Cancellation Memo, Proposed Cancellation of DOE-STD-1158-2010, Self-Assessment Standard for Department of Energy (DOE) Contractor Criticality Safety Programs
The standard contains generic lines of inquiry that can be used by Federal and contractor criticality safety practitioners to assess criticality safety programs performance against ANSI/ ANS-8.19-2005, Administrative Practices for Nuclear Criticality Safety. While retaining this information would be useful, DOE-STD-1158-2010 does not meet the criteria for a DOE standard as specified in Appendix A of DOE O 252. 1A.
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
Department of Energy
National Nuclear Security Administration
P.O. Box 5400
Albuquerque, NM 87185
June 27, 2018
MEMORANDUM FOR JEFFREY FEIT
OFFICE OF QUALITY ASSURANCE & NUCLEAR
SAFETY MANAGEMENT PROGRAMS
OFFICE OF ENVIRONMENT, HEALTH, SAFETY AND
SECURITY
FROM: DANIEL SIGG ~\
DEPUTY ASSOCIATE ADMINISTRATOR FOR SAFETY~
SUBJECT: Proposed Cancellation ofDOE-STD-1158-2010, Self
Assessment Standard for Department ofEnergy (DOE)
Contractor Criticality Safety Programs
The National Nuclear Security Administration (NNSA) Office of Safety submits DOE
STD-1158-2010, Self-Assessment Standard for Department ofEnergy (DOE) Contractor
Criticality Safety Programs, for cancellation in the RevCom system for the Technical
Standards Program. DOE-STD-1158-2010 is a reference document and does not contain
requirements that need to be made mandatory via DOE regulatory or contractual
prov1s10ns.
The standard contains generic lines of inquiry that can be used by Federal and contractor
criticality safety practitioners to assess criticality safety programs performance against
ANSI/ ANS-8.19-2005, Administrative Practices for Nuclear Criticality Safety.
While retaining this information would be useful, DOE-STD-1158-2010 does not meet
the criteria for a DOE standard as specified in Appendix A ofDOE O 252. lA.
Specifically, the Standard does not:
• provide specific standardized approaches, methodologies, technical criteria, or
other information on accomplishing a task, developing a plan, and/or performing
a calculation or assessment to implement a DOE requirement; nor
• provide a common shared approach or methodology for implementing a DOE
requirement such that its implementation is consistent across DOE programs and
operations.
The point of contact for this document is Lawrence J. Berg, NNSA Office ofNuclear
Safety Services. Mr. Berg can be reached at (301) 903-0125 or via email at
larry.berg@nnsa.doe.gov.
The comment period should be 60 days. We understand that the comment period for this
document will not begin until the document is posted and available on RevCom for
Technical Standards Program.