
• 48 CFR 970.5223.1, Integration of Environment, Safety and Health into Work
Planning and Execution
• 10 CFR 851, Worker Safety and Health Program
• DOE O 226.1B, Implementation of DOE Oversight Policy
• DOE O 422.1, Conduct of Operations
• DOE O 433.1B, Maintenance Management Program for DOE Nuclear Facilities
• DOE P 450.4A, Integrated Safety Management Policy
• DOE O 450.2, Integrated Safety Management
DOE G 450.4-1C, Attachment 4, Work Planning and Execution, describes how activity-
level WP&C fits into DOE’s ISMS. In general, operating organizations perform work
using both site-wide safety programs (e.g., fire protection and emergency planning) as
well as facility- and activity-specific safety processes. Some of these programs are
established at the site level to address, for example, radiation protection, environmental
protection, industrial hygiene, industrial safety, and emergency planning. Other
programs, such as those for configuration management and conduct of operations, are
more appropriately specified at the facility or project level. Some processes, such as
quality inspection or those used for task-level WP&C, can be specified at the activity
level.
All safety control measures, programs, and processes—regardless of the level at which
they are specified, and regardless of whether they are mandatory or voluntary—flow
down and should be implemented at the appropriate work level to achieve adequate
safety (Figure 3). Both DOE and the operating organization should review existing
processes and programs to ensure they are properly integrated, flow down to the task or
activity level, and adequately address ISMS requirements. For these reasons, an ISMS
should include processes for selecting and applying site and facility processes or
procedures to use in developing work-specific control measures.
Section 18
The WP&C process should define work activities and boundaries in sufficient detail to
enable work planners and planning teams to incorporate all ISMS functional elements for
a defined scope of work and to produce an appropriate ALWCD. The extent of
documentation and level of authority for authorizing work to begin can then be graded to
the complexity and hazards associated with the work.
19
DOE-HDBK-1211-2014
Figure 3: An Illustration of Major Interactions between Organizational Levels for the Five
ISM Core Functions
6.1.4 WP&C and Crosscutting Programs
Performance Expectations:
1. The process(es) and requirements for incorporating ISMS CFs and GPs and quality
assurance (QA) criteria into activity-level work planning, control, and execution are
clearly documented (see 48 CFR 5223-1(b)(2) and (b)(5), 10 CFR 830.122(d) and
(e), DOE O 422.1, Attachment 2, para. 2.a(6)(a), DOE O 433.1B, Attachment 2,
para. 1.a, 2.a.(1)(b), and 2.a.(2)(a)).
2. The organizational structure, functional roles, responsibilities, levels of authority,
accountability, and interfaces for those managing, planning, performing, and
assessing work are clearly defined and documented (see 48 CFR 5223-1(b)(1) and
(b)(2), 10 CFR 830.122(a), DOE O 433.1B, Attachment 2, para. 1.a, 2.b, and 2.d,
DOE O 422.1, Attachment 2, para. 2.a.(1), 2.a(3) and 2.a.(4)).
20
DOE-HDBK-1211-2014
Good Practices:
Worker Safety and Health Program
ALWPC activities should integrate with the requirements and guidance for hazard
identification, assessment, and prevention in DOE’s Worker Safety and Health Program,
which is defined by:
• 10 CFR 851, Worker Safety and Health Program, and
• DOE G 440.1-1B, Admin Chg 1, Worker Safety and Health Program for DOE
(Including the National Nuclear Security Administration) Federal and Contractor
Employees.
Configuration Management Process
An effective configuration management process can provide confidence that information
used to plan work is accurate and up to date. DOE-STD-1073-2003 provides detailed
expectations and examples for developing configuration management processes for
DOE facilities and activities. DOE O 420.1C requires contractors to establish
configuration management processes for all Hazard Category 1, 2, and 3 nuclear
facilities. Per DOE-STD-1073-2003, WP&C processes should ensure that when work
activities are performed, consistency is maintained between design requirements, the
physical configuration of the facility or activity, and relevant documentation (including
analyses, drawings, and procedures).
Personnel authorized to approve work should ensure that the change control process is
executed to identify changes that could impact the safety basis. If, during the
performance of work, additional changes affecting the safety basis are identified, these
changes should also undergo the change control process, including the USQ process,
and work should not resume until the changes have been analyzed and approved. A
post-work review is particularly important for work that was performed on an emergency
basis where limited time was available for work planning. Document control and change
control processes can ensure that developed and revised documents are maintained
current and available to the users.
WP&C procedures should ensure that the site or facility configuration management
process is effectively implemented so that design and physical configuration of the
facility or activity, as well as the relevant documentation (including analysis, drawings,
and procedures), are maintained up-to-date when work activities are completed.
Section 19
Maintenance Management Program
DOE O 433.1B, Admin Chg 1, Maintenance Management Program for DOE Nuclear
Facilities, requires DOE facility operators to develop and implement a Nuclear
Maintenance Management Program (NMMP) for Hazard Category 1, 2, and 3 nuclear
facilities.
DOE G 433.1-1A, Nuclear Facility Maintenance Management Program Guide for Use
with DOE O 433.1B, includes detailed guidance in Section D, “Planning, Scheduling, and
Coordination of Maintenance,” that relates directly to activity-level WP&C for
maintenance of safety SSCs. The maintenance management program includes the
process for planning, scheduling, coordination, and control of maintenance activities,
21
DOE-HDBK-1211-2014
and emphasizes equipment availability. The process includes the application of a
cognizant system engineer (CSE) program in accordance with DOE O 420.1C, Facility
Safety, in the planning and execution of maintenance activities.
Key considerations for the control of maintenance activities are:
• A maintenance program should be integrated with the WP&C program and with
ISMS.
• Coordination is needed where various groups (e.g., mechanical, electrical,
instrumentation and control) are involved in a work activity or are concurrently
working in the same area.
• The WP&C program should ensure that work activities are consistent with the facility
safety basis and effectively identified, initiated, planned, approved, scheduled,
coordinated, performed, and reviewed for adequacy and completeness.
• The program should ensure the availability and operability of the safety SSCs that
are a part of the facility’s safety basis.
• The WP&C system should provide the data necessary to properly plan and schedule
maintenance activities.
• The maintenance organization should establish high qualification standards for all
personnel supervising and performing maintenance activities.
• Maintenance management should oversee work to ensure that it is conducted in
accordance with DOE, contractor, and facility policies and procedures.
• Configuration control is maintained by ensuring that systems and equipment are
restored to their original condition following maintenance.
Quality Assurance Program
DOE and its contractors are required to achieve quality for all work based upon the
principles and requirements of the quality assurance program (QAP), as specified in:
• 10 CFR Part 830, Subpart A, Quality Assurance Requirements; and
• DOE O 414.1D, Quality Assurance.
In addition, the contracts for construction, operations, maintenance, and D&D for many
of DOE’s Hazard Category 1, 2, and 3 nuclear facilities include the following consensus
standard:
• NQA-1-2008, Quality Assurance Requirements for Nuclear Facility Applications, with
the NQA-1a-2009 addenda.
DOE has also issued DOE G 414.1-2B, Quality Assurance Program Guide, which
provides information on principles, requirements, and practices used to establish and
implement an effective QAP for nuclear facilities consistent with the requirements of
DOE O 414.1D and 10 CFR Part 830, Subpart A. All 10 QA criteria listed in DOE O
414.1D and 10 CFR 830.122 are directly relevant to activity-level WP&C at Hazard
Category 1, 2, and 3 nuclear facilities.
22
DOE-HDBK-1211-2014
6.1.5 Conduct of Operations Relationship to WP&C
Performance Expectations:
Section 20
1. Organizational structure, functional roles, responsibilities, levels of authority,
accountability, and interfaces for those managing, planning, performing, and
assessing work are clearly defined and documented (see 48 CFR 970.5223-1(b)(1)
and (b)(2), 10 CFR 830.122(a), DOE O 433.1B attachment 2, para. 1.a and 2.b, DOE
O 422.1, Attachment 2, Appendix A, para. 2.a.(1) and 2.a.(4)).
2. Personnel are trained on the activity-level work planning and control process and
understand how their function contributes to and integrates with the process (see 10
CFR 830.122(b) and (d), 48 CFR 970.5223-1(b)(2) and (b)(3), DOE O 422.1,
Attachment 2, para. 2.a(6)(b) and 2.b(5)(a), DOE O 433.1B, Attachment 2, para.
2.g).
3. WP&C processes are coordinated (see 48 CFR 970.5223-1(b)(2), 10 CFR
830.122(a) and (d), DOE O 422.1, Attachment 2, para. 2.a(6)(a), and DOE O
433.1B, Attachment 2, para. 2.b).
4. A graded approach methodology is incorporated into the WP&C process that
determines the rigor for implementing these work planning and control attributes
based on the significance and associated consequences of the activity (see 48 CFR
970.5223-1(b)(4) and (b)(6), DOE O 433.1B, Attachment 2, para. 2.h).
Good Practices:
DOE O 422.1, Conduct of Operations, states: “A Conduct of Operations Program
consists of formal documentation, practices, and actions implementing disciplined and
structured operations that support mission success and promote worker, public, and
environmental protection.” Conduct of Operations is a time-tested process that seeks to
ensure that management systems are in place to reduce human error, system failures,
and latent hazardous conditions.
The term “operations” in DOE encompasses the work activities of any facility or
organization, from building infrastructure to scientific research and nuclear facilities.
Examples include, but are not limited to, operating science and technology machines,
operating equipment, construction, decontamination and decommissioning,
dismantlement, environmental characterization and monitoring activities, waste handling,
research and development, maintenance, and laboratory analysis activities.
Given the above, the term “operations” is synonymous with “activity-level work,” as
defined in this Handbook. However, for facilities with routine, day-to-day operations,
management of Conduct of Operations may not necessarily reside in a WP&C
organization or be applicable to the entire WP&C program.
For example, an operations organization may control operations procedures, such as
alarm response and valve checklist procedures. Operator rounds may not need to be
listed on a daily schedule. Normal operating procedures could be performed as
standalone documents. This will vary, as no two facilities or organizations are alike.
Nonetheless, ISMS is involved in all aspects of operations. Conduct of Operations
supports ISMS by providing techniques and practices to identify and analyze the
23
DOE-HDBK-1211-2014
hazards, develop and implement hazard controls, and perform work within controls.
Conduct of Operations is one of the safety management programs recognized in 10 CFR
Part 830, Nuclear Safety Management.
6.1.6 Research and Development Activities’ Relationship to WP&C
Good Practices:
Section 21
This Handbook is applicable to R&D activities to the extent that they are consistent with
ALW as defined in Section 5.0. Likewise, DOE O 422.1, Conduct of Operations, states
that the term “operations” is defined as a “general term to encompass the work activities
accomplished by [a] facility or project,” including, but not limited to, “…operating science
and technology machines,…research and development,…and laboratory analysis
activities.” Managing R&D ALW sometimes calls for a delicate balance between the
R&D objective, the operational bounds of the facility, and the hazards associated with
the R&D project. The R&D objective may be achieved through various processes to
satisfy ISM and WP&C requirements.
A researcher might have multiple active R&D projects, ranging from continuous
operations (e.g., material aging), to campaign operations (e.g., R&D with variable
changes), to one-time activities (e.g., R&D testing). Each of these projects can range
from simple to complex, those with standard industrial hazards to those with unique
hazards, and those well suited to institutional WP&C processes to those requiring
additional processes to safely address unique hazards. As with other types of ALW, a
laboratory’s process for safely planning, controlling, and executing R&D activities should
be commensurate with the hazards and complexity of the work.
Laboratory WP&C programs, processes, and procedures should address the hazards,
complexity, and work environment during the planning, control, and execution of R&D
project work. Workers and ES&H SMEs should be routinely engaged by project
managers to contribute expert-based identification and analysis of hazards and develop
controls consistent with applicable programmatic requirements and standards.
Management, worker, and SME reviews of R&D ALWCDs should focus on the hazards
associated with the activity. Safety committees are a useful resource for reviewing
projects and identifying applicable standards for certain hazards (e.g., ALARA,
biological, laser, electrical) as needed. Changes to work scope should be evaluated to
determine any new or changing hazards and the need to adjust controls or modify the
method of project execution.
6.1.7 Supporting Facility-Level Documents
Performance Expectation: Organizational structure, functional roles, responsibilities,
levels of authority, accountability, and interfaces for those managing, planning,
performing, and assessing work are clearly defined and documented (see 48 CFR
970.5223-1(b)(1) and (b)(2), 10 CFR 830.122(a), DOE O 433.1B, Attachment 2, para.
1.a and 2.b, and DOE O 422.1, Attachment 2, Appendix A, para. 2.a).
Good Practices:
Integrated Safety Management can be viewed as having three levels: institutional,
facility, and activity. Integration of all three levels needs to be effective for activity-level
work to be planned and safely executed. Some of the key institutional-level interfaces
24
DOE-HDBK-1211-2014
necessary for successful activity-level WP&C were described earlier in this section of
this Handbook. The following is a discussion of facility-level interfaces.
DOE rules and directives addressing nuclear safety require the development of facility-
level documents that, collectively, form the basis for safety and operation of a nuclear
facility. Activity-level WP&C programs and procedures at DOE nuclear facilities should
be integrated with the facility-level nuclear safety documents and other institutional-level
documents (e.g., ISM System Description, Worker Safety and Health Program), to
ensure that the planned work is consistent with safe operations.
Section 22
The following is a brief summary of key facility-level documents:
Documented Safety Analysis (DSA)
The DOE nuclear safety rule, 10 CFR Part 830, Nuclear Safety Management,
establishes requirements for contractors to ensure that the facility-level safety basis is
applied and maintained for all work in the facility. Section 830.202, Safety basis, states:
(a) The contractor responsible for a hazard category 1, 2, or 3 DOE nuclear
facility must establish and maintain the safety basis for the facility... (4) Prepare a
documented safety analysis for the facility; and (5) Establish the hazard controls
upon which the contractor will rely to ensure adequate protection of workers, the
public, and the environment.
Technical Safety Requirements (TSRs)
Specific limits, controls, and related actions are established in TSRs to describe the
specific parameters and requisite actions for the safe operation of a nuclear facility.
These limits, controls, and related actions are established consistent with the identified
hazards and work permitted in the facility. Section 830.205 of the Nuclear Safety Rule
states that: “(a) A contractor responsible for a hazard category 1, 2, or 3 DOE nuclear
facility must: (1) Develop technical safety requirements that are derived from the
documented safety analysis.”
Unreviewed Safety Question (USQ) process
The USQ process is an important tool to evaluate whether changes affect the safety
basis. The contractor’s use of the process ensures that the safety basis for the facility is
not undermined by changes in the facility, the work performed, the associated hazards,
or other factors that support the adequacy of the safety basis. The USQ process
provides the contractor with the flexibility to conduct day-to-day operations by requiring
that only those changes and tests with a potential to impact the safety basis be approved
by DOE. 10 CFR 830.203(d) provides the specific requirements.
As part of ALWCD approval (see Section 6.4.5), the USQ determination process is
applied after the ALWCD completes verification and validation. This determination
serves as a benchmark for whether the safety basis is being preserved.
Additional Facility-Level Documents
25
DOE-HDBK-1211-2014
Other facility safety plans or specific operations safety plans developed for and
maintained by the facility operations, engineering, or safety organizations may also be
used by the work planning team to help ensure that the planned work is consistent with
these safety documents.
6.1.8 The Graded Approach and Tailoring in WP&C
Performance Expectations:
1. A graded approach methodology is incorporated into the work planning and control
process that determines the rigor for the level of analysis, documentation, and
actions, commensurate with the activity-specific and facility-specific factors listed in
the definition in 10 CFR 830.3 (see 48 CFR 970.5223-1(b)(4), 10 CFR 830.3, and
DOE O 433.1B, Attachment 2, para. 1.a, and 2.h).
2. Administrative and engineering controls to prevent and mitigate hazards are tailored
to the work being performed and associated hazards. Emphasis should be on
designing the work and/or controls to reduce or eliminate the hazards and to prevent
accidents and unplanned releases and exposures (48 CFR 970.5223-1(b)(6)).
Good Practices:
Section 23
Contractor line management may apply a graded approach and tailoring based on the
complexity and hazards of individual work activities or the collective scope of work
activities at a given facility. The logic, method of implementation, and basis for grading
should be documented and communicated, and the necessary degree of rigor should be
documented by work processes.
Emphasis should be on designing the work and controls to reduce or eliminate the
hazards and to prevent accidents and unplanned releases and exposures. The purpose
of grading is to determine the level of effort, degree of detail, and rigor of application of
the WP&C guideline elements, remaining consistent with their importance to safety when
planning work. The purpose of tailoring is to determine the types of controls that are
appropriate to the hazards associated with the planned work. Neither grading nor
tailoring may be used to implement the USQ process or hazard controls that are
documented in approved TSRs.
A thorough analysis of the hazards associated with the work is used to ensure that the
degree of detail and formality in planning the work, identifying and implementing hazard
controls, developing work instructions, specifying worker qualifications and skills
requirements, and determining the amount of field supervision required are appropriate
for ensuring that work is accomplished safely and reliably.
The graded approach considers the safety classification of the equipment impacted by
the work (i.e., safety-class, safety-significant, defense-in-depth, worker safety-related)
and the assumptions concerning equipment availability, operation, and performance that
are documented in the applicable facility safety basis documents. Safety system CSEs,
facility DSA safety analysts, and SMEs should be used to ensure that defense in depth
is not unacceptably compromised.
26
DOE-HDBK-1211-2014
The graded approach is applied to an organization’s WP&C program and processes to
ensure that the level of analysis, associated documentation, and related actions are
commensurate with the complexity of the work, performance risk, and the following
activity-specific or facility-specific factors:
• The impact or consequences on safety, safeguards, and security;
• The types of hazards (radiological, biological, chemical, physical) and associated
consequences involved if not properly controlled;
• The relative importance of radiological and non-radiological hazards;
• The lifecycle stage of a facility or activity;
• The impact or consequences on the programmatic mission of a facility;
• The particular characteristics of a facility or activity; and
• Any other relevant factors.
Work activities should be described at a level of detail that allows work planners to
ensure acceptable results given the complexity of the work, frequency of performance,
the significance of the work, the hazards associated with the work, and worker
knowledge and experience. The quality of work planning activities should be sufficient to
ensure safe and reliable performance of work. WP&C procedures should provide the
work planner and work planning team with clear guidance on applying the graded
approach in a manner that ensures thorough planning, facility and worker safety, public
safety, and protection of the environment while allowing the appropriate flexibility to
accomplish work without imposing overly conservative or unnecessary restrictions,
costs, or burdens.
Section 24
Contractors may apply the graded approach to classes or categories of facilities or
activities (e.g., roof replacement on office buildings as a class), but care should be
exercised to ensure that the characteristics of a particular work instance are consistent
with the assumptions and analysis used to grade the class. Legacy hazards in re-
purposed buildings may need to be addressed. Also, the grading for a roof replacement
on a chemical laboratory building is likely inconsistent with the grading that may be
documented for working on office buildings. In both instances, a separate grading should
be performed considering applicable factors and criteria to determine the necessary
controls.
The logic, method of implementation, and basis for grading should be documented and
communicated, and the necessary degree of rigor should be documented by work
processes (procedures, instructions, specifications, and controls).
6.1.9 Measuring System Effectiveness for Activity-Level WP&C
Performance Expectations:
1. Organizations use their assessments and issues management processes to drive
WP&C improvements (see 48 CFR 970.5223-1(b)(1) and (c)(5), 10 CFR 830.122(c),
(i) and (j), DOE O 422.1, Attachment 2, para. 2.a(3), DOE O 433.1B, Attachment 2,
para. 1.a, 2.o, and 2.p).
2. On an annual basis, the contractor shall review and update, for DOE approval, its
safety performance objectives, performance measures, and commitments consistent
27
DOE-HDBK-1211-2014
with and in response to DOE’s program and budget execution guidance and direction
(48 CFR 970.5223-1(e)).
Good Practices:
Measurement is the key to improving towards, or sustaining, excellent performance.
Some metric attributes include:
1. A change in performance should result in visible change in the chosen metric(s).
2. A change in the metric(s) means performance has changed.
3. The metric should incentivize the organization to undertake positive actions.
4. Performance measurement data needs to be easy to gather; otherwise, it will be
inaccurate or poorly acted upon.
Performance expectation #2 can be applied to activity-level WP&C and the ISMS. Safety
performance objectives, measures, and commitments should consider:
• The context and operational definitions of objectives, measures, and commitments.
– Identifying the processes that accomplish the objectives, measures, and
commitments.
– Deciding on the measures in the processes that are relevant to performance.
– Setting up data sources and gathering the data that can be analyzed to provide
the results of the measures. Performance measures data should be replicable.
• Robust performance measurement approaches (e.g., leading/lagging indicators and
trending).
DOE G 450.4-1C, Integrated Safety Management Guide, Attachment 13, “Safety
Performance Objectives, Measures, and Commitments,” provides an overview and
detailed information concerning the implementation of ISMSs.
Additional information about measuring activity-level WP&C performance is provided in
Appendix B of this Handbook. It provides a list of candidate WP&C performance
measures (referred to as “metrics” in the Appendix) that were derived from a survey of
15 of DOE’s major sites and 6 external organizations with extensive WP&C experience.
6.2. Defining the Scope of Work
6.2.1 Work Identification and Request
Performance Expectation: A defined process is used to identify and request work (see
48 CFR 970.5223-1(b)(5) and (c)(1), 10 CFR 830.122(d) and (e), DOE P 450.4A, DOE
O 433.1B, Attachment 2, para. 1.a).
Section 25
Good Practices:
The work activity should be identified in sufficient detail and clarity so that the hazards
associated with the work can be identified; appropriate controls can be selected; and
appropriate schedules and priorities can be established. A work identification process
28
DOE-HDBK-1211-2014
should allow anyone in the organization to submit requests for work and allow others to
supplement the request with relevant information for effective screening, validation, and
prioritization.
The following is a list of possible elements to include in the work identification process:
• Name of requester and contact information,
• Detailed description of the activity or issue, including previously identified or known
hazards,
• Detailed location of the activity (facility name/building number/room number),
• Information from a preliminary scoping walkdown,
• Unique identifier for the applicable SSCs,
• Identification of DSA information (e.g., hazard categorization, SSC safety
designation, TSRs), and the
• Requested date for completing the activity.
6.2.2 Work Screening, Validation, Prioritization, and Backlog Control
Performance Expectations:
1. A defined process is used to prioritize requested work; work priority is managed to
achieve integration among all necessary interfaces (see 48 CFR 970.5223-1(b)(2)
and (b)(4), 10 CFR 830.122(a), (d), and (e), and DOE O 433.1B, Attachment 2, para.
1.a).
2. Procedure scope and applicability are readily apparent (DOE O 422.1, Attachment 2,
Appendix A, para. 2.p(3) (a)).
Good Practices:
Work screening is the first step to determine whether the work needs to be performed
and whether the description of work is adequate. This screening evaluation is
preliminary and does not preclude changes later (e.g., USQ screening determinations) in
the work planning process. Screening considerations may include:
• Corrective action program applicability;
• Evaluation of the activity against any facility or safety basis impact; and
• Evaluation of the need for additional support from functional areas such as safety
and security disciplines.
Validation is the outcome of the work screening process and should be completed in
order for the work planning process to proceed with prioritization activities. Work
prioritization should consider:
• Operational need,
• Resource constraints (e.g., personnel availability, status of procurement actions),
29
DOE-HDBK-1211-2014
• Special controls required (e.g., facility conditions required for the work),
• Level of planning required, and
• Possible efficiencies gained by coordinating work planning to coincide with other
activities requiring, for example, the same shutdown at the same location.
Collaboration among cognizant groups is important to enable the work planning team to
set and establish priorities. Figure 4 illustrates a priority system from the DOE
maintenance guide (DOE G 433.1-1A).
•Priority 1 ‐ Emergency or severe adverse impact on
personnel safety; limits facility operation (top priority:
work today and provide special coverage if necessary).
•Priority 2 ‐ Urgent; hinders facility operation (schedule
within 24 hours).
•Priority 3 ‐ Necessary; has potential to degrade or
hinder facility operation (schedule within seven days).
•Priority 4 ‐ As time permits.
Non‐outage work
Section 26
•Priority 5 ‐ Hot shutdown or hot standby.
•Priority 6 ‐ Cold shutdown.
Outage work
(subcategories for
Priority 5 and 6 work as
part of outage planning
are also useful)
Figure 4: A Prioritization System (from DOE G 433.1-1A)
Backlog is work that is requested, but not complete. It is commonly used as a
performance indicator of organizational effectiveness. Backlog work should be reviewed
periodically, as determined by the organization, to validate the continued accuracy and
prioritization of documented deficiencies and needed work. The system should provide a
list of work requests with a brief description of work required, priority assigned, date
initiated, and plant conditions required for performing the work. Reviews are most
effectively conducted on a predetermined frequency to identify issues and trends for
work that has not been completed. Backlog reviews determine how to re-prioritize the
work request or whether it is still applicable. Factors that may need resolution and could
prompt re-prioritization decisions can include:
• Does the work affect nuclear safety?
• Does the work affect safety or safeguards and security systems?
30
DOE-HDBK-1211-2014
• If the work is not performed, could public safety, worker safety, safeguards and
security, or the environment be degraded?
• Will the Department’s program missions be degraded if the work is not performed?
• Will there be any regulatory consequences if the work is not performed?
• Are there resource issues or other conflicts inhibiting the work?
6.2.2.1 Emergency Work
Performance Expectation: A defined process is used to prioritize requested work;
work priority is managed to achieve integration among all necessary interfaces (see 48
CFR 970.5223-1(b)(2) and (b)(4), 10 CFR 830.122(a), (d), and (e), and DOE O 433.1B
attachment 2, para. 1.a).
Good Practices:
Emergency work should not be used to fast-track other work. To uphold the rare
application of emergency work, it should be approved and released by senior
management or qualified designee (e.g., facility managers, shift managers or other
qualified designees). The WP&C program separately identifies high priority work through
normal approval processes.
Emergency work processes should contain provisions for:
• Senior manager or qualified designee approval and release of emergency work;
• Entry criteria for emergency work, e.g.:
– Prevent an accident or mitigate consequences following an accident.
– Prevent or mitigate imminent danger to personnel, property, or the
environment (e.g., release of or exposure to radioactive material or
hazardous chemicals).
– Prevent or mitigate a significant breach in security.
– Restore ability to obtain critical information or provide critical functions
following a serious impairment.
• A structured process to document all emergency work performed;
• Use of workers, SMEs, and supervisory resources in real-time to analyze hazards,
identify controls, and safely execute work within controls;
• SMEs to provide real-time guidance for addressing safety and technical issues and
providing necessary hold, inspection, witness, or verification points to indicate work
was performed per current standards;
• Conducting a pre-job brief;
• Work to be accomplished without delay or interruption until the condition is stabilized;
• Testing required and acceptance criteria;
• Conducting a post-work review; and
31
DOE-HDBK-1211-2014
Section 27
• The final disposition of WP&C documents used and their retention requirements.
6.2.2.2 Systematic Testing and Repairs of Failed Components
Performance Expectations:
1. Define the work scope by identifying all activities required to complete the work (48
CFR 970.5223-1(c)(1), 10 CFR 830.122(d) and (e), and DOE P 450.4A).
2. Procedure scope and applicability are readily apparent (DOE O 422.1, Attachment 2,
Appendix A, para. 2.p(3) (a)).
Good Practices:
Troubleshooting is the process of locating and identifying malfunctions through
deductive and inductive reasoning or testing. The process includes activities such as
identifying components or systems to be evaluated, providing an expectation of
outcome, and identifying repair actions to be made based on evaluation results.
Troubleshooting and the resulting repair actions should be performed on separate
ALWCDs unless the failures can be narrowed to a limited number of components based
on systems design. In that case, it is permissible to systematically test and repair or
replace those components on an ALWCD provided that an approved revision to the
ALWCD is completed. Areas of consideration for such work include:
• Individually sequence each testing activity and repair or replacement activity in the
work document and identify the hazards and controls for each activity.
• Identify components or systems to be evaluated (including applicable hazard
identification and mitigation), providing an expectation of evaluation outcome,
identifying repairs to be made based on evaluation results, and specifying the testing
for the specific repairs.
6.2.3 Work Scope Development
Performance Expectations:
1. Define the work scope by identifying all activities required to complete the work (48
CFR 970.5223-1(c)(1), 10 CFR 830.122(d) and (e), 10 CFR 830.202(b)(1), and DOE
P 450.4A).
2. Procedure scope and applicability are readily apparent (DOE O 422.1, Attachment 2,
Appendix A, para. 2.p(3) (a)).
Good Practices:
Development of a complete, detailed, and accurate scope of work establishes the
foundation for the remaining portions of the work planning process. Considerations to
address include:
• Identifying the necessary tasks for accomplishing the assigned work scope in order
to identify hazards (i.e., what to do);
• The mechanisms/approaches for completing the assigned work scope (i.e., how to
do it);
32
DOE-HDBK-1211-2014
• The established boundaries for completing the assigned work scope (i.e., information
to help prevent "scope creep" and work location); and
• The work type (e.g., maintenance, projects, operations, R&D).
Sufficient time and resources should be allocated for this activity to be successful. The
requestor should describe the requested work activity scope and boundaries in sufficient
detail to allow the work planning team to determine the necessary tasks and associated
steps so that all hazards can be identified and analyzed, appropriate controls
established, and adequate work instructions developed. The work should be accurately
described, bounded, and clearly communicated through the ALWCDs. To some extent,
work scope development is iterative (see Section 6.4.3.1).
Section 28
An initial scoping walkdown may be performed, as determined by the RM or work
supervisor. These walkdowns (which may be performed by an individual or a team) may
be necessary to refine the scope of a particular activity and facilitate hazard
identification. The number of walkdowns and the personnel needed to participate in the
walkdowns varies depending on the complexity and hazards of the activity. Scoping
walkdowns often facilitate later work planning efforts in hazard identification and in
developing JHAs and ALWCD. For activities requiring an ALWCD, the scoping
walkdowns may facilitate the planning team’s efforts in developing draft work instructions
and hazard identification for use in the JHA process.
The work scope should be developed considering the following types of information:
• The purpose and type of activity or work being performed, the location, and the
desired outcome;
• A list of specific tasks necessary to accomplish the scope of work;
• Principal types of hazards directly involved or expected to be encountered, especially
unique hazards involved with both the activity and the work environment;
• Closely associated or collocated work activities, systems, or components that are not
part of the scope;
• Uncertainties that could affect the performance of facility systems;
• Historical facility documentation and process knowledge;
• Lessons learned applicable to the work to be performed;
• Nuclear safety and environmental impacts that could result from performance of the
work or special techniques or tools that might challenge the facility or site safety
basis; and
• Any special tools or techniques to be used that could introduce hazards.
6.2.4 Planning Team
Performance Expectation: Organizational structure, functional responsibilities, levels
of authority, and interfaces are established for those managing, performing, and
assessing the work (see 48 CFR 970.5223-1(b)(1) and (b)(2), 10 CFR 830.122(a), DOE
O 433.1B, Attachment 2, para. 1.a and 2.b, and DOE O 422.1, Attachment 2, Appendix
A, para. 2.a(1)).
33
DOE-HDBK-1211-2014
Good Practices:
Planning teams should be established for the planning of work activities that are
complex or potentially hazardous. The team can assist in the development of all phases
of ALWCD preparation. Planning team members should have detailed knowledge of
organizational WP&C processes and procedures. The planning team should include, at
a minimum, a worker, a work planner, and a safety professional. In some cases,
planning support from in-place permit processes and other approval processes are
sufficient to supplement the work planner. See Appendix C for good practices in
collaborative team approaches.
Performance Expectation: Personnel with the appropriate functional area expertise
are used to plan the work (see 48 CFR 970.5223-1(b)(2) and (b)(3), 10 CFR 830.122b
and d, and DOE O 422.1, Attachment 2, Appendix A, para. 2.a(6)).
Good Practices:
Personnel to consider for planning team participation include the following:
• Person-in-charge/RM,
• Work supervisor,
• Worker,
• System engineer
• Facility management representatives, and
• SME representatives (technical and ES&H professionals):
– Radiological Control,
– Engineering,
– Industrial Hygiene,
– Industrial Safety,
– Environmental,
– Nuclear Safety,
– Fire Protection,
Security,
Operations,
QA, and
Other SMEs.
Section 29
When feasible, the planning team should conduct planning activities as a single group.
This is essential for complex, hazardous work where many SMEs with relatively narrow
scope can better address the full work scope.
Workers should be involved in the work planning process to lend the benefit of their
knowledge and experience, to communicate their concerns, and to provide their input
concerning workability, preferred methods and approaches.
The planning team should communicate the scope of the planned work to the operations
organization to determine:
34
DOE-HDBK-1211-2014
• The facility conditions under which the work can be performed;
• Operating modes to be established before the work can be accomplished for work
affecting operating facilities;
• The proposed scope and method for accomplishing post-work testing intended to
verify operability;
• Criteria for returning equipment to service, and
• Criteria for restoring facility conditions and operating modes.
6.2.5 Acceptance Criteria
Performance Expectation: Establish acceptance/performance criteria to verify
completion of the work (see 10 CFR 830.122(d), (e), and (h), DOE O 433.1B,
Attachment 2, para. 2.q, and DOE O 422.1 Attachment 2, Appendix A, para. 2.h(5)(d)).
Good Practices:
An important element of defining the scope of work is establishing clear acceptance
criteria that determine whether the work was performed successfully. The level of
formality of the acceptance criteria and associated documentation should be
commensurate with the complexity, hazards, or mission significance of the work. This
level of formality could range from none for low-hazard, simple tasks (e.g., relocating
simple laboratory equipment, staging non-hazardous materials or equipment, or general
cleanup) to specific acceptance criteria for higher-hazard, complex, or mission-critical
tasks (e.g., performance criteria and functional requirements for safety SSC
maintenance). Acceptance criteria development is addressed in Section 6.4.3.2.
6.3. Planning the Work – Identify and Analyze Hazards
DOE regulations state that work planning is required to ensure that all hazards have
been identified and analyzed. This section describes common methods for conducting
hazard identification, hazard analysis elements and documentation, and the objective of
the hazard analysis walkdown and rountable review. Identifying and analyzing hazards
includes addressing:
• Potential hazards (e.g., hazards unique to the activity, legacy hazards, collocated
work area hazards);
• Likely consequences of the hazards;
• Likelihood of occurrence; and
• Other contributing factors (e.g., environmental, weather, aging, human factors, etc)
that have an impact on hazards.
6.3.1 Hazard Identification
Performance Expectation: Identify hazards with the work and the work environment;
including potential undesirable events for the protection of workers, the public and the
environment (see 48 CFR 970.5223-1(c)(2), 10 CFR 830.122(e) and .202(b), 10 CFR
851.21(a), DOE P 450.4A, DOE O 433.1B, Attachment 2, para. 2.d, and DOE O 422.1
Attachment 2, Appendix A, para. 2.i(a)(1), (b), and (c)).
35
DOE-HDBK-1211-2014
Good Practices:
Section 30
Hazard identification is most effectively performed using the planning team approach.
The safety basis requirements of 10 CFR Part 830 requires the contractor responsible
for a DOE nuclear facility to analyze the facility, the work to be performed, and the
associated hazards. The worker safety and health requirements of Part 851 require
contractors to establish procedures to identify existing and potential workplace hazards
and assess the risk of injury and illness associated with them. Hazard identification may
also include hazards that may impact facility resources. Hazard identification methods
should satisfy the required elements for nuclear safety management and worker safety
and health programs.
Activity-level hazard identification should address the hazards associated with individual
tasks and associated steps. There is no single ideal system of hazard identification. The
most appropriate systems vary to some extent with the work involved, and there is
usually the need for a combination of methods to be used. Hazard identification should
consider:
• Specific areas and activities of the work environment;
• Processes performed; and
• Occupations and their related tasks.
Hazards associated with specific work areas or processes may be found within facility-
level documents (see Section 6.1.6). Information collected from the appropriate hazard
identification techniques may then be used to perform a hazard analysis.
6.3.2 Identify Safety Requirements, Standards, and Guidance
Performance Expectation: Identify standards and requirements to address the
hazards associated with the work and the work environment; including potential
undesirable events, for the protection of workers, the public and the environment (see 48
CFR 970.5223-1(b)(5) and (c)(2), 10 CFR 830.122(e) and 202(b)(2), 10 CFR
851.20(a)(4) and .23, DOE P 450.4A, DOE O 433.1B, Attachment 2, para. 2.d, and DOE
O 422.1, Attachment 2, Appendix A, para. 2.a(6) and 2.i(a)(1), (b), and (c)).
Good Practices:
Work planning includes identifying DOE’s safety requirements, standards, and guidance
that apply to the identified work activity hazards. Contractors should ensure that work is
planned in accordance with applicable regulations and those requirements and
standards in their contract while considering available guidance, manufacturer’s
information, and other resources to ensure that all relevant hazards are identified.
Other sources of requirements, standards, and guidance include facility design basis
and safety basis information, operating experience and lessons learned, injury and
illness data, and other resources.
6.3.3 Hazard Analysis
36
DOE-HDBK-1211-2014
Performance Expectation: Analyze the hazards with the work and the work
environment; including potential undesirable events (e.g., “what-if” scenarios), and select
controls necessary for the protection of workers, the public and the environment (see 48
CFR 970.5223-1(b)(6), (c)(2) and (c)(3), 10 CFR 830.122(e), 10 CFR 851.121(a)(1)-(8),
DOE P 450.4A, DOE O 422.1, Attachment 2, Appendix A, para. 2.a(6)), and DOE O
433.1B, Attachment 2, para. 1.a and 2.d).
Good Practices:
The objective of hazard analysis is to develop a comprehensive understanding of the
hazards associated with an activity.
Section 31
Activity-level hazard analysis has a different emphasis than facility-level hazard analysis,
since it is primarily focused on worker protection. However, there is an important linkage
between facility-level and activity-level hazard analysis in terms of the flow of hazards
information and data. Facility-level information and assumptions related to hazardous
material inventory (e.g., quantity, form, and location) feed into a activity-level hazards
analysis in order to help identify the range, types, likelihood and consequences of
potential hazards that workers may encounter while carrying out their duties (e.g., valve
maintenance on a high-pressure liquid hazardous waste line). Conversely, activity-level
hazards analysis may yield insights into hazards that have not been adequately covered
within the facility-level analysis and, as such, may warrant further evaluation.
An effective approach used at many DOE sites is to begin with a work screening process
that considers the complexity of work to be performed and potential hazards associated
with the activity. These factors determine the necessary safety disciplines that should be
involved in the hazards analysis, the level of analysis required, and the documentation
(e.g., work permits, work instructions) required to authorize work.
The hazard analysis should be based on the following principles. It should:
• be comprehensive and systematic;
• be qualitative and/or quantitative;
• distinguish between activity-wide or task-specific hazards and controls;
• be complementary to other safety studies;
• use established methods and data; and
• review the adequacy of existing controls.
A hazards analysis considers events and actions, planned and unplanned, as well as
potential failures of equipment, processes, people, and procedures.
Several DOE sites have employed computer-based tools to help automate activity-level
hazard screening and analysis. Most of these systems provide electronic linkages to
safety-related requirements and guidance, as well as specific facility and hazards
information. Some systems go even further by providing checklists or questions that help
guide planning teams through hazard analysis.
37
DOE-HDBK-1211-2014
Hanford, for example, links the automated job hazard analysis with WP&C, medical,
training, and human resource systems. With decommissioning in progress, reduced
operational facilities, increased use of sub-contractors, and use of matrix workers in
resource pools at the site, supervisor and planner knowledge of qualifications became
more challenging. The integrated system architecture has helped consolidate and
reduce data entry, track employees across the complex and across multiple ALWCDs,
identify resource pools, and ensure qualifications are up to date.
Savannah River National Laboratory moved to an electronic database system for hazard
analysis, as well, to allow hazards screening to be completed more efficiently and
ensure that workers, researchers in this case, utilize the most up to date procedures and
controls. The electronic system provides a Hazards and Controls Summary documents
with succinct descriptions of hazards and controls associated with each task so that they
will be more easily conveyed to all workers.
Section 32
While these systems can be valuable tools, they need to be used with care so as not to
replace sound human judgment and analytical thinking. Job hazard analysis tools should
be evaluated for their effectiveness in addressing the specific hazards associated with
activity-level work and to ensure these tools are maintained current. Automated job
hazards analysis tools should not be relied upon as the sole means of job hazards
analysis. Automated job hazards analysis tools should be applied as a starting point and
supplemented by evaluation of specific hazards associated with the individual work
activity.
IHRTs (also known as senior management review boards) are often used to evaluate
high-impact activities that involve unique processes or hazards. The Independent
Hazard Review (IHR) is a thorough and objective review, supported by designated
experts, and is not intended to capture low- or medium-hazard activities, but rather high-
hazard activities (such as explosive synthesis or high-risk radiological activities),
activities that are complicated by multiple administrative controls to mitigate hazards, or
activities where severe consequences could result from the failure of a control.
To ensure the quality and the objectivity of the IHR, the following typically apply to the
review:
• Reviewers are not be directly involved in the subject work.
• Reviewers have current expertise in the subject area.
• The concurrence signatures for all applicable review group members are obtained
prior to executing the work.
• Reviewers are chosen from an approved list of individuals maintained by facility.
Key factors of success in the IHR process are:
• Providing the IHR Team with a complete review package; no missing or incomplete
pieces;
• Well written work scopes, with clear task breakdowns;
• IHR team members complete a thorough review of the review package prior to the
IHR meeting;
38
DOE-HDBK-1211-2014
• Using multidisciplinary teams; technical and scientific experts, who understand the
operation or activity; safety professionals (health physics, industrial safety, industrial
hygiene, explosives safety); environmental professionals, and; facility personnel, who
are familiar with area hazards.
• Including walkdowns of work locations.
6.3.3.1 General Hazard Analysis
A general hazard analysis is the documented identification, analysis, and specification of
controls for those hazards routinely encountered in a wide variety of work activities and
work environments. General hazards and controls are limited to those mitigated by:
• Worker’s site or facility safety orientation and training. Workers are trained in general
safety and health requirements and are expected to apply controls as the hazards for
the situation and activities present themselves. A critical aspect in all cases is the
individual’s responsibility to remain cognizant of job conditions and to stop or pause
work if a hazard emerges or is encountered that was not appropriately addressed.
• General PPE (e.g., gloves, hearing protection, sturdy footwear for foot protection,
and eye protection, such as safety glasses, goggles, or a face shield).
Often, postings such as signs or warning barricades identify hazards and controls to
alert workers to the need for applying general or nonspecialized PPE. Some examples
are hearing protection for a high-noise hazard in an emergency diesel generator room
(when the diesel is running), eye protection when using shop equipment, or use of hard
hats in areas with overhead bumping hazards.
Section 33
ALWCDs, including JHAs, should not specify general hazards (e.g., standard industrial
hazards) and controls because workers are trained to identify these types of hazards
and the controls needed to mitigate the hazards. Specifying general hazards and
controls in ALWCDs could result in diluting the importance of addressing the controls for
hazards associated with accomplishment of specific activities and the work environment
detailed in the ALWCD.
6.3.3.2 Job Hazard Analysis
A JHA, also known as a job safety analysis (JSA), is the most basic and widely used tool
to identify hazards associated with activity–level work. A JHA is the systematic
examination of an activity intended to identify potential hazards, assess the degree of
hazard, and evaluate practical measures to control the hazard. The JHA involves
breaking the activity into basic tasks and associated steps as necessary to support
hazard evaluation. It involves analyzing each basic task or step of an activity to identify
potential hazards and to determine the controls to safely perform the work.
The planning team, including experienced workers and supervisors may perform a JHA
by analyzing the activity through walkdowns, discussion and observation (See Section
6.3.3.3). This approach has two distinct advantages. First, it involves more people, which
allows for a wider base of experience. Second, the participation of stakeholders
promotes faster acceptance of the ALWCD. See Appendix C for summary descriptions
of other hazard analysis methods with team approaches.
39
DOE-HDBK-1211-2014
The JHA technique is based on a step-by-step hazard analysis. To be effective, JHA
should be applied to an activity that is neither too broad nor too simple. For example,
manufacturing and pushing a button are too broad and too simple for such analysis.
Lathe work, press tool work, spray painting, electric arc welding, and sheetmetal work
are examples of appropriate activities that are suitable for hazard analysis using JHA (in
terms of activity scope and potential hazard severity).
The JHA aims for accident prevention. To achieve this aim, it is important that the
hazard controls developed from JHAs be integrated into the work, for example, as part of
the ALWCD.
During the JHA process, an evaluation of hazards is performed during or following a JHA
walkdown or roundtable review (see Section 6.3.3.3). Standard industrial hazards and
controls that are expected of all workers (e.g., slip, trips, and falls; bee stings; bending;
pinch points; et al) do not need to be included in the JHA. This allows the JHA process
to focus on the unique hazards of the activity. The work planner or work planning team
should:
• Review maintenance/equipment history, relevant lessons learned and other forms of
feedback to assist in identifying hazards and controls;
• Evaluate activity-specific controls required by other hazard assessment or analysis
documents (e.g., as low as reasonably achievable (ALARA) job review, industrial
hygiene exposure assessment, shock and arc flash hazard analysis), and
incorporate them into the JHA;
• Evaluate known radiological, chemical, biological, and physical processes and their
associated hazards with the work environment;
• Review manufacturer- or vendor-provided operating instructions and safety
documentation (e.g., equipment manuals, Material Safety Data Sheets, Safety Data
Sheets, etc.) for hazards, warnings, operating limitations or controls and evaluate for
incorporation in the JHA;
Section 34
• Review drawings, notes, video, and photographs and conduct discussions with
planning team members familiar with work sites;
• Review and validate the activity tasks, work scope, and draft work instructions;
• Identify and discuss the hazards associated with the activity, each task and
associated steps, and the work environment, including potential undesirable events
(e.g., the potential consequences of improperly performing or not performing the
step);
• Identify and discuss potential transients or accidents (e.g., “what if”, Failure Modes
and Effect Analysis (FMEA), fault tree analysis for scenarios such as spills, fires,
exposures, failures, changing conditions, interference, alarms, unexpected
equipment actuations, errors and their consequences);
• Prescribe specific controls necessary to eliminate or mitigate each identified hazard
for the protection of workers, the public, and the environment; and
• Review work tasks from a human performance perspective to identify and either
eliminate or develop contingencies for error-likely situations.
40
DOE-HDBK-1211-2014
6.3.3.3 JHA Walkdowns or Roundtable Reviews
The objective of the walkdown or roundtable review, performed as part of the JHA, is to
interactively ensure all hazards are identified; determine whether all hazards have
adequate controls; determine whether identified controls are compatible; and determine
whether the work can be done safely and in compliance with applicable requirements.
To be most effective, draft work instructions and a draft JHA should be developed and
made available to support the walkdown or roundtable. The walkdowns include an
examination of work environments where activities are to be performed to familiarize the
work planning team (or work planner for lower hazard or less complex work) with the
physical conditions, potential stressors, and expected tasks.
A walkdown may be augmented by conducting a roundtable using technology and
information obtained during the walkdown or by examination of pictures, drawings,
specifications, or other technical data. However, roundtables and the use of technology
and data reviews should not be used to circumvent the need for a walkdown. A
walkdown is always preferred and should be performed unless it is not feasible (e.g.,
ALARA considerations, equipment not set up when activity was planned or room is
sealed) or the risk is unacceptable and outweighs the benefits. In situations such as this,
a roundtable should be conducted at a minimum. The work planner, in consultation with
the planning team, decides when to conduct roundtable reviews of ALWCDs to more
effectively communicate with personnel involved in the planning of the activity. The work
planner may determine that a roundtable review is not necessary. However, for new or
complex operations or significant changes in the scope of work or tasks, a roundtable
review should be considered.
If a portion of the work environment is not accessible or the walkdown cannot be
performed, steps should be included in the ALWCD (e.g., hold point) to verify that
conditions are as planned. If conditions are not as planned, the work should be stopped
or paused so that the change control process can be implemented.
The work planning team (or work planner for less complex or less hazardous activities)
walks down the requested work using the draft JHA and draft work instructions to:
• Document the work needed, objectives to be accomplished, condition to be achieved
or corrected, problem being addressed, and expected outcome;
Section 35
• Identify or confirm the specific tasks and associated steps necessary to accomplish
the work and support hazard identification and subsequent analysis;
• Identify the hazards associated with the work environment and each task or activity
necessary to accomplish work;
• Identify any hazards that can be eliminated or reduced from the work tasks through
process re-engineering or other changes;
• Identify the need to assess and quantify the hazards (e.g., noise decibel levels;
radiation dose rates; chemical volumes or airborne levels; temperature limits or
extremes; fluid or gas pressures; electrical voltage and amperage; weight of lifted or
suspended components) so that analysis will result in the identification of appropriate
controls;
• Identify planned transitions and the associated hazards and controls;
41
DOE-HDBK-1211-2014
• Determine if the work activity is clearly and adequately bounded (e.g., physical
boundaries such as equipment or components to which work activity is limited,
specific work environment to which work is confined; conditions under which work
can be performed; and organizations responsible for the various tasks); and
• Document worksite conditions, using photographs if necessary, to ensure
appropriate consideration of special or unique planning requirements or
circumstances.
6.4. Planning the Work – Develop and Implement Hazard Controls
Performance Expectations:
1. Hazards associated with the work are evaluated before work is performed and an
agreed upon set of ES&H standards and requirements are identified that provide
adequate assurance that employees, the public, and the environment are protected
from adverse consequences (48 CFR 970.5223-1(b)(5)).
2. Hazard controls are developed and implemented to ensure adequate protection of
workers, the public and the environment (see 48 CFR 970.5223-1(c)(4), and 10 CFR
830.202(b)(5) and .204(b)(4)).
3. Contractors must establish and implement a hazard prevention and abatement
process to ensure that all identified and potential hazards are prevented or abated in
a timely manner (10 CFR 851.22).
4. Develop and Implement Hazard Controls. Applicable standards and requirements
are identified and agreed-upon, controls to prevent/mitigate hazards are identified,
the safety envelope is established, and controls are implemented (DOE P 450.4A
and 48 CFR 970.5223-1(c)(3)).
Good Practices:
DOE rules and directives require that hazard controls be identified and implemented to
prevent or mitigate potential consequences from DOE activities to workers, public, and
the environment. For hazard category 1, 2, and 3 nuclear facilities, hazard control
identification and implementation starts with the DSA and TSRs and extends through
activity-level JHAs. For work activities with ALWCDs, controls should be integrated into
the work documents rather than simply referencing the JHA, TSR or DSA.
6.4.1 Safety SSCs and Technical Safety Requirements
The operations organization has the principal function to manage the operability of
safety SSCs and comply with TSRs.
Operations procedures (i.e., ALWCDs) should provide sufficient direction to ensure that
the facility is operated within its design basis and supports safe operation of the facility.
This should include emergency operating procedures; operating procedures for all
phases of operation, maintenance, and procedures for all surveillances required by TSR;
Security Plan implementation; Emergency Plan implementation; fire protection;
procedures governing the administrative aspects of operation of the facility; etc..
Section 36
42
DOE-HDBK-1211-2014
A system should be developed to control all procedures that provide assurance of safe
operation. Procedures that are important to safety need to be identified for special
attention to ensure they are performed reliably and given proper attention in proportion
to the hazards that they control. The system should include the mechanism for review,
approval, revision, control, and temporary changes to the procedures. Please refer to
DOE G 423.1-1A for additional guidance on these matters.
The DSA identifies safety SSCs and controls required to mitigate the consequences of,
and lower the probability of, accidents to workers, the public, and the environment.
Controls credited to maintain safety SSCs operable for all modes of operation are
identified in the TSRs. TSR Surveillance Requirements (SRs) are used to ensure that
safety SSCs are operable and available and Specific Administrative Controls (SACs)
implementing procedures ensure SAC safety functions identified in the DSA is met. As
such, the ALWCDs developed to implement TSR SR and SAC implementing procedures
should be technically accurate, workable, and clearly identify the acceptance criteria in
order for Operations personnel to determine if a system is operable or a SAC’s safety
function is met.
6.4.2 Establish a Hierarchy of Controls
Performance Expectation: Contractors must select hazard controls based on the
following hierarchy:
(1) Elimination or substitution of the hazards where feasible and appropriate;
(2) Engineering controls where feasible and appropriate;
(3) Work practices and administrative controls that limit worker exposures; and
(4) Personal protective equipment (10 CFR 851.22(b)).
Performance Expectation: Administrative and engineering controls to prevent and
mitigate hazards are tailored to the work being performed and associated hazards.
Emphasis should be on designing the work and/or controls to reduce or eliminate the
hazards and to prevent accidents and unplanned releases and exposures (48 CFR
970.5223-1(b)(6)).
Good Practices:
DOE’s hierarchy of controls for addressing hazards is to first eliminate or substitute
hazards where feasible and appropriate. This is the desired method for preventing
exposure of workers to a hazard. Then, if elimination or substitution is not an option,
control of worker exposure to the hazards need to occur in the following order of
preference:
• Engineered controls - Controls that mitigate a hazard through the use of engineered
machinery or equipment (e.g., work remotely via manipulators, gloveboxes).
• Administrative controls - Contractor safety policies and processes, ALWCDs,
hazardous energy control, supervision, schedules, and training.
• PPE - Includes all clothing and other work accessories designed to create a barrier
against workplace hazards (e.g., safety goggles, blast shields, hard hats, hearing
protectors, gloves, respirators, aprons, and work boots).
43
DOE-HDBK-1211-2014
Key considerations during hazard control development for the JHA include:
• Ensure controls are identified for each task-specific hazard.
• Preference should be given to passive controls over active controls (see Section 5.0,
Definitions).
• Analyze the identified hazards collectively to arrive at the optimum set of controls for
the work being performed.
• Ensure that the selected controls do not conflict with each other or introduce
additional hazards (e.g., anti-c requirement exacerbates heat stress environment).
Section 37
• Explore the possible need for an implementation strategy in cases where steps to
implement a control might be necessary. This might include special training, special
postings, or implementing a disposition strategy per the hazard analysis process
(e.g., ALWCD with continuous use work instruction, pre-job brief).
• How to maintain the control throughout the activity or until the hazard has been
eliminated or reduced to a point where the control is no longer necessary.
6.4.3 ALWCD Development
Performance Expectations:
1. Develop instructions necessary to complete work activities safely and efficiently,
including integration of specific hazard controls. Identify and integrate into the
instructions applicable technical and administrative requirements (e.g., ES&H, QA,
Security, Emergency Management, etc.) (see 48 CFR 970.5223-1(b)(5) and (c)(3),
10 CFR 830.122(d) and (e), DOE O 433.1B, Attachment 2, para. 2.f, and DOE O
422.1, Attachment 2, Appendix A, para. 2.a(6) and 2.b(5)).
2. Establish acceptance/performance criteria to verify completion of the work (see 10
CFR 830.122(d), (e), and (h), DOE O 433.1B, Attachment 2, para. 2.q, and DOE O
422.1, Attachment 2, Appendix A, para. 2.h(5)(d))
3. For hazards identified either in the facility design or during the development of
procedures, controls must be incorporated in the appropriate facility design or
procedure (10 CFR 851.22(a)(1)).
4. The operator (e.g., responsible manager) must establish and implement operations
practices for developing and maintaining accurate, understandable written technical
procedures that ensure safe and effective facility and equipment operation (DOE O
422.1, Attachment 2, Appendix A, Para 2.p).
5. Methods for approving, posting, maintaining, and controlling access to electronic
operations documents (procedures, drawings, schedules, maintenance actions, etc.)
if electronic documents are used. (DOE O 422.1, Attachment 2, Appendix A, Para
2.a(7).
Good Practices:
The ALWCD should contain only the information needed to perform the work. Examples
include permits, drawings, sketches, manufacturer instructions, required attachments to
perform the work (e.g., pre-job and post-job briefing sheets, inspection forms), in
addition to the ALWCD. All other documentation compiled during planning activities
44
DOE-HDBK-1211-2014
should be separated and maintained, if needed upon request. Examples include the job
hazard analysis, arc flash evaluations, and floor loading evaluations.
6.4.3.1 Work Scope
Good Practices:
Work scope development (Section 6.2.5) is the entry point for an iterative process to
determine the need for development and level of detail for an ALWCD. A thoughtful
analysis of the work is required, breaking down the work into discrete tasks and breaking
tasks down into work steps that can be analyzed for associated hazards. This is done
using a graded approach (i.e., more in-depth analysis for complex, high-hazard
activities).
Improvements from the initially developed scope of work can be derived from the
following:
• Review and update the work needed, objectives to be accomplished, condition to be
achieved or corrected, problem being addressed, and expected outcome;
• Review and update the hazards directly involved or expected to be encountered, with
both the activity and the work environment;
• Review and update lessons learned applicable to the work to be performed;
Section 38
• Review of safety basis, environmental or regulatory impacts that could result from
performance of the work;
• Review and update any special tools or techniques that will be used that could
introduce their own hazards; and
• Review and update equipment, components, and locations described in the work
request.
Completion of scope development will factor heavily in determining the level of planning
and ALWCD type (see Section 6.4.3.2) needed to perform the activity. High-hazard,
high-complexity, and infrequently performed activities, along with activities performed by
multiple disciplines, warrant the highest level of planning. Due to the potential
consequences from ineffective performance, ALWCDs for these activities undergo the
highest level of discipline in their preparation and implementation and should include
step-by-step work instructions listed in a specified sequence that require verbatim
compliance (see Section 6.4.3.3).
Frequently performed lower-hazard or lower-complexity activities may only require
ALWCDs with a work scope statement. The statement should communicate the scope,
work boundaries, and limits of the work to be performed such that the associated
hazards are identified, analyzed and mitigated.
6.4.3.2 ALWCD Types
Good Practices:
45
DOE-HDBK-1211-2014
Work planning is an iterative function that includes work scope development, job hazard
identification and analysis, hazard control incorporation, and work instruction
development, which should be performed simultaneously in preparing an ALWCD. The
complexity and hazards of the activity, the location where the work is being performed,
and the frequency of the work affect the probability of consistent, safe and reliable
performance.
Organizational processes and procedures manage these factors by defining the types of
ALWCD, manner of incorporating JHA controls into the ALWCD, and the subsequent
level of detail communicated to the worker.
An example of ALWCD types (Detailed, Moderate, Minor, and Model) is described below
(see Appendix D for additional considerations and examples while developing Detailed
or Moderate ALWCDs).
Level 1: Detailed ALWCD
Detailed ALWCDs are most appropriate for activities that are highly complex, highly
hazardous, performed infrequently, or involve multiple disciplines or organizations.
Detailed ALWCDs typically include:
• Scope,
• Precautions and limitations,
• Prerequisites and initial conditions,
• Special training and medical requirements,
• Special tools and equipment,
• Work instructions,
• Post-work activities,
• Closeout,
• Status logs and data sheets, and
• Additional supporting documentation.
Appendix D contains a recommended Detailed ALWCD format, including information to
consider while developing Detailed ALWCDs and associated work instructions.
Level 2: Moderate ALWCD
Moderate ALWCDs are appropriate for activities that are moderately complex,
moderately hazardous, and performed frequently. Moderate ALWCDs contain either
general directions or step-by-step instructions, as appropriate to the SOW and the
complexity and hazards of the activity. A moderate ALWCD may be appropriate in cases
where no special hazard controls are needed. Moderate ALWCDs may also be
appropriate for activities that are fairly complex, fairly hazardous, and performed
infrequently when detailed instructions are available in existing documents such as
vendor manuals and operating procedures. In general, Moderate ALWCDs rely less on
detailed work instructions and more on the SOW. Reliance on the SOW should be
deemed appropriate only after careful consideration of the factors defined in
Section 39
46
DOE-HDBK-1211-2014
organizational procedures (see also Appendix A). See Appendix D for consideration
during the development of Moderate ALWCDs.
Level 3: Minor ALWCD (No Work Instructions Required)
Minor ALWCDs are appropriate for routine activities that are fairly simple, do not affect
nuclear safety, do not increase the probability of upset conditions, are performed
frequently, and rely solely on SOW to mitigate hazards that are minor in nature. As such,
work instructions do not need to be developed and formally communicated to the worker
in either an ALWCD or through cross-reference to an existing work instruction or another
ALWCD. Minor ALWCDs contain a statement of work with a bounding scope statement
and limitations that rely on SOW. Reliance on the SOW should be deemed appropriate
only after careful consideration of the factors discussed in organizational procedures
(see also Appendix A).
Model ALWCD
ALWCDs ranging from Detailed to Minor are often used to perform repetitive or
reoccurring work activities. Model ALWCDs should be used for activities that are
repeated or very similar work when the activity is next performed. The most recently
closed ALWCD, with any associated feedback, should be used by the work planner or
planning team as a model ALWCD the next time similar work is performed. Prior to each
use, model ALWCDs are to be reviewed to ensure the accuracy of the task description
and to verify that the hazards and environmental aspects have been identified, and that
controls are appropriate to the intended work. The review incorporates safety feedback
for improvement, previous comments, operating experience, activity-specific information
and appropriate authorization, approval, and release prior to execution.
6.4.3.3 ALWCD Use Categories
Good Practices:
Organizational WP&C processes and procedures should establish expected ALWCD
use categories, which detail the expected manner in which ALWCD work instructions
should be performed.
Example use categories include Continuous Use and Reference Use.
Continuous Use
ALWCDs categorized as Continuous Use (sometimes referred to as Use Every Time)
should be utilized for activities where improper performance could result in unacceptable
consequences.
ALWCDs categorized as Continuous Use should be at the work location, open to the
work instruction being performed, completed as written in a step-by-step sequence, and
should be signed or documented unless otherwise specified. Detailed ALCWDs should
be considered for the Continuous Use categorization.
Reference Use
47
DOE-HDBK-1211-2014
ALWCDs categorized as Reference Use should be utilized for routine, less complex
activities where improper performance does not result in unacceptable consequences.
These ALWCDs do not require documented verification upon satisfactory completion of
the individual steps or the entire task. ALWCDs categorized as Reference Use should be
located near the work location and readily available upon request. Although step-by-step
compliance with work instructions is expected, it can be accomplished by workers
periodically referencing the ALWCD, conducting effective pre-job briefings, or utilizing
SOW. Moderate ALWCDs containing step-by-step work instructions should be
considered for the Reference Use categorization.
6.4.3.4 ALWCD Preparation
Good Practices:
The Planning Team should develop ALWCDs necessary to complete work activities
safely and efficiently in accordance with DOE O 422.1, DOE-STD-1029, and the
organization’s writer’s guide or procedure for WCD development. The WCD should:
Section 40
• Clearly identify the boundaries which are not to be exceeded during ALWCD
execution
• Identify prerequisite actions and initial conditions to be completed prior to continuing
the ALWCD execution
• Identify all resources needed to ensure that the activity can be accomplished without
unnecessary interruption or pauses such as:
– Documents necessary for accomplishing the work (e.g., procedures, drawings,
vendor manuals, specifications, requirements, performance criteria, permits).
– Special equipment, tools, materials, and parts needed for the work along with
their instrument ranges, accuracy, and calibration requirements.
– Special mockup, training, qualifications, or medical requirements.
– Required support services, permits, and hold points such as QA/quality control
(QC), radiological controls, industrial hygiene, fire watches, confined space entry,
and hot work.
– Independent verification personnel.
• Ensure SME identified technical and administrative requirements and controls (e.g.,
ES&H, QA, Security, Safety Basis) are implemented;
• Integrate activity wide and task-specific hazard controls identified in the JHA are
appropriately documented and readily identified;
– Activity wide hazards and associated controls should be identified in the ALWCD
Precautions and Limitations,
– Task specific hazards and controls should be identified in the ALWCD Work
Instructions.
o Personnel hazards should be identified with a Warning.
o Equipment/facility hazards should be identified with a Caution.
48
DOE-HDBK-1211-2014
– Clearly identify when hazard controls are able to be relaxed due to the mitigation
or reduction of specific hazards;
• Provide work instructions which:
– Identify the tasks and hazard controls required to safely and efficiently complete
the ALWCD
– Follow the logical flow of the work activity
– Consider SOW competencies in determining the level of detail required to safely
and efficiently execute the ALWCD
– Are user friendly and capable of being performed as written,
– Preclude the potential for misinterpretation or error
– Consider the hazards associated with the activity, complexity of the activity,
frequency of activity performance, and potential consequences of improper
execution of the activity while determining the level of detail required to safely
and efficiently execute the ALWCD.
• Establish acceptance or performance criteria to verify completion of the work;
A good practice being used by many contractors is clearly denoting steps or work
instructions implementing acceptance criteria in TSR SRs and on the associated data
sheets. Examples include work instructions with the step’s text in bold letters, inserting
an identifier in the ALWCD margin, and inserting a Note preceding the step or work
instruction stating that the step or work instruction implements a TSR control.
6.4.4 ALWCD Verification and Validation
Performance Expectations:
1. Readiness is confirmed prior to scheduled work performance, with regard to system,
prerequisite controls, work environment, people, documents, tools and materials (see
48 CFR 970.5223-1(b)(1) and (4), DOE O 433.1B, Attachment 2, para. 1.a, 2.d and
2.i).
2. Directives include provisions to use walkthroughs (procedure execution with actual or
simulated operation of components by subject matter expert(s)) to validate procedure
changes and revisions. (DOE O 422.1, Attachment 2, 2.p(4)(h)).
Section 41
3. Directives include provisions for review of new and revised procedures prior to use
and periodically for technical accuracy and human factors considerations. (DOE O
422.1, Attachment 1, 2.p(7)(a)).
4. Procedure reviews include validation walkthroughs (DOE O 422.1, Attachment 1,
2.p(7)(e)).
Good Practices:
Guidance should be provided for the development, writing, verification, validation,
approval, and use of procedures (see DOE G 433.1B).
ALWCD Verification
49
DOE-HDBK-1211-2014
Verification involves reviewing a new or revised ALWCD to determine whether it is
technically accurate and in the proper format. The review should ensure that the work
activity is adequately described, all hazards are analyzed and controls are established,
acceptance or performance criteria is specified, and that human factors principles and
appropriate administrative policies are incorporated. A review of the ALWCD technical
accuracy against the design requirement should be performed for the system or
component it concerns (e.g., comparing the vendor manual and design specifications
with the procedure).
Verification should be conducted by one or more reviewers who were not involved in
writing the procedure but are representative of the intended users. Reviewers from other
disciplines, such as health physics, engineering, and operations, should be considered
for involvement in the process.
ALWCD Validation
Validation comprises the review of a ALWCD by representatives of the disciplines or
organizations intended to perform the activity to determine its usability and correctness,
whether it can be performed exactly as written, and whether it is within the intended
SOW. This review evaluates whether the ALWCD provides sufficient and
understandable direction to the worker and whether it is compatible with the equipment
or system being operated or maintained. Validations should be performed at the location
where the work will be performed to identify any issues with equipment, the ALWCD,
access and egress, unanticipated hazards, and controls. In certain hazardous
circumstances, such as a high-radiation area, it may be necessary to identify issues
without performing the validation at the work location.
Contractors should apply the graded approach to determine the rigor of Verification and
Validation for the different levels of ALWCDs. For example, a Level 3 ALWCD, with no
work instructions or specific hazard controls may not warrant Verification and Validation,
whereas a Level 3 ALWCD with specific hazard controls may warrant Verification, at a
minimum. Verification and Validation reviews (see Appendix E) should be the final step
in ALWCD development prior to being submitted to the ALWCD approval process.
6.4.5 ALWCD Approval
Performance Expectation: ALWCDs are formally reviewed and approved (see 48 CFR
970.5223-1(b)(1) and (b)(2), 10 CFR 830.122(a), (d), and (e), DOE O 433.1B,
Attachment 2, para. 2.d and 2.f, and DOE O 422.1, Attachment 2, Appendix A, para.
2.h(5)(b), and 2.p(6)).
Good Practices:
Once the ALWCD is verified and validated, it should be routed for review and approval.
Different levels of work may require different levels of approval based upon work
complexity and hazards. The review and approval process may be iterative, requiring
incorporation and disposition of review comments. The following should be performed as
part of the review and approval process:
• Obtain review and concurrence from the responsible WP&C manager that the
ALWCD has been properly developed and reviewed;
Section 42
50
DOE-HDBK-1211-2014
• Route to appropriate affected organizations and SMEs (i.e., operations,
maintenance, safety, engineering, quality assurance, and environmental) for review
and to:
– Confirm the technical adequacy of the ALWCD through ALWCD Verification;
– Concur that hazard controls are appropriate for the work and that applicable
programmatic and regulatory requirements are adequately incorporated in the
ALWCD; and
– Ensure that all comments received are satisfactorily resolved prior to ALWCD
approval.
• Perform Independent Hazard Review for high-impact work (e.g., high-hazard, high-
complexity, first-time-use, multiple work groups)per established criteria (see Section
6.3.3);
• Complete the USQ process; and
• Route to the appropriate responsible manager for final approval.
6.4.6 ALWCD Change Process
Performance Expectations:
1. The operator must establish and implement operations practices for developing and
maintaining accurate, understandable written technical procedures that ensure safe
and effective facility and equipment operation, addressing the following elements:
a. A process for procedure changes (pen and ink or page changes) and revisions
(complete reissues) (DOE O 422.1, Attachment 2, Appendix A, para. 2.p(4));
b. A process for training personnel on new, revised, or changed procedures (DOE
O 422.1, Attachment 2, Appendix A, para. 2.p(5)); and
c. A process for approval of new, revised, or changed procedures (DOE O 422.1,
Attachment 2, Appendix A, para. 2.p(6)).
2. The contractor responsible for a hazard category 1, 2, or 3 DOE nuclear facility must
implement the DOE approved USQ procedure in situations where there is a:
(1) Temporary or permanent change in the facility as described in the existing DSA;
(2) Temporary or permanent change in the procedures as described in the existing
documented safety analysis;
(3) Test or experiment not described in the existing DSA; or
(4) Potential inadequacy of the DSA because the analysis potentially may not be
bounding or may be otherwise inadequate (10 CFR 830.203(d)).
Good Practices:
Contractors should establish processes to change approved ALWCDs. These processes
should ensure that changes in work scope, field conditions, or work execution are
thoroughly reviewed, analyzed (including adequacy of existing hazards analysis and
51
DOE-HDBK-1211-2014
specified controls), documented, and approved before being implemented. These
processes should include:
• Requirements for the clear identification of the ALWCD change’s scope in order to
adequately identify and analyze associated hazards, implement hazard controls,
and develop supplemental work instructions;
• Identification of personnel authorized and required to concur or approve ALWCD
changes;
• Definitions of administrative, editorial and technical changes; change significance
levels (e.g. pen and ink, field change, revision); and the criteria for implementing the
change significance levels, including change control criteria for the USQ and
configuration management processes;
• Methods of incorporating changes into ALWCDs;
• Criteria for reconvening the ALWCD planning team for ALWCD changes;
• Requirements to review the existing hazard analysis after any changes to the
ALWCD to determine if new hazards were created, any existing hazards were
modified, addition of conflicting controls, or if any existing hazards were eliminated
by the change;
Section 43
• Requirements to brief or train workers on the changes.
6.5. Planning the Work – Scheduling
Performance Expectation: An integrated schedule(s) is developed that balances
priorities and resources in a disciplined manner to ensure that work is accomplished
safely and efficiently. The scheduling process has provisions for work not requiring a
formal schedule. The schedule is managed through a formal change control process
(see 48 CFR 970.5223-1(b)(2), (b)(4) and (b)(6); 10 CFR 830.122(a), (d) and (e); and
DOE O 433.1B, Attachment 2, para. 1.a, 2.b, and 2.d).
Good Practices:
6.5.1 Schedule Attributes and Detail
The majority of attributes and detail described below are derived from DOE G 433.1-1A
and adapted for all activity-level work.
A schedule is a management tool to control and direct activity-level work (ALW)
activities. The schedule should be a concise method for tracking completion of ALW
tasks. Management can use it to integrate facility activities, determine the critical path,
and explore alternatives when needed. Routine activities previously defined and
approved by line management (e.g., operator rounds, instrument source checks, pre-
operational equipment checks, basic shop work) may not need to be listed on facility
schedules. The following attributes should be included in the schedule or scheduling
process:
52
DOE-HDBK-1211-2014
• Approved work is incorporated in schedules (e.g., daily, weekly);
• Responsible manager approves schedules prior to use;
• Work identified on approved schedules is considered authorized;
• Conflicting work is precluded;
• Coordination of related work activities, when required, is clearly identified;
• The schedule report format is appropriate for the user. The level of detail in the
schedule needed by the facility manager may be different from the level of detail
needed by a craft supervisor;
• The schedule is reviewed and accepted by those responsible for getting the work
done (e.g., Work Supervisor, RM, PIC);
• The schedule is an accurate, living document and flexible to deal with unanticipated
events;
• A hierarchy of schedules of varying detail, used by different levels of personnel, is
obtained from a common database;
• Intermediate milestones are available as an overall measure of the progress of ALW
activities and identify tasks significantly behind schedule; and
• All supervisory personnel report progress of work and have an understanding of the
schedule process appropriate to their needs and uses.
In a site or facility where the WP&C process is functioning well, work is identified in a
timely way and sent to the work planner or planning team. On weekly and daily
schedules, work groups are given the quantity of work that they can accomplish. The
most important work is scheduled first.
The detail included in the overall schedule should be that required to ensure
coordination of work and to allow assessment of progress. It is particularly important to
include details of activities that have interfaces among the various craft and support
personnel. The following are some examples of detail that may be required:
• Facility management are able to identify and establish required facility configuration
(e.g, equipment status, operating modes, lockout needs);
• Radiological protection personnel are able to anticipate the need for RWPs,
technician support, and major radiological protection actions, such as installation of
temporary shielding for a particular task;
Section 44
• QC personnel and other inspection groups are able to anticipate the need for their
presence at the job site;
• Critical resource needs, such as overhead cranes and scaffolding, are described in
sufficient detail to avoid interference, conflicts, and work delays;
• The schedule is craft-loaded and the sequence and timing of activities adjusted to
ensure that resource requirements are consistent with resource availability;
• Tests, inspections, or other tasks that may identify additional work are scheduled as
early as possible to permit time for completion of the additional work within the
established time frame; and
53
DOE-HDBK-1211-2014
• Significant post-ALW testing is factored into the schedule. Time is allotted for testing,
lineup, and other activities required for returning systems to service. System
interactions and operator resources are considered when scheduling system and
facility startup.
Schedules should be periodically reviewed. Opportunities for schedule improvements
should be explored during the review process. This should include the review of TSRs
and other regulatory requirements to determine whether changes that may result in work
efficiency or schedule improvements are safe.
The schedule review process and worker input to the planning process requires a sense
of ownership of the schedule for those who are expected to implement it. The individuals
responsible for the work should likewise be the individuals responsible for reporting
progress of the work.
6.5.2 Schedule Integration
Integration of major activities is key to successful schedule development. There should
be an integrated ALW schedule that includes work to be done by both site personnel and
non-facility contractors. The planning organization should involve non-facility contractors
as early as possible in the planning process to ensure their work is integrated and
scheduled properly.
By providing sufficient detail in the integrated ALW schedule to coordinate activities and
track progress, a more efficient use of technical support and resources can be achieved.
The integrated ALW schedule should form the basis for progress reporting. For example,
work can be scheduled and combined with other ALW activities on the same equipment,
or with other ALW on similar equipment in proximity. Program outages to coincide with
equipment changeout or modification could be scheduled simultaneously with an
instrument calibration, equipment lubrication, or other preventive or predictive
maintenance that requires a similar lockout/tagout.
A computerized scheduling system may enable personnel to be responsive to the needs
of management. Depending upon the type of computerized scheduling system
employed, the following advantages are possible:
• Rapid update capability;
• Ease in exploring alternatives;
• Resource determination and capability;
• Work-site congestion identification; and
• Tailored reports to specific groups or users.
Multi-week scheduling can be used to ensure that the highest priority work is being
completed on a weekly basis. Appendix F provides more information on effective multi-
week scheduling.
Effective daily schedules are generated through the multi-week process. Daily schedules
ensure that the highest priority work is being completed on a daily basis; that clarity,
consensus, and commitment regarding work to be done is achieved through joint
54
DOE-HDBK-1211-2014
Section 45
prioritization; and that clear expectations are communicated to work groups for daily
assignments. Daily schedules are important to ensure that work is properly coordinated
even when there are last-minute schedule changes. A daily schedule is generally used
as the basis for discussions at daily meetings (e.g., Plan-of-the-Day). Daily meetings
with affected individuals should be conducted to focus on the progress of key activities
and to provide short-range coordination of scheduled activities. Meetings should be
managed to use the time of the managers and supervisors efficiently, minimizing
redirection of work in progress, and preventing delays to oncoming work shifts.
A detailed review of the daily schedule should be an integral part of shift turnover
activities to ensure that the oncoming shift is familiar with any recent adjustments made
to the schedule and ongoing activities. This is particularly important for operator
turnovers to ensure that operators know the status of the facility and are familiar with
upcoming ALW activities.
A three-day outlook schedule, updated and issued daily, has proven useful at many
facilities. This schedule provides the detail necessary to control the present day‘s work
and provides an opportunity for a look ahead without an unreasonable amount of data.
Extending the outlook period further than about five days or not issuing the schedule on
a daily basis increases the risk that data may not be current when needed.
Supervisors may elect to identify fill-in work assigned to maintain crew productivity. If fill-
in work has facility condition requirements associated with it, then it should be identified
on the rolling schedule so that all cognizant groups are aware of the activities.
6.5.3 Schedule Approval and Changes
Schedule approval includes an evaluation of the current facility/project conditions and
configuration to coordinate and integrate other scheduled work activities; minimize
impacts such as priority, schedules, and resources; determine availability of required
facilities, systems, or equipment; address conflicting controls (including integration of
workers from different companies or organizations); and address access restrictions.
Once the ALWCD is approved and identified on a responsible manager approved
schedule (e.g., Plan of the Day, Plan of the Week), the work is authorized and ready to
be released (see Section 6.6.1). It is recognized that many activities may not require an
ALWCD. Contractors should include mechanisms within their work control process to
account for approval and authorization of such activities.
Emergent work identified after the schedule has been approved follows the normal work
planning process based on prioritization. The new work is reviewed against the already
authorized activities and changes are approved at the same approval authority level to
ensure that no conflicts exist prior to authorization. This also holds true for the ALWCD
change process (see Section 6.4.6).
6.6. Performing Work within Controls
Performance Expectation: Work is performed within controls (DOE P 450.4A and 48
CFR 970.5223-1(c)(4)).
Good Practices:
55
DOE-HDBK-1211-2014
Section 46
This section discusses attributes and good practices associated with ISMS Core
Function 4. Once the planning effort is completed, the work group is responsible for
executing the activity in accordance with the ALWCD. A bias is set on proving that work
activities are safe before proceeding, rather than proving them unsafe before halting.
The work group does not proceed and does not allow others to proceed when safety is
uncertain. Line management is supportive of these decisions. If the activity cannot be
performed as prescribed, then employ the ALWCD change process (see Section 6.4.6)
for disposition prior to proceeding with the activity.
6.6.1 Preparation and Release of Work
Performance Expectation: Work is formally authorized to proceed (see 48 CFR
970.5223-1(b)(1), (b)(2) and (b)(7), 10 CFR 830.122.e, DOE O 433.1B, Attachment 2,
para. 2.b and 2.d, and DOE O 422.1, Attachment 2, Appendix A, Para. 2.a (2) and
2.h(5)(b)).
Good Practices:
There is a process to confirm adequate preparation and readiness to begin work prior to
authorizing the performance of work at the facility, project, or activity level. The formality
and rigor of the process and the extent of documentation and level of approval is based
on the hazards and complexity of work. Readiness is assured by verifying that controls
are adequate to mitigate the identified hazards and that the controls are implemented
prior to commencement of work (DOE G 450.4-1C, Attachment 2, Section 4).
For example, facility personnel should be apprised of scheduled activities to ensure
coordination. This may be accomplished by publishing and updating a short-duration
rolling schedule covering the current week. Routine activities previously defined and
approved by line management (e.g., operator rounds, instrument source checks, pre-
operational equipment checks, basic shop work, etc.) may not need a formal release and
may be performed on an ongoing basis, unless otherwise directed by the release
authority.
The work supervisor should be provided with ALWCDs in time to allow for adequate
preparation and pre-job brief before starting the activity. ALWCDs are reviewed by
workers prior to work performance to ensure workability and familiarity with the activity.
Personnel are not given work until the activity is ready to be done, the equipment has
been cleared and prepared, the materials are available to do the activity, and work
groups have coordinated through joint prioritization in the scheduling meetings, as
appropriate.
A workability review, based on site requirements, should be conducted prior to obtaining
work release. The work group will use this opportunity to look at the ALWCD work
instructions in context with current conditions at the job site, including a walkdown when
conditions permit. Many organizations have found a checklist useful in completing such
reviews. During the review, check or verify the following:
• determine if circumstances have changed since the activity was planned that could
affect the safe performance of work,
56
DOE-HDBK-1211-2014
• ensure that the hazards analysis results translate to the actual work environment
(i.e., reflect actual conditions),
• all hazards that could potentially affect the safety of workers have been identified and
that selected controls are appropriate and adequate,.
• all necessary parts, tools, and special equipment are on-hand,
• support organizations (e.g., system engineers, QC inspectors) have allocated trained
and qualified personnel to support the activity;
Section 47
• all necessary permits and documents are prepared and ready; and
• the impact of tools and temporary equipment (e.g., scaffolding, rigging, power
supplies, welding equipment, enclosures, insulation, shielding) on facility systems
and equipment are understood and accepted.
Prior to releasing the work, the release authority should consider the following:
• Is the activity authorized (on the approved schedule)?
• Is the ALWCD approved?
• Are current conditions consistent with the ALWCD?
• Are there other ongoing activities that this work may adversely affect?
• Do building occupants need to be notified of any aspect of the work (e.g., noise,
duration, limited access, etc)?
• Is the facility in the proper configuration and is there any impact on the safety basis
(e.g., have TSRs been implemented)?
6.6.2 Pre-Job Brief
Performance Expectation: Pre-job briefings should be conducted (see 48 CFR
970.5223-1(c)(4), 10 CFR 830.122.e, 10 CFR 851.25(a), DOE O 433.1B, Attachment 2,
para. 2.d, DOE O 422.1, Attachment 2, Appendix A, Para. 2.l).
Good Practices:
A pre-job briefing (based on site requirements) should be conducted each work period
(day or shift if there is more than one shift per day) prior to performing work or
periodically as noted below. The supervisor or designee may conduct additional pre-job
briefings at the start of a new activity or suite of tasks, when new personnel are
assigned, or when there is a major change.
Pre-job brief frequency, detail, and extent vary according to hazards associated with and
the complexity of the activity, consequence of recognized failure mode, mission
significance, and the experience of the work group. At the less frequent (e.g., performed
for the first time), more detailed range is work that is hazardous, complex, or performed
by teams or multiple individuals with different skill sets. This work may require the
integration and coordination of several activities or related tasks. At the more frequent,
less detailed range of activities are workers performing routine, low-hazard activities.
57
DOE-HDBK-1211-2014
The pre-job brief should be conducted in a work environment that fosters attention and
participation. The supervisor or designee should familiarize themselves with various
aspects of the activity prior to conducting the pre-job brief. The following is a list of things
to consider:
• Topics identified by the planner in the ALWCD;
• Scope of work;
• Relationship of the work to applicable regulatory requirements (e.g.,TSRs, DSA),
radiation work/confined space permits, material safety data sheets, safety data
sheets, etc.;
• Hazards and associated controls (e.g., precautions, limitations, warnings, cautions);
• Prerequisites, such as facility configuration, operating mode, lockout and tagout,
isolation requirements, alarm deactivation, and outages;
• Key points from diagrams, drawings, vendor documentation, and other supporting
documents;
• Workability walkdown results;
• Emergency escape routes;
• Worker training and certification requirements;
• Needed support resources;
• Staging of parts, tools, and equipment;
• Human performance improvement techniques;
• Lessons learned;
• Hold points;
• Interfaces between crafts or with other organizations; and
• The resolution of a stop work action prior to restarting the work.
Section 48
The workgroup (e.g., supervisor or designee, workers and support personnel) then
conduct an interactive pre-job brief using all of the necessary documentation, (e.g.,
ALWCD, RWP, permits) to review and confirm the workgroup’s readiness to perform the
activity. The content of the pre-job brief should address the following:
• Situational awareness of factors (e.g., weather conditions, noise, lighting) that may
impact the activity, other ongoing activities, or collocated workers;
• Each member of the workgroup has reviewed the current ALWCD and understands
the tasks and associated hazards and controls for activities to be performed;
• Applicable lessons learned are identified and discussed from previous performance
of identical or similar activities;
• Workgroup personnel have the training and qualifications to perform their assigned
tasks, including familiarity with applicable general hazards;
• Workgroup personnel have required medical approval to perform their assigned
tasks;
• Workgroup personnel understand the work scope and boundaries for the activity;
58
DOE-HDBK-1211-2014
• Workgroup personnel are cognizant of any critical steps associated with the activity,
the mistakes that can be made at those points, the worst thing that could happen,
and the barriers or defenses that are needed;
• Workgroup personnel are aware of holdpoints;
• Responsibility for specific tasks is assigned to specific workers and support
personnel;
• Workgroup personnel understand the ALWCD prior to performing work;
• Workgroup personnel readiness and fitness-for-duty is evaluated that day;
• Expectations for workgroup personnel to apply and follow procedures, observe limits,
and work within the released scope of work;
• Expectations for workgroup personnel for prompt communications to their supervisor
for changes in the work scope, situations where the ALWCD cannot be followed or
performed as written, unexpected conditions are encountered, or other conditions
that may require re-evaluation of the activity;
• Expectations for workgroup personnel to use pause work or stop work actions;
• Identify actions in the event of an upset condition;
• Activity coordination between different work groups;
• Expected results (e.g., acceptance criteria, housekeeping); and
• Workgroup questions.
Most sites have a fairly standard format for conducting pre-job briefings prior to the
execution of work. A reverse pre-job briefing assists in engaging the work force by
fostering an environment where employees can raise concerns without fear of retaliation
and promoting a questioning attitude. Reverse-briefing techniques include asking:
• Open-ended questions to promote a more thorough discussion;
• Each worker to describe their respective role/responsibility in performing the task;
• Each worker to describe hazards, controls and critical steps associated with their
assignment;
• Workers about previous operating experiences or lessons learned;
• Workers to describe communication methods (voice, phone, radio, etc.);
• Workers to identify any known error precursors;
• Workers to discuss Human Performance Improvement tools (e.g., self-check, peer-
check, questioning attitude, effective communication, time out) that can be used
during the job; and
• Workers to describe potential problems including “worst case scenarios” and
associated responses.
Section 49
For more information regarding the reverse pre-job briefing process, refer to URS –
Nuclear Waste Partnership LLC, outlined in WP 04-AD30303, Pre-Job & Post-Job
Reviews.
59
DOE-HDBK-1211-2014
6.6.3 Performing Work
Performance Expectation: Work is performed and documented in accordance with the
ALWCD. Documentation includes acceptance results, problems encountered during
execution of the work, and feedback information considered useful for improving the
work process (see 48 CFR 970.5223-1, para. (b)(5) and (c)(3)-(5), 10 CFR 830.122.d-e,
DOE P 450.4A, DOE O 433.1B, Attachment 2, para. 2.d and 2.f, and DOE O 422.1,
Attachment 2, Appendix A, para. 2.a (3)(b); 2.b.(1), (2) and (5); 2.h(5)(c); and 2.p(1), (8),
and (9)).
Good Practices:
Following the pre-job briefing, workers should conduct the activity and record results in
accordance with the ALWCD.
Workers should:
• Perform work in accordance with the ALWCD;
• Understand their responsibility and authority to stop or pause work if conditions are
deemed unsafe or if there is doubt concerning how to proceed safely;
• Promptly report unintended failures to follow ALWCD or supporting document
requirements.
• Ensure that safety issues or errors discovered during the course of performing work
are reported promptly, and the effect on current work activities is thoroughly
assessed, before proceeding.
• Keep the work supervisor informed;
• Know where to go, what to do, and who to call for help if new or different hazards or
circumstances other than addressed in the ALWCD are encountered;
• Look for collocated hazards that the ALWCD did not address. If such hazards exist,
stop or pause work and inform supervision;
• Continue to assess current field conditions at the work site to ensure that conditions
are as expected to perform the work safely. If conditions are not as expected, stop or
pause work and inform supervision;
• Verify work is done on specified equipment in the ALWCD;
• Follow ALWCD use categories consistent with locally developed procedures; and
• Follow alarm, upset condition, and abnormal operating procedures as applicable.
Line Management and first line supervisors should:
• Oversee the work to ensure compliance with the ALWCD;
• Provide accurate and timely status reports;
• Demonstrate visible leadership at the work site and in employee work areas,
including coaching, mentoring, and reinforcing standards and positive behaviors;
• Coordinate supporting and interfacing work activities; and
60
DOE-HDBK-1211-2014
• Ensure the timely availability of tools, supplies, and parts.
6.6.3.1 Stop/Pause Work Expectations and Responsibilities
Performance Expectations:
1. Stop work authority is defined and available to all contract and subcontract personnel
(48 CFR 970.5223-1, para. (i)).
2. Contractor Management: Establish procedures to permit workers to stop work or
decline to perform an assigned task because of a reasonable belief that the task
poses an imminent risk of death, serious physical harm, or other serious hazard to
workers, in circumstances where the workers believe there is insufficient time to
utilize normal hazard reporting and abatement procedures (10 CFR 851.20, para
(a)(9)).
3. Workers: Stop work when the worker discovers employee exposures to immediately
dangerous conditions or other serious hazards; provided that any stop-work authority
must be exercised in a justifiable and responsible manner in accordance with
procedures established in the approved worker safety and health program (10 CFR
851.20, para. (b)(9)).
Section 50
4. Policies clearly define operations personnel authority, accountability, and
relationships with other groups, including Stop-Work authority (DOE O 422.1
Attachment 2, Appendix A, Para. 2.a(1)(f)).
5. Contractor and subcontractor employees have the responsibility and the right to
report concerns relating to the environment, safety, health or management of DOE-
related activities, including those that have not been resolved through normal work
processes (see DOE O 442.1a, Attachment 1, and DOE O 442.2, Attachment 1,
para. 1).
Good Practices:
This section discusses one methodology for identifying and resolving situations involving
the use of stop-work authority. A pause work concept is also introduced. In order for
either concept to be successful, managers and supervisors should be responsive and
supportive of each request without recrimination, stigma, or punishment. Below are
recommended responsibilities and actions for concerned employees, employees
performing the activity, and responsible managers.
A concerned employee should initiate a Pause Work when a condition of concern or an
unexpected condition is perceived to exist. For example, a step in the procedure cannot
be worked as written or another task being performed in the adjacent area presents a
conflict. In many such instances, the performing employee or the responsible manager
may be able to correct the condition of concern with minimal effort and time. In simple
cases, the situation could be resolved via face to face communications such that the
concerned employee is satisfied with the solution or explanation. However, if the
condition represents an imminent risk of death, serious physical harm, or other serious
hazard to workers, a concerned employee should promptlyinitiate a formal Stop Work
action.
61
DOE-HDBK-1211-2014
Stop Work Action:
Once aware of a potentially unsafe condition that represents an imminent risk of death,
serious physical harm, or other serious hazard to workers, the concerned employee
should perform the following:
• Stop the unsafe work activities and those of any other individuals in the area who
may be affected by the situation.
• Clear all at-risk personnel from the area and warn others trying to enter the area.
• Inform all affected personnel of the reason for the work stoppage.
• Notify the the line foreman, supervisor, or manager of the situation.
When necessary, the responsible manager takes immediate and interim corrective
actions to protect personnel. All employees should honor Stop Work declarations by
stopping work. When a Stop Work is in effect, the responsible manager should only
allow work to continue that will not interfere with, impact, or circumvent the Stop Work
declaration.
Stop Work Resolution:
Upon declaration of the Stop Work action, the concerned employee should contact the
cognizant supervisor, responsible manager, and the appropriate ES&H and Quality
(ESH&Q) representative, and describe the situation that resulted in the Stop Work.
The concerned employee documents the details of the Stop Work action and the
responsible manager evaluates the Stop Work action, including a determination whether
the Stop Work action affects other locations/activities across the site.
The responsible manager, in consultation with the process owner, concerned employee,
and applicable ESH&Q representative(s), determines the appropriate corrective action(s)
to resolve the potentially unsafe condition, keeping the following in mind:
Section 51
• Follow related organizational processes, such as:
– Control of nonconforming items;
– Corrective action system;
– Identification, reporting, and resolution of Price-Anderson noncompliances;
– Event investigation and occurrence reporting; and
– Lessons learned.
• Proposed corrective actions should reduce or eliminate the hazards and not
introduce new or additional hazards.
• Keep employee(s) apprised of the Stop Work action resolution.
The responsible manager implements the agreed upon corrective action(s) in
accordance with locally approved processes. These corrective actions are reviewed by
line management and appropriate subject matter experts in order to support a formal
62
DOE-HDBK-1211-2014
and documented resumption of activities or restart of operations. Line management’s
formal approval should consider the following:
• Contact the concerned employee who reported the situation for an evaluation of the
action(s) taken. If unavailable, select a peer of that employee to evaluate the action
taken.
• If the actions taken implement applicable requirements and the concerned employee
agrees with the action taken, document that an acceptable resolution has been
achieved.
• If the actions taken do not implement applicable requirements or satisfy the
concerned employee, consult with the concerned employee, Facility Manager, and
appropriate ESH&Q representative in order to resolve concerns.
• The employee may seek to further address the concern, if it becomes necessary,
through local processes for employee concerns. If the concern is a technical ES&H
matter, a differing professional opinion (DPO) may be initiated through the DOE
process in DOE O 442.2 (see http://www.hss.doe.gov/nuclearsafety/qa/dpo.html).
The responsible manager directs employees affected by the Stop Work declaration to
resume activities.
A good practice for the affected organization is to maintain a completed Stop Work
action form as a facility record in accordance with locally approved procedures.
Pause Work Action:
For conditions of concern or when encountering unexpected conditions,, the concerned
employee should initiate a Pause Work if performing the work, or ask the employee
performing the work to Pause Work, and raise the concern with the employee or
supervisor. When confident that the condition of concern has been corrected, the
concerned employee should verbally concur with the supervisor or performing employee.
If another employee requests a Pause Work from a task due to a safety concern, the
performing employee(s) should honor the Pause Work and correct the condition that
caused the Pause Work. Inform the concerned employee when the situation is
corrected, and request his or her verbal concurrence with the correction.
Actions taken under a Pause Work should not normally warrant a formal corrective
action plan or be further tracked and trended. However, resolutions may result in
changes to the ALWCD through the change control process and the supervisor should
consider reporting the Pause Work action to the appropriate authority, depending on the
nature of the concern.
6.6.3.2 Monitoring Work, Status Updates, and Turnovers
Performance Expectation: The operator must establish and implement operations
practices to ensure that operators are informed of conditions, manage equipment
deficiencies, ongoing activities, while promptly notifying operating personnel and
supervisors of changes in the facility status, abnormalities, or difficulties encountered in
Section 52
63
http://www.hss.doe.gov/nuclearsafety/qa/dpo.html
DOE-HDBK-1211-2014
performing assigned tasks (see DOE O 422.1, Attachment 2, Appendix A, para. 2.b.(1),
2.h(5)(c), and 2.l).
Good Practices:
The role of the work supervisor is a key element to the successful execution of work.
DOE-HDBK-1117-99, Guide to Good Practices for Maintenance Supervisor Selection
and Development, contains a wealth of information regarding attributes needed to be an
effective supervisor. Care should be exercised in the selection of these individuals.
Responsible managers and first line supervisors communicate management
expectations to the workforce and exhibit integrity in directing the work efforts of
personnel. Their roles include asking questions, coaching, mentoring, evaluating
personnel for fitness for duty, monitoring progress of work, reinforcing standards and
positive behaviors, and coordinating with other organizations to support the effort. It is
critically important that a supervisor maintain the big picture on the progress of an
activity and consistently look ahead to anticipate the needs of his or her personnel in
support of the activity.
During the course of the work, the supervisor and responsible manager routinely ensure
work is being safely and compliantly executed in accordance with the ALWCD and solicit
feedback from the workers by spending time on the floor and in employee work areas.
Any issues should be properly documented, disclosed to the appropriate levels of
supervision, and addressed. When the activity is being performed, consider the following
information for entry into the ALWCD status log or other equivalent mechanism:
• Work interruptions (Pause Work/Stop Work);
• Work delays (such as unavailability of material, support personnel, work area
access);
• Work clarification;
• Progress/status and turnover of work completed – daily or per shift; and
• Documentation of unexpected events or conditions encountered during the
performance of the activity.
In some work situations, it may be necessary to turn an activity over to another shift.
Effective processes need to be in place to ensure that a smooth turnover of
responsibility and work status occurs. An accurate and up-to-date status log is a key
part of that process. Ideally, the offgoing supervisor and oncoming supervisor should
meet on the jobsite and go over the conditions of the work and any problems
encountered over the previous shift. Staging of materials and other needed resources
should also be discussed. Additionally, any other activity that is ongoing or scheduled
that could be impacted by this work or could otherwise affect this work should be
discussed. See also DOE-STD-1038-93 (CH-1), Guide to Good Practices for Operations
Turnover.
6.6.4 Post-Work Testing
Performance Expectations:
64
DOE-HDBK-1211-2014
1. Management of equipment deficiencies, maintenance activities, post-maintenance
testing, and return to service include ALWCDs that specify retest requirements to
ensure, prior to restoration to service, proper functioning, effectiveness of the
maintenance, and that no new problems were introduced (DOE O 422.1, Att. 2 para.
2.h(5)(d) and (e)).
2. The Nuclear Maintenance Management Plan must clearly address the process for
conducting post-maintenance testing to verify that safety SSCs can perform their
intended function when returned to service (DOE O 433.1B, Attachment 2, para.
2.q).
Good Practices:
Section 53
ALWCDs specify testing requirements to ensure functionality and that no new problems
were introduced as a result of the work. For example, the safety functions of safety
SSCs are protected by the established controls within TSRs.
Post-work testing should verify the completion of work activities and ensure the
following:
• The work was performed correctly;
• The outcome is acceptable;
• The work does not introduce or cause other deficiencies or problems;
• Applicable design, safety, and interface criteria are met;
• Safety SSC performance criteria and functional requirements are met;
• Systems and equipment affected by the work operate correctly; and
• Affected equipment is restored to normal or desired operational status.
Additional considerations to prepare for, or conduct, post-work testing include:
• Providing specific instructions or reference a separate test instruction and provide
traceability to testing data;
• Providing a place to record the data directly on the ALWCD or reference it on data
sheets or instructions;
• Establishing the conditions necessary to conduct tests (e.g., flow, differential
pressure, temperature, input signal values, and fluid type);
• Ensuring testing measures performance versus criteria on key parameters and
allows for documentation and review of test data for the equipment;
• Using TSR surveillances to verify operability of safety SSCs;
• Ensuring that the testing has been tailored to the specific activity that was performed;
and
• Performing the testing identified in the ALWCD.
6.6.4.1 Post-Work Acceptance
65
DOE-HDBK-1211-2014
Post-work acceptance activities may include verification that the activity was performed
correctly; the outcome is acceptable; the systems and equipment affected by the work
operate correctly and are restored to normal or desired operational status; or the work
environment has been restored, including packaging and removal of any wastes
generated during the course of work, and is left in a clean and orderly condition.
The RM accepts completed work. The acceptance process includes confirmation that
post-work testing and acceptance activities verified that acceptance criteria and
requirements have been met (e.g., values are within ranges specified by engineering).
The acceptance process may include interface with system engineers prior to equipment
or systems being returned to service. The acceptance process should be commensurate
with the type of work that was performed. Appendix D contains additional information on
post-work testing and acceptance.
6.6.4.2 ALWCD Closeout
Performance Expectation: Timely updates and improvements are incorporated into
affected documents (such as engineering drawings, training documents, operating
procedures, hazard analysis) (see 10 CFR 830.122(c), (d) and (e)).
Good Practices:
Once work is completed, the completed ALWCDs should be reviewed for:
• Forms properly filled out;
• Results, observations, and comments recorded;
• Information describing issues, problems, deviations, abnormal conditions, and
resultant actions taken;
• As-found and as-left conditions;
• Change control and documentation completion issues;
• Design or functional issues from acceptance or post-maintenance testing;
• The need for possible changes to safety management programs, safety analyses,
process safety information, drawings, or other analysis or documentation as a result
of the completed work;
Section 54
• The need to update equipment history; and
• Lessons learned and other feedback and improvement information.
Following review and completion of documentation, the ALWCD should be routed for
record retention.
6.7. Providing Feedback on Adequacy of Controls and Continuing to Improve Safety
Management
6.7.1 Post-Work Review
66
DOE-HDBK-1211-2014
Performance Expectation: Reviews are conducted to collect feedback, including
lessons learned (see 48 CFR 970.5223-1(b)(2) and (c)(5), 10 CFR 830.122(c), (d) and
(e), DOE P 450.4A, and DOE O 433.1B, Attachment 2, para. 2.l and 2.o).
Good Practices:
Post-work reviews are the chief information source for lessons learned (both positive
and negative) from every work activity. The goal of these reviews is to improve WP&C
processes and their implementation. The post-work review process should include
participation by appropriate workgroup members. Items to discuss include what went
right, what went wrong, and what can we do to improve. The results should be
documented and catalogued so they may be used by the organization to implement
lessons learned in future work activities.
6.7.2 Document Lessons Learned
Performance Expectation: Feedback and lessons learned information is analyzed to
identify improvement opportunities. Improvement opportunities are effectively
implemented (see 48 CFR 970.5223-1(b)(1), (c)(2) and (c)(5), 10 CFR 830.122(c) and
(d), DOE P 450.4A, and DOE O 433.1B, Attachment 2, para. 2.o and 2.p).
Good Practices:
Documentation associated with the planning and execution of completed work, including
feedback and lessons learned information, should be archived and easily retrievable to
allow it to be used in the planning of similar work activities in the future.
Sources of lessons learned should be reviewed to identify specific lessons learned for
incorporation or use in planning work activities. Corporate databases supported by the
Office of Health, Safety and Security are listed on
http://energy.gov/hss/services/reporting. Sources of lessons learned that may be
applicable to work being planned include:
• DOE Corporate Lessons Learned database including the Corporate Operating
Experience Review Program;Accident Investigation reports;
• Injury and illness data (Computerized Accident/Incident Reporting System (CAIRS));
• assessments, audits, and appraisals;
• causal analyses and root cause determinations;
• stakeholder feedback;
• deficiency reports;
• ALWCD planning and post-work critiques;
• emergency readiness assurance activities;
• Occurrence Reporting and Processing System (including near-miss reports);
• Noncompliance Tracking System;
• Operational Readiness Reviews;
67
http://energy.gov/hss/services/reporting
DOE-HDBK-1211-2014
• personal experiences and observations captured in post-job briefs;
• process improvement initiatives;
• Price-Anderson Amendments Act findings; and
• safety meetings.
6.7.3 Implement Lessons Learned
The WP&C process should involve supervisors, workers, and facility personnel to
consider how the quality and safety outcomes could be improved. Personnel involved in
work planning and execution should be trained on the importance of, and mechanisms
for, providing feedback and lessons-learned information and incorporating the
information into ongoing and future work activities. Lessons learned may be integrated
into the planning of work in a variety of ways, including:
• addressing them as a topic for a pre-job briefing,
Section 55
• attaching them for review by those approving the ALWCD,
• incorporating them into hazard controls, or
• incorporating them directly into work instructions.
Effectiveness reviews are one way to establish that lessons learned are driving
continuous improvement. These reviews should involve observations of work in the field
to verify that lessons learned are being implemented. Additionally, lessons learned
developed from activity-level WP&C deficiencies may be rolled up in management
review activities for broader application.
6.7.4 Assessing Performance
Performance Expectation: Contractors monitor and evaluate all work performed under
their contracts, including the work of subcontractors, to ensure work performance meets
the applicable requirements for environment, safety, and health, including quality
assurance and integrated safety management. A contractor assurance system assures
both the DOE and contractor managements that work is being performed safely,
securely, and in compliance with all requirements; issues are being identified and
managed; and that the systems of control are effective and efficient (DOE O 226.1B,
Attachment 1, para. 1, 2.a, 2.b(2) and 2.b(3)(a)-(b), and DOE O 422.1, Attachment 2,
Appendix A, Para. 2.a(3)).
Good Practices:
A contractor assurance system:
• Monitors and evaluates safety performance;
• Performs self-assessment and feedback and improvement activities;
• Performs trending and analysis to support proactive decisions; and
• Provides evidence to assure DOE and contractor management that work is being
performed safely, hazards are identified and managed, and controls are effective.
68
DOE-HDBK-1211-2014
Contractors should be aware that DOE oversight includes WP&C as a core performance
area for nuclear safety to warrant special attention for its role in protecting workers, the
public, and the environment from potential hazards (see DOE G 226.1-2).
Performance assessment should contain three principal elements:
• A comprehensive set of routine operational awareness activities that, through direct
on-the-floor observation, evaluate the effectiveness of WP&C activities (e.g., work
planning walkdowns, hazard analyses, pre-job briefs, execution of work).
Assessment of effectiveness can be based upon the following examples:
– Performance compared to industry benchmark or locally established WP&C
performance metrics (see Section 6.1.8 and Appendix B),
– Issues and corrective action status,
– Related occurrence reports,
– Prior activity-level WP&C assessment results,
– WP&C program implementing procedure changes;
• A comprehensive method for selecting the type, sample size, and frequency of
routine operational awareness activities to assure WP&C is effectively implemented;
and
• Periodic formal assessments including self-assessments, internal and external
independent assessments, and operational awareness activities are identified and
conducted.
Formal assessment of activity-level WP&C program effectiveness should be
incorporated into integrated assessment schedules. Identified deficiencies and strengths
should be documented using organizational issues management programs, and
corrective actions should be tracked to completion. Assessments should be done using
Criteria and Review Approach Documents (CRADs) that provide assessment objectives,
criteria, and approach guidelines for performing assessments targeted at the particular
area of activity level WP&C. CRADs are available to perform these assessments in DOE
G 226.1-2.
Section 56
Assessment and metrics data should be analyzed both vertically (within a program,
project, or organization) and horizontally (across different programs, projects, and
organizations at a site) to identify trends and potential problems.
A safe working environment is impossible without an effective safety culture. A method
to allow objective and systematic measurement of the organizational behaviors that
impact safety performance is a useful tool to better understand organizational trends.
See Appendix G for further information.
69
DOE-HDBK-1211-2014
7.0. ACRONYMS
ALARA ................................................................As low as reasonably achievable
ALW ....................................................................Activity-level work
ALWCD ...............................................................Activity-Level Work Control Document
AQM ....................................................................Automated Qualification Matrix
ASME ..................................................................American Society of Mechanical Engineers
CF .......................................................................Core Function
CFR.....................................................................Code of Federal Regulations
CSE.....................................................................Cognizant System Engineer
D&D ....................................................................Decontamination and Decommissioning
DEAR ..................................................................Department of Energy Acquisition Regulation
DOE ....................................................................U.S. Department of Energy
DSA.....................................................................Documented Safety Analysis
EFCOG ...............................................................Energy Facility Contractors Group
ES&H ..................................................................Environment, safety, and health